the world bank€¦ · ppe personal protective equipment qae quality at entry ... 03/09/2006...

53
Document of The World Bank Report No: ICR00001696 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-41780 TF-56629 TF-58076) ON A CREDIT IN THE AMOUNT OF SDR 4.4 MILLION (US$ 6.25 MILLION EQUIVALENT) TO THE REPUBLIC OF ARMENIA FOR A AVIAN INFLUENZA PREPAREDNESS (AIP) PROJECT December 14, 2010 Sustainable Development Department South Caucasus Country Department Europe and Central Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 08-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

Document of

The World Bank

Report No: ICR00001696

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IDA-41780 TF-56629 TF-58076)

ON A

CREDIT

IN THE AMOUNT OF SDR 4.4 MILLION

(US$ 6.25 MILLION EQUIVALENT)

TO THE

REPUBLIC OF ARMENIA

FOR A

AVIAN INFLUENZA PREPAREDNESS (AIP) PROJECT

December 14, 2010

Sustainable Development Department

South Caucasus Country Department

Europe and Central Asia Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

CURRENCY EQUIVALENTS

(Exchange Rate Effective July 31, 2010)

Currency Unit = Armenian Dram (AMD)

AMD 1.00 = US$0.0027

US$ 1.00 = AMD 370

FISCAL YEAR

January 1 – December 31

ABBREVIATIONS AND ACRONYMS

ADCCF Animal Disease Control and Compensation Fund

AHIF Animal and Human Influenza Facility

A/H1N1 Swine Influenza virus, subtype H1N1

ASF African Swine Fever

BSL Bio-Safety Level

CDCP Center for Disease Control and Prevention

CVL Central Veterinary Laboratory

EMP Environmental Management Plan

FSVSI Food Safety and Veterinary State Inspection

GOA Government of Armenia

GPAI Global Program for Avian Influenza and Human Pandemic Preparedness and Response

HPAI Highly Pathogenic Avian Influenza

HSMP Health Systems Modernization Project

H5N1 Avian Influenza A virus, subtype H5N1

IMTF Inter-Ministerial Task Force

IT Information Technology

Marz Administrative Regions of Armenia

M&E Monitoring and Evaluation

MOA Ministry of Agriculture

MOH Ministry of Health

NADSS National Animal Disease Surveillance System

OIE World Organization for Animal Health

PAD Project Appraisal Document

PDO Project Development Objectives

PPE Personal Protective Equipment

QAE Quality at Entry

QAG Quality Assurance Group

San-Epid State Hygiene and Anti-Epidemic Inspectorate

SQP Sanitary Quarantine Post

VSI Veterinary State Inspection

Vice President: Philippe Le Houerou

Country Director: Asad Alam

Sector Manager: Dina Umali-Deininger

Project Team Leader: Brian Bedard

ICR Team Leader: Brian Bedard

Page 3: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

REPUBLIC OF ARMENIA

AVIAN INFLUENZA PREPAREDNESS (AIP) PROJECT

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design............................................. 1

2. Key Factors Affecting Implementation and Outcomes ............................................ 1

3. Assessment of Outcomes ....................................................................................... 2

4. Assessment of Risk to Development Outcome ........................................................ 3

5. Assessment of Bank and Borrower Performance ..................................................... 3

6. Lessons Learned .................................................................................................... 3

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ............ 3

Annex 1. Project Costs and Financing ........................................................................ 4

Annex 2. Outputs by Component ............................................................................... 5

Annex 3. Economic and Financial Analysis ................................................................ 6

Annex 4. Bank Lending and Implementation Support/Supervision Processes .............. 7

Annex 5. Beneficiary Survey Results ......................................................................... 8

Annex 6. Stakeholder Workshop Report and Results .................................................. 9

Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR .................... 10

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ...................... 11

Annex 9. List of Supporting Documents ................................................................... 12

MAP

Page 4: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

i

A. Basic Information

Country: Armenia Project Name: Avian Influenza

Preparedness Project

Project ID: P099832 L/C/TF Number(s): IDA-41780,TF-

56629,TF-58076

ICR Date: 02/01/2011 ICR Type: Core ICR

Lending Instrument: ERL Borrower: REPUBLIC OF

ARMENIA

Original Total

Commitment: USD 6.3M Disbursed Amount: USD 5.4M

Revised Amount: USD 5.0M

Environmental Category: B

Implementing Agencies:

Ministry of Health, HSMP-PIU

Ministry of Agriculture - ARSP-PIU

Cofinanciers and Other External Partners:

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 03/09/2006 Effectiveness: 09/05/2006 09/05/2006

Appraisal: 03/13/2006 Restructuring(s): 09/15/2008

Approval: 06/02/2006 Mid-term Review: 03/17/2008 02/10/2008

Closing: 07/31/2009 07/31/2010

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately Satisfactory

Risk to Development Outcome: Moderate

Bank Performance: Moderately Unsatisfactory

Borrower Performance: Moderately Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

Unsatisfactory Government: Moderately Satisfactory

Quality of Supervision: Moderately

Unsatisfactory

Implementing

Agency/Agencies: Moderately Satisfactory

Overall Bank

Performance:

Moderately

Unsatisfactory

Overall Borrower

Performance: Moderately Satisfactory

Page 5: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

ii

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem Project

at any time (Yes/No): No

Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): No

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status: Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Agricultural extension and research 18 18

Animal production 11 11

General public administration sector 42 42

Health 27 27

Other social services 2 2

Theme Code (as % of total Bank financing)

Health system performance 17 17

Other communicable diseases 33 33

Pollution management and environmental health 17 17

Rural services and infrastructure 33 33

E. Bank Staff

Positions At ICR At Approval

Vice President: Philippe H. Le Houerou Shigeo Katsu

Country Director: Asad Alam D-M Dowsett-Coirolo

Sector Manager: Dina Umali-Deininger Juergen Voegele

Project Team Leader: Brian G. Bedard Mark R. Lundell

ICR Team Leader: Brian G. Bedard

ICR Primary Author: Gotz A. Schreiber

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

The overall objective of the Project is to minimize the threat in Armenia posed to humans

by the highly pathogenic avian influenza (HPAI) and other zoonoses in domestic poultry,

Page 6: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

iii

and to prepare for the control and response to an influenza pandemic and other infectious

disease emergencies in humans. To achieve these goals, three areas will be supported:

(i) prevention, (ii) preparedness and planning and (iii) response and containment.

Achieving these goals will contribute to diminishing the burden of disease and loss of

productivity in Armenia, limiting the regional spread of HPAI, and enhancing economic

and social prospects at the national, regional, and global levels.

Revised Project Development Objectives (as approved by original approving authority)

The objective of the Project is to minimize the threat in Armenia posed by the HPAI

infection and other livestock diseases, and to prepare for the control and response to an

influenza pandemic and other zoonoses or infectious disease emergencies in humans.

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 :

Evidence* of improved effectiveness of participating animal and public health

services in limiting the spread of an HPAI outbreak and consequent pandemic in

Armenia.

Value

quantitative or

Qualitative)

No human case as of

February 1, 2006

No human pandemic

No human pandemic

Contain spread

and number of

cases.

No human

pandemic

No human

pandemic

Date achieved 02/01/2006 06/03/2006 07/31/2010

Comments

(incl. %

achievement)

Indicator 2 : Evidence* of widespread adoption of recommended practices for the prevention

and control of HPAI among poultry producers, distributors, and retail vendors.

Value

quantitative or

Qualitative)

No human case as of

February 1, 2006 0 new cases 0 new cases

Date achieved 02/01/2006 06/03/2006 07/31/2010

Comments

(incl. %

achievement)

Indicator 3 : Improving trend in poll of experts designed to gauge HPAI readiness in Armenia.

Value

quantitative or

Qualitative)

Moderate readiness Advanced

readiness Advanced readiness

Date achieved 02/01/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

No such poll or survey was ever carried out. The outcome assessment is that of

the ICR mission, reflecting the technical, institutional and human capacity

created by the project.

Page 7: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

iv

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Component I.A:

Detailed assessment of the Veterinary State Inspection of the MOA

Value

(quantitative

or Qualitative)

Partial FAO assessment 100% complete

OIE assessment and

gap analysis

completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 2 : National AI strategic plan developed and adopted by government.

Value

(quantitative

or Qualitative)

MOA and MOH AI

Action Plan 100% complete Completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 3 : Component I.B:

BSL-2+ attained in one reference laboratory.

Value

(quantitative

or Qualitative)

BSL-2+ not attained in

reference laboratory

BSL-2+ attained

in reference

laboratory

BSL 2 status

achieved

Date achieved 06/01/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 4 : Self-assessment of the veterinary services executed.

Value

(quantitative

or Qualitative)

No self-assessment made 100% complete Completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 5 : 100% monitoring of poultry breeding stock farms.

Value

(quantitative

or Qualitative)

25% monitoring 100% monitoring 40%

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

This activity was minimally implemented

Page 8: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

v

Indicator 6 : Component I.C:

Emergency supplies procured and available at strategic locations in the field.

Value

(quantitative

or Qualitative)

Minimal

Supplies for 120

staff and 40 teams

procured and

deployed

Supplies for 120

staff and 40 teams

procured and

deployed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 7 : One mobile incineration units deployed and accessible by areas at risk.

Value

(quantitative

or Qualitative)

0 mobile incinerators

deployed

One mobile

incinerator

deployed

No mobile

incinerators

deployed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Incinerator use was found not permissible under Armenian environmental

regulations

Indicator 8 : Number of farms in which unconfined backyard poultry farming addressed and

demonstrated

Value

(quantitative

or Qualitative)

0 2000 0

Date achieved 06/02/2006 06/30/2006 06/30/2006

Comments

(incl. %

achievement)

Activity was not implemented

Indicator 9 : Compensation Fund established with clear operating modalities

Value

(quantitative

or Qualitative)

No Compensation Fund

Compensation

Fund fully

functional

No Compensation

Fund established

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Drafting of legal and operational documents was completed, but these

instruments were not implemented nor ratified by project completion.

Indicator 10 :

Component II.A: National strategic plans for improvement of public health

surveillance and disease control systems prepared according to WHO

recommendations and approved and fully resourced for implementation.

Value

(quantitative

or Qualitative)

MOA and MOH AI

Action Plan Completed Completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 11 : Component II.B: Increased surveillance and outbreak investigation capacity.

Value

(quantitative Varies by province

100% of provinces

w/ functional

100% of provinces

w/ functional

Page 9: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

vi

or Qualitative) capacity capacity

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 12 :

Number of public health laboratories available for routine influenza diagnosis

and typing, rehabilitated and equipped, and with appropriate biomedical waste

management systems

Value

(quantitative

or Qualitative)

2 labs

a) Genetic Center PCR

Lab-temporarily carries

out AF diagnosis

b) CDC PCR Lab # in the

stage of development

1 lab, TBD at

project launch

a) NIH PCR lab

CDC lab capable of

avian influenza

diagnosis;

NIH lab capable of

PCR diagnosis of

HPAI

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 13 : Number of health personnel trained in influenza virus surveillance and control.

Value

(quantitative

or Qualitative)

TBD at project-launch TBD at project

launch

More than 2300

staff trained

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 14 : Increased laboratory capacity to collect and analyze specimens per day for viral

typing, sub-typing and isolation in times of surged specimen load.

Value

(quantitative

or Qualitative)

0/day 30/day Not recorded by

labs

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

No lab records available of daily analysis loads during surge but no outbreaks

occurred during project to trigger specimen submission.

Indicator 15 : % of positive tests of specimens confirmed by reference laboratory.

Value

(quantitative

or Qualitative)

0 100%

No positive

specimens

confirmed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 16 : Component II.C: Strategy for procurement and access to human influenza

vaccine on the basis of well-defined criteria developed.

