thomas viaduct ms construction document report - november 15
TRANSCRIPT
ACTION
BOARD OF EDUCATION OF HOWARD COUNTY MEETING AGENDA ITEM
TITLE: New Middle School #20 Construction Document Report DATE: November 15, 2012
PRESENTER(S): Bruce Gist, Director, School Construction Michael Lahowin, Principal in Charge, TCA Architects OVERVIEW: New Middle School #20, which will be located on the Oxford Square school site, will be an adaptation of the prototype middle school design. This prototype, based on the General Education Specifications for New Howard County Middle Schools, dated June 1994, is designed to accommodate a population of 662 students in Grades 6–8, plus 40 full-time equivalent special education students, for a total of 702 students and is the fifth iteration of this design. Since the design development phase, additional refinements have been made as a result of continued meetings with the Howard County Public School System’s staff, local code authorities, and the site developer. These refinements include: the use of polished concrete in corridors and the cafeteria, the reconfiguration of the service area for additional mechanical/electrical equipment, reconfigured custodial toilet rooms per revised ADA codes and additional skylights in classrooms for more natural daylight. Due to the unique location of the building and the concerns that have been raised, the appendix now includes an emergency plan summary. Energy efficiency has remained a primary driver of this project’s design. This project will utilize the United States Green Building Council LEED for Schools version 2009 and is intended to achieve a LEED Silver certification.
RECOMMENDATION/FUTURE DIRECTION: It is recommended that the construction document report for New Middle School #20 be approved. Submitted by:
Approval/ Concurrence:
Ken Roey, Executive Director Facilities Planning and Mgmt.
Raymond H. Brown Deputy Superintendent of Operations
Bruce Gist, Director
School Construction
Middle School #20 Howard County Public School System
Construction Document Report
November 15, 2012
View of Middle School #20 Main Entrance
! ! ! Construction Document Report! ! !! ! ! Middle School #20! ! ! FOR THE BOARD OF EDUCATION OF HOWARD COUNTY:! !! ! ! Chairman ! ! ! ! ! ! Sandra H. French! ! ! Vice Chairman ! ! ! ! ! Frank J. Aquino, Esq.! ! ! Members! ! ! ! ! ! Allen Dyer, Esq.! ! ! ! ! ! ! ! ! ! Ellen Flynn Giles! ! ! ! ! ! ! ! ! ! Brian J. Meshkin! ! ! ! ! ! ! ! ! ! Janet Siddiqui, M.D.! ! ! ! ! ! ! ! ! ! Cynthia L. Vaillancourt! ! ! ! ! ! ! ! ! ! Cole T. Rosenberg (Student)
! ! ! Superintendent of Schools ! ! ! Renee A. Foose, Ed.D.
! ! ! Deputy Superintendent of Operations!! Ray Brown! ! ! !
! ! ! Executive Director! ! ! Facilities Planning & Management! ! Ken Roey
! ! ! Director of School Construction!! ! Bruce Gist
! ! ! November 15, 2012
Middle School #20 • Construction Document Report 1
Table of Contents 3! Schematic Planning Advisory Committee & Design Team
4! Design Development & Construction Document Phase Participants
! ! ! !! ! ! ! Project Information
! ! ! 5! Project Description & Continuation of the School Design Process
! ! ! 6! Project Facts and Schedule
! ! ! 7! Sustainable ‘Green’ Design Goals
! ! ! ! Design Drawings, Space Analysis & Cost Estimate
! ! ! 8! Vicinity Map
! ! ! 9! Aerial Site Photo
! ! ! 10! Site Context
! ! ! 11! Proposed Site Plan Notes & Construction Document Phase Site Plan Refinements
! ! ! 12! Proposed Site Plan
! ! ! 13! Proposed First Floor Plan
! ! ! 14! Proposed Second Floor Plan
! ! ! 15! Floor Plan Narrative
! ! ! 17! Exterior Building Changes
! ! ! 18! Building Elevations
! ! ! 19! Main Entrance Elevation!
! ! ! 20! Space Analysis
! ! ! 25! Construction Cost Estimate
! ! ! ! Appendix
! ! ! A-1! Emergency Plan (3 pages)! ! !
! !!
Middle School #20 • Construction Document Report 2
! !! ! Schematic Planning Advisory Committee! !
! ! Planning Committee! ! !
Joyce Agness! ! ! HCPSS, Dept. of Special Education, Instructional FacilitatorBerit Batterton! ! ! Elkridge Landing Middle School, StudentJennifer Blasko! ! Elkridge Landing Middle School, Parent and TeacherDave Bruzga! ! HCPPS, Secondary School Administrative DirectorGina Cash! ! ! Elkridge Landing Middle School, PrincipalCindy Jamieson! ! Elkridge Landing Middle School, TeacherJohn Jenkins! ! J. Vinton Schafer & Sons, Inc.Dan Keiser! ! ! HCPSS, Construction Program ManagerMegan Kruger! ! Patuxent Valley Middle School, TeacherTed Ludicke! ! HCPSS, Systems Support, Service DeskNancy McClanahan!! Patuxent Valley Middle School, PTA Vice PresidentKerry McGowan! ! Hammond Middle School, PrincipalGloria Mikolajczyk! ! MSDE School Facilities, Architect SupervisorRon Miller! ! ! HCPSS, Safety, Environment, and Risk Management ManagerRobert Motley! ! Patuxent Valley Middle School, PrincipalJudy Pattik! ! ! HCPSS Old Cedar Lane, Special Education CoordinatorKen Roey! ! ! HCPSS, Facilities Planning & Management Executive DirectorStephanie Sloane! ! Murray Hill Middle School, Science TeacherScott Washington! ! HCPSS, Design and Preconstruction Services ManagerJosh Wasilewski! ! Patuxent Valley Middle School, Assistant PrincipalThalia White! ! Murray Hill Middle School, ParentBetsy Zentz!! ! HCPSS, Interagency SpecialistLiz Zinger! ! ! Murray Hill Middle School, Math Specialist
! !! !! ! Architects
! ! Mike Lahowin, AIA! ! Principal in Charge, LEED AP! ! Robyn Toth! ! ! ! Project Manager, LEED AP
! ! Design Team! ! ARCHITECT! ! ! TCA Architects! ! ! ! Annapolis, MD! ! CIVIL ENGINEER! ! Fisher, Collins & Carter, Inc. ! ! Ellicott City, MD! ! STRUCTURAL ENGINEER! Johnson Engineering Assoc.! ! Darnestown, MD!! ! M/E/P ENGINEER! ! James Posey Associates! ! ! Baltimore, MD! ! DAYLIGHTING ENGINEER! EMO Energy Solutions! ! ! Falls Church, VA! ! ROOFING CONSULTANT! Gale Associates, Inc.! ! ! Baltimore, MD! ! ACOUSTICAL ENGINEER! Miller, Beam & Paganelli, Inc.! ! Reston, VA
Middle School #20 • Construction Document Report 3
Design Development & Construction Document ! ! Phase Participants
Maureen Blaner! ! HCPSS, Health ServicesStephanie Blaney! ! HCPSS, InternJennifer Blasko! ! Elkridge Landing Middle School, Parent and Teacher Lisa Boarman! ! HCPSS, Coordinator, School Counseling & Related ServicesOlivia Claus! ! HCPSS, Manager, Custodial ServicesMark Coates! ! HCPSS, Coordinator, Fine Arts OfficeLaurie Collins! ! HCPSS, Instructional Facilitator, Family & Consumer Services
