the world bank for official use onlydocuments.worldbank.org/curated/en/584941468341086125/...p. o....

42
Document of The World Bank FOR OFFICIAL USE ONLY Report No: 60183-TZ PROJECT PAPER ON A PROPOSED ADDITIONAL CREDIT IN THE AMOUNT OF SDR 36.4 MILLION (US$ 59 MILLION EQUIVALENT) TO THE UNITED REPUBLIC OF TANZANIA FOR THE TRANSPORT SECTOR SUPPORT PROJECT June 6, 2011 Transport Sector Country Department AFCE1 Africa Region This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: duonghanh

Post on 23-Mar-2018

238 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

Document of

The World Bank

FOR OFFICIAL USE ONLY

Report No: 60183-TZ

PROJECT PAPER

ON A

PROPOSED ADDITIONAL CREDIT

IN THE AMOUNT OF SDR 36.4 MILLION

(US$ 59 MILLION EQUIVALENT)

TO THE

UNITED REPUBLIC OF TANZANIA

FOR THE

TRANSPORT SECTOR SUPPORT PROJECT

June 6, 2011

Transport Sector

Country Department AFCE1

Africa Region

This document has a restricted distribution and may be used by recipients only in the

performance of their official duties. Its contents may not otherwise be disclosed without World

Bank authorization.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

CURRENCY EQUIVALENTS

Exchange Rate Effective April 30, 2011

Currency Unit = Tanzania Shilling (TZS)

TZS 1,508.50 = US$1

US$1.621 = SDR 1

FISCAL YEAR

July1 – June 30

ABBREVIATIONS AND ACRONYMS

AF Additional Financing

AfDB Africa Development Bank

AGL Aeronautical Ground Lighting

BADEA Arab Bank for Economic Development in Africa

CAS Country Assistance Strategy

CD Chart Datum

CODAP Coordination of Donor Aided Projects

COST Construction Sector Transparency

CTCP2 Second Central Transport Corridor Project

CPS County Partnership Strategy

CQS Cost and Qualification Selection

DANIDA Danish International Development Agency

DFID Department for International Development

DP Development Partner

DVELA Driver and Vehicle Examination and Licensing Agency

EC European Commission

EIA Environmental Impact Assessment

EMP Environmental Management Plan

ESIA Environmental and Social Impact Assessment

FA Financing Agreement

FBS Fixed Budget Selection

FM Financial Management

GoT Government of Tanzania

GoZ Revolutionary Government of Zanzibar

IATA International Air Transport Association

IBRD International Bank for Reconstruction and Development

IC Individual Consultant

ICB International Competitive Bidding

IDA International Development Association

IFMS Integrated Financial Management System

IFR Interim Financial Report

IRP2 Second Integrated Roads Project

ISR Implementation Status and Results Report

Page 3: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

JICA Japan International Cooperation Agency

JISR Joint Infrastructure Sector Review

LCS Least Cost Selection

MCC Millennium Challenge Corporation

MKUKUTA Mkakati wa Kukuza Uchumi na Kupunguza Umaskini Tanzania

Growth and Poverty Reduction Strategy for mainland Tanzania)

MKUZA Mkakati wa Kukuza Uchumi na Kupunguza Umaskini Zanzibar (Growth and Poverty Reduction Strategy for Zanzibar)

MoIC Ministry of Infrastructure and Communications, Zanzibar

MOID Ministry of Infrastructure Development

MoT Ministry of Transport

MoW Ministry of Works

NCB National Competitive Bidding

NRSA National Road Safety Agency

NYD Not Yet Due

OP/BP Operational Policy/Bank Procedure

OPEC Organization of the Petroleum Exporting Countries

ORAF Operational Risk Assessment Framework

PAD Project Appraisal Document

PDO Project Development Objective

PEFAR Public Expenditure and Financial Assessment Review

PFM Public Financial Management

PFMRP Public Financial Management Reform Program

PMO-RALG Prime Minister‟s Office - Regional Administration and Local Government

PMU Project Management Unit

PPP Public Private Partnership

PPRA Public Procurement Regulatory Authority

PRSC Poverty Reduction Support Credit

RAIS Road Accident Information System

RAP Resettlement Action Plan

SDR Special Drawing Rights

SIL Specific Investment Loan

SSS Single Source Selection

TAA Tanzania Airports Authority

TANROADS Tanzania National Roads Agency

TPA Tanzania Port Authority

TSIP Transport Sector Investment Program

TSSP Transport Sector Support Program

TZS Tanzanian Shillings

Vice President: Obiageli Katryn Ezekwesili

Country Director:

