themis fdmo review management topics − 1 october 5, 2004 management topics manfred bester

14
THEMIS FDMO Review Management Topics − 1 October 5, 2004 Management Topics Manfred Bester

Upload: erik-wilson

Post on 02-Jan-2016

218 views

Category:

Documents


1 download

TRANSCRIPT

THEMIS FDMO Review Management Topics − 1 October 5, 2004

Management Topics

Manfred Bester

THEMIS FDMO Review Management Topics − 2 October 5, 2004

Management Topics

Overview• Ground System Schedule• Personnel Plan• Ground Systems Costs• IT Security• Risk Management• Document Status• PDR Peer Review RFA Status

THEMIS FDMO Review Management Topics − 3 October 5, 2004

Ground Systems Schedule

Ground Systems Schedule• THEMIS MOC and SOC Configuration During Phase C / D• Development of Detailed Operations Plans and Procedures• Flight Dynamics Software Configuration and Verification with

GNCD Support• FOT Training in Classroom and During Mission I&T• End-to-end Data Flow Testing with BGS, NASA/GN and TDRSS• Launch and Mission Simulations• Dress Rehearsals• Peak Activities In Phase D, Taper Down During Phase E

THEMIS FDMO Review Management Topics − 4 October 5, 2004

Ground Systems Schedule

THEMIS FDMO Review Management Topics − 5 October 5, 2004

Operations Org Chart

All Aspects of THEMIS Operations Are Performed at UCB / SSLGSFC / GNCD Provides Support in Form of Consulting and Certification

Additional Consulting Support by AI Solutions

THEMIS FDMO Review Management Topics − 6 October 5, 2004

O&GS Team Members

THEMIS Operations & Ground Systems Team– Mission Operations Manager (M. Bester)

• Mission Operations– Deputy Mission Operations Manager (M. Lewis)– Flight Controllers (M. Eckert, J. McDonald, T. Neal, J. Thorsness, TBH, TBH)– Programmer/Analyst (TBH, TBH)– Student Aides (4)

• Science Operations– Science Operations Manager (T. Quinn)– Programmer/Analysts (J. Vernetti, TBH)– Student Aides (4)

• Flight Dynamics– Flight Dynamics Lead (S. Frey)– Flight Dynamics Engineers (J. McDonald, D. Rummel, TBH)– Student Aides (2)

• Ground Station Operations– Ground Station Manager (R. Sterling)– Ground Station Technician (H. Bersch)– Student Aide (1)

• IT Network Systems– IT Network Systems Manager (J. Loran)– System Administrators (R. Boyd, W. Herrick, C. Quan, B. Satow, K. Edgecomb)

THEMIS FDMO Review Management Topics − 7 October 5, 2004

MOC Staffing

MOC Staffing During Launch & Early Orbit Operations• UCB Flight Operations Team• 24 Hour Staffing with Prime and Secondary Shifts• Critical Commanding During Prime Shift Only• Swales and UCB Engineering Team on Console During Prime

Shift• Instrument Scientists on Console During Instrument

Commissioning• Additional Support Teams Monitor Probe Status Remotely

MOC Staffing During Normal Operations• THEMIS Follows FAST / RHESSI / CHIPS Model• Normal Operations Eventually Run with 8 x 5 Staffing• Transition to Autonomous Operations After First Tail Season• Orbit and Attitude Maneuvers Always Treated as Special

Operations

THEMIS FDMO Review Management Topics − 8 October 5, 2004

Ground Systems Costs

Ground Systems Costs• Cost Effective Approach Based on Successful FAST / RHESSI /

CHIPS Model• Mission Operations, Science Operations, Flight Dynamics and

Ground Station Operations Integrated Into One Coherent Facility• Phase-in THEMIS Operations Team Gradually• Hire New Personnel to Enlarge Existing Operations Team• Ground Systems Costs Remain Within CSR Budget• Ground System Development Fully Funded• Required Trade Study Performed in Phase B

THEMIS FDMO Review Management Topics − 9 October 5, 2004

Ground Systems Support

Supporting Analyses• RF Link Analysis• Data Volume Analysis• Ground Station and TDRSS Coverage Analysis• Maneuver Analysis• Tracking Accuracy Analysis

Interface Control Documents• Probe to Ground Stations• Ground Stations to MOC• MOC to SOC, FDC to MOC, FDC to SOC• MOC to GSFC/FDF

Support Agreements with Various Organizations• NASA/GSFC GNCD (Code 570)• NASA/GSFC MSP (Code 451)• Ground Stations (WGS, MILA, AGO, HBK) and Space Network

THEMIS FDMO Review Management Topics − 10 October 5, 2004

NASA GSFC/GNCD Support• FDAB Support Via SOW for FY05

– MSASS Upgrade Including Nutation Estimation Utility and Small Level of Usage Support (R. Harman)

– Attitude Error Analysis Support for Swales Aerospace (R. Harman)– Validation of FreeFlyer (R. DeFazio, K. Richon)

– Generate Benchmark Runs with GMAN– Compare FreeFlyer Runs Against GMAN– Assess Ability of FreeFlyer to Meet THEMIS Mission Requirements– UCB Will Contract AI Solutions to Generate FreeFlyer Benchmark Runs