! ! Greg Connor ! ! HCPSS, Asst. Manager, Grounds ServicesDeborah Espitia! ! HCPSS, Coordinator, World Languages ProgramRosalie Edwards! ! HCPSS, Area Field Representative, Food & Nutrition ServicesCarol Fritts! ! ! HCPSS, Coordinator, Career & Technology EducationBruce Gist! ! ! HCPSS, Director, School ConstructionDan Hagan! ! ! J. Vinton Schafer & Sons, Inc.Tim Heinrich! ! HCPSS, HVAC Control SpecialistJim Hobson!! ! Eng. Specialist, Dept. Inspections, Licenses & PermitsJohn Jenkins! ! J. Vinton Schafer & Sons, Inc.Dan Keiser! ! ! HCPSS, Construction Program ManagerMolly Kelley! ! HCPSS, Instructional Facilitator, Media Technical Services Hummy Khan! ! HCPSS, Asst. Manager, Building ServicesMary Klatko! ! HCPSS, Director, Food & Nutrition ServicesJim Kramerq! ! HCPSS, Leadman for Electrical DepartmentSharon Kramer! ! HCPSS, Coordinator, Business & Computer Management SystemsEddie Liberto! ! HCPSS, HVAC SpecialistTed Ludicke! ! HCPSS, Technology Dept. Systems Support Service DeskTodd McMahon! ! HCPSS, Project Management SpecialistDonald Mock! ! Fire Protection Engineer, Dept. Inspections, Licenses & PermitsGino Molfino! ! HCPSS, Resource Teacher, Art, Fine Arts OfficeRobert Motley! ! Patuxent Valley Middle School, Principal
! ! Larry O’Neill! ! HCPSS, Building ServicesSusan Overstreet! ! Environmental Planning Supervisor, Howard County GovernmentJudy Pattik! ! ! HCPSS, Coordinator, Special EducationLinda Rangos! ! HCPSS, Coordinator, Health/Physical EducationGreg Rogers! ! HCPSS, Plumbing SpecialistMolly Schaefer! ! HCPSS, InternStephanie Sloane! ! Murray Hill Middle School, Science TeacherRenato Toledo! ! HCPSS, Asst. Manager, Audio Visual ServicesLaura Wallen! ! Murray Hill Middle School, Social Studies TeacherScott Washington! ! HCPSS, Design and Preconstruction Services ManagerJoshua Wasilewski! ! Patuxent Valley Middle School, Assistant PrincipalMary Weller! ! HCPSS, Coordinator, Secondary ScienceRobert White! ! HCPSS, Instructional Facilitator, MusicJulie Wray ! ! ! HCPSS, Coordinator, Instructional Technology! ! !Penny Zimring ! ! HCPSS, Instructional Facilitator, Gifted and TalentedElizabeth Zinger! ! Murray Hill Middle School, Math Specialist
Design TeamChuck Crovo! ! Civil Engineer, Fisher Collins & Carter, IncJim Graf! ! ! MEP Engineer, James Posey AssociatesSteve Hudson! ! Principal, James Posey AssociatesBob Johnson! ! Structural Engineer, Johnson Engineering Assoc.Mike Lahowin! ! Principal in Charge, TCA ArchitectsDale Mediary! ! Civil Engineer, Fisher Collins & Carter, IncBrian Romie! ! MEP Engineer, James Posey AssociatesMike Sherren! ! MEP Engineer, James Posey AssociatesMike Smith! ! ! TCA ArchitectsRobyn Toth! ! ! Project Manager, TCA ArchitectsRob Nyikos!! ! Food Service Consultant, Nyikos and Associates
Middle School #20 • Construction Document Report 4
Project DescriptionMiddle School #20 is to be located on a 20.21 acre site within the planned community of Oxford Square in Hanover and will be an adaptation of the current prototype middle school design. The prototype middle school plan is a two-story building designed to accommodate a population which includes 662 students in Grades 6 thru 8, plus 40 full-time equivalent special education students, for a total of 702 students. The “Space Analysis” section of this report contains a complete listing, program size, and actual size of every space included in this middle school design. It is the intent that the design and construction of this new middle school achieve a LEED
(Leadership in Energy and Environmental Design) ‘Silver’ designation making this facility yet another ‘Green’ school for the Howard County Public School System. The 2009 version of ‘LEED for Schools’ released by the U.S. Green Building Council (USGBC) will provide the necessary goals and requirements to obtain LEED Certification.(See page 7 for Sustainable ‘Green’ Design Goals.)
Continuation of the School Design Process This Construction Document Report is intended to explain and illustrate those aspects of the Middle School #20 design which have changed since the Design Development Report.
The planning process for Middle School #20, was described in detail in the schematic design report submitted to the Board of Education (BOE) and approved on February 23, 2012.
Following approval of the schematic design, a formal schematic design submittal was sent to the Maryland State Department of Education (MSDE) and later approved by them for continuation into the design development phase.
During the design development phase, the plan had undergone some minor refinements; however, the basic design remained the same with the primary effort during the design development phase being the continued refinement and development of all spaces within the school.
Following the Board’s approval of the design development report on July 12, 2012, a design submittal was sent to MSDE and later approved for continuation into the last phase of the design process, the construction document phase.
While the proposed site and floor plans in this report are very similar to those in the design development report, much of the recent work entails the development of the ‘blueprints’ from which the school will be constructed. Much of the detailing during this phase occurs above the ceilings, in the walls, and on the roof incorporating all of the mechanical, electrical, and structural elements necessary to turn this design into a buildable set of documents.
Noteworthy refinements to the project since design development approval are noted below:
•! The list of design development phase participants on page 4 has been updated to include all ! participants involved in the construction document phase.•! The ‘Project Facts’ and ‘Project Schedule’ on page 6 have been updated to include the latest building ! square footage and project dates.• The LEED scorecard on page 7 has been updated to indicate 54 anticipated credits, two more credits
than were indicated in the design development report.•! Construction document phase site plan refinements have been noted on page 11.•! Construction document phase floor plan refinements are identified on pages 13 and 14.•! The ‘Space Analysis’ on page 20 now includes construction document phase square footages.• The ‘Cost Estimate’ on page 25 has been updated by the Construction Manager for this phase.• An ‘Emergency Plan’ has been added as an Appendix to address safety concerns for this site.
