Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P.E.– WisDOT Project Leader May 16, 2017

Upload: others

Post on 23-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Tim Hanley, P.E.– WisDOT Project ManagerDaniel Schave, P.E.– WisDOT Project LeaderMay 16, 2017

Page 2: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Review purpose and needs for the project Identify alternatives (solutions) to address the

needs Discuss next steps

2

Page 3: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

3

Page 4: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Regional and local traffic Approximately 3,700 vehicles per day 16% trucks

Constructed in 1998 Existing asphalt 8 inches thick asphalt 24 crashes in 5 year period Run-off-the-road crashes present Ice and snow primary factors

4

Page 5: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Purpose Maximize the life of the pavement Improve safety

Needs Deteriorating pavement (cracking and rutting) Four culvert pipes in poor condition Deteriorating railroad crossing pavement

5

Page 6: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

6

Page 7: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

7

Page 8: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

8

Four culverts are in poor condition Proposing to replace three Two by railroad in Oxford One by 5th Drive Repair one 1 mile east of 5th Drive

Size/location unchanged

Page 9: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

9

Page 10: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

10

Page 11: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Resurface Recycle Replacement

All alternatives include: Culvert pipe repair Railroad crossing surface replacement Five-day detour required (WIS 13, WIS 21 and I-39) Centerline rumble strips Safety edge installation

11

Page 12: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

12

Page 13: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Reduce head-on fatal/injury crashes by 44% Increase “awareness” Inattentive driving Limited Visibility Rain, snow or fog

Low installation cost

Not installed near intersections or commercial driveways

13

Page 14: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

6% reduction in all crashes Low cost of installation Reduces hazard of low shoulders Creates “smooth transition” back onto roadway

14

Normal Edge Safety Edge

Page 15: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

15

Resurface Mill (remove) 2 inches of pavement Place 1.75 inches of new pavement

Temporarily eliminates rutting/cracking. Underlying issues not addressed.

Limited traffic impacts (flagging operation, 5 day detour)

Cost = $1.5 million – $2 million

Page 16: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

16

Remove 2 inches of asphaltPlace 1.75 inches of asphaltInstall centerline rumble stripsLane and shoulder width unchanged

Page 17: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

17

Recycle Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt

Addresses more of the rutting and cracking issues Limited traffic impacts (flagging operation, five-day

detour) Cost = $2.4 million – $3 million

Page 18: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

18

Remove 2 inches of asphaltRecycle 4 inches of asphaltPlace 1.75 inches of asphaltInstall centerline rumble stripsLane and shoulder width unchanged

Page 19: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

19

Replacement Remove all pavement Replace with new pavement

Removes pavement not past its useful life (wastes money) Possible real estate impacts (slope widening) Greater traffic impact (four-month detour) Cost = $3.7 million – $4.5 million

Page 20: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

20

Remove all existing asphaltReplace with 6 inches of new asphaltInstall centerline rumble stripsLane and shoulder width unchangedSlopes possibly widened

Page 21: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

21

Five-day detour (Monday – Friday) State signed detour route via WIS 13, WIS 21, I-39 Local access maintained at all times

V. Oxford

Closure

Page 22: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Meet with local officials: April 26, 2017 Public involvement meeting: May 16, 2017 Select preferred alternative: June 2017 Project design complete: August 2018 Construction currently scheduled: Summer 2019

22

Page 23: Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P ... · Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses

Daniel Schave, P.E. WisDOT Project Leader 715-421-8084 [email protected]