thomas schmidt, global product manager phase shifters ... · with unbalanced load sharing of...
TRANSCRIPT
Phase-shifting transformersThomas Schmidt, Global Product Manager Phase Shifters, Transformer Days 2011
Phase shifting transformersOptimized utilization of contracted transmission capacity
© ABB Group July 11, 2011 | Slide 1
Benefits to youHi h i i d li bilitHigher revenues, savings, increased reliability
How does a utility earn money?
Generation of electrical powerGeneration of electrical power
Transmission of electrical power
Distribution of electrical power Distribution of electrical power
Trading of electrical power
© ABB Group July 11, 2011 | Slide 2
Why phase-shifting transformers?C t f ffi i t AC t k tiComponents for efficient AC network operation
Phase-shifting transformers (PST) enablers for the increased use of renewable energy
PSTs optimize the utilization and/or losses of existing transmission lines
PST b l t th tf li f FACTS d i PSTs belong to the portfolio of FACTS devices
PSTs are the valve in your grid
PSTs may manage n-1 situations
© ABB Group July 11, 2011 | Slide 4
Why phase-shifting transformers?E bli th f blEnabling the use of renewable power sources
Transport of large amounts of electrical power over long distances will play an important role in achieving European goals for energy efficiency and for the use of renewablesgoals for energy efficiency and for the use of renewables
Bulk HVDC transmission will change power flow patterns in the supplied AC gridsthe supplied AC grids
Increased injection of independent, often fluctuating renewable power
Consequential AC transmission bottlenecks need to be managed PSTs!
Permits for new transmission corridors are difficult to obtain
© ABB Group July 11, 2011 | Slide 5
Examples for changes in load flow around GermanyI t ti b t t iInterconnections between countries
Wind
Congestion of North – South Corridor
Changed load pattern due to nuclear power reduction
Wind
Wind CoalWindUnscheduled load of flows in Belgium
Congestion of East –West Corridor
Nuke
© ABB Group July 11, 2011 | Slide 6
Power flow control with phase-shifting transformersS ll l li tiSmaller scale applications
Additional infeed into urban network - new generation pattern
New power flows in EHV network New power flows in EHV network cause angle difference at infeeds to municipal networks
N d t bl k iti1 > 2 2
G GG
Need to block parasitic power flow and overload due to transmission angle differences in feeding network(s)
1 2 2Cables dimensionedfor radial flow
feeding network(s)
Generator has contracts with two utilities
Defined sharing of real power to different systems/customersG
© ABB Group July 11, 2011 | Slide 7
Power flow control with phase-shifting transformersO ti i ti f l d h i d t i i itOptimization of load sharing and transmission capacity
Two synchronous systems.
Transmission lines with different
VS , S VL , Lwith different impedances e.g. overhead / cable or 400 kV / 110 kV.
PG LTransmission angle
P
GG
L
Transmission angle
difference S - L
drives power flow with unbalanced load sharing of linessharing of lines.The low impedance line is overloaded, limiting the total transmission capacity of the corridor.
PST impose an additional circulating current, thus i i th
LL L
of the corridor.
Pimproving the balance of power flows.The total transmission capacity increases
GP
© ABB Group July 11, 2011 | Slide 8
increases.
Typical applications for PSTs
Avoid transmission line overloading in normal operation
Avoid post-contingency transmission line overloads
Increase N-1 secure capacity of transmission corridors
Control unscheduled load flowsControl unscheduled load flows
Keep load flows on contract paths
Minimize overall losses in the network Minimize overall losses in the network
© ABB Group July 11, 2011 | Slide 9
Power flow control with phase-shifting transformersPh hifti t f fl t llPhase shifting transformers are power flow controllers
)sin( LSLS
XVVP
XLS
X
VS-VLTh h l
V
I The phase angle
(equivalent to quadrature voltage) between two
VLVS
S - L +
systems determines the power exchange
)i ( LSVVPX XT
S L
)sin(
LST
LS
XXPX
LS
© ABB Group July 11, 2011 | Slide 10
TechnologyPST P i i lPST Principle
V1S
V2S
V1L
V
V3S
V2S
V3L
V2L
Starting with a symmetrical three-phase system with a certain load flow A PST shall be used to control the load flowThe PST takes a fraction of the two neighbor phases voltageCombines them as a difference voltageWhich is then injected into the third phase
© ABB Group July 11, 2011 | Slide 11
Example: TERNA RondissoneI N 1 t i i itIncrease N-1 secure transmission capacity
Customer need
Increase N-1 secure import capacity to Italy
ABB response
Support by preliminary PST designs for system study and specification
Support for protection and control engineering
Supply of 2 x 1630 MVA PSTs, protection and control for PST and bypass bays, integration of > 50 heritage bays into MMIinto MMI
Customer benefits
Import capacity increased by approx 1000 MW Import capacity increased by approx. 1000 MW
© ABB Group July 11, 2011 | Slide 12
Example: 1630 MVA, 400 kV / 400 kV, +18°C
© ABB Group July 11, 2011 | Slide 13
Example: Municipality of Ulm, GermanyF fl t t t thForce power flow onto contract path
Customer need
Maximize power supply via infeed with low transmission fee, but limit to 80 ± 0.5 MW
Suppress transfer flows through the city’s cable network
ABB response
Support with realistic PST data for system studies
Help with specification of PST and control system
Delivery of 100 MVA, 7° PST with very fine steps
Viertelstundenwerte vom 25.11.2005 - 1.12.2005
30
40
50
60
70
80
90
Customer benefits
Transmission fees to EHV grid operator absolutely
0
0
20
-11-200500:00:00
26-11-200500:00:00
27-11-200500:00:00
28-11-200500:00:00
29-11-200500:00:00
30-11-200500:00:00
01-12-200500:00:00
02-12-2000:00:0
Zeit
minimized
Pay-back in 18 months!