Middle School #20 • Construction Document Report 5
! ! Project Facts! ! Total size of site! ! ! ! ! ! ! ! 20.21 acres
! ! Size of forest conservation easement on site! ! ! ! 5.49 acres
! ! Useable area for school site! ! ! ! ! ! 14.72 acres
! !
! ! On-site car parking provided! ! ! ! ! ! 119 cars
! ! On-site bus parking provided! ! ! ! ! ! 17 busses
! ! Middle School Building Square Footage! ! ! ! 95,838 gsf
! ! Student capacity (662 + 40 special education students)! ! 702 students
! !! ! ! ! !
! ! ! ! !
! ! Project Schedule
! ! Schematic Planning Meetings Completed! ! ! January 19, 2012 (completed)
! ! Schematic Design presented to Board of Education! ! for Review and Approval! ! ! ! ! February 23, 2012 (completed)
! ! Design Development presented to Board of Education! ! for Review and Approval! ! ! ! ! July 12, 2012 (completed)
! ! Construction Documents presented to Board of Education! ! for Review and Approval! ! ! ! ! November 15, 2012
! ! Project out for Bids (1 month)! ! ! ! ! January 22, 2013
! ! Bids Received! ! ! ! ! ! ! February 19, 2013
! ! Construction Starts! ! ! ! ! ! ! May 1, 2013
! ! Construction Completed (16 months)!! ! ! August 15, 2014
Middle School #20 • Construction Document Report 6
Sustainable ʻGreenʼ Design GoalsIt is the intent that the design and construction of the new middle school achieve a LEED (Leadership in Energy and Environmental Design) Silver certification, making this facility a ‘Green’ school.
Simply stated, a ‘Green’ school is a building designed to conserve energy, water, and materials, thus reducing negative impacts on human health and the environment. A ‘Green’ learning environment provides natural daylight, enhanced classroom acoustics, improved indoor air quality, thermal comfort, and opportunities to integrate green features into the school's curriculum.
In order to measure and compare how ‘Green’ a building is, the U.S. Green Building Council (USGBC), founded in 1993, has developed industry standards with design and construction rating systems and guidelines for many different building types.
One such rating system is the USGBC 2009 Edition of “LEED for SCHOOLS” to which the design and construction of Middle School #20 will closely adhere. Final LEED certification levels are based on the number of credit points obtained in the “LEED for SCHOOLS” rating system. The four levels of certification from lowest to highest are: Certified, Silver, Gold, and Platinum.
We have included an ‘in progress’ LEED scorecard below which summarizes the credits most likely obtainable at this time. As the project continues to evolve, new credits may be possible while others may become increasingly difficult to engineer or too costly to provide. At this time we have identified 54 likely credits (with an additional ’8 possible credits’) allowing for the loss of some and still complying with the goal of a LEED ‘Silver’ Building.
Middle School #20 • Construction Document Report 7
Prereq 1 Prereq 2 Prereq 3 Credit 1 Credit 3 Credit 4 Credit 5
Fundamental Commissioning of the Building Energy SystemsMinimum Energy Performance Fundamental Refrigerant Management Optimize Energy Performance, 24% energy savingsEnhanced CommissioningEnhanced Refrigerant Management Measurement & Verification
Prereq 1 Credit 1 Credit 3
Water Use Reduction, 20% ReductionWater Efficient Landscaping, No Potable Use or No IrrigationWater Use Reduction, 30% Reduction
Prereq 1 Prereq 2 Credit 1 Credit 4.2 Credit 4.3 Credit 4.4 Credit 5.2 Credit 6.1 Credit 6.2 Credit 7.2 Credit 10
Construction Activity Pollution PreventionEnvironmental Site AssessmentSite Selection Alternative Transportation, Bicycle Use Alternative Transportation, Low Emitting & Fuel Efficient VehiclesAlternative Transportation, Parking Capacity Site Development, Maximize Open Space Stormwater Design, Quantity ControlStormwater Design, Quality ControlHeat Island Effect, RoofJoint Use of Facilities
Sustainable Sites Possible Credits: 11
Water Efficiency Possible Credits: 7
Energy and Atmosphere Possible Credits: 12
Materials and Resources Possible Credits: 7
Indoor Environment Quality Possible Credits: 12
Innovation and Design Process Possible Credits: 4
Prereq 1 Credit 2 Credit 4 Credit 5 Credit 7
Storage & Collection of Recyclables Construction Waste Management, Divert 75% from Disposal Recycled Content, 20% Regional Materials, 20%Certified Wood
Prereq 1 Prereq 2 Prereq 3 Credit 3.1 Credit 3.2 Credit 4.1 Credit 4.2 Credit 4.3 Credit 4.4 Credit 6.1 Credit 6.2 Credit 7.1 Credit 7.2 Credit 8.1
Minimum IAQ Performance Environmental Tobacco Smoke (ETS) ControlMinimum Acoustical Performance Construction IAQ Management Plan, During Construction Construction IAQ Management Plan, Before Occupancy Low-Emitting Materials, Adhesives & Sealants Low-Emitting Materials, Paints & Coatings Low-Emitting Materials, Flooring Systems Low-Emitting Materials, Composite Wood & Agrifiber ProductsControllability of System, Lighting Controllability of System, Thermal ConfortThermal Comfort, DesignThermal Comfort, Verification Daylight & Views, Daylight 90% of Classrooms
Credit 1.1 Credit 1.2 Credit 1.3 Credit 2
Innovation in Design, Maximize Open SpaceInnovation in Design, Green Cleaning ProgramInnovation in Design, Low Mercury LightingLEED Accredited Professional
54 Total Credits (not including 8 maybe credits)
LEED for Schools 2009 ScorecardMiddle School #20
L E E DLEADERSHIP IN ENERGY & ENVIRONMENTAL DESIGN
LEED for Schools 2009 Rating Scale:Certified 40-49 Silver 50-59 Gold 60-79 Platinum 80-112
Regional Priority Credits Possible Credits: 1
Credit 3 Regional Priority, SSc6.2
Vicinity MapThe new 20.21 acre middle school site is located within the newly planned community of Oxford Square in Hanover, Maryland. Oxford Square is located on Coca Cola Drive approximately one tenth of a mile north of the Coca Cola Drive/Route-100 intersection.
Public water, sewer, and natural gas will serve the site.
Middle School #20 • Construction Document Report 8
SE LNI
295
100
1
RKCIR
PA
DRCOCA
COLA
DRIVE
RACE
RD
HIGHTECHDR
PARK
WAY
DR
DORSEY
ROAD
FAUL
KNER
RO
AD
FORE
STAV
E
OHIOAV
E
DORSEY
RU
NROAD
SANTA BARBARAROAD
SAN
TOMAS
RD
CK
DR
AMBERTON
LOUDON
AVE
SYCAMORE
HIGHLAND
MELROSE AVE
ATHOL AVE
DOMAPLE
AVE
FOREST
AVE
MAGNO
LIA
LENN
OX A
VECE
DAR
AVE
RSEY
RD
S HANOVE
SMITH
AVE
R
WASHIN GTONBLVDTROY HILLDR
SITEHANOVER
CLE
0 1/8 1/4 1/2
scale in miles
! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! Aerial Site Photo
Middle School #20 • Construction Document Report 9
OXFORDSQUARE
DEVELOPMENT
SITE
Site Context !! ! ! ! ! !The middle school’s 20.21 acre site is located in the planned community of Oxford Square. Oxford Square is comprised of 111 acres, 33 of which are set aside for open space with the remainder being developed. There will be two separate entrance roads into Oxford Square from Coca Cola Drive, as indicated on the lower right corner of the graphic above.