Sector Director:

John Murray McIntire

Jamal Saghir

Sector Manager: Supee Teravaninthorn

Task Team Leader: Negede Lewi

Page 4: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National
Page 5: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

UNITED REPUBLIC OF TANZANIA

TRANSPORT SECTOR SUPPORT PROJECT ADDITIONAL FINANCING

CONTENTS

Additional Financing Data Sheet .............................................................................................. i

I. Introduction ........................................................................................................................... 1

II. Background and Rationale for Additional Financing ...................................................... 1

III. Proposed Changes .............................................................................................................. 3

IV. Appraisal Summary ........................................................................................................... 6

Annex 1: Results Framework and Monitoring ................................................................... 10

Annex 2: Operational Risk Assessment Framework (ORAF) ........................................... 15

Annex 3: Detailed Description of New Project Activities ................................................... 18

Annex 4: Revised Project Costs ............................................................................................ 24

Annex 5: Revised Economic Analysis .................................................................................. 25

Annex 6: Procurement ........................................................................................................... 26

Page 6: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National
Page 7: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

i

UNITED REPUBLIC OF TANZANIA

TRANSPORT SECTOR SUPPORT PROJECT

ADDITIONAL FINANCING DATA SHEET

Basic Information - Additional Financing (AF)

Country Director: John M. McIntire

Sector Manager: Supee Teravaninthorn

Team Leader: Negede Lewi

Project ID: P126206

Expected Effectiveness Date: October 30, 2011

Lending Instrument: Specific Investment Loan

(SIL)

Additional Financing Type: Restructuring and

Scale Up‟

Sectors: Aviation (97%); and Ports (3%).

Themes: Infrastructure services for private sector

development (30%); Rural services and

infrastructure (40%); and Trade and Facilitation

(30%)

Environmental category: Category B – Partial

Assessment

Expected Closing Date: June 30, 2015

Joint IFC: NO

Joint Level: N/A

Basic Information - Original Project

Project ID: P055120 Environmental category: Category B –Partial

Assessment

Project Name: Transport Sector Support Project Expected Closing Date: June 30, 2015

Lending Instrument: Specific Investment Loan

(SIL)

Joint IFC: NO

Joint Level: N/A

AF Project Financing Data

[ ] Loan [ X ] Credit [ ] Grant [ ] Guarantee [ ] Other:

Proposed terms: Standard IDA Credit Terms

AF Financing Plan (US$m)

Source Total Amount (US $m)

Total Project Cost:

Co-financing:

Borrower:

Total Bank Financing:

IBRD

IDA

New

Recommitted

59.00

0.00

0.00

0.00

59.00

Page 8: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

ii

Client Information

Recipient:

Ministry of Finance

P. O. Box 9111

Dar es Salaam - Tanzania

Fax: +255 22 2117790

Agencies:

Tanzania National Roads Agency

Eng. Patrick A. L. Mfugale, CE

P. O. Box 11364

Dar es Salaam - Tanzania

Telephone No.: +255 22 2926001/6

Fax No.: +255 22 2926011

Email: [email protected]

Ministry of Infrastructure and Communications (MoIC) Zanzibar

Dr. Vuai I. Lila

Principal Secretary, MoIC

Zanzibar

Emails: [email protected]; [email protected]

Tel: +255 24 2232841

Dir: +255 24 2231391

Mob: +255 777 413080

+255 784 304180

Fax: +255 24 2231465

Prime Minister‟s Office - Regional Administration and Local Government (PMO-RALG)

Mrs. Eline Kayanda

Engineer

PMO – RALG

Mob: +255 713448835

Email: [email protected]

AF Estimated Disbursements (Bank FY/US$m)

FY 2012 2013 2014 2015

Annual 5.00 20.00 20.00 14.00

Cumulative 5.00 25.00 45.00 59.00

Page 9: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

iii

Project Development Objective and Description

Original project development objectives: The project development objectives (PDOs) are to

improve the condition of the national paved road network, to lower transport cost on selected

roads, and to expand the capacity of selected regional airports.