Value

(quantitative

or Qualitative)

1449 poultry workers ,

who are vaccinated

99,061 at risk population

New HI vaccine

for 1450 poultry

workers + at-risk

66,000 doses

procured;

no new HI vaccine

Page 10: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

vii

population, TBD

at project launch

was developed or

used

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

No new suitable HI vaccine became available for use in humans.

Indicator 17 : Strategy to access antivirals for national use (e.g., stockpiling) developed.

Value

(quantitative

or Qualitative)

420 doses Tamiflu Stock maintained

at the same level

Stock level

maintained

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 18 : A contingency plan for procurement of AI vaccine for humans is developed

should one become available and needed.

Value

(quantitative

or Qualitative)

Initial contacts w/

manufacturer

Procurement of

350,000 doses for

at- risk population,

TBD

No plan developed,

since no new HI

vaccine was

developed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

No new suitable HI vaccine became available for use in humans.

Indicator 19 :

Cumulative incidence rate (CIR)

CIR = total cases

pop x yrs exposure

Value

(quantitative

or Qualitative)

0.0/million 0.0/million CIR= 0.0/million

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 20 : % change in AI case fatality rate.

Value

(quantitative

or Qualitative)

0% fatality rate 0% fatality rate 0% fatality rate

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 21 : Component III.A: Political and civic leadership organized around a national

strategic risk communication plan.

Value

(quantitative

or Qualitative)

AI Action Plan revised to

include a National

Strategic Risk

Communication Plan

100% complete

National AI Action

Plan was not

revised to include a

NSRCP

Page 11: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

viii

(NSRCP) 10% complete

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 22 : Research-based risk communication strategies and products, responding to the

needs of priority audiences, are developed.

Value

(quantitative

or Qualitative)

NSRCP and priority

audience communication

needs assessment 0%

implemented

100 % complete Not completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

No evidence of reports indicating such preparations under AI project but

developed under parallel USAID program.

Indicator 23 : Consistent awareness-raising and behavior change interventions made with

population at risk using appropriate communications channels.

Value

(quantitative

or Qualitative)

Knowledge, attitude and

practices studies and

design of

communications products

25% implemented

100% complete

No KAP survey

implemented;

communications

products developed

without it

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

KAP survey was carried by UNICEF and USAID in 2006. No budget available

for KAP in late 2009.

Indicator 24 :

Communications strategies and products highlighting the actions and investments

of participating ministries and the mobilization of group resources to contain the

epidemic, generating social trust and credibility.

Value

(quantitative

or Qualitative)

NSRCP 10% complete 100% complete No NSRCP

completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 25 : Evidence of consistent communication and information technologies, to promote

reporting of outbreaks, fast response and an uninterrupted social dialogue.

Value

(quantitative

or Qualitative)

Secretariat Information

Center operational at 50%

of demand

100% complete Not functioning

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Government reluctant to continue ongoing communication dialogue considering

no outbreaks and reduced risks assessment.

Indicator 26 : Evidence of consistent communication and information technologies, to promote

reporting of outbreaks, fast response and an uninterrupted social dialogue.

Value Secretariat Information 100% complete Not functioning

Page 12: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

ix

(quantitative

or Qualitative)

Center operational at 50%

of demand

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 27 :

Production and dissemination of informational products that educate priority

audiences about possible scenarios and mitigation and pandemic control actions

to be undertaken.

Value

(quantitative

or Qualitative)

NSRCP 10% complete 100% complete Completed

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

Indicator 28 : Methodology defined and monitoring and evaluation periodically undertaken.

Value

(quantitative

or Qualitative)

ARSP PIU and MOH PIU

with M&E capacity

Detailed surveys

completed

No surveys

undertaken

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

M&E methodology was not developed, and no M&E capacity was established

Indicator 29 : Methodology defined and monitoring and evaluation periodically undertaken.

Value

(quantitative

or Qualitative)

ARSP PIU and MOH PIU

with M&E capacity

Detailed surveys

completed

No surveys

undertaken

Date achieved 06/02/2006 06/30/2006 07/30/2010

Comments

(incl. %

achievement)

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 09/22/2006 Satisfactory Satisfactory 0.00

2 11/21/2006 Satisfactory Satisfactory 0.30

3 03/26/2007 Satisfactory Satisfactory 1.13

4 04/04/2008 Satisfactory Satisfactory 3.06

5 06/26/2009 Satisfactory Satisfactory 4.04

6 03/10/2010 Satisfactory Satisfactory 4.80

Page 13: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

x

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring &

Key Changes Made DO IP

09/15/2008 S S 3.33

I. Disbursement Profile

Page 14: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

In 2005 the highly pathogenic H5N1 avian influenza virus emerged as a global threat,

and in January 2006 the Bank’s Board approved the Global Program for Avian Influenza

and Human Pandemic Preparedness and Response (GPAI) to provide immediate

emergency assistance to countries seeking support to address this public health threat. By

January 2006 cases of highly pathogenic avian influenza (HPAI) had been reported in

Croatia, Romania, Russia, Ukraine, Greece, Turkey and Iraq. HPAI outbreaks in

neighboring Azerbaijan led to five human deaths there and the culling of some 500,000

birds in several commercial poultry farms. Situated on major migratory bird flyways and

with outbreaks reported in neighboring countries, Armenia clearly faced both a public

health and an economic risk. The veterinary and public health services systems had

limited diagnostic and surveillance capacity to address the HPAI threat. Border

inspection posts were underequipped, and public awareness capacity was weak.

Biosecurity at the commercial poultry farms was reasonably good, but the large free-

ranging segment of the poultry population lacked biosecurity and was vulnerable to HPAI

infection.1

At the end of October 2005 the Ministry of Agriculture (MOA) established an Inter-

Ministerial Task Force (IMTF) on Avian Influenza to coordinate nationwide measures to

combat the potential spread of HPAI in Armenia. Soon afterwards MOA collaborated

with the Ministry of Health (MOH) in drafting an Action Plan, and in January 2006 the

Government (GOA) drafted a broader National Strategy for Avian Influenza, to be

implemented by an Inter-Ministerial Committee on AI (IMCAI), to which the IMTF was

to report. To prevent transboundary incursion of the disease, GOA prohibited the import

of poultry and poultry products from countries with reported H5N1 cases. Following a

Bank-supported risk assessment,2 GOA requested Bank assistance through the GPAI to

address the risks associated with HPAI and mitigate the potential impact on animal and

public health and the economy. The project was prepared as a component of the Bank-

wide horizontal adaptable program loan instrument (APL) for avian influenza and under the

procedures for emergency investment operations (OP 8.50) in early 2006 and approved

by the Board on 2 June 2006. If became effective on 5 September 2006.

A PHRD Cofinancing Grant of US$0.8 million was provided at the same time, and an

AHI Facility Grant of US$2.0 million was added in 2007. Of the IDA Credit SDR 3.49

million (US$5.36 million equivalent) were disbursed and SDR 0.91 million cancelled; of

the PHRD Grant US$0.7 million were disbursed; and the AHI Grant was fully disbursed.

1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)

1 The Armenian poultry subsector comprises some 10 million birds, of which 45 percent are kept under

free ranging backyard conditions. The subsector generates about 7.5% of Gross Agricultural Output

and about 1.5% of the country’s GDP. Gross annual output is estimated at US$60-80 million. 2 World Bank Assessment of HPAI in Armenia, Avian Influenza Rapid Response Actions , February 2006.

Page 15: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

2

The overall objective of the Project was to “minimize the threat posed to humans by

HPAI infection and other zoonoses in domestic poultry and prepare for the control and

response to an influenza pandemic and other infectious disease emergencies in humans.”

To achieve this, three areas were to be supported: (i) prevention, (ii) preparedness and

planning and (iii) response and containment.

The key performance indicators were:

Evidence of improved effectiveness of participating animal and public health

services in limiting the spread of an HPAI outbreak and consequent pandemic in

Armenia;

Evidence of widespread adoption of recommended practices for the prevention

and control of HPAI among poultry producers, distributors, and retail vendors;

Improving trend in poll of experts designed to gauge HPAI readiness in Armenia.

1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and

reasons/justification

The PDO were amended in early 2008 to reflect the Project restructuring carried out in

response to GOA’s request after the severe outbreaks of African Swine Fever (ASF) that

struck Armenia beginning in 2007. A review carried out in November 2007 at the

request of GOA concluded that supporting ASF control actions would not compromise

the Project’s integrity or original objectives. The PDO were therefore amended to read:

“The objective of the Project is to minimize the threat in Armenia posed by the HPAI

infection and other livestock diseases, and to prepare for the control and response to an

influenza pandemic and other zoonoses or infectious disease emergencies in humans.”

The Results Framework and PDO indicators were not changed.

1.4 Main Beneficiaries,

The PDO targeted humans threatened by HPAI infection and other infectious disease

emergencies, but the PAD also refers to three other specific groups of beneficiaries: (i)

private poultry farmers receiving competitive grants to improve their on-farm biosecurity,

(ii) stakeholders (undefined) receiving information and public awareness training to

guard against HPAI; and (iii) poultry owners that would be compensated for culled

poultry. Institutional beneficiaries were the Veterinary State Inspection (VSI)3 of the

MOA, its staff and its laboratory, surveillance and inspection services, and the MOH, its

staff, its laboratory and epidemiological surveillance units, and the infectious disease

reference hospital. The works, equipment, vehicles, training, consumables and technical

assistance to be provided for the VSI and the MOH, their laboratories, their surveillance

capability, their communications and information technology, were intended to upgrade

significantly their capacity to detect any future outbreak of HPAI and to respond rapidly

and effectively to any emerging threat from the virus. This enhanced detection and

response capacity, coupled with a substantial public awareness and information campaign

and a compensation facility, was intended to ensure that poultry owners’ risk of losing

their flocks to the virus would be minimized and that any humans infected with H5N1

would receive immediate and effective treatment.

3 Since 2007 Food Safety and Veterinary State Inspection (FSVSI).

Page 16: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

3

1.5 Original Components (as approved)

The Project had four components.

Component I: Animal Health

(i) Support was to be provided for the development of a national policy framework, a

national strategic plan and an enabling regulatory environment in accordance with OIE

standards and recommendations (on bio-security, vaccination, control of animal

movement, border controls, culling and carcass disposal, compensation, etc.) and for

updating the essential information on migratory birds.

(ii) The animal disease surveillance and diagnostic capacity of the VSI (now FSVSI) and

its reference and regional diagnostic laboratories -- to detect, report and follow up

suspected and/or confirmed cases of HPAI -- was to be strengthened through the

refurbishment of the central laboratory in Yerevan and its upgrading to biosafety level 3

(BSL-3), the modernization (works and equipment) of marz-level laboratories and border

posts, the provision of rapid test kits, laboratory consumables, sprayers, disinfectants and

vehicles, and technical training of VSI and marz-level veterinary and border post staff in

disease surveillance, outbreak management, laboratory diagnosis and analysis of

epidemiological data and risk-based AI surveillance.

(iii) Support was to be provided for the development and, if necessary, implementation of

an HPAI Outbreak Containment Plan, with clearly detailed roles of the various

institutions involved. This was to include support for virus eradication at source, i.e., for

culling of infected and likely to be infected poultry, compensating their owners, and

safely disposing of carcasses and potentially infectious materials in a biosecure manner in

special burial facilities (Bekkari pits) and/or incinerators. The Project would support the

establishment of a compensation policy and a compensation fund, and financing would

be provided for compensation in the event of mandated culling. To protect veterinary

and laboratory personnel, personal protective equipment was to be provided for them and

for staff and temporary workers involved in culling and disposal.