Oxford Square will contain high-density residential housing, office buildings containing first floor retail and dining establishments, a community center and town meeting hall. Construction has yet to begin in Oxford Square but we have been told that ‘Phase 1’ will begin in 2013. During this phase, the developer will extend a road and public utilities to the school site from Coca Cola Drive.
The entire community, including the school site, is zoned TOD [Transit Oriented Development], therefore, all new construction within Oxford Square is required to comply with the ‘Route 1 Design Manual’ as well as Howard County’s ‘Green Neighborhood requirements’.
Refer to the next page for a more detailed description of the middle school site development.
Middle School #20 • Construction Document Report 10
Site plan graphic courtesy of Preston Scheffenacker Properties
Proposed Site Plan NotesKey features of the proposed site plan are listed below and identified by circled numbers on the following page.
1.! School bus parking for 17 busses. The bus driveway is separate from the parent drop-off driveway to ! reduce vehicular congestion on site.
2.! To provide as much car parking on site as possible, 119 parking spaces have been provided among four ! areas on the site.
3.! Parent drop-off and pick-up area adjacent to the main entrance with an ample queuing area to ! eliminate interference with the main parking lot.
4.! Service drive with emergency vehicle access to the paved play area and four staff parking spaces.
5.! Paved play area adjacent to gymnasium and cafetorium.
6.! Master planned area for future portable classrooms, if needed.
7.! Locations for stormwater management bio-retention facilities.
8.! Potential location for future outdoor classroom area.
9.! Playfields have been located adjacent to the gymnasium, cafetorium, and locker rooms, such that ! students will not have to cross vehicular roads or driveways to access.
Construction Document Phase Site Plan RefinementsThe refinements identified by letters in hexagons on the following page are the most noticeable changes since the design development phase.
A.! Added a temporary access road to allow access to the site from Coca Cola Drive during construction.
B.! Added a school marquis site sign on a masonry base.
C. Reconfigured the service area to enlarge the mechanical equipment enclosure for an additional generator and to ensure that dumpsters are at least 15 feet from the building.
D. ! Added a six foot high fence along the perimeter of the school’s property to control how pedestrian ! traffic enters and leaves the school site. The fence was recommended during a meeting where ! HCPSS staff, the Police department, Fire and Rescue department and the Office of Emergency ! Management routinely analyze school sites for potential safety hazards. See the Appendix of this ! report for the Emergency Plan that was generated as a result of the meeting.
! ! !
Middle School #20 • Construction Document Report 11
80
90
100
100
110
90
100
110
120
130
140
150
150
110
100
110
100
130
140
100
110
100
110
120
120
140
80
90
70
70
80
90
100
70
70
80
90
110
120
130
140130
130
70
8090
70
70
78
9294
98
82
84
86
88
96
112
112
106106
104
104
102
8486
88 8684
92
94
94
96
96
96
96
96
98
98
98
98
98
102
102
102
104
104
104
106
106
106
108
108
108
112112
112
114
114
122 124
128
128
132
132
134
134
136
136
138
138
142
142
144
144
146
146
148
148
150
116
116
118118
80
90
100
100
90
120
110
110
110
100
100
100
100
130
130
140
140
64
64
6464
64
66
66
66
66
68
68
68
68
68
72
72
68
68
68
68
72
72
72
74
74
76
76
76
78
78
78
82
82
82
84
84
86
86
88 92
92
94
94 96
96
96
98
96
94
92
102
102
104
104
104
104
104
106
106
106
108
108
112
114
114
116
118
128
128
132
132
132
134
134
134
136
136
138
138
142
142
144
144
146
146
148
118
100
110
70
100
80
66
66
66
66
114
112108
110
106
100
114
112
102100
90
84
86
88
88
92
94
9496
96
98
98
98
100
102
12812
6
100
98
98
86
126
100
110
110
120
110
116
116
120
120
100
90
110
86
116
116
116
104
114
106
94
94
108
10211
6116
112
92
88
130' x 275'PLAYFIELD
MIDDLE SCHOOL#20
95,838 gsf
180' x 300'PLAYFIELD
75' x 185' PLAY AREA
PARKING 'B'
PARKING 'C'
SWM FACILITY
FUTURE OUTDOOR CLASSROOM
PUBLIC FORESTCONSERVATION
EASEMENT(SHADED)
5.49 ACRES
20' PUBLIC UTILITY EASEMENT
50'
LANDSCAPE EASEMENT
RESIDENTIAL(4/5 STORY)
RESIDENTIAL(3 STORY)
ST
GEOTHERMAL WELL FIELDFOR SCHOOL
ST
20' STORM DRAINEASEMENT
(4) FUTURE PORTABLE CLASSROOM
PATAPSCO VALLEY BUSINESSCENTER PROPERTY
50' COLONIAL PIPELINECOMPANY GAS UTILITY
EASEMENT
PUBLIC WATER LINE TO SCHOOL
250' SOFTBALLFIELD #1
SERV
ICE
AREA
PARKING 'A'PARENT DROP
250' SOFTBALLFIELD #2
PATAPSCO VALLEY BUSINESSCENTER PROPERTY
10'PRIVATE 10' PATHWAY EASEMENT
ENVIRONMENTAL STUDY AREA
OXFORD SQUARECOMMUNITY CENTER
BUS LOOP
17
1
HC
HC HC HC HC
30' USE SETBACK
30' USE SETBACK
SWM
SWM
UNDERGROUND RAINWATER STORAGE TANK (TYP. OF 2)
BIKE RACKS
BIKE RACKS
FIRE HYDRANT
17
17
7919
4
FLAG POLE
GRASS PAVERS
TEMPORARY ACCESS ROAD
6' H. FENCE
86
1
4
27
3
5NUMBERS IN CIRCLES AND LETTERS IN HEXAGONS REFER TO SITE PLAN NOTES ON PAGE 11.C
9
7
B A
D
0 50 10025
• Middle School #20 Construction Document Report
Proposed Site Plan12tca architects
PUBLIC FOREST CONSERVATION EASEMENT:
USABLE AREA FOR SCHOOL SITE:
TOTAL:
5.49 ACRES
14.72 ACRES
20.21 ACRES
ZONING: TOD (TRANSIT ORIENTED DEVELOPMENT)
SITE NOTES FOR OXFORD SQUARE SITE - PARCEL 'B'
CAR SPACES =
BUS SPACES =
PARKING TABULATIONS 119
17
Cr.7 Cr.8 Cr.9Cr.6 Cr.10
Seminar 2
Sci.Lab 4
Prep. Sem.S
Cr. 17
T
Open toMedia Center
Below
Gifted & Talented
7th Grade
WorldLanguage
SS
Roof Below
GB
TS
IDFELEC.