The PDO has been revised to reflect the additional activities financed under the Additional

Financing. The revised PDOs are: to improve the condition of the national paved road network, to

lower transport cost on selected roads and to Songo Songo Island, and to expand the capacity of

selected airports.

Project Description

1. Component A: (IDA financing US$ 186.5 million) Rehabilitation and upgrading of the

Korogwe – Mkumbara - Same and Arusha – Minjingu roads, and the preparation of design

and bidding documents for about 911 km of national roads, and capacity building for

TANROADS.

2. Component B: (IDA financing US$ 57.5 million) Paving and rehabilitation of the runway

at Kigoma airport, and Tabora airports; Extension, rehabilitation and paving of the runway

and the replacement of the apron, terminal and car parking at Bukoba airport.

3. Component C: (IDA financing US$ 6.0 million) Improved road safety management by

supporting the establishment of (i) a National Road Safety Agency (NRSA), (ii) a Driver

and Vehicle Examination and Licensing Agency (DVELA) and (iii) a Road Accident

Information System (RAIS).

4. Component D: (IDA financing US$ 5.0 million) Promotion of public private partnerships

(PPP) through: (i) capacity building for the implementation of PPP projects, (ii) feasibility

studies for potential PPP projects, and (iii) Provision of transaction advisors for projects

found feasible.

5. Component E: (IDA financing US$ 5.0 million) Emergency repair of parts of national

roads and bridges damaged by floods in one hundred locations throughout Tanzania.

The proposed additional credit would help finance the costs associated with:

1. Component B2: (IDA financing US$ 57.0 million) Rehabilitation and extension of

Zanzibar airport taxiways and apron. (Scale up of the airport component)

2. Component F: (IDA financing US$ 2.0 million) Rehabilitation of the Songo Songo Island

jetty. (New component added)

Page 10: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

iv

Safeguard and Exception to Policies

Safeguard policies triggered:

Environmental Assessment (OP/BP 4.01)

Natural Habitats (OP/BP 4.04)

Forests (OP/BP 4.36)

Pest Management (OP 4.09)

Physical Cultural Resources (OP/BP 4.11)

Indigenous Peoples (OP/BP 4.10)

Involuntary Resettlement (OP/BP 4.12)

Safety of Dams (OP/BP 4.37)

Projects on International Waters (OP/BP 7.50)

Projects in Disputed Areas (OP/BP 7.60)

Yes

No

No

No

Yes

No

Yes

No

No

No

Does the project require any exceptions from Bank policies?

Have these been approved by Bank management?

Yes

Yes

Conditions and Legal Covenants:

Financing Agreement

Reference

Description of Condition/Covenant Date Due

Article V - 5.01 The Implementation Agreement has been duly

executed on behalf of the Recipient and

TANROADS, and the Project Implementation

Plan has been adopted.

By Effectiveness

Article V - 5.02 The Implementation Agreement has been duly

authorized or ratified by the Recipient and

TANROADS and is legally binding upon the

Recipient and TANROADS in accordance with

its terms.

By Effectiveness

Schedule 2

Section I E.2

The Recipient shall: (a) not later than thirty

days after Effectiveness, open and maintain an

escrow account in a commercial bank on terms

and conditions satisfactory to the Association,

including appropriate protection against set-off,

seizure or attachment (“Escrow Account”); (b)

thereafter, but not later than December 31, 2011,

deposit into the Escrow Account such amounts

as shall be required pursuant to the RAP to pay

compensation to the Affected Persons; and (c)

ensure that all amounts so deposited into the

Escrow Account shall be exclusively used to

pay compensation to the Affected Persons in

accordance with the RAP.

Thirty days after

Effectiveness

Page 11: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

1

I. Introduction

1. This Project Paper seeks the approval of the Executive Directors to provide an additional

credit in an amount of US$59 million to the United Republic of Tanzania for the Transport

Sector Support Project (TSSP); (P055120, Credit number 4724-TZ).

2. The proposed Additional Credit would help finance the costs associated with: (i) a scale

up of the airport component of the project, through the rehabilitation and extension of the

Zanzibar airport taxiways and apron, and (ii) the addition of a new component, the rehabilitation

of the Songo Songo Island Jetty. The PDO is also being revised to reflect the additional activities

financed under the Additional Financing. The closing date of the project will remain as per the

original project, i.e. June 30, 2015.