(iv) To improve biosecurity at the level of backyard poultry holdings, the project intended

to provide small matching grants, on a competitive basis, to poultry owners to convert

their free-range backyard poultry operations to confined small-scale enterprises, with

recipients contributing at least 25% of the conversion cost themselves.

Component II: Human Health

(i) To enable the MOH services to implement the National Strategy for AI, their

organizational and logistical capacity was to be strengthened through the provision of

training, technical assistance, protective gear, transport, and information and

communications equipment, including for the regional branches of the San-Epid network.

(ii) The national public health surveillance system was to be upgraded through the

establishment of a reference laboratory for the diagnosis of HPAI, improved laboratory

capacity at the central level and in remote regions, laboratory capacity upgrading at the

Page 17: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

4

Republican Infectious Diseases reference hospital, rehabilitation of laboratory premises

in Syunik marz and at the Infectious Diseases hospital, and support for specimen

collection, transportation and laboratory investigations through the provision of

equipment and consumables. The health information and telecommunication systems

were to receive technical assistance and investments in IT hardware and software as well

as internet access. For improved surveillance effectiveness the Project also was to assist

with the development of updated standard reporting guidelines, registries, forms and

information material, and with case standardization, notification and feedback between

the center and the marzes, and with staff training at different levels of the health system

in clinical management, epidemiology, laboratory reporting, laboratory biosafety,

molecular diagnostic techniques and molecular epidemiology.

(iii) To strengthen health system response capacity, the project intended to support

activities to help contain and prevent the spread of HPAI through social distancing,

containment and mass prophylactic activities. This was to include expanded regular

seasonal influenza vaccination, procurement of anti-viral drugs and influenza vaccines

for high-risk population groups, provision of prophylactic and preventive equipment and

supplies for patient care in the intensive care unit of the Infectious Diseases reference

hospital and for active case detection.

Component III: Public Awareness and Implementation Support

(i) The project would provide support for the design, implementation and evaluation of an

integrated information and communications strategy to raise public the awareness with

the aim of elevating knowledge, promoting behavior-change in populations at-risk,

controlling the spread of the virus, preventing infection, fostering timely reporting and

supporting containment measures. At-risk populations were to be informed about

preparedness plans and mitigation measures across pre-pandemic and pandemic phases.

Measures called for in the Environmental Management Plan (EMP) for safe culling of

backyard poultry and disposal of carcasses would also be covered.

(ii) To ensure effective coordination of HPAI control and response activities, support was

to be provided to bolster project implementation and monitoring capacity at the existing

project implementation structures in both MOA and MOH. The Inter-Ministerial

Committee for Avian Influenza (IMCAI), supervising the work of the Inter-Ministerial

Task Force (IMTF) for Avian Influenza, would receive support to establish a Secretariat

with four staff to oversee and monitor the national awareness activities. The Secretariat

would be responsible for reviewing annual work plans and ensure coordination and

linkages across relevant agencies and international partners. In HPAI outbreak situations,

it would also be the National Disease Crisis Center (NDCC), responsible for triggering

emergency responses by MOA and MOH, monitoring the actions taken, and coordinating

public statements to the media. The two existing project implementation units in MOA

and MOH, the Agricultural Reform Support Project Implementation Unit (ARSP-PIU)

and Health Systems Modernization PIU (HSMP-PIU), were to be supported in their

fiduciary tasks of procurement and financial management. Both were to be strengthened

with additional fiduciary staff, and MOA and MOH would appoint project coordinators

Page 18: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

5

for their respective components. Finally, support was to be provided for project

monitoring and impact evaluation. In addition to semi-annual progress reports containing

relevant data compiled by the two ministries and focusing on output indicators,

implementation status and use of project funds, specific surveys were to be carried out to

obtain data for various indicators. Annual impact evaluation reports were to ascertain the

effectiveness and impact of project interventions and to cover both quantitative and

qualitative aspects.

Component IV: Support for Critical Imports

This component was to finance, in the event of a confirmed outbreak of a human HPAI

pandemic, under Emergency Recovery Assistance procedures, critically needed imports

to support a response program to such a pandemic. The list of eligible items included

protective clothing and gear, pharmaceuticals and vaccines, medical and veterinary

supplies and equipment. Other items could have been added with the prior agreement of

the Bank in the case of a pandemic.

1.6 Revised Components

In order to respond to the devastating outbreaks of African Swine Fever (ASF) that began

in April 2007, the Animal Health component was restructured following the mid-term

review in February 2008. Laboratory staff training was expanded to include ASF

diagnosis and surveillance. Three emergency management disinfection vehicles were to

be procured, three tire washes to be constructed at the border inspection posts near the

border with Georgia, and additional disinfectants to be procured. Project financing for

the culling compensation fund was increased by US$300,000 to US$1,050,000, with

US$750,000 of this earmarked for ASF compensation (subject to several conditions).

Public awareness and communication activities were to include also ASF, and project

funds were reallocated to facilitate this.

At the same time, the original project facility to provide matching grants to backyard

poultry producers to switch from free-range to caged poultry management, which had

proven to be impractical, was cancelled and the funds were reallocated for the provision

of international TA to develop a diagnostic manual, dealing with the diagnosis, pathology

and treatment of the most prevalent livestock and poultry diseases in Armenia.

1.7 Other significant changes

Two other significant changes were made.

(i) US$2 million in additional funding from the AHIF Trust Fund became effective on 8

June 2007.

(ii) The closing date was extended by one year, from 31 July 2009 to 31 July 2010 in

order to allow for the completion of the CVL rehabilitation and modernization.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

(including whether lessons of earlier operations were taken into account, risks and their

mitigations identified, and adequacy of participatory processes, as applicable)

Page 19: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

6

The project was prepared within the framework of the GPAI and under the provisions of

the Bank’s emergency policy guidelines (OP/BP 8.50). Although several other donors

readily agreed to dedicate some resources from ongoing operations to help meet the

HPAI threat, only the GPAI offered the possibility of stepping in very quickly with an

overarching assistance effort to meet the critical needs in the policy, planning, public

health, veterinary services and public awareness fields. However, with the limited funds

available, the focus had to be limited and clear, and care had to be taken to avoid

duplication or conflicts with initiatives planned or already begun by others. To ensure

this, the project design drew directly on the findings and recommendations of an HPAI

risk assessment carried out in January/February 2006 and on reports prepared by or for

WHO, FAO and USAID on Armenia’s HPAI preparedness. The multiple sources of

background information and related recommendations provided further rationale for

support of interventions to mitigate the risks associated with HPAI. Lessons were also

incorporated from several HPAI projects appraised for other countries during the

preceding months, although these were all only just entering their actual implementation

phase.

The basic project design was sound, based on the global guidelines applicable to GPAI-

supported operations and on the country-specific assessments mentioned above.

However, due to the very rapid preparation and appraisal, a number of aspects were not

fully developed or evaluated and left to be dealt with during project implementation,

notably on the Animal Health side as outlined below. It was also recognized that,

although the most effective preparedness measures would require fundamental systemic

reforms, the project was being prepared as a rapid response project and could not fully

address all the issues. The project was designed to focus on the key elements for

optimizing risk reduction on an urgent basis. Regardless, the complexity of the

interventions led to considerable implementation delays for several project activities,

significant redesign of some planned activities (e.g., BSL-2 instead of BSL-3 at the

central veterinary laboratory), and failure to implement others altogether (e.g., poultry

sector restructuring, rehabilitation/construction of Bekkari pits, provision of incinerators).

Conversely, several important activities not considered at the time of appraisal

subsequently had to be added in order to ensure that the project objectives would be

achieved (e.g., major central veterinary laboratory building rehabilitation). On the

Human Health side, in contrast, project activities were quite clearly specified; they

constituted HPAI-specific complements and refinements to the ongoing Health Systems

Modernization Project where needs and gaps were readily identifiable.

The hurried preparation also meant that not enough attention was paid at that time to

refining the Results Framework, the outcome and monitoring indicators, their baseline

values, and the instruments by which these indicators were to be obtained. Since this

weakness was not subsequently corrected during project implementation, monitoring

project progress and assessing outcomes was made rather difficult.

A QAG assessment undertaken in 2007 gave the project an overall assessment of

“moderately unsatisfactory” and rated Bank inputs and processes moderately

unsatisfactory as well. Of the eight major aspects rated, two were rated moderately

Page 20: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

7

unsatisfactory: (i) poverty, gender and social development, and (ii) policy and

institutional aspects. Fiduciary aspects were rated satisfactory, all others moderately

satisfactory.

2.2 Implementation

Implementation benefitted from the fact that both of the line ministries with a principal

stake in the project, the Ministry of Health and the Ministry of Agriculture, maintained

sustained interest in the project throughout implementation and each had an existing and

experienced PMU to manage project implementation. Counterpart funding was adequate

and provided in a timely fashion. Procurement and financial management were

satisfactory; all financial management and audit reports were provided on time and were

found satisfactory.

The rushed and in several respects incomplete preparation and appraisal process caused a

number of implementation delays and problems, mainly in the Animal Health field,

because specifics still needed to be defined and agreed to. An initially rather more

descriptive than action-oriented Project Operational Manual (POM) also contributed to

start-up delays in a number of areas because the roles, actions and responsibilities of

different agencies and institutions were not clearly defined. After the POM was revised

in 2007 with the assistance of an international consultant, implementation performance

improved considerably.

Components I, II and III were, with some notable exceptions, largely implemented,

although the project’s closing date had to be extended by one year to ensure this.

Component IV (Support for Critical Inputs) was not implemented, because no HPAI

pandemic developed; the funds were reallocated.

Four major activities envisaged in the PAD were not carried out or not completed:

(i) The plans for poultry sector restructuring to improve backyard poultry biosecurity

were dropped when, after considerable further study, it became evident that it would be

financially, socially and structurally impractical to shift 4.5 million poultry from free-

ranging backyard to confined production arrangements. The funds allocated for this were

reallocated; part of it was utilized to produce a well-designed, practical handbook and

training for practitioners on the management of the most prevalent animal diseases in

Armenia and an extensive training program on biosafety in three marzes.

(ii) The establishment of a compensation fund for poultry owners was not achieved by

project closing and the Credit funds earmarked for it were cancelled (SDR 650,000). The

preparatory work needed (drafting of legislation, statutes and operational guidelines) was

successfully completed, albeit after much delay, but the necessary legislation has not yet

been enacted. This is now expected to be accomplished after and outside the project

framework and will entail the creation of an Animal Disease Control and Compensation

Fund. Compensation to owners of pigs killed by ASF was provided out of the

Government’s own budget; the funds reallocated after the MTR within the restructured

IDA Credit for this purpose were not used and were cancelled.

Page 21: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

8

(iii) Investments planned for environmentally acceptable disposal of animal carcasses

were not carried out. The plan to rehabilitate existing bio-thermal Bekkari burial pits had

to be abandoned when it was discovered that most, if not all, of these pits were located at

environmentally unacceptable places.4 The alternative of using mobile incinerators was

also found impractical, not only due to very high costs but due to severe legal and

regulatory restrictions on their use in Armenia which the project was unable to address.

Carcass disposal thus continues to take place through burial, which is an acceptable

procedure, but it is only sporadically monitored for safety.

(iv) No integrated national communications strategy was developed, adopted or

implemented. Communications and awareness raising efforts were carried out, but were

designed and implemented in an ad-hoc fashion.

Both the Government (GOA) and IDA displayed appropriate flexibility when it became

necessary to modify project content in response to needs not adequately identified during

appraisal (e.g., major civil works at the CVL and the Meghri border post) or arising

afterwards (inclusion of AFS response measures). The mid-term review in early 2008 led

to a project restructuring that allowed it to address other major livestock diseases, expand

the public awareness activities beyond HPAI, further strengthen the veterinary service’s

diagnostic and response capacity, expand the national animal disease surveillance and

information system, and facilitate the diagnosis and monitoring of swine flu (H1N1) in

the public health sector.