V
Seminar 1
Gen. Stor.
CC
Cr.2 Cr.3
Kiln
Related Services
Art
Media Center Prep Sem.S
S.E.Res. 1
Pupil
Conf.Records
Off. Off.
S
Elec.
S
SE T
6th GradeStor.
Main Office
A.P.Conf.Princ.
WkrmS
T
T
Health Suite
Off.CotCot
Store
T
T
S
Staff Lounge
LobbyCan
Mech.
Electrical
KitchenDry Stor
Dish
Ensem.Cust. Off.
S
Off.
CC
TT
R
F
Stage
Cafeteria
Activity Rm.S
Gymnasium
Stor
B
G CC
Stor
PlanT
LaundryTwl
Boys' Lkrs
T
ShowerShower
T
Girls' Lkrs
R/P Stor
R/P Ext. Stor.
ComputerLab
MDFTech
Resource
MediaProduction
Off.
Sci.Lab 3
Sci.Lab 2
Sci.Lab 1
S
Planning(Cr. 19)
Cr.4
Cr.5Cr.1
6th Grade
SMedia Stor
Eq.
Lobby
Ramp
GuidanceReception
Service Area
Twl
TT
R/P Off.R / P Activity
Room
R/PS
T
Stor
HomeEconomics
TechnologyLab
S Res.S
ProductionLab
Choral Room
Band Room
Stor.
P-1
P-2
P-3
Inst. Stor.
Plan
IDFVol./Comm.
Equip. Stor.
Health Cr.
S
T
T
S.E.Conf.
GB
V
Mech. Header
DUST
PrincSec
Cust. Stor
TREAT/ EXAM
U
0 16 328
• Middle School #20 Construction Document Report
Proposed First Floor Plan
13tca architects
CC = CUSTODIAL CLOSETCR = CLASSROOMS = STORAGE ROOMT = TOILETIDF = INTERMEDIATE DISTRIBUTION FRAME ROOMMDF = MAIN DISTRIBUTION FRAME ROOM
ABBREVIATIONS
Floor Areas
First FloorSecond Floor
Total School AreaRec. and Parks
Total Building
65,908 s.f.27,138 s.f.
93,046 s.f.2,792 s.f.
95,838 s.f.
= ADMINISTRATIVE SPACES
LEGEND
= GRADES 6-8
= ARTS & TECHNOLOGY
= SPECIAL EDUCATION
= CENTRAL SUPPORT SPACES
= BUILDING SERVICES
= SCIENCE LABS
= RECREATION AND PARKS
FLOOR PLAN NOTECHANGED THE FLOOR FINISH FOR ALL CORRIDORS AND THE CAFETERIA FROM VINYL COMPOSITION TILE (VCT) TO POLISHED CONCRETE. THE USE OF POLISHED CONCRETE WILL SIGNIFICANTLY REDUCE MAINTENANCE COSTS BY ELIMINATING THE NEED TO PROVIDE CHEMICALS, SUPPLIES AND LABORERS TO STRIP AND WAX VCT IN THESE SPACES EACH SUMMER.
REPLACED THE PULL DOWN ROLLING GRILLES WITH EGRESS DOORS THAT ALLOW THE BUILDING TO BE ZONED FOR AFTER HOURS USE. PULL DOWN ROLLING GRILLES HAVE BEEN REMOVED AS REQUIRED BY HOWARD COUNTY DEPARTMENT OF LICENSES AND PERMITS. EXISTING GRILLES CREATED A POTENTIAL DEAD END CONDITION IF OCCUPANT WAS ON THE PRIVATE SIDE OF THE GRILLES.
RE-CONFIGURED THE CUSTODIAL TOILET ROOM TO COMPLY WITH THE 2010 ADA STANDARDS.
ENLARGED TOILET ROOM TO COMPLY WITH THE 2010 ADA STANDARDS. REPLACED COAT CLOSET IN THE PRINCIPAL'S OFFICE WITH A TALL WARDROBE CABINET.
3
4
1
2
3
4
1
2 1TYP. FOR ALLCORRIDORS
Cr.7 Cr.8 Cr.9Cr.6 Cr.10
Seminar 2
Cr.14 Cr.13Cr.15
Sci.Lab 4
Sci.Lab 5
Prep. Sem.S
Cr. 17
T
Open toMedia Center
Below
S.E.Resource 2
Gifted & Talented
7th &8th
Stor. Planning(Cr. 18)
7th Grade
8th Grade
WorldLanguage
SS
Roof Below
Cr.12 Cr.11
GB
BG
TS
IDFELEC.
V
Seminar 1
Gen. Stor.
Cr. 16(Sci. Lab 6)
SE Stor.
S.E.Resource 3
S
CC
Kiln
Art
S
SE TElectrical
Kitchen
Dry Stor
RCafeteria
Gymnasium
Stor
Stor
PlanT
LaundryTwl
Boys' Lkrs
T
ShowerShower
T
Girls' Lkrs
R/P Stor
R/P Ext. Stor.
Sci.Lab 3Planning(Cr. 19)
Twl
Equip. Stor.
Health Cr.
S.E.Conf.
Mech. Header
S
0 16 328
• Middle School #20 Construction Document Report
Proposed Second Floor Plan
14tca architects
CC = CUSTODIAL CLOSETCR = CLASSROOMS = STORAGE ROOMT = TOILETIDF = INTERMEDIATE DISTRIBUTION FRAME ROOMMDF = MAIN DISTRIBUTION FRAME ROOM
ABBREVIATIONS= ADMINISTRATIVE SPACES
LEGEND
= GRADES 6-8
= ARTS & TECHNOLOGY
= SPECIAL EDUCATION
= CENTRAL SUPPORT SPACES
= BUILDING SERVICES
= SCIENCE LABS
= RECREATION AND PARKS
Floor Areas
First FloorSecond Floor
Total School AreaRec. and Parks
Total Building
65,908 s.f.27,138 s.f.
93,046 s.f.2,792 s.f.
95,838 s.f.
Upper Gymnasium
Roof Below
Roof Below
Roof Below
2
FLOOR PLAN NOTE
1TYP. FOR ALLCORRIDORS
FLOOR PLAN NOTECHANGED THE FLOOR FINISH FOR ALL CORRIDORS FROM VINYL COMPOSITION TILE (VCT) TO POLISHED CONCRETE. THE USE OF POLISHED CONCRETE WILL SIGNIFICANTLY REDUCE MAINTENANCE COSTS BY ELIMINATING THE NEED TO PROVIDE CHEMICALS, SUPPLIES AND LABORERS TO STRIP AND WAX VCT IN THESE SPACES EACH SUMMER.
