tideflats area transportation study final report ppt 11-06-16
DESCRIPTION
PPT of the Tideflats Area Transportation Study Final Report given by Kell McAboy, Planner, Port of Tacoma to the RAMP (Regional Access Mobility Partnership) meeting July 6, 2011.TRANSCRIPT
![Page 1: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/1.jpg)
PORT OF TACOMA
![Page 2: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/2.jpg)
PORT OF TACOMA
Sponsors
Port of Tacoma WSDOTCity of Fife SSA Marine City of Tacoma Pierce CountyMarine View Ventures FMSIB
Tideflats Area Transportation StudyFinal Report
![Page 3: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/3.jpg)
PORT OF TACOMA
• Identify future transportation needs for the growth of freight-related traffic to and from the Tideflats area
• Increase mobility and accessibility by reducing traffic congestion
• Promote regional economic competitiveness
• Accomplish a coordinated transportation plan
Tideflats Area Transportation StudyGoals and Objectives
![Page 4: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/4.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyStudy Area
![Page 5: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/5.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyTruck Volumes
![Page 6: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/6.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyExisting Traffic “Hot Spots”
![Page 7: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/7.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyBaseline Projects
![Page 8: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/8.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyHousehold and Employment Growth
![Page 9: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/9.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyTraffic and Truck Growth
![Page 10: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/10.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyFirst Level Screening Criteria
![Page 11: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/11.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudySecond Level Evaluation Criteria
![Page 12: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/12.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyRecommended Projects
Tideflats Area Access
![Page 13: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/13.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyRecommended Projects
Port Access
![Page 14: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/14.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyRecommended Projects
Industrial Access
![Page 15: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/15.jpg)
PORT OF TACOMA
Tideflats Area Transportation StudyRecommended Projects
Local Access
![Page 16: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/16.jpg)
PORT OF TACOMA
• Cost of Recommended Projects is $290-335 Million• Tideflats Area Access: $140-150 Million • Industrial Access: $110-130 Million• Port Access: $5-10 Million• Local Access: $35-45 Million
• Baseline projects total $485-540 Million• Existing Funding Commitments is $196 Million• Remaining Funding Need over 20 Years estimated
$579-679 Million
Tideflats Area Transportation StudyOrder of Magnitude Costs
![Page 17: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/17.jpg)
PORT OF TACOMA
• Medium- and long-term transportation requirements to accommodate area traffic growth
• Coordinated recommendations that meet the needs of stakeholders
• Information needed to support funding pursuits
Tideflats Area Transportation StudyOutcomes
![Page 18: Tideflats Area Transportation Study Final Report PPT 11-06-16](https://reader033.vdocuments.us/reader033/viewer/2022061212/547af65fb4af9fbe158b4df0/html5/thumbnails/18.jpg)
PORT OF TACOMA
Next Steps, Questions and Answers