A notable aspect of project implementation was the generally effective coordination

among and across different institutions and with projects and initiatives supported by

other donors and international technical agencies such as FAO and WHO, with the Inter-

Ministerial Task Force on Avian Influenza playing a key role in this regard. This ensured

that project activities dovetailed, rather than duplicated or conflicted, with those

supported by other external donors and thereby facilitated consistency in approach and

efficiency of resource use. Particularly beneficial were the relations with FAO and WHO

projects and staff (which provided important technical expertise during implementation),

with USDA (which provided complementary veterinary TA) and with a USAID project

(which stepped in with a substantial public information and awareness effort and a

training program for rural veterinarians when the project’s own communications

component was very slow in getting started). On at least one occasion, however, the

Bank’s willingness to cooperate with other donors had a serious negative effect: many

months were lost when USAID after a long delay backed out of financing the design of

the CVL refurbishment, necessitating a lengthy new procurement process for a suitable

laboratory design company.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

4 Deep, circular holes lined with cement where animal carcasses are buried and covered. The resulting

bio-thermal action of disposal kills any pathogens. This method of carcass disposal is acceptable

practice in Armenia, and it was the intention to rehabilitate many of these pits. This approach,

however was abandoned in favor of incineration/

Page 22: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

9

Rather inadequate attention was given to the M&E design during project appraisal.

Although the QAE review pointed out the need to remedy this deficiency and

recommended a simpler framework with more emphasis on outcomes and impacts, this

issue was not addressed during implementation. The framework set out in the PAD was

heavy on process and weak on outcome and impact indicators, included too many

indicators that were both vague and difficult to measure, and in several cases would have

required periodic surveys or studies to obtain valid findings. It included too many

indicators, and it relied heavily on reports from implementing agencies that were in fact

not prepared/submitted/collected/processed and/or on surveys (e.g., KAP surveys) that

were not carried out. The EMP requirement to develop M&E indicators for

environmental monitoring, to be submitted in annual reports, was also not complied with.

An M&E specialist was to be contracted at project onset, but the qualifications of the

initially selected candidate were considered inappropriate and no further effort was made

to find a suitable specialist. Project implementation therefore proceeded without an

M&E specialist. As a consequence very little M&E was conducted, and regular M&E

reports were not issued. The special surveys envisaged at appraisal and included in the

initial project budget were not carried out.

2.4 Safeguard and Fiduciary Compliance

Compliance with fiduciary policies was satisfactory. All audits were satisfactory.

The only Safeguard applicable for the project was Environmental Assessment (OP 4.01),

and the project was assigned Environmental Category B. The Environmental

Management Plan (EMP) approved in September 2006 emphasized three key areas: (i)

public awareness to protect the public against exposure to infectious agents, (ii)

environmentally acceptable waste disposal of carcasses, and (iii) safe management of

laboratory wastes. Public awareness has been effectively raised. A laboratory waste

management plan was developed late in the project, but is satisfactory and being adhered

to, with safe waste management by means of autoclaving. But compliance with the EMP

in developing and applying safe animal carcass disposal procedures has been

unsatisfactory. The investments envisaged to facilitate environmentally acceptable

carcass disposal were not carried out. The original plan to rehabilitate existing bio-

thermal Bekkari pits had to be abandoned when it became clear that many, if not all of

them, were located at environmentally unacceptable places. The alternative of using

mobile incinerators then considered was also found impractical, not only due to very high

costs,5 but due to severe legal and regulatory restrictions on their use. As a consequence,

carcass disposal continues to take place through burial and is rarely monitored for safety.

Pigs killed by ASF were often inadequately disposed of (e.g. dumped into rivers or left in

forests) or transported from their place of death for burial elsewhere, thereby increasing

the threat of spreading infectious materials.

5 Large-capacity (1 t/hour) incinerators are not suitable for use as mobile units. Furthermore, the

transportation of mobile units from one disposal site to the next is logistically problematic, especially

were gas is used as fuel.

Page 23: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

10

The EMP requirement to develop M&E indicators for environmental monitoring, to be

submitted in annual reports, was also not met.

2.5 Post-completion Operation/Next Phase

The project has helped establish critically important institutional and technical capacities

in the veterinary services sector, that had received very little attention and support over

the past two decades. Their continued and effective operation is essential for both public

health and livestock sector productivity and profitability, and this will require adequate

budgetary allocations for operation and maintenance. To expand service coverage to

other key livestock diseases such as brucellosis, to complete the establishment of the

computer- and internet-based animal disease surveillance system (NADSS) and to

establish and finance an Animal Disease Control and Compensation Fund (ADCCF) will

require financial resources that GOA may find difficult to mobilize. Budgetary

sustainability is, thus, a serious concern and further external support will be desirable

over the next few years. Accordingly, discussions are ongoing to consider a new IDA

project or other donor programs that would support further strengthening of the

veterinary services.

On the policy side, the legal basis for operating an ADCCF, with mandatory animal

registration and fees, remains to be established. GOA is determined to do this in the near

future, and MOA is taking the lead on this. A new Veterinary Law providing for such a

facility has been drafted, as have the legal instrument to set up an ADCCF and the draft

charter. Enactment of these legal provisions and establishment of the ADCCF will be

critically important to ensure livestock owner compliance with animal disease reporting

and eradication requirements.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

Project objectives, design and implementation remain highly relevant for Armenia today.

The country’s human health services and especially its animal health services are today

far better prepared and equipped to detect and respond to outbreaks of highly infectious

diseases, including zoonoses, than they were in 2006. The devastating outbreaks of AFS

in 2007 and 2008 and the appearance of the A/H1N1 swine flu virus in 2009 indicate the

importance of having in place effective disease surveillance, diagnostic, control and

treatment capabilities. The project investments in communication and multi-sectoral

collaboration were beneficial in preparing the groundwork to rapidly respond to the

H1N1 threat and the and equipment (including vehicles), training and laboratories were

utilized in the response to the African Swine Fever outbreaks. And the high prevalence of

brucellosis among humans illustrates the close link between animal disease control and

public health and this was also address with project resources that were applicable such

as the information systems, training materials, etc.

3.2 Achievement of Project Development Objectives

The Project largely achieved its PDOs, but not fully. Surveillance, diagnostic, control

and response capacity in both the animal and human health sectors have been improved

Page 24: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

11

considerably, not merely with regard to HPAI but also to other zoonoses and infectious

diseases, and the threat posed by HPAI and other livestock diseases has thereby been

much reduced. The National Pandemic preparedness plan for MOA/MOH was updated

and the legal framework (decree/charter) and operational manual were drafted for Animal

Disease Control and Compensation Fund. In the human health sector, where

considerable institutional and staff capacity upgrading had already been initiated under

the Health Systems Modernization Project, the project met important additional needs

relevant to the health care system’s ability to cope with potential HPAI or other

epidemics. Two public health laboratories engaged in routine influenza diagnosis and

typing were rehabilitated and equipped with appropriate biomedical waste management

systems. In the animal health sector, the project provided the essential technical capacity

(equipment and training) to detect and respond to possible outbreaks of HPAI, but also

much needed general upgrading of facilities, staff skills, policies and operating modes in

a sector long neglected. Thus, the veterinary services were equipped with vehicles for

surveillance and response measure throughout Armenia. The National Reference

Laboratory was upgraded to the BSL 2+ status and six regional veterinary laboratories

were refurbished.

Armenia did not experience any known outbreaks of HPAI, and the country’s capability

to respond to such an outbreak has therefore not been tested (except in a successful field

simulation). But its human and animal health institutions are now clearly far better

equipped and prepared than in 2006. This has been illustrated by the rapid and effective

response to the outbreak of ASF, which was contained in Tavush and Lori marzes, in

2007 and 2008.

However, two important gaps remain in the country’s capacity to minimize the threat of

zoonoses and other livestock diseases, that the project intended to fill: there is still no

acceptable, officially monitored and enforced national system for disposing safely of

highly infectious animal carcasses other than through burial, and there is still no

institutionalized arrangement to compensate livestock owners when their animals are

killed by an epizootic disease or culled on government orders.

3.3 Efficiency

The analysis undertaken at project completion related AIPP project costs to the economic

value of a stream of losses avoided in human health and the poultry industry from project

activities (see Annex 3). An outbreak with a mutated virulent virus is assumed to occur

with a probability of once every five years, and the first outbreak is assumed to occur in

2011. The project benefits are expressed as the expected value of the economic losses

avoided over the period of 2011-2025 in the “With Project” scenario over the “Without

Project” scenario.

The human health benefits estimated comprise the economic value of: (i) hospitalization

costs averted, (ii) income losses avoided from days lost due to illness, and (iii) lifetime

income losses avoided due to the reduction in fatal HPAI cases. Poultry industry benefits

were also estimated in terms of loss avoidance; they include the economic value of: (i)

poultry meat production losses avoided, and (ii) egg production losses avoided, and (iii)

the avoidance of the loss of the layers before the end of their productive lives. The

Page 25: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

12

number of human and poultry affected in an outbreak of HPAI and the death rate

estimates were difficult to estimate; nevertheless, the estimates and sensitivity analysis

provided robust results.

The base case scenario assumes that the percentage of the population affected by HPAI

infection is reduced by the project from 5% to 2% and that the mortality rate among those

affected is likewise lowered from 3% to 1.5%. For the poultry sector it assumes that the

percentage of birds affected and killed or culled is reduced from 5% to2%. The results of

the analysis show a 53% ERR, a benefit/cost ratio of 4.5 and an NPV of US$42.4 million.

Assigning only 50% of the human health benefits to the project, because of reduced

benefit assumptions and/or because of the simultaneously implemented Health Systems

Modernization Project and other HPAI-related initiatives launched in Armenia at the time,

the analysis shows a 33% ERR, a benefit/cost ratio of 1.8 and an NPV of US$16.5

million, confirming the project’s economic value added.

Project benefits are primarily driven by key assumptions regarding the gross attack rate

for the human population and for the mortality rate among those affected as well as by

the likely frequency of HPAI outbreaks. This is to be expected in a project that is

intended to prepare for a contingency for which neither timing nor severity can be

reliably predicted.

3.4 Justification of Overall Outcome Rating

The overall outcome rating is “Moderately Satisfactory”. The project was and still is

highly relevant for Armenia. Its PDOs were not fully achieved. Its efficiency was

satisfactory.

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

The project’s poverty and gender impacts – through the avoidance of losses of livestock

and income and the payment of compensation for poultry lost to culling – are potentially

significant, but are only likely to be realized in the event of an HPAI outbreak. Backyard

poultry are an important feature of rural livelihood systems, particularly for the poorer

households, and it is primarily women who manage birds and realize income (be it

through sales or home consumption) from their small backyard flocks.

(b) Institutional Change/Strengthening

The project has left the beneficiary institutions in both the veterinary and the human

health fields, but particularly in the former, significantly strengthened and better prepared

to detect, respond to and contain future outbreaks of HPAI and other zoonoses and highly

infectious diseases. Epidemiological surveillance, disease monitoring, laboratory

diagnostics, field response capabilities and patient treatment capability have all been

upgraded through investments in human resources, facilities and equipment and through

the development of updated operating protocols and guidelines. This was evidenced

already during project implementation by the much improved capacity of the veterinary

services to organize and carry out ASF control measures and, on the human health side,

Page 26: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

13

by the rapid development and application of a monitoring and rapid response system for

swine flu (A/H1N1) in 2009.