II. Background and Rationale for Additional Financing

3. Country Context: The modified and scaled-up activities under the Additional Financing

(AF) are fully consistent with the development objectives of the project as well as with the

country‟s poverty reduction strategy (Kiswahili acronym MKUKUTA II), the Zanzibar Strategy

for Growth and Reduction of Poverty (Kiswahili acronym MKUZA II), and the Bank‟s Country

Assistance Strategy (CAS) of March 1, 2007, which all emphasize the need for improved

transport infrastructure. The activities included under the AF are also aligned with and would

contribute to the economic and social objectives of the World Bank‟s New Africa Strategy of

March 2011 through the provision of increased connectivity and transport facilitation in the

project areas.

4. Transport Sector Investment Program (TSIP): The activities are also consistent with the

10 year Tanzania TSIP (2007/08-2016/17) which the TSSP is supporting in partnership with the

different Donors including the African Development Bank (AfDB), the Japan International

Cooperation Agency (JICA), the European Commission (EC), the Danish International

Development Agency (DANIDA), the Millennium Challenge Corporation (MCC), the

Department for International Development (DFID), the World Bank, as well as Korea, Kuwait,

Abu Dhabi, the Arab Bank for Economic Development in Africa (BADEA) and Organization of

the Petroleum Exporting Countries (OPEC). Donor Partners are well coordinated in a Transport

Sector Development Partner group whose secretariat is provided by the EC. Annual Joint

Infrastructure Sector Review (JISR) meetings are being held where the implementation of TSIP

is being reviewed and progress monitored through a joint Performance Assessment Framework

linked to the growth cluster of the MKUKUTA. Joint (GoT-DP) Technical Committee meetings

are held quarterly to review progress of the implementation of the action program agreed during

the JISR meetings. The same country partnership strategy (CPS) would be followed under the

AF.

5. Original credit and AF: The original credit amount is US$270 million. The credit was

approved on May 27, 2010 and became effective on December 1, 2010. It supports the three

years slice of the TSIP through the rehabilitation and preparation of designs for part of the paved

national road network, and the rehabilitation and/or upgrading of regional airports. It also

supports the establishment of the National Road Safety Agency (NRSA) and Driver and Vehicle

Examination and Licensing Agency (DVELA), and a Road Accident Information System. The

Page 12: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

2

project promotes public private partnerships (PPP) through: (i) capacity building for the

implementation of PPP projects, (ii) feasibility studies for potential PPP projects, and (iii)

provision of transaction advisors for projects found feasible. It also supports the emergency

repair of parts of the national roads and bridges damaged by floods in 2009/2010 in 21 regions.

The Project Development Objectives (PDOs) are to improve the condition of the paved national

road network, to lower transport cost on selected roads, and to expand the capacity of selected

regional airports. The PDO has been revised to better focus the objectives of the project. The

scope of the project however is being expanded by a scale up of the airport component, through

the rehabilitation and extension of the Zanzibar airport taxiways and apron, and (ii) the addition

of a new component, the rehabilitation of the Songo Songo Island jetty.

6. Implementation Performance: The achievement of the PDO, overall implementation

progress, and sub-ratings of the project are all satisfactory except for procurement which was

rated moderately unsatisfactory, during February 2011 supervision mission, due to some delays

in implementing the agreed procurement plan. The delays were attributable to inadequate

procurement capacity at Tanzania National Roads Agency (TANROADS) due to excessive

workload. With the recruitment of three additional procurement specialists in December 2010,

there are signs that the project performance with regard to procurement is improving. The

emergency repair of parts of the national roads and bridges damaged by floods in 2009/2010 has

been progressing well with the implementation of 106 small contracts in 21 regions. As of

February 28, 2011 about 585 kilometers of roads has received emergency maintenance while 212

culverts were reconstructed. The recruitment of consultants and contractors for the other

components of the project has now reached an advanced stage after delays in implementing the

agreed procurement plan. The International Development Association (IDA) has already given

the no objection to award one of the major roads contracts (US$50.38 million), while the bids for

the remaining two roads and three airports works contracts are under evaluation. Competition for

the works has been satisfactory, and the lowest evaluated and/or lowest priced bids are generally

within appraisal estimates.

