1Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Prioritization of Infrastructure Improvements
Davis Garden TIF Board
September 23, 2011
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 2/15
2Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Purpose
Review and prioritize the potential list of infrastructureimprovements that may be funded by the $1 milliondeposit into the Davis Garden TIF District Increment
Fund.
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 3/15
3Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Davis Garden TIF District BoundaryMap
Sub-District A – The Canyon
Sub-District B – Davis Garden
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 4/15
4Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Davis Garden TIF District: CurrentStatus
• Appraised values in the Davis Garden TIF District are only $3million above the adjusted base value. There will be insufficientincrement in the short term to cover any TIF reimbursements.TIF administrations will only be partially covered.
• The potential $1 million contribution related to the amendedINCAP Phase I development agreement is likely to be the onlydiscretionary funds available for infrastructure improvements in
the short term.
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 5/15
5Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
INCAP’s Phase I DevelopmentAgreement
INCAP’s Phase I development agreement consisted of thefollowing components:
The project’s environmental remediation and demolitioncomponents have been completed for sum time
On June 22nd City Council authorized a third amendment to thedevelopment agreement that allows INCAP to deposit $1 million
into the Davis Garden District Tax Increment Fund for futureinfrastructure improvements that benefit the District in lieu of thedeveloper constructing median improvements, streetscape andother public improvements
TIF Improvement Category AmountEnvironmental Remediation $1,575,612.70
Demolition $1,432,633.30
Median Improvements, Streetscape & Other Public Improvements $1,000,001.00
TIF Eligible Project Costs $4,008,247.00
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 6/15
6Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
City staff put together a list of projects that could befunded with the $1 million could be utilized to fund anumber of proposed public infrastructure improvementsprojects throughout the District
• King’s Demonstration Plaza• King’s Permanent Plaza• King’s Parking• Rosemont Plaza
• Rosemont Safe Route• Davis Corridor Bicycle Facility• 7th Street Bicycle Facility• Matching Funds for Kessler Theater Infrastructure
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 7/15
7Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
King’sHighwayPermanentPlaza withadditionalamenities
7th Street
Davis StreetDavis Street
T y l e r S t r e e t
K i n g K i n g ’ ’ s s
H i g h w a y
H i g h w a y
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 8/15
8Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
King’sHighwayParking
Davis StreetDavis Street
K i n g K i n g ’ ’ s s
H i g h w a y
H i g h w a y
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 9/15
9Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
RosemontPlaza
Davis StreetDavis Street
N .
R o s e m
o n t A
v e
N .
R o s e m o n t A
v e
M a r y C l i f f R d
M a r y C l i f f R d
7 t h 7 t h S t r e e t S t r e e t
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 10/15
10
Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Rosemont Safe Route
• Reduce 38’, 3-lane road to24’, 2-lane road with 14’dedicated bicycle path
• Reduce with of intersectionsto ease crossing
• Reduce width of slip lane by
adding cycle track
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 11/15
11Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Rosemont Safe Route (cont.)
• Increase safety
• Increase ridership
• Physically separate carsfrom bicycle traffic
• Ease crossing distance forpedestrians
• Decrease accident rates forall modes of transit
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 12/15
12Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Davis Street Corridor Bicycle Improvements – EarlyImplementation (2011-12)
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 13/15
13Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Matching Funds for Kessler Theater Infrastructure• $59,691.00 in TIF funding will be leveraged by $179,200.00 in
matching funds from TxDot (NCTCOG Grant)
Potential Infrastructure Improvements
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 14/15
14Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Kessler Theater landscape construction estimate:
Potential Infrastructure Improvements
DESCRIPTION COST TOTAL
A Hardscape/Pedrestian AmenitiesPedestrian Amenities Construction $129,381.00Pedestrian Amenities PS&E and Design $12,938.10
$142,319.10B Landscaping
Landscaping Construction $66,088.00Landscaping PS&E and Design $6,608.80
$72,696.80C Intersection Improvements
Intersection Improvements Construction $2,000.00Intersection Improvements PS&E and Design $200.00
$2,200.00D Other (Demolition of curbs & sidewalks)
Other Construction $6,803.00Other Construction PS&E and Design $680.30
$7,483.30
SubtotalConstruction Costs $204,272.00
PS&E and Design $20,427.20Environmental Assessment $5,000.004.5% of Total Construction Hard Costs $9,192.24TOTAL $238,891.44
•
TxDot Funding – 75%• TIF Funding – 25%
Funding Source
TxDot Funding $179,200.00
TIF Funding $59,691.44TOTAL $238,891.44
8/4/2019 TIF Board Briefing_Potential Infrastructure Imprv_9!14!11
http://slidepdf.com/reader/full/tif-board-briefingpotential-infrastructure-imprv91411 15/15
15Office of Economic DevelopmentWWW.DALLAS-ECODEV.ORG
Staff recommendations for proposed Infrastructure Improvements:
Non funded projects:
Project Est. Cost Source
Matching funds for NCTCOG Grant $60,000
100% OED;
leverages approx.$180K in outside
funds
King’s Demonstration Plaza $301,568 100% OEDKing’s Permanent Plaza $194,483 100% OED
King’s Parking $40,357 100% OEDRosemont Plaza $201,512 100% OED
Davis Corridor Bicycle Facility $159,000 100% OED
City of Dallas Design Studio –
Concept for reconfiguration of W.Davis Street from Montclair to Zang
Boulevard
$35,880 100% OED
Total $992,800
Rosemont Safe Route $36,272 Unfunded
Seventh Street Bicycle Boulevard $85,844 Unfunded
Public Art for King's PermanentPlaza
$300,000 Unfunded
Funding SourceStratford Funds $1,000,000 OEDPotential Grant for Public Art $300,000 Private/Non-ProfitOther Unfunded Projects $122,116 Private/Non-Profit
Total Project Cost $1,422,116
Potential Infrastructure Improvements