(c) Other Unintended Outcomes and Impacts (positive or negative)

As a result of intensive dialogue with Bank staff and consultants, TA provided and a

project-funded study tour to Germany, MOA and GOA are now determined to establish

an Animal Disease Control and Compensation Fund comparable in design, functions and

financing arrangements to those in a number of Western European countries. This would

be not merely a facility to pay compensation to poultry owners for animals killed or

culled due to HPAI, but a farmer-funded facility to finance or co-finance infectious

animal disease surveillance, prevention, control and eradication measures.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

Not applicable.

4. Assessment of Risk to Development Outcome

Rating: Moderate

The risk to sustaining the project outcomes is moderate, mainly because of the uncertain

prospects of adequate future budgetary support for the operation, including staff salaries,

and maintenance of the upgraded laboratory and other service facilities. The

establishment, now planned by GOA for the near future, of an Animal Disease Control

and Compensation Fund, with mandatory animal registration and mandatory annual fees,

to pay or co-pay for essential epidemiological surveillance and control measures would

greatly allay concerns over the financial sustainability of the much strengthened

veterinary services.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Moderately unsatisfactory

The rushed appraisal left a number of important issues to be resolved or fully developed

during implementation. Several subcomponents envisaged in the PAD could not be

implemented at all because they were inadequately prepared and appraised and proved to

be unrealistic (poultry sector restructuring) or in violation of existing laws and

regulations (Bekkari pit construction, incinerators). The Results Framework and the

M&E arrangements required significant further refinement – but were subsequently

largely ignored.

A QAE assessment undertaken in 2007 gave the project an overall assessment of

“moderately unsatisfactory” and rated Bank inputs and processes “moderately

unsatisfactory” as well. The overall rating may have been overly critical; indeed, of the

eight major aspects rated, only two – (i) poverty, gender and social development, and (ii)

Page 27: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

14

policy and institutional aspects – were rated moderately unsatisfactory. Fiduciary aspects

were rated satisfactory, all others moderately satisfactory. In its detailed response the

Region took issue with a number of QAR statements and judgments. Where it

acknowledged weaknesses and lacunae in the PAD, it pointed out that these were to be

addressed during the initial implementation phases.

(b) Quality of Supervision

Rating: Moderately unsatisfactory

The quality of Bank supervision was mixed, satisfactory on financial management,

procurement and technical issues, but very spotty on others. Notable was the failure to

follow up on the need to refine the Results Framework and M&E arrangements and,

related to this, on the project’s failure to prepare regular M&E reports. The HSMP-PIU

prepared and provided semi-annual progress reports as required under the provisions of

the Financing Agreement, but the ARSP-PIU never did, and the Bank’s task team did not

remind the PIU or demand these reports. Progress reporting therefore took place mostly

orally in face-to-face meetings or phone and video conferences, with only brief

summaries provided in supervision Aide Memoires. Progress indicators and M&E

summary reports were not attached to these Aide Memoires. Aide Memoires also tended

to be issued with considerable delays after SPN missions, thereby delaying action on

issues identified and recommendations made by the supervision missions. The project

restructuring, which included the expansion to African Swine Fever and other livestock

diseases, was initiated at the time of the mid-term review in February 2008, but it took

until December 2008 to complete the Bank-internal process of preparing the necessary

documentation to amend the Financing Agreement. The task team did not reflect the

restructuring in an update of the Results Framework and/or monitoring indicators,

although this was proposed to be done. Neither did it follow up on the EMP requirement

to develop M&E indicators for environmental monitoring, to be submitted in annual

reports.

Positive aspects of Bank supervision included the proactive approach to collaboration and

coordination with other donors and projects, even though this did on occasion cause

difficulties and delays in implementation. The task team also demonstrated a forward-

looking approach, recognizing the project as a platform for longer-term institutional

capacity building beyond merely a one-time emergency preparedness operation. The

introduction of a pilot operation on participatory disease surveillance, the support for a

computer-based animal disease surveillance system, the expansion of project activities to

AFS, to brucellosis and to swine flu all attest to this.

(c) Justification of Rating for Overall Bank Performance

Rating: Moderately Unsatisfactory

5.2 Borrower Performance

(a) Government Performance

Rating: Moderately satisfactory

Page 28: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

15

The Government remained fully committed to the project and its objectives. Adequate

counterpart funding was provided, and when project financing for specific expenditures

was not (yet) accessible, as was the case when compensation payments were made to

owners of pigs killed by AFS, GOA readily provided its own budgetary resources

instead. However, failure to implement the steps required to establish the Compensation

Fund was a notable shortcoming.

(b) Implementing Agency or Agencies Performance

Rating: Moderately satisfactory

MOH implemented its project activities very effectively, dovetailing them with the

broader program of activities funded by the Health Sector Modernization Project (HSMP),

and its HSMP-PIU performed the requisite management and fiduciary responsibilities

very well, led by the component coordinator in the PIU. Progress reports were regularly

prepared, as were financial management and procurement reports.

Performance under the animal health component, where no prior experience with Bank

operations existed and a number of issues had not been adequately set out at the time of

appraisal, was marred by some problems. Fiduciary aspects were satisfactorily managed

by the ARSP-PIU, and the component coordinators performed well with respect to

implementation coordination. The failure to employ an M&E specialist and to produce

semi-annual progress reports was a serious shortcoming, however. The decision-making

process within the VSI (later FSVSI) was often very slow, causing considerable delays on

several project activities. The important staff training program did not begin until mid-

2008. MOA itself remained strongly committed to the project and its objectives and

provided effective leadership throughout. It did not, however, manage the process of

establishing the Compensation Fund (or Animal Disease Control and Compensation

Fund) very effectively, and so this important institution has still not been set up. Neither

the FSVSI nor MOA took a proactive role in seeking a solution to the problem of safe

animal carcass disposal when neither Bekkari pit construction nor incinerators were

found to be a viable option, especially once the massive ASF outbreaks made this a

matter of high urgency.

There proved to be little need for the Secretariat of the Inter-Ministerial Committee

established under the project. The Inter-Ministerial Committee was essentially dormant

throughout the project life, since no HPAI outbreak was registered. Inter-ministerial

coordination was effectively handled by the Inter-Ministerial Task-Force established

prior to project preparation, headed by the Deputy Minister of Agriculture and comprised

of working level representatives of the key ministries and agencies (agriculture, health,

nature protection, emergencies, police, etc). The only task actually handled by the

Secretariat was to manage the public awareness, information and communication

subcomponent of the project; this was very slow in getting off the ground, but was finally

ably organized by an international consultant working closely with a communications

specialist employed for this purpose from December 2006 until July 2009.

(c) Justification of Rating for Overall Borrower Performance

Rating: Moderately satisfactory

Page 29: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

16

6. Lessons Learned

Ambitious multi-sector operations such as the AIPP require sufficient time to

implement. While many specific emergency response activities (e.g., procurement of

protective gear, equipment, consumables) can be carried out quickly, institutional

strengthening and capacity building take time. Although critical response mechanisms

can be put in place, a three-year timetable to implement significant institutional reform is

therefore not realistic and investments in more systemic reforms are required.

Effective coordination of activities with other donors and projects requires time and

can delay implementation. The efforts to cooperate with other donors’ HPAI and

veterinary services support operations were useful in harmonizing approaches and

achieving efficiencies in resource allocations and use. But they also entailed some cost,

especially in terms of slippages from initial work plans. Where cross-donor coordination

is envisaged, it is therefore prudent to incorporate flexibility into implementation

schedules.

Project interventions should be designed to be flexible and allow response to

unexpected but related priorities. The project gained significant recognition when it was

recognized that resources were not restricted for HPAI could be used to supported related

problems in the animal and public health sectors including response to H1N1, ASF and

endemic diseases such as brucellosis. The high quality practical training materials which

were developed under the project cover a broad spectrum of diseases and have been used

as training materials, as field manuals for veterinarians and animal health workers and for

students in the university.

A well designed and implemented M&E framework is essential for effective monitoring

of project implementation. Although the project implementation did progress reasonably

well, the absence of effective, meaningful and systematically applied M&E arrangements

made it difficult to monitor progress and to identify problems and take corrective action

in a timely manner.

Creating project-specific coordination bodies outside existing civil service structures is

not necessarily advisable. It tends to imply a transfer of responsibility from mainline

officials to staff with mere “consultant” status, create unwanted and resented parallel

lines of communication and/or decision-making, and foster an attitude of disinterest and

disengagement among those responsible for the sector or subsector.

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/implementing agencies

The Government agrees with the assessment provided in this Implementation Completion Report.

(b) Cofinanciers

n/a

Page 30: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

17

(c) Other partners and stakeholders

(e.g. NGOs/private sector/civil society)

n/a

Page 31: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

18

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in USD Million equivalent)

Components Appraisal Estimate

(USD millions)

Actual/Latest

Estimate (USD

millions)

Percentage of

Appraisal

ANIMAL HEALTH 5.56 5.43 98

HUMAN HEALTH 2.75 4.06 148

PUBLIC AWARENESS AND

IMPLEMENTATION SUPPORT 0.91 1.02 112

CRITICAL IMPORTS 0.23 0.00 n.a.

Total Baseline Cost 9.45 10.50 111

Physical Contingencies

0.00

0.00

0.00

Price Contingencies

0.00

0.00

0.00

Total Project Costs 9.45 10.50 111

Front-end fee PPF 0.00 0.00 .00

Front-end fee IBRD 0.00 0.00 .00

Total Financing Required 9.45 10.50 111

(b) Financing

Source of Funds Type of

Cofinancing

Appraisal

Estimate (USD

millions)

Actual/Latest

Estimate (USD

millions)

Percentage of

Appraisal

Avian and Human Influenza Facility 0.00 1.96 n.a.

Borrower 2.15 2.42 113

International Development

Association (IDA), Cr. 4178 6.42 5.36 86

JAPAN: Ministry of Finance - PHRD

Grant 0.80 0.69 88

IDA Cr. 4095 (RESCAD) 0.00 0.08 n.a.

Page 32: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

19

Annex 2. Outputs by Component

Component 1: Animal Health

A. National Policy Framework and Development of a National Strategic Plan

A1: Policy development and enabling environment

With support from the project and the OIE, the VSI/FSVSI carried out a PVS assessment

in 2007, followed by a gap analysis in 2009 and the formulation of a strategic plan in

2010. This work took much longer than planned or necessary, but it did establish a

framework for medium-term strengthening of the service that would raise its PVS rating

from 2 to 3 (“satisfactory”). The development of the legal and operational documentation

for setting up and operating a Compensation Fund was not completed during the project.

The causes included ineffective leadership and process management within MOA, some

ineffective TA early in the process, poor management of the discussion among different

departments within MOA, and failure to obtain high-level political support until very late

in the project. Only after the MTR in February 2008 and a subsequent, highly

informative study tour of key officials to Germany did this process gain momentum, and

GOA now intends to establish a more broadly mandated Animal Disease Control and

Compensation Fund in the near future. As a consequence of this failure, project funds

earmarked for compensation poultry and pig owners could not be used and were

cancelled. Compensation to pig owners whose swine were lost to AFS was paid from

GOA budget resources; the absence of clear operating instructions resulted in significant

problems and irregularities in the administration of this compensation program.

A2: Updating Essential Information on Migratory Birds

A national NGO, the Armenia Society for Protection of Birdlife (ASPB) carried out study

in eight major high-risk areas, covering three seasons, of the flight, rest and nesting

patterns of migratory birds, so as to identify locations with high risk of HPAI

transmission from wild birds to domestic poultry. The study developed a useful

framework for risk assessment. It also raised significant concerns about the waste

management at commercial poultry farms, an issue also looked into by the subsequent

poultry sector restructuring study, but there was no further follow-up on this issue.