7. Rationale: The Borrower has requested the additional financing in its letter dated March

30, 2011. The key rationale for such request is the huge need for infrastructure and the limited

capacity for local financing. The request comes at this early stage of implementation because

Tanzania would like to make use of IDA-15 allocation for these high priority sub-projects, and

also because of their readiness for implementation. As less than 12 months have elapsed since

effectiveness of the project a waiver was required for such early processing of an AF and was

received from the Regional Vice President (RVP) Africa Region on April 20, 2011.

8. Foreseen risk factors: The risk of the original project and in the Operational Risk

Analysis Framework (ORAF) found in Annex 2 is assessed as Medium- Likelihood. One of the

main risks related to the weakness of the procurement capacity of TANROADS has been

remedied through the employment of additional procurement specialists. The additional finance

credit involves two additional implementing ministries, the Ministry of Infrastructure and

Communications Zanzibar (MoIC) and Prime Minister‟s Office - Regional Administration and

Local Government (PMO-RALG). MoIC Zanzibar is involved in the execution of the Second

Central Transport Corridor Project (CTCP2) and is being strengthened through this project.

Page 13: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

3

Appropriate measures will be taken to enhance and assist PMO-RALG to implement the Songo

Songo Island jetty improvement.

9. Governance in Transport Sector: Tanzania completed the process of formation of

agencies to provide autonomy in project implementation through the creation of TANROADS in

2000 under the executive agencies act, 1997. The process has worked well, even though the level

of autonomy of TANROADS needs to be further strengthened. TANROADS has robust

professional capacity and systems to ensure responsible and efficient project implementation.

The Roads Fund Board was established in 1998 to ensure the availability of sufficient funds for

maintenance of roads through the levy of a surcharge on fuel. This innovation has resulted in the

availability of sustainable funding for roads maintenance. The Tanzania Airports Authority

(TAA) was established as a semi-autonomous agency under the Ministry of Transport (MoT) in

1999 under the executive agencies act, 1997. TAA is planned to become fully autonomous,

corporate body, and the drafting of the Bill is ongoing (planned to be finalized in 2012). On the

maritime transport side, Tanzania Ports Authority (TPA) is a corporate body under the MoT

since 2004. TPA is planned to become a landlord port whereby all/most operations at the ports

will be done by the private sector. TPA is currently developing a strategy to that effect. Tanzania

has been a pilot country under the Construction Sector Transparency (COST) initiative since

2008. The first public disclosure of project information was made in February 2011, the case of

six major government projects. This initiative will be carried forward and strengthened.

III. Proposed Changes

10. The PDO has been revised to reflect the additional activities financed under the

additional financing. The reworded objective is to improve the condition of the national paved

road network, to lower transport cost on selected roads and to Songo Songo Island, and to

expand the capacity of selected airports.

11. The AF will improve: (i) the Zanzibar Airport allowing for a substantial increase in

passenger traffic and aviation safety, and stimulate the island‟s tourism sector which is the

mainstay of the local economy, (ii) access to Songo Songo Island. The monitoring indicators

have also been revised to reflect the contributions of the activities towards the project objective.

12. There will be two additional implementing ministries, the MoIC, Zanzibar and PMO-

RALG. There has been longstanding collaboration with both, the MoIC under the on-going

CTCP2, and the PMO-RALG under the completed CTCP.

13. Rehabilitation and Extension of Zanzibar Airport Taxiways and Apron: This is a scale up

of the airport component of the TSSP. The AF will finance the works and the associated

supervision services to rehabilitate, expand and/or extend the existing taxiways and apron.

Under the on-going CTCP2 the runway of the Zanzibar airport was extended and rehabilitated

and works were completed in August 2010. In addition to enhancing the development impact of

the investments made under CTCP2, as the Revolutionary Government of Zanzibar (GoZ) has

secured a loan from the China Exim Bank to finance a new terminal building, the funds proposed

under the AF would materialize the full financing of the airport investments needs. The air traffic

at Zanzibar airport is expected to grow from today‟s 0.5 million passengers to 1.3 million by

Page 14: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

4

2030. This increasing traffic coupled with the deteriorated condition of the taxiways and apron

makes their rehabilitation and expansion very urgent. The bottlenecks with regards to the apron

and taxiway can even be seen in current operations of the airport. Since the longest taxiway

(taxiway C) has deteriorated to the extent that it can no longer be used by large aircraft, and the

taxiway to the northern end of the runway (taxiway A) is too close to surrounding buildings, only

one remaining taxiway (taxiway B) is usable. Often the apron gets so filled up with aircraft that

additional arriving aircraft need to park on the taxiway. At this point the runway becomes

inaccessible to larger aircraft on the apron, until taxiway B has been cleared.