ADDED SKYLIGHTS TO CLASSROOM 15 TO PROVIDE ADDITIONAL NATURAL DAYLIGHT.
1
2
Floor Plan NarrativeIn addition to the basic features of the layout listed on page 12, Middle School #20 will maintain the following spatial relationships developed for the original prototype design:
Access and Circulation
! Entrances
The main entrances are clearly marked for visitors by both their location and by the architectural significance of the projecting main stairwell.
Entrances have been arranged to distribute student traffic during arrival and departure times, to meet code egress requirements, and to permit easy access to the gym and cafeteria for after-hours activities. Particular attention has been paid to providing an adequate number of doors in the heavily populated classroom areas for dismissal time.
! Corridor Arrangement
A conscious effort was made to develop a corridor pattern which is clear-cut in its arrangement and easy to supervise. Stairs have been located at the four corners of the two-story wing. As noted, an elevator has been provided very close to the main entrance for the use of handicapped persons and for the easy movement of furniture and equipment.
The main interior stair at the front of the building is next to the main entrances and is immediately adjacent to the administrative area.
Student Lockers have been located along corridor walls throughout the classroom areas in response to a decision by the original planning committee that concentrated areas (pods) of lockers be avoided. Lockers have been located on just one side of corridors wherever possible to minimize congestion.
Student Restrooms are located on both floors near stairways in all three grade level areas and adjacent to the cafeteria and gymnasium entrances. The cafeteria/gymnasium lobby restrooms are also intended to be used during after-hours activities. Teachers' toilets have been located on both floors of the classroom wing and adjacent to the staff lounge.
The administrative area has a central location adjacent to the main entrance with a view of the parent drop-off area. This area is adjacent to the health suite and to the staff lounge and workroom. Both the health suite and the staff lounge have separate entrances from main corridors. The teachers' mail boxes, which will be in the workroom, can be conveniently serviced from the administrative area. Proximity to the cafeteria was also a consideration in the location of the staff lounge.
A volunteer/community room has been placed in a centralized location convenient to the front entrances.
The guidance suite is located in an easy-to-reach location, convenient to the office area, yet with a distinct identity.
Classrooms are located in the two-story portion of the school and arranged so that each grade level has its own distinct area. Most classrooms are located on exterior walls with windows.
As noted, science laboratories have been placed on both levels convenient to all three grade levels. Four of the five labs are adjacent to prep rooms and project/seminar rooms.
Middle School #20 • Construction Document Report 15
Floor Plan Narrative (continued)
Teacher planning rooms, special education classrooms, seminar rooms, and storage rooms have been distributed in the two-story classroom wing.
A related services therapy room, special education conference room, and a handicapped accessible toilet have been located on the first floor of the classroom area.
The media center is the symbolic, as well as the actual center of the school. It is located on the first floor in the middle of the classroom area and is visible from the second floor corridors above. Natural daylight from above brightens this dramatic two-story high space and the rooms surrounding it on both floors. The media center can be entered from all three adjacent corridors to encourage student use.
The computer lab and technology resource room can be entered and monitored from the media center, to which they have a strong connection. Both rooms can also be entered from the adjacent corridor.
The gifted and talented resource room has a central location in the second floor classroom area overlooking the media center.
The art classroom and the health classroom have been located on the first floor, near other related-arts spaces and are easily reached from all classroom areas. Both of these rooms are located on an exterior wall with windows.
The world language classroom has been placed in the center of the second floor classroom area.
The technology education rooms, home economics classroom, music suite, and recreation and parks suite have been located on the first floor away from the quiet two story classroom wing, yet are easy to access both during the school day and for after hours use.
The gymnasium has been located so that it can be entered from the classroom side of the school or from a lobby which also serves the cafeteria entrance. Direct access has been provided from the gym to the outdoor paved play area and to the playfields. The gym and the adjoining activity room have been placed for easy, but controlled, access during after-hours activities. Locker rooms are designed to be entered from inside the gymnasium for visual control by physical education teachers and also to have direct access to the outside.
The cafeteria has been located for easy access by after-hours users and in close proximity to the music rooms for use of the stage. For after-lunch recess there is direct access to the outdoor paved play area and there is convenient access to the gymnasium and to restrooms. It was important to the original planning committee that there be visibility from the cafeteria to the paved play area to help with lunch time supervision. Kitchen serving lines are entered from inside the cafeteria and there is convenient access to the service area for trash removal. An operable wall has been provided at the front of the stage to permit use of this area as a teaching station during lunch periods. A ramp has been provided for handicapped access to the stage.
The kitchen has a full-preparation arrangement and is convenient to the service area for deliveries and trash removal.
The custodial areas are placed on a main corridor near the service entrance and adjacent to the mechanical and electrical rooms. Custodial closets have been distributed throughout the school and sized to accommodate the latest HCPSS custodial services requirements.
The service area has direct corridor access to the center of the school, allowing for convenient deliveries and trash removal.
Middle School #20 • Construction Document Report 16
Exterior Building Changes
The community of Oxford Square will include residential housing with a traditional design aesthetic. That being said, and after working through several iterations of the exterior design with the developer, traditional building materials and design elements will be incorporated into the exterior facade of the school for compatibility with the surrounding community.
The exterior walls will be comprised of several colors of modular face brick (2-1/4”H. x 8”L.) in running bond pattern where the original prototype design utilized closure sized face brick (4”H. x 8”L.). Steep slope roof surfaces have been added to the design and will be covered with prefinished standing seam metal roofing where indicated above the main entrance stair tower and the recreation and parks activity room. The parapet walls at the flat roof areas will be capped with an exterior insulation finish system to provide the appearance of a precast concrete cornice. Finally, the exterior windows will be prefinished aluminum (project-out sash) with mullion subdivisions with rounded window heads and the exterior entrance frames will be a prefinished aluminum storefront product.
The main elevation comparison on the following page illustrates the significant transformation which has taken place to the ‘skin of the building’ from the Folly Quarter Middle School prototype design.
Middle School #20 • Construction Document Report 17
• Middle School #20 Construction Document Report
Building Elevations
18tca architects
Folly Quarter (Prototype) Elevation
East (Right Side) Elevation
South (Front) Elevation
Middle School #20 • Construction Document Report 20
Space AnalysisMiddle School #20Net areas indicated in square feet.