B. Strengthening Disease Surveillance and Diagnostic Capacity

B1: Strengthening Animal Disease Surveillance and Diagnostic Capacity

The initially postulated aim of establishing a Bio-Safety Level 3 (BSL-3) central

veterinary laboratory was scaled back after further study to BSL-2, since this would

clearly satisfy the requirements of a diagnostic laboratory. This was effectively achieved,

although after much delay caused initially by the failure of USAID to carry out the

technical design work, then by the need to undertake more substantial civil works than

had been anticipated, and lastly by unusually lengthy contract negotiations. Following a

substantial modernization of the laboratory building, the necessary equipment was

installed, rapid test kits and reagents were provided, staff were trained, and operating

Page 33: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

20

protocols were developed and are adhered to. Diagnostic capacity has therefore been

considerably improved.

The 10 marz-level veterinary stations were upgraded through the provision of heating,

water and gas supply as well as office furniture and equipment. Six of the associated

small laboratories were also upgraded, partly with support also from an EU TACIS

project, with serological facilities to allow basic field testing for HPAI and brucellosis.

However, the civil works renovations carried out by GOA with its own funds were not

well done, and the marz laboratories were therefore still not operating effectively when

the project closed. Six border posts were similarly modernized and equipped. One of

them, Meghri at the border with Iran, required substantial new construction.

A laboratory waste management plan was developed, although only in late 2009, and its

recommendations have been put into effect. SOPs for laboratory tests and operations

were finalized with TA assistance in early 2010, as an important precondition for

eventual CVL accreditation by the OIE.

40 mobile surveillance and rapid response teams were established and provided with

vehicles, protective gear and special equipment. Sprayers and disinfectant were procured

and provided for the border posts and in selected strategic locations.

Once the HPAI threat had diminished and the devastating outbreaks of AFS, which began

in April 2007, drew attention to the high risks and costs of other highly infectious animal

diseases, the project focus was broadened to include not only AFS, but also brucellosis

and other infectious diseases more generally. Specifically, three emergency management

disinfection vehicles and additional disinfectants were procured, and three tire washes

were constructed at the border inspection posts to Georgia.

As a first step in addressing the problem of widespread brucellosis among both ruminants

and humans, the project in its final phase also supported the work of an inter-agency

working group (with participation also of FAO and USDA) to develop a national

brucellosis control strategy that will merit longer-term donor support.

B2: Veterinary Services Training and AI Surveillance

A medium-term staff training plan was developed with international TA support, and a

substantial number of topical training courses and events for different target groups

(laboratory staff, VSI staff, field-level veterinarians, university faculty and students, etc.)

were organized. The program, which only really began in mid-2008 because the

formulation of the training plan was much delayed, covered laboratory practices,

epidemiological surveillance and diagnosis, field-level surveillance as well as one table-

top and one field-level real time outbreak simulation exercise in which staff of multiple

agencies participated.

Although not foreseen at appraisal, a participatory disease surveillance (PDS) system was

introduced on a pilot basis in a number of communities, by which monthly animal disease

information is provided from the village level in two marzes to the center for inclusion in

Page 34: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

21

the central surveillance data base.

The central disease information data base (NADSS), using the TADInfo software

developed by FAO, has been put in place and is functioning, but in the absence of full

internet access in all marzes and of interactive access for all users, information from

many locations continues to be provided in hard copy to the center and only then

computerized. At the center, NADSS amalgamates the information for subsequent

manual geo-positioning and analysis. The system appears to operate well for the

monitoring of ASF and brucellosis. Although the TADInfo software was not originally

designed for the entry of poultry disease information data, IT staff of the VSI have been

able to adapt the software to accept poultry data. They have also developed the capability

to enter data in both of the two officially adopted Armenian language scripts.

These various measures significantly improved animal disease surveillance capacity from

pre-project passive surveillance to active surveillance, reporting and data analysis.

C. Outbreak Containment Plan

C1: Targeting virus eradication at the source

Procedures were developed and training was conducted for efficient and safe culling of

infected poultry and poultry in the surrounding eradication zones. These were

successfully tested and demonstrated during a field-level simulation exercise. Carcass

disposal, however, remains an issue. Neither the planned rehabilitation and construction

of bio-thermal Bekkari pits nor the acquisition of mobile incinerators were carried out;

both were blocked by the Government on the basis of environmental safety. Carcasses

are therefore buried which, although this is an acceptable method of disposal, requires

diligent monitoring and remains an important issue to be addressed.

The preparatory work needed for establishing and operating a Compensation Fund

(drafting of legislation, statutes and operational guidelines) was successfully completed,

albeit after much delay, the necessary legislation has not yet been enacted and the

Compensation Fund has not yet been established. Since this was a disbursement

condition for this subcomponent, the project funds allocated to provide compensation

were not used, but eventually cancelled. The project was amended after the MTR to

include African Swine Fever (AFS) in the compensation scheme, but GOA compensated

the owners of pigs lost to AFS from its own resources. Independent monitors employed

by the project found much to be concerned about in the actual administration of this

program, because adequate operating and verification principles and procedures had not

been developed and applied. GOA recognizes that an effective, reliable and trusted

compensation system is an essential condition for livestock owner compliance with rapid

infectious disease reporting and intends to establish an Animal Disease Control and

Compensation Fund in the near future outside the project framework.

C2: Veterinary Personnel Safety

The project provided significant quantities of personal protective equipment for all

personnel likely to be at high HPAI infection risk.

Page 35: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

22

C3: Restructuring the Poultry Sector

The planned restructuring of the farmyard and backyard poultry sector to improve

biosecurity was not implemented once further detailed study indicated that it would be

financially, socially and structurally impractical to shift 4.5 million poultry from free-

ranging backyard to confined production arrangements. Emphasis was placed instead on

public information and awareness raising with respect to safe handling of backyard

poultry.

Instead, the effort to improve poultry sector biosafety was shifted to an awareness and

training program for animal health personnel on basic biosafety, including containment,

vaccination, culling, etc. This was successfully carried out in two marzes. The training

material developed is available for future use in the entire country. In addition,

international TA was secured to help develop a very useful manual for veterinary

practitioners on the diagnosis, pathology and treatment of the most prevalent livestock

and poultry diseases in Armenia.

Component 2: Human Health

A. Enhancing Public Health Program Planning and Coordination

The project provided essential training and equipment to key public health institutions to

enable them to perform the functions assigned to them in the national HPAI strategy and

action plan. This included 15 vehicles for the regional centers of the State Hygiene and

Anti-Epidemic Inspectorate (San-Epid), the CDCP and the Norq Infection Hospital as

well as 40 units of disinfection equipment (including 30 mobile units) along with

disinfectants for San-Epid and CDCP. Protective gear (3500 protective coveralls, 2000

safety goggles, 5500 respirator masks, 5000 pairs of gloves) was provided to health

service personnel at potentially high risk of infection. The Norq Hospital received

special equipment (7 inhalators, 1 ultrasound nebulizer) for patient care, and additional

laboratory equipment was supplied to the Scientific Center of Forensic Medical

Examination at MOH. The intended procurement of rapid HPAI test kits was rendered

unnecessary when another donor supplied 400 of them instead.

B. Strengthening of National Public Health Surveillance Systems

B1: Improvement of Laboratory Networks

The project provided critically important upgrading of diagnostic capabilities. It did this

while coordinating closely with other donors so as to optimize the efficiency of external

support and avoid duplication and waste. By 2008, three PCR-laboratories were

established with buildings renovated and the requisite equipment provided, at the CDCP,

at the San-Epid center in Syunik marz and at the Norq Infection Hospital. The project

financed the rehabilitation of the laboratory premises at the latter two locations and the

entire equipment at hospital laboratory. Other donors provided the equipment at the

CDCP and the San-Epid center in Syunik.

The project also financed the construction of four Sanitary Quarantine Posts (SQP) and

Page 36: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

23

the substantial rehabilitation of three others: at four land crossings from Georgia and one

from Iran and at the airports in Yerevan and Gyumri. It equipped all of them with

furniture, medical and disinfection equipment as well as IT equipment for effective

monitoring. 10 vehicles and three thermal imagers to screen passengers for body

temperature were also procured. The construction program experienced significant

delays, however, mainly due to lengthy debates among different government institutions

and with one bilateral aid agency.

B2: Improvement of Health Information and Telecommunications Systems

To strengthen the health information and telecommunication system, 60 computer sets

and other office equipment (copiers, fax machines, scanners, printers, multimedia

projectors, laptops, servers, modems, digital cameras, etc.) were provided, along with

internet connection, for 14 San-Epid locations and the Norq Hospital.

B3: Training and Development of Standard Reporting Forms and Guidelines

In close cooperation with others, especially the US-American CDC, protocols, standard

forms and guidelines were developed and subsequently introduced to the relevant staff in

training events. With local and international TA, a training program on “Avian Influenza

surveillance and treatment” was developed in the first half of 2007 and initiated

immediately thereafter. International consultants also assisted with the “Development of

Armenian public health system, needs assessment plan and monitoring & evaluation

system for the Avian Influenza, HIV/AIDS and other public health threats”, which

produced a number of specific assessments and proposals on various aspects of the public

health system.6 The training program funded by the project covered mainly

epidemiology, clinical treatment of HPAI patients, and laboratory processes. About 3300

infectious diseases specialists, epidemiologists, general practitioners, pediatricians,

family doctors, nurses, laboratory staff, etc. received specific training.

C. Strengthening Health System Response Capacity

To help strengthen health system response capacity, the project provided 66,000 doses of

seasonal influenza vaccines for 2006/7, 2007/8 and 2008/9, to prevent infection among

high-risk groups, as well as a substantial stockpile (2000 boxes) of the anti-viral drug

“Tamiflu”.

Component 3: Public Awareness and Implementation Support

A. Public Awareness through Information and Communication Services

6 Inter alia: (i) Proposal to Modernize the Public Health System of Armenia, (ii) Report on legal and

regulatory framework of the Armenian health care system, including proposals for changes towards a

Public Health oriented system, (iii) Proposal for Establishing an Effective PH Laboratory Network in

Armenia with the CDCP as the National Reference Centre, (iv) Report on strengthening the National

Disease Surveillance System in Armenia, (v) Report on Elements for a Public Health Monitoring and

Evaluation System, and (vi) Curriculum for TOT on '' Avian Influenza Surveillance and treatment''.

Page 37: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

24

The project provided support for the design, implementation and evaluation of a program

of public information and awareness raising, targeted at various population groups and

aimed at inducing behavioral change with respect to management of poultry and poultry

products. The program also sought to inform people about preparedness plans and

mitigation measures across pre-pandemic and pandemic phases. This work did not really

get off the ground until after the mid-term review in early 2008. Fortunately, a USAID

project managed a very effective public information campaign in 2006 and 2007, and

UNICEF ran a specially targeted campaign for children in 2006 and 2007.

Performance improved considerably in 2008, when an international consultant provided

effective guidance, helped develop the draft of a national “Advocacy, Communication

and Social Mobilization Strategy to Promote Bio-Security”, and organized a series of

workshops for key personnel of the State Food Safety and Veterinary Inspectorate and

the State Epidemiological Inspectorate, for marz-level veterinarians and medical officers,

and for media professionals. Through the first half of 2009, when this component was

closed, project-funded information and awareness activities were carried out covering

avian influenza, seasonal influenza, African Swine Fever and brucellosis with television

and radio spots, posters, brochures and leaflets. Much of the public information material

relating to HPAI originated with the USAID project that had filled the gap left by the

long delayed start-up of the AIPP public awareness component. The AIPP was able to

build on this foundation and then to expand it to ASF, seasonal influenza and brucellosis.