14. Songo Songo Island Jetty: The rehabilitation of the jetty is not only an essential transport

facility to the Songo Songo Island but also a recommended social mitigation measure for the

closed Bank financed Songo Songo gas extraction project (P002797). During the implementation

of the Songo Songo gas extraction project, the existing jetty on Songo Songo Island was taken

over by the project and a new jetty was constructed on the western shoreline of the island for the

use of the Songo Songo villagers. This new jetty has not been providing satisfactory services for

the villagers, as it submerges during high spring tidal periods. As the jetty is constructed on a

drying foreshore, it cannot be used at low spring tidal periods or allow local craft to remain

safely afloat at all states of the tide. The aim is to assist to rectify the situation and the project

interventions would include: (a) raising the height and increasing the width of the existing

structure and extending it to deeper water allowing local boats access during low spring tidal

periods; and (b) constructing a breakwater to minimize the effects of adverse weather on the site

of the jetty; and construction of ramps and stairs. Since the Songo Songo Energy Project closed

on December 31, 2010 it was decided that this component would be attached to the Transport

Sector Support Project (TSSP).

Changes to Project Outcome Indicators

15. Table 1 below shows the changes of the project‟s outcome indicators:

Table 1: Changes to the Project Outcome Indicators

Indicator Original target Changes with

AF

Revised target

Average vehicle

operating cost on

Korogwe – Same road

Down to 23 US cents from

34 US cents per kilometer by

FY13/14

No changes No revision

Average vehicle

operating cost on

Arusha – Minjingu road

Down to 25 US cents from

45 US cents per kilometer in

FY13/14

No changes No revision

Roads in good and fair

condition as a share of

total classified roads

Improvement from 66% in

FY08/09 to 70% in FY13/14 No changes No revision

Passenger volume at

Bukoba Airport Up from 26,628 in FY08/09

to 34,000 in FY2013/14 No changes No revision

Passenger volume at

Kigoma airport Up from 28,859 in FY08/09

to 40,000 in FY2013/14 No changes No revision

Passenger volume at

Tabora airport Up from 22,912 in FY08/09

to 30,000 in FY2013/14 No changes No revision

Page 15: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

5

Passenger volume at

Zanzibar airport New sub-component New target Up from 0.5 million in

FY09/10 to 0.66 million

in FY13/14 Project Beneficiaries Direct beneficiaries: 5.15

million (of which female-

percentage)

Increased

beneficiaries Direct beneficiaries

revised to 5.7 million

Revised Project Costs

16. Table 2 below shows the changes of the project cost by component.

Table 2: Revised Project Costs by Component (US$ million)

Component Original

Cost (IDA

only)

Changes with

AF Revised Cost

A. Rehabilitation and preparation of designs for

rehabilitation of paved trunk roads 186.5 - 186.5

B. Improvement of airports

B1. Improvement of Regional airports

B2. Improvement of Zanzibar airports

57.5 57.5

57.0 57.0

C. Improvement of road safety 6.0 - 6.0

D. Promotion of public-private partnerships 5.0 - 5.0

E. Emergency Road and Bridge Repair 15.0 - 15.0

F. Rehabilitation of Songo Songo Island Jetty (new) - 2.0 2.0

Total 270.0 59.0 329.0

Institutional Implementation Arrangements

17. The Component B2 will be implemented by the Zanzibar MoIC, while component F will

be implemented by PMO-RALG. The TANROADS would continue to be responsible for the

overall coordination of the projects including: (i) the management of the designated account; (ii)

financial management and reporting of the overall project; (iii) ensuring the execution of the

audit of the project; (iv) preparation of quarterly financial and bi-annual progress reports with

inputs from PMO-RALG and MoIC; and (v) oversight of the procurement and contract

management activities of the other executing agencies. In order to ensure that the project is

effectively implemented TANROADS, PMO-RALG and MoIC will ensure that appropriate

staffing arrangements are maintained throughout the life of the project.