Middle School Prototype (Folly Quarter) Schematic DD CD
Phase Phase PhaseACTIVITY/PROGRAM AREAS TOTAL NET TOTAL NET TOTAL NET TOTAL NET
ADMINISTRATIVE COMPLEXPrincipal's Office (incl. toilet) 1 253 253 243 250Assistant Principal's Office 1 180 180 178 178Conference Room 1 193 193 191 191Workroom (includes 2 storage rooms) 1 447 447 508 508Reception Area (includes coat closet) 1 295 295 295 295Volunteer/ Community Room 1 157 157 157 157Secretarial 1 450 450 327 327Principal's Secretary 0 0 0 99 99School Store 1 62 62 61 61
2037 2037 2059 2066
ARTArt Studio (includes kiln room & stor.) 1 1579 1579 1569 1529
1579 1579 1569 1529
CAFETERIA/FOOD SERVICECafeteria 3517 3542 3535 3535Stage (includes ramp) 1213 1233 1214 1205Kitchen and related spaces 2405 2405 2402 2402
7135 7180 7151 7142
COMPUTER RELATED INSTRUCTIONComputer Lab 1 717 717 691 691
717 717 691 691
CUSTODIAL AREASCustodial Office (includes toilet) 1 189 189 189 192Work Storage Area 1 60 60 60 56General School Storage 1 187 291 (2) 275 (2) 275 (2)Outside Equipment Storage 1 131 131 128 128Decentralized Custodial Closets 4 77 77 95 (2) 98 (2)
644 748 747 749
Middle School #20
Middle School #20 • Construction Document Report 21
Middle School Prototype (Folly Quarter) Schematic DD CD
Phase Phase PhaseACTIVITY/PROGRAM AREAS TOTAL NET TOTAL NET TOTAL NET TOTAL NET
WORLD LANGUAGEWorld Language (includes storage) 1 906 906 857 857
906 906 857 857
GENERAL ACADEMIC AREASClassrooms 17 12821 13212 (17) 13028 (17) 12994 (17)Storage 3 368 612 (3) 541 (4) 535 (4)Planning Rooms 3 1162 1471 (2) 1457 (2) 1433 (2)Seminar Rooms 3 1416 808 (2) 764 (2) 764 (2)Second Floor Workroom 1 304 0 0 0
16071 16103 15790 15726
GIFTED & TALENTEDGifted & Talented Resource Room 1 741 741 751 751Storage 1 79 79 77 77
820 820 828 828
GUIDANCESecretarial/ Reception (incl. closets) 1 384 384 360 360Counselors' Offices 2 273 273 295 295Record Storage 1 219 219 219 219Conference Room 1 250 250 250 250Pupil Services Office 1 109 109 109 109
1235 1235 1233 1233
HEALTH SUITELavatories 2 113 113 113 113Waiting 1 300 300 168 168Cot Rooms 2 180 180 182 182Walk-in Closet 1 36 36 33 33Treatment/Exam 0 0 0 95 95Office 1 81 81 98 98
710 710 689 689
HEALTH EDUCATIONHealth Education Classroom 1 791 791 781 797
791 791 781 797
HOME ECONOMICSHome Economics Classroom (inclu. stor.) 1 1667 1667 1660 1658
1667 1667 1660 1658
Middle School #20
Middle School #20 • Construction Document Report 22
Middle School Prototype (Folly Quarter) Schematic DD CD
Phase Phase PhaseACTIVITY/PROGRAM AREAS TOTAL NET TOTAL NET TOTAL NET TOTAL NET
MEDIA CENTERMain Reading Room 1 3334 3334 3277 3268Technology Resource Room 1 401 401 401 401Office/Work Space 1 130 130 130 130Media Production 1 339 339 339 339Storage Area (incl. distribution equip.) 1 543 543 508 506
4747 4747 4655 4644
MUSICChoral Room 1 979 979 996 996Band Room 1 1347 1347 1391 1391Ensemble Room 1 276 276 276 276Instrument Storage 1 189 189 195 195Materials Storage 1 79 79 79 79Teacher Planning 1 133 133 141 141Practice Rooms 3 141 141 141 141
3144 3144 3219 3219
PHYSICAL EDUCATIONGymnasium 1 5615 5615 5615 5631Shower Areas 2 276 276 202 202Lockers 2 1148 1148 1139 1139Laundry 1 115 115 114 114Storage (Large Equipment) 1 320 320 313 313Storage (Small Equipment) 1 88 88 88 88Storage (Towel) 2 120 120 110 110Office with Shower/Toilet 1 262 262 266 266Activity Room 1 777 777 777 777Platform Storage 1 86 86 86 86
8807 8807 8710 8726
SCIENCEScience Laboratories 5 5597 5597 5528 5532Preparation Room 3 407 294 (2) 294 (2) 292 (2)Storage Room 2 165 165 165 157Project (Seminar) Room 2 308 308 308 308
6477 6364 6295 6289
Middle School #20
Middle School #20 • Construction Document Report 23
Middle School Prototype (Folly Quarter) Schematic DD CD
Phase Phase PhaseACTIVITY/PROGRAM AREAS TOTAL NET TOTAL NET TOTAL NET TOTAL NET
SPECIAL EDUCATIONClassroom & Instructional Spaces 3 1218 1184 1240 1240Related Services Therapy (incl. stor.) 1 621 485 450 450Conference Room 1 230 364 404 402Storage 3 366 269 (3) 216 216Handicapped Accessible Toilet 1 85 85 86 86
2520 2387 2396 2394
STAFF LOUNGEStaff Lounge (includes 2 toilets) 1 680 680 547 547
680 680 547 547
TECHNOLOGY EDUCATIONTechnology Laboratory 1 1356 1356 1187 1187Production Laboratory 1 855 855 953 950Storage Rooms 2 259 259 298 300Audio/Video Production Laboratory 1 108 108 0 0Dust Room 0 0 0 89 90Resource Center 1 72 72 77 77
2650 2650 2604 2604
Space Analysis Summary
TOTAL NET SQ. FOOTAGE: 63337 63272 62481 62388
GROSS AREA FACTOR (Walls, Circulation, Toilets, Stairs,Mech./Elec. Rms., etc.)
Efficiency = Net/Gross 29270 29335 30474 30658Efficiency = 68% 68% 67% 67%
Total for Middle School #20 92607 92607 92955 93046Gross Square Footage
See following page for Recreation and Parks area tabulations
Middle School #20
Middle School #20 • Construction Document Report 24
Recreation and Parks Space Analysis SummaryMiddle School #20
Middle School Prototype (Folly Quarter) Schematic DD CD
Phase Phase PhaseACTIVITY/PROGRAM AREAS TOTAL NET TOTAL NET TOTAL NET TOTAL NET
RECREATION AND PARKSActivity Room 1 1972 1972 1968 1929 Office 1 113 113 111 111 Toilet 1 33 33 47 47 Storage Room 1 83 83 121 121 Kitchen Area 1 65 65 65 65Storage Room (in Cafeteria) 1 84 84 84 82Storage Room (Ext. Access) 1 170 170 174 174
TOTAL NET SQ. FOOTAGE: 2520 2520 2570 2529
GROSS AREA FACTOR 389 389 222 263Efficiency = Net/Gross (Walls & Circulation) 87% 87% 92% 91%
Total for Recreation and Parks 2909 2909 2792 2792
Total for School (see previous page) 92607 92607 92955 93046
Grand Total for Middle School #20 95516 95516 95747 95838Gross Square Footage
Middle School #20
Construction Cost EstimateMiddle School #20! !