All multi-media messaging7 was reviewed by the IMCAI Secretariat to ensure that the

public received coordinated, non-confusing information. After the first round of

transmissions, the national TV channels refused further free-of-charge broadcasting,

despite the governmental directive that public-good messages are to be broadcast free of

charge. The fees demanded exceeded the possibilities of the project, and broadcasting

was therefore limited thereafter to several regional TV stations. Unfortunately, the video

clip on AFS and compensation arrangements was not aired on TV at all, and this was an

important contributing factor when the AFS compensation program experienced

problems.

In 2008, telephone hotlines were set up at FSVSI and at San-Epid, but if they ever

functioned, it was not for long, and they were not operational at the time of the ICR

mission. A KAP (Knowledge, Attitudes and Practices) survey was carried out in 2006 by

UNICEF and USAID, and its findings helped guide the design of the project’s

communications tools, but a second one planned for late 2009 or early 2010, to assess the

impact of the campaign, was not implemented because it was neither budgeted for nor

included in the project’s M&E framework.

Nevertheless, it is generally considered that the public awareness efforts made by the

project and other agencies (USAID, UNICEF and FAO) on HPAI and AFS have been

successful, as is borne out by interviews with various stakeholders in the rural areas.

7 In addition to the AIPP’s communications activities, USAID, UNICEF and FAO also generated public

information on avian influenza. All flowed through the Secretariat for review and approval before

being published.

Page 38: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

25

B. Coordination and Implementation Support

B1: National Coordination

The project supported activities to improve coordination and collaboration among the

various public sector institutions and other domestic stakeholders. The main tool in this

regard was the establishment of a Secretariat for the Inter-Ministerial Committee for

Avian Influenza (IMCAI), which in turn was expected to oversee the work of the Inter-

Ministerial Task Force (IMTF) for Avian Influenza. This Secretariat was to review

annual work plans and ensure coordination and linkages across agencies and international

partners and to implement the national HPAI awareness activities. In HPAI outbreak

situations, it was to trigger emergency responses by MOA and MOH, monitor the actions

taken, and coordinate public statements to the media.

The Secretariat was set up, but there proved to be little need for it. Inter-ministerial

coordination was effectively handled by the IMTF headed by the Deputy Minister of

Agriculture and comprised of working-level representatives of the key ministries and

agencies (agriculture, health, nature protection, emergencies, police, etc). The IMCAI

was essentially dormant throughout the project life, since no HPAI outbreak was

registered. The need for coordination across ministries was strong during the early period

of HPAI outbreaks in neighboring countries, but with most activities subsequently falling

strictly within the realm of one ministry or the other, coordination where necessary took

place without the need for intermediaries.

The only task actually handled by the Secretariat was to manage the public awareness,

information and communication subcomponent of the project; this was very slow in

getting off the ground, but was finally ably organized by an international consultant

working closely with a communications specialist employed for this purpose from

December 2006 until July 2009.

B2: Project Implementation

To ensure effective implementation, fiduciary management and project M&E, the

existing project implementation units at both MPH and MOA were provided with

additional fiduciary staff and operating resources. Each PIU was strengthened with the

addition of a Project Coordinator for its respective project components. The fiduciary

and general facilitation and coordination functions were well managed. On the other

hand, the important position of M&E specialist at the ARSP-PIU was never filled, with

serious negative consequences for implementation monitoring and impact assessment.

B3: Monitoring and Evaluation (M&E)

Although project funding was envisaged for M&E activities, little was actually done or

achieved. The M&E framework and arrangements were neither fully developed during

appraisal, nor adequately finalized afterwards. No M&E specialist was employed, and no

meaningful M&E activities were carried out. The EMP requirement to develop M&E

indicators for environmental monitoring, to be submitted in annual reports, was not met.

Progress monitoring took place essentially through irregular and ad-hoc reporting from

Page 39: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

26

implementing agencies, and progress monitoring by the Bank’s task team was largely

through occasional site visits, meetings and audio and video conferences. No semi-

annual project progress reports were produced, except by the HSMP-PIU for the human

health component. Specific surveys proposed in the PAD to assess progress for certain

indicators were not carried out. No impact evaluation assessments or reports were

prepared.

Component 4: Support for Critical Imports

This component was not implemented, because no HPAI pandemic arose and the

disbursement conditions therefore were not triggered. The funds (SDR 160,000) were

reallocated.

Page 40: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

27

List of Animal Health Workshops and Trainings

Subject Date Participants

Number Target Group

Creation of a national

compensation scheme

04.04.2007 21 MoA, FSVSI, MoF, WB, FAO, poultry

farm owners/managers

AI and data management and

analysis

04.05.2007 37 FSVSI, RVDAC at Central and Marz

level, poultry farms, FAO, USDA, MoH,

Avian Influenza field simulation

exercise

04.06.2008 101 MoA, FSVSI, RVDAC, FAO, WB,

USDA, MoH, local government agencies

(police, village mayors, marz governors),

community veterinarians,

Bio-safety 23.06.2008 38 FSVSI, RVDAC, community

veterinarians

Poultry diseases, their treatment

and prevention

24.06.2008 10 Poultry farms

PDS: Decisionmakers’ workshop 14.10.2008 24 FSVSI, RVDAC, MoH, AAU

PDS: Introductory training 11-14.11.2008 16 FSVSI, RVDAC, community

veterinarians

Leadership for Strategic Health

Communication

10-12.02.2009 37 FSVSI, RVDAC, MoH

PDS: Refresher training 2-5.03.2009 13 FSVSI, RVDAC

PDS: Result Workshop 5-7.05.2009 16 FSVSI, RVDAC

“Working Together for Armenian

Health Preparedness

18-20.05.2009 33 MoA, MoH (central and marz levels), for

Marz- level veterinarians and medical

officers

“The Role of Media during Health

Crisis Situation for Selected Media

Professionals”

21-22.05.2009 18 Media

Data management and analysis

(TADInfo)

21.07.2009 21 FSVSI, RVDAC

Serological training 22-26.07.2009 9 Marz lab technicians

Parasitological, bacteriological and

autopsy training

29.06-03.07.2009 9 Marz lab technicians

Emerging infections and

biosecurity

28.07.2009 … Lab technicians

Training in brucellosis 15-17.09.2009 20 Armenian Agrarian University faculty

and students

“Livestock Sector Biosafety,

Biosecurity, Field Diagnosis and

Immediate Control Measures”

12-16.10.2009

19-23.10.2009

47 FSVSI, Community Veterinarians, Farm

veterinarians, Lab technicians, Rapid

Response Team Members, Deputy Dean

Workshop on revision and

finalization of the Strategy on

Brucellosis

27-28.07.2010 14 MoA, MoH, PIU, FAO

MoA-Ministry of Agricultural

MoH- Ministry of Health

MoF- Ministry of Finance

RVDAC- Republican Veterinary Diagnostic and Anti-epidemic Center

FSVSI- Food Safety and Veterinary State Inspection

AAU- Armenian Agrarian University

FAO- Food and Agriculture Organization

PIU- Project Implementation Unit

Page 41: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

28

Annex 3. Economic and Financial Analysis

(including assumptions in the analysis)

A. Introduction

This analysis seeks to quantify the benefits of a scenario, a major HPAI outbreak in

Armenia, that did not (yet) materialize and for which solid empirical data are essentially

absent. It can, thus, only provide order-of-magnitude approximations. Moreover, the

project’s objective was to prepare the country for the eventuality of a major HPAI

outbreak, and with each passing year without such an outbreak the economic valuation of

the project diminishes because of discounting.

B. Project Costs

Project costs totaled US$10.5 million, comprising US$8.1 million from IDA and IDA-

administered Trust Funds and US$2.4 million equivalent from GOA. Annual

incremental recurrent O&M costs are assumed at 10% of the project investment costs,

which in turn were about 60% of total project expenditures in the human and animal

health sectors. The exchange rate used was US$1 = AMD 370. Conversion factors on

project costs were not used in this analysis.

Table 3.1: Project Costs (US$ ‘000)

2006 2007 2008 2009 2010 Total 2011-2025

(Annual)

IDA AIPP, Cr. 41780 42 1,862 988 1,352 1,112 5,355

IDA RESCAD, Cr. 40950 75 75

PHRD TF 56629 1 230 116 237 109 694

AHIF TF 58076 515 1,365 80 1,960

GOA 15 834 359 756 456 2,420

Total Project Costs 57 3,001 1,978 3,711 1,757 10,505

Recurrent incremental O&M costs 3 184 525 630 630

C. Project Benefits

The project benefits estimated are the cost of human hospitalizations averted, the income

losses avoided due to reduced rates of infection, hospitalization and deaths, and the

production losses of poultry meat and eggs averted. Other benefits, such as the much

improved capacity to detect and respond to other zoonoses and infectious diseases, or the

reduction in scale and cost of poultry culling and compensation programs due to better

surveillance and control measures are not considered. Secondary effects, such as the

prevention of abrupt and severe changes in poultry prices on farm incomes or consumer

incomes and of cross-price elasticity effects on other livestock subsectors were also

ignored.

It is assumed, for the base-case scenario, that a severe HPAI outbreak with a mutated

virulent virus would occur every five years, with the first one in 2011, after project

Page 42: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

29

completion. The time period for the benefits stream being considered is 2011-2025. A

discount rate of 12% per annum and an exchange rate of AMD 370/US$ were used.

1. Human Health Benefits

The project’s main impact on human health is to decrease the percentage of the human

population infected by HPAI, thereby decreasing the number of hospitalizations required

and decreasing the number of deaths attributable to HPAI. The benefits are therefore

expressed in terms of loss avoidance and include:

(i) the economic value of hospitalization costs averted: AMD 42,000 for an

average stay of 7 days per hospitalized person;

(ii) the economic value of income loss avoidance from days lost due to illness:

assumes 25% of the affected population would lose 3 days of take-home income

and 50% of the hospitalized survivors would lose 30 days of income, at a daily

wage of AMD 5000;8

(iii) income loss avoidance from fatal HPAI cases: average take-home income of

AMD 105,000/month over 15 years for all HPAI deaths prevented.9

For the base case, the incidence if HPAI infection among the human population (Gross

Attack Rate) was estimated at 5%, with 10% of those affected requiring hospitalization

and 3% of those affected dying from the disease (the Without-Project scenario).10 The

With-Project scenario estimates are that only 2% of the population would be affected by

HPAI infection, with 10% of the affected being hospitalized and a death rate of only

1.5% among those affected.

2. Poultry Sector Benefits

There are close to 11 million poultry in Armenia, mostly chickens, but also some ducks,

geese, guinea fowl and turkeys. About 70% of these birds are kept by medium and small

farms and or in household backyards. It is in these two segments of the poultry that the

risk of HPAI outbreaks is highest, since biosecurity at the large commercial poultry farms

is quite good.

The project’s impact on the poultry industry is to decrease the number of poultry infected

by HPAI and, thus, the number of poultry deaths caused by HPAI. Economic project

benefits arise therefore in terms of loss avoidance. They include:

(i) the economic value of poultry meat production loss avoided: the number of

broiler poultry deaths averted at the average live chicken farmgate price of

AMD 1750 per live chicken, and assuming that 50% of the birds killed are

broilers to be used for meat;

8 The other 50% are assumed to be children and retirement-age adults.

9 The number of persons in this group is assumed to decline by 2% annually, reflecting normal mortality

rates. 10

Similar World Bank projects used, at appraisal, Gross Attack Rates as high as 30%.

Page 43: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

30

(ii) the economic value of egg production losses avoided: an average of 150 eggs

per layer per year at a farmgate price of AMD 40 per egg, assuming that 50% of

poultry deaths are layer hens; and

(iii) the meat value of the layer hens at the end of their productive lives: assumed to

be 75% the value of a broiler.