– GTDS Software Upgrade and Small Level of Usage Support (M. Beckman)

• FDF Support Via PSLA– Assignment of BGS Transmit and Receiver Tracker IDs– Verification and Certification of BGS Two-way Doppler Tracking– Pre-launch Data Flow and Simulations Support for OD– Orbit Determination Support Following Launch

GSFC/GNCD Support

THEMIS FDMO Review Management Topics − 11 October 5, 2004

AI Solutions Support

AI Solutions Support• FreeFlyer Software

– UCB Already Has “Engineer” Version– Upgrade to FreeFlyer Mission Once THEMIS Compatibility Verified

• THEMIS Configuration– Spacecraft Definition Files for THEMIS Probes

• Software User Training– FreeFlyer– GTDS

• Flight Dynamics Support– Maneuver Planning Support– Orbit Determination Support

• Operations Support– Support L&EO Operations

THEMIS FDMO Review Management Topics − 12 October 5, 2004

NASA GN and SN Resource Requirements in PSLA• THEMIS FY04 PSLA Signed and FY05 PSLA Currently

Boarded by GSFC/MSP (Code 451)• PSLA Under MSP Configuration Control• Compatibility Test Van (CTV) for GN/SN End-to-end Testing

Additional Documentation Requirements• RF ICD (Probe to GN and SN) – Submitted to GSFC/MSP• Network Requirements Document (NRD) − Draft in 2005• RF Compatibility Test Plan (CTP) − Draft in 2005

Data Flows and Scheduling for Ground Testing & Mission Operations Simulations• Supported and Coordinated by GSFC/MSP

Ground System Development• Support of Experiments with Berkeley Ground Station to

Determine Accuracy of Two-way Doppler Tracking

GSFC/MSP Support

THEMIS FDMO Review Management Topics − 13 October 5, 2004

Documents Relevant to Ground Systems Risk Management• NPG 7120.5B, NASA Program and Project Management

Processes and Requirements• NPG 8000.4, Risk Management Procedures and Guidelines• NPD 8700.1, NASA Policy for Safety and Mission Success• NPG 8715.3, NASA Safety Manual• NPG 2810.1, Security of Information Technology• NPD 8621.1, Mishap Reporting and Investigating Policy• NPG 8621.X (Draft), NASA Procedures and Guidelines for

Mishap Reporting, Investigating and Record Keeping• SP-6105, NASA Systems Engineering Handbook

Risk Management Approach• Continuous Risk Management (CRM)• Identify, Analyze, Plan, Track and Control Risks

Risk Management

THEMIS FDMO Review Management Topics − 14 October 5, 2004

Status of Relevant DocumentsDocument Title Doc. No. Assignee Due Date Status

THEMIS Mission Requirements Document (MRD) THM-SYS-001 Taylor Jun 2004 Signed

THEMIS Information Technology Security Plan (ITSP) THM-SYS-021 Bester Feb 2004 Signed

THEMIS Risk Management and Contingency Plan (RMCP) THM-SYS-022 Bester Nov 2004 Started

THEMIS Project Data Management Plan (PDMP) THM-SYS-012 Quinn Jun 2004 Signed

THEMIS Project Service Level Agreement (PSLA) 451-PSLA-THEMIS GSFC/451 Sep 2004 Signed

THEMIS RF Interface Control Document (RFICD) 451-RFICD-THEMIS GSFC/451 Oct 2004 Draft

THEMIS RF Compatibility Test Plan (RFCTP) 450-TBD GSFC/450 Jul 2005

THEMIS Network Requirements Document (NRD) 450-TBD GSFC/450 Jul 2005

THEMIS Command Format Specification THM-SYS-102 Taylor Oct 2004 Draft

THEMIS Telemetry Data Format Specification SAI-SPEC-1210 Kraeuter Oct 2004 Draft

THEMIS Ground Data Systems Interface Control Document THM-SYS-117 Bester Oct 2004 Started

THEMIS Attitude Determination System (ADS) Requirements THM-SYS-028 Bester Oct 2004 Draft

THEMIS GSFC/FDF to MOC Interface Control Document 595-TBD GSFC/595 Mar 2005

THEMIS Ground Operations Coordination SAI-PLAN-0623 LeBoeuf Oct 2003 Signed

THEMIS Mission Operations Plan (MOP) THM-SYS-013 Bester Nov 2004 Started

THEMIS Flight Operations Plan (FOP) THM-SYS-018 Bester Oct 2005 Started

THEMIS Flight Operations Test Plan (FOTP) THM-SYS-019 Bester Oct 2005 Started

THEMIS Flight Operations Team Certification Plan (FOTCP) THM-SYS-025 Lewis Oct 2005 Started

THEMIS Ground Station Certification Plan THM-SYS-TBD Bester Mar 2005

THEMIS Launch and Ascent Handbook THM-SYS-026 UCB Oct 2005

THEMIS On-orbit Handbook THM-SYS-027 UCB Oct 2005

THEMIS Spacecraft User’s Manual SAI-TBD Swales Oct 2005