! ! ! ! ! ! ! Schematic! ! DD! ! CD! ! ! ! ! ! ! Phase! ! Phase! ! Phase
Site Work! ! ! ! ! ! $ 2,932,385! ! $ 4,477,406!! $ 2,779,218
Building! ! ! ! ! ! $ 23,651,223! $ 23,386,332! $ 23,601,799_______________________________________________________! ____________ ___________Total for Project! ! ! ! ! $ 26,583,608! $ 27,863,738! $ 26,381,017
Add-Alternate Options:
1. Furnish and install dust collection system in Production Lab ! ! ! + $ 20,0002. Furnish and install telescoping bleachers in Gymnasium ! + $ 33,1203. Install playfield irrigation and rainwater harvesting systems + $ 424,8644. Substitute LED site pole lights for base bid metal halide fixtures ! + $ 30,0005. Substitute LED exterior building lights for base bid fixtures! + $ 24,300_________________________________________________________ ! ____________Total for Project (including Add-Alternate Options)! ! ! $ 26,913,301
Notes • Construction cost estimate was prepared by the construction manager, J. Vinton Schafer & Sons, and
assumes that bids will be received in February 2013.
•! Construction cost includes cost of food service equipment.
• Estimate includes a design development phase cost estimate contingency of +5%.
•! Estimate assumes non-wage rate pricing. (Add +9% for wage rate.)
•! Estimate does not include a project contingency, A/E design fees, CM construction fees, and ! other related costs.
•! Estimate includes a cost contingency for constructing a LEED ‘Silver’ design.
Middle School #20 • Construction Document Report 25
Building Location
Middle School #20 has been placed at the most remote location from the railroad tracks on the school site. The distance between the school and the tracks is over 1500 feet. There is a significant elevation difference between the tracks and the school which is as much as 20 feet lower than the school. In addition to the change in elevation, there are other natural barriers between the school and the railroad tracks, such as a stream which is located north of the school site and a large wooded area to the north and west which will be preserved as part of the forest conservation agreement. Built structures will also be located between the school and the railroad tracks such as the existing warehouse north of the site and the future construction of community buildings to the west of the school.
Emergency Plan - Middle School #20
Middle School #20 • Construction Document Report A-1
Emergency Access
The school site can be reached either directly from Route 100 onto Coca Cola drive or from Route 1 via backroads that lead to Hi Tech Road which connects to Coca Cola Drive north of Banbury Drive. Once on Coca Cola Drive, there are two entrances into the Oxford Square development with connecting roads to the school site, therefore, providing two paved options for vehicles at any given time.
Evacuation Routes
Members of County agencies (Police, Fire and Rescue, Office of Emergency Management) have reviewed evacuation from the site via the access routes previously noted. Building evacuation locations and reunification areas will have the annual review that all school plans must undergo. The annual reviews will take into consideration any plan changes that need to be implemented due to future community development. This would include walking routes, traffic patterns and potential alternate shelter areas.
Building design
To provide a shelter-in-place facility in the event of potential pollutants being located directly outside of the building, the mechanical engineer has provided a HVAC system which will negate the possibility of pollutants being entrained into the building through the outdoor air intakes associated with the facility’s heating, ventilating, and air-conditioning (HVAC) equipment. This will be accomplished by utilizing passive and active safety measures included within the facility’s mechanical design to help safeguard the occupants during such a situation. These measures are described in greater detail in the following paragraphs.
The passive safety measures include both two-stage filtration within all rooftop units, as well as appropriate setbacks for all rooftop equipment from the roof’s edge. All rooftop units will be equipped with 2-inch thick MERV 8 pre-filters and 4-inch thick MERV 13 final filters. In addition, a minimum setback of 10-feet from the roof’s edge will be maintained for all rooftop equipment, helping to minimize entrainment of pollutant sources located at grade. Both of these items are routine safety measures for HCPSS school projects.
Active safety measures include an emergency outdoor air shut-off switch located within the administration area. When this switch is activated, the building automation system will close the outdoor air dampers associated with all rooftop unit equipment, allowing the units to still operate and function under a recirculation mode.
In addition, the building has on-site electrical generators and control logic provided as part of the building automation system that closes the outside air intakes to HVAC systems under a shelter condition. The active control measure described above is beyond the typical shelter scenario implemented on typical HCPSS projects.
Finally, all the windows, aluminum storefront and exterior doors installed at this school will comply with strict performance requirements to minimize outside air infiltration. Products are tested in accordance with American Standard Test Method (ASTM) E283 to determine compliance for minimal rate of air infiltration through exterior windows, curtain walls and doors.
Emergency Plan - Middle School #20
Middle School #20 • Construction Document Report A-2
Potential hazards
The rail line adjacent to the school property carries the same products typically transported over major highways. There is a voluntary ban on products with high hazard toxic/poison inhalation hazards due to the rail line passing through Washington D.C. Schools have emergency procedures in the event of outside environment contamination.
Pedestrian traffic crossing tracks is a potential hazard, therefore fencing and warning signage will be provided along the perimeter of the school site property.
Emergency responders
There is currently a fire and rescue station just 3 1/2 miles away from the school site at the intersection of Dorsey Road and Ridge Road. In addition, a second (new) station is scheduled to open in 2015 at the intersection of Route 1 and Montevideo road, which will also be 3 1/2 miles away.
(see image to right)
Summary
The location of the school site does not present exposures that require specific design alternations to the building. It is important that the HVAC system be capable of shutting down and windows closing to prevent a minimal amount of outside air into the building in the event of a shelter-in-place scenario. The HCPSS emergency plan template addresses the potential exposures currently anticipated for a school at this site. It is understood that the surrounding site will be developed after the construction of the school and will consist of commercial and residential buildings. Plans will be flexible to adjust to those changes to the surroundings and the above agencies will be consulted for input during the annual emergency plan review and appropriate changes will be incorporated.
Emergency Plan - Middle School #20
Middle School #20 • Construction Document Report A-3
100
1
RK
CIR
PA
DRCOCA
COLA
DRIV
E
RACE
RD
HIGHTECHDR
PARK
WAY
DR
DORSEY
ROAD
RACE
R
OAD
FORE
STAV
E
OHIOAV
E
DORSEY
RUN
ROAD DO
FOREST
RSEY
RD
WASHIN GTONBLVD
SITEHANOVER
CLE
BANBURY DRIVE
0 1/8 1/4 1/2
scale in miles
MEADOWRIDGE
ROAD
95
LOUDEN AVE
MONTEVIDEO ROAD
WRIG
LEY
AVE
WATERLOO ROAD
ARUNDELMILLS
HANOVER RD
HANO
VER
RD
295
BALT
IMORE
- W
ASHI
NGTO
N PA
RKW
AY
PROPOSEDFIRE ANDRESCUESTATION
#12
EXISTINGFIRE ANDRESCUESTATION
#21
DORSEY RD
RIDG
E R
D
ARUNDEL MILLSBLV
D
WRIGHT RD
DORCHESTER BLVD