For the present analysis, the poultry population affected by an outbreak (Gross Attack

Rate) of HPAI was estimated at 5% of the small farm and backyard poultry population --

a “low infection rate” scenario -- with a 100% mortality rate of the birds affected by

HPAI (the Without-Project scenario). In addition, an equal number of birds, in and

around the locations where HPAI outbreaks are confirmed, was assumed to be destroyed

through culling as a precautionary virus control measure.

The With-Project scenario assumes that only 2% of the small farm and household poultry

would be affected by HPAI and would die, and that an equal number would be destroyed

by the eradication program. The project can only affect the number of poultry that

become infected and that need to be culled, but it has no effect of decreasing the

mortality rate among the poultry flocks infected. As in the case of the human health

sector, the actual numbers of poultry affected by an HPAI outbreak are difficult to

estimate since there is little empirical information and a divergence of opinions within the

veterinary profession.

In the analysis, poultry production in the absence of an HPAI outbreak is assumed to

grow at a 2% annual rate.

D. Economic Rate of Return and Sensitivity Analysis

The analysis relates the project costs (Table 3.1) to the benefits from the economic value

stream of losses avoided as a result of project activities in human health and in the

poultry industry, expressed as the expected value of the economic loss avoided from an

outbreak occurrence once in three years during the period from 2011 to 2025. It is

expected that the benefits from the project expenditures on laboratories, equipment,

patient care facilities, public awareness programs and increased human capital will

continue to accrue over this entire 15-year period. The project investment costs were

incurred from 2006 to 2010.

The market prices used for poultry and poultry products are considered to be economic

prices, because the markets operate freely with no production quota system and no

subsidies for poultry or poultry inputs. Wages and other market prices used in the

analysis are also assumed to be economic prices.

Table 3.2 presents the results of the economic analysis based on the above base case

assumptions and parameters for the combination of both human health and poultry sector

losses avoided. The results are quite robust, with a 53% IRR, a benefit-cost ratio of 4.5

and a NPV of US$42.4 million.

Page 44: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

31

Table 3.2: Economic Returns and Sensitivity Analysis

Infection Rate

Humans

Mortality Rate

Humans

Infection Rate

Poultry 2006-2025

Scenario Without

project

With

project

Without

project

With

project

Without

project

With

project

NPV

(US$ mill.) IRR

C/B

ratio

1 outbreak every five years, first outbreak in 2011

1 (base case) 5.0 2.0 3.0 1.5 5.0 2.0 42.4 53 4.5

2 3.0 1.5 3.0 1.5 5.0 2.0 23.3 40 2.5

3 5.0 2.0 3.0 2.0 5.0 2.0 40.5 51 4.3

4 3.0 2.0 3.0 2.0 5.0 2.0 18.5 35 2.0

5 3.0 1.5 3.0 1.5 5.0 3.0 20.5 36 2.2

6 3.0 2.0 3.0 2.0 5.0 3.0 15.8 31 1.7

Only 50% of human health benefits attributed to the project

7 5.0 2.0 3.0 1.5 5.0 2.0 16.5 33 1.8

8 3.0 1.5 3.0 1.5 5.0 2.0 7.0 23 0.8

9 5.0 2.0 3.0 2.0 5.0 2.0 15.6 32 1.7

10 3.0 2.0 3.0 2.0 5.0 2.0 4.6 19 0.5

11 3.0 1.5 3.0 1.5 5.0 3.0 5.6 21 0.6

12 3.0 2.0 3.0 2.0 5.0 3.0 3.2 17 0.3

1 outbreak every three years, first outbreak in 2011

13 5.0 2.0 3.0 1.5 5.0 2.0 63.4 55 6.2

14 5.0 2.0 3.0 2.0 5.0 2.0 59.0 54 5.7

15 3.0 1.5 3.0 1.5 5.0 2.0 36.2 43 3.5

16 3.0 2.0 3.0 2.0 5.0 2.0 27.2 38 2.7

17 3.0 1.5 3.0 1.5 5.0 3.0 32.0 40 3.1

18 3.0 2.0 3.0 2.0 5.0 3.0 22.9 34 2.2

Only 50% of human health benefits attributed to the project

19 5.0 2.0 3.0 1.5 5.0 2.0 32.9 42 3.1

20 5.0 2.0 3.0 2.0 5.0 2.0 30.7 40 3.0

21 3.0 1.5 3.0 1.5 5.0 2.0 19.3 33 1.9

22 3.0 2.0 3.0 2.0 5.0 2.0 14.8 30 1.4

23 3.0 1.5 3.0 1.5 5.0 3.0 15.1 29 1.5

24 3.0 2.0 3.0 2.0 5.0 3.0 10.6 25 1.0

1 outbreak every seven years, first outbreak in 2011

25 5.0 2.0 3.0 2.0 5.0 3.0 28.0 42 2.7

26 3.0 1.5 3.0 1.5 5.0 2.0 16.2 33 1.6

27 3.0 2.0 3.0 2.0 5.0 3.0 9.7 25 0.9

Only 50% of human health benefits attributed to the project

28 5.0 2.0 3.0 2.0 5.0 3.0 11.1 27 1.1

29 3.0 1.5 3.0 1.5 5.0 2.0 6.3 22 0.6

30 3.0 2.0 3.0 2.0 5.0 3.0 1.9 15 0.2

The human health benefits substantially outweigh those in the poultry production sector.

The two parameters that drive the economic value of the human health benefits are (i) the

project impact on the percentage of the human population affected by HPAI infection,

Page 45: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

32

and (ii) the project effectiveness in reducing the expected mortality rate from HPAI

infection. The effects of changes made in these parameters can be significant, as depicted

in Table 3.2. Nevertheless, even with parameters indicating relatively small

improvements in the percentage of the human population affected by HPAI and in the

number of human deaths attributable to HPAI, the returns remain robust. For example,

Scenario 4 with very low impact rates of the project on the percentage of the human

population affected and the number of human deaths still renders an IRR of 35%, a B/C

ratio of 2.0 and a NPV of US$18.5 million,.

Changes in the key parameters for the poultry industry have less impact on the overall

outcomes. This is illustrated in Scenarios 5 and 6.

The timing of likely HPAI outbreaks has a significant influence on the results of the

analysis, since benefits begin to flow at different times and/or at lesser frequency.

Estimates were therefore made also for scenarios with a new HPAI outbreak only once in

three years and only once in every seven years, with the first one occurring in 2011. As

shown in Scenarios 25 through 27, a reduced frequency of HPAI outbreaks considerably

reduces the aggregate benefit stream. By the same token, more frequent outbreaks raise

the economic value of project benefits, as Scenarios 13 through 18 illustrate.

Finally, there is the question of ascribing all human health benefits simply to the AIPP,

when there was also the important Health Systems Modernization Project under

implementation in Armenia at the time, along with a substantial public awareness

program supported by USAID. It may thus be argued that the AIPP cannot claim the

total economic value steam of losses avoided, especially in human health. Scenarios 7

through 12, 19 through 24 and 28through 30 reflect the assumption that only half of the

human health benefits are attributable to the AIPP. The returns remain quite robust,

except when the human health impact assumptions are greatly scaled down and there is a

low frequency of HPAI outbreaks.11

E. Conclusion

Project benefits are primarily driven by key assumptions regarding the gross attack rate

for the human population and for the mortality rate among those affected as well as by

the likely frequency of HPAI outbreaks. This is to be expected in a project that is

intended to prepare for a contingency for which neither timing nor severity can be

reliably predicted.

The non-robustness of the Gross Attack Rates and death rate estimates for both humans

and poultry make the economic analysis less convincing than desired. Nevertheless, the

overall benefits from the project in terms of the decrease in human suffering and deaths

11 Separate rates of returns for human health benefits and for benefits to the poultry industry are not

presented, because AIPP project activities are an integrated package which would not be undertaken

separately.

Page 46: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

33

alone are significant and can be argued to justify this and other similar projects. The

economic returns are robust except under sensitivity analysis parameters that significantly

reduce the likely incidence of HPAI outbreaks and very severely restrict the project

benefits.

Page 47: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

34

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty Lending

Mark R. Lundell Lead Agricultural Economist ECSSD TTL

Frauke Jungbluth Senior Agricultural Economist ECSSD TTL

Arusyak Alaverdyan Operations Officer ECSSD Operations

Robert Bambauer Animal Health Specialist Cons. Animal health

Enis Baris Senior Health Specialist MNSHH Human health

Mario Bravo Senior Communications Officer EXTOC Communications

Amy Evans Safeguards Specialist ECSSD Safeguards

Artavazd Hakobyan Operations Analyst ECSSD Operations

Susanna Hayrapetyan Senior Health Specialist ECSH1 Human health

Arman Vatyan Senior Fin. Management Spec. ECSO3 Financial

management

Yingwei Wu Senior Procurement Specialist ECS ECA Procurement

Supervision/ICR

Frauke Jungbluth Senior Agricultural Economist ECSSD TTL

Brian G. Bedard Senior Livestock Specialist ECSSD TTL, animal health

Mario Bravo Senior Communications Officer EXTOC Communications

Amy Evans Safeguards Specialist ECSSD Safeguards

Artavazd Hakobyan Operations Officert ECSSD Operations

Susanna Hayrapetyan Senior Health Specialist ECSH1 Human health

Arman Vatyan Senior Fin. Management Spec. ECSO3 Financial

management

Yingwei Wu Senior Procurement Specialist ECS ECA Procurement

Gotz Schreiber Economist Cons. Compensation Fund

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY06 23.43 83.42

FY07 0.01 0.07

Total: 23.44 83.49

Supervision/ICR

FY06 1.35 0.75

FY07 32.86 84.80

FY08 30.11 103.77

FY09 27.36 102.75

FY10 24.38 94.05

FY11 5.32 25.42

Total: 168.26 578.52

Page 48: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

35

Annex 5. Beneficiary Survey Results

(if any)

n/a

Page 49: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

36

Annex 6. Stakeholder Workshop Report and Results

(if any)

n/a

Page 50: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

37

Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR

There were no significant comments from the borrower. The response from the

Government was as follows:

“I have reviewed ICR and I have no comments. It is fine from our point of view.”

Gagik Khachatryan

Agriculture Reform Support PIU

54B, Komitas ave.

Yerevan, PO 375014

Armenia

Phone: (37410) 297301, 297302, 297303

Fax: (37410) 297308

Page 51: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

38

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders

N/A

Page 52: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

39

Annex 9. List of Supporting Documents

1. Republic of Armenia, Avian Influenza Preparedness (AIP) Project, Project Appraisal

Document, World Bank, 1 May 2006, Report No. 35392-AM

2. Environmental Assessment and Management Plan for the Armenia Avian Influenza

Preparedness Project, Yerevan, 2006

3. Aide Memoires 2006-2010

4. Implementation Status Reports 2006-2010

5. Letters to the Government 2006-2010

6. MTR and Restructuring Documents

7. Project Operational Manual, Yerevan, August 2006

8. Armenia CJCS, “Implementation Completion Report” (Final Evaluation and

Preparation of Implementation Completion report on Behalf of the Government of

Armenia), Yerevan, July 2010

Page 53: The World Bank€¦ · PPE Personal Protective Equipment QAE Quality at Entry ... 03/09/2006 Effectiveness: 09/05/2006 09/05/2006 Appraisal: 03/13/2006 Restructuring(s): ... productivity

40

MAP

I N S E R T

M A P

H E R E

AFTER APPROVAL BY COUNTRY DIRECTOR

AN ORIGINAL MAP OBTAINED FROM GSD MAP DESIGN UNIT

SHOULD BE INSERTED

MANUALLY IN HARD COPY

BEFORE SENDING A FINAL ICR TO THE PRINT SHOP.

NOTE: To obtain a map, please contact

the GSD Map Design Unit (Ext. 31482)

A minimum of a one week turnaround is required