© ABB Group July 11, 2011 | Slide 14
ReferencesE i ll d i PST j tEconomically driven PST project
Municipal utility of Ulm, DE
EnB Supply from EnBW via
three 110 kV substations
One line leased with very
EnBW
~ 0 MW
One line leased with very favourable conditions up to 80 MW
UW Ost
~ 0 MW
Incentive for PST: savings in transmission feesSWU
UW West
UW SüdDellmensingen
0 – 80 MW
© ABB Group July 11, 2011 | Slide 15
Example: Municipality of UlmP b k i 2 f ll l it ti f t t thPay-back in < 2 years, full exploitation of contract path
Viertelstundenwerte vom 25.11.2005 - 1.12.2005
90
15 min values 25.11.2005 - 1.12.2005
70
80
n M
W
Without PSTWith PST
” in
MW
50
60
ellm
ensi
ngen
inow
“Sou
th
20
30
40
Wirk
leis
tung
Dal
pow
er fl
o
0
10
20
Rea
025-11-2005
00:00:0026-11-2005
00:00:0027-11-2005
00:00:0028-11-2005
00:00:0029-11-2005
00:00:0030-11-2005
00:00:0001-12-2005
00:00:0002-12-2005
00:00:00
ZeitTime
© ABB Group July 11, 2011 | Slide 16
Example: Municipality of Ulm100 MVA 110 kV / 110 kV 7° i 32 t100 MVA, 110 kV / 110 kV, +7° in 32 steps
Two active parts
Single tank
© ABB Group July 11, 2011 | Slide 17
References – Power flow control on merchant lineMATL L thb id C d 2005MATL Lethbridge, Canada, 2005
© ABB Group July 11, 2011 | Slide 18
Specifying a phase-shifting transformer
Each unit is engineered to its specific purpose!
Physical size and cost depends on throughput power and angle regulation range
Angle regulation range to be specified by load flow studies
Angle increments, short circuit impedance to be determined from system requirements
Protection and control of PSTs has special requirements
It is highly recommended to contact your PST supplier early during the system specification stage!
© ABB Group July 11, 2011 | Slide 19
ABB phase-shifting transformer solutions
Center of Competence for PSTs in Bad Honnef since 2000
Wide range of experience:
100 MVA …1630 MVA
110 kV …400 kV
+ 7°…. ± 79°
Single and multiple active part designs
87 units total, 24 delivered + 7 in pipeline from Bad Honnef, 2 in pipeline in Cordoba.
Additi l t b ff d f Additional support can be offered for:
System studies (load flow, short circuit, insulation coordination)coordination)
Preparation of specifications
Protection and control
© ABB Group July 11, 2011 | Slide 20
Protection and control
ABB’s extra services for youS tSupport
Support during pre-tender stage Developing and optimizing economical transformer concept
Q i k i i f h i l l i f l Quick iterations of technical solutions for system planners Special PST design tool Quick budgetary costing
© ABB Group July 11, 2011 | Slide 21
ABB’s extra services for youP j t ti d t t diProject execution and system studies
Professional project execution Project management Engineering Manufacturing Testingg Transport Erection/ commissioning After sales service
© ABB Group July 11, 2011 | Slide 22
After sales service
ABB’s extra services for youP j t ti d t t diProject execution and system studies
System studies Load flow Insulation coordination Switching Transformer protectionp Transient overvoltage protection Short circuit withstand capability Energizing the line with the PST
© ABB Group July 11, 2011 | Slide 23
Energizing the line with the PST
ABB’s extra services for youABB ti itiABB activities
Conferences
IEC/ IEEE standardization
New solution development
Consultancy
New solution development
Research & Development
Application support
Trouble shouting Trouble shouting
Protection & Control Protection & Control
Wide Area Monitoring (WAM)
© ABB Group July 11, 2011 | Slide 24
ABB’s extra services for youS ti t i lSupporting material
IEC 62032 / IEEE C12.135 double logo standard
G id f th li ti Guide for the application, specification and testingof PSTs
Extensive technical presentation
PST fl PST flyer
PST reference list
PST h kli t PST checklist
PST fast tender tool(ABB internal use only)(ABB internal use only)
PST bibliography
© ABB Group July 11, 2011 | Slide 25
© ABB12/10/2010 | Slide 26