18. The MoIC would keep the existing project management arrangements, for the

implementation the airport component of the CTCP2, over the period of the implementation of

the AF. This includes keeping a Project Manager, holding such qualifications and experience

Page 16: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

6

acceptable to the World Bank, who will be managing the implementation of the component. The

Project Manager will directly report to the Permanent Secretary of MoIC and will be responsible,

among others, for the overall implementation of the Component B2. The Project Manager will:

(i) oversee all the activities of the contractor and supervising consultant and provide appropriate

guidance and direction to them as required, (ii) deal with all project correspondences

appropriately, (iii) review payments certificate prepared by supervising consultant to approval

for payment by the Permanent Secretary, (iv) deal with claims emanating from the construction

contracts, and (v) closely monitor safety and operations at site. MoIC would continue providing

the Project Manager with such facilities as will enable him or her to perform the assignment

effectively during the duration of the project. These include, but are not limited to, an office,

transport, IT facilities and connection, and support staff.

19. The PMO-RALG in collaboration with the District Council at Kilwa shall be responsible

for implementation of Component F of the project including approval of the designs,

procurement of works and services and supervision of construction. PMO-RALG headquarters

shall assign a Project Coordinator who will be responsible for the implementation of the

component. PMO-RALG through the Local Government Authorities (LGA) in Kilwa will ensure

that Local communities are involved in the rehabilitation operation and maintenance of the jetty

as part of community participation through employment. PMO-RALG will pursue the creation of

Local Community Jetty Management Committee and ensure that through the LGA in Kilwa the

capacity of the committee is developed in order to carry out routine maintenance to inculcate to

them a sense of ownership and ensure sustainability of the jetty.

20. After the election in Tanzania held in October 2010, GoT split the Ministry of

Infrastructure Development (MOID), that was responsible for the implementation of the

component C and D of the TSSP, into two ministries, namely Ministry of Transport (MoT) and

Ministry of Works (MoW). The split have no adverse effect on the performance of the project as

the MoW and MoT took over the responsibility for the implementation of the Component C and

D of the project, respectively.

IV. Appraisal Summary

Economic

21. The overall cost for the airport, including the work already done on the runway surface

and extension, under the CTCP2 is estimated to be US $ 105.60 million. Moving data from the

2004 Tanzania Tourism Sector Survey forward, with an annual income growth rate of two

percent representing the growth in spending per tourist, it was estimated that tourism expenditure

in Zanzibar per passenger will rise from US$248.82 in 2013 to US$624.90 in 2032, with

additional income due to the added passenger flows created by the project, growing from an

annual total of US$14.30 million in 2013 to US$190 million annually in 2032. Measuring the

local benefits estimated to be gained in fishing, agriculture, and other business ventures, in the

same periods the overall estimated benefit for the period is US$1,680.60 million. The entire

project investment was then discounted against revenues for the 20 year period between 2012

and 2030. The results show an internal rate of return of 12.3 percent, and a positive net present

value (NPV) of US$198.23 million at a discount rate of 12 percent.

Page 17: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

7

Financial Management

22. There are no changes being proposed to the financial management (FM) arrangements of

the original Credit under TSSP. The designated account under the original financing will also be

used for the additional financing. The financial reporting for the additional financing will be

integrated into the financial reports for the original credit, and figures for each financing

separately reported therein. The entire additional financing management would be coordinated

and managed by TANROADS, using the existing TSSP FM arrangements which have been

found to be satisfactory. The FMS risk rating is moderate. This includes the accounting, planning

and budget, internal and external audit, flow of funds, and submission of Interim Financial

Reports (IFRs). The assessment of TANROADS financial management capacity took into

consideration the FM performance of the IDA projects (CTCP2 and TSSP) currently being

implemented by TANROADS, and the CTCP which closed in December 2009 which are rated

satisfactory. A review of the TANROADS‟ latest available unqualified audit reports for the years

ended June 30, 2008, 2009, and 2010 were found to be satisfactory.

Procurement Arrangements

23. The procurement arrangement for the proposed AF would include two additional

implementing entities. The procurement for the Component B2 will be implemented by the

Zanzibar MoIC, while that of the Component F will be implemented by PMO-RALG. However

the TANROADS would continue to be responsible for the oversight of the procurement and

contract management activities of the two agencies. Procurement for the proposed Additional

Financing would be carried out in accordance with the World Bank‟s "Guidelines: Procurement

of Goods, Works and Non Consulting Services under IBRD Loans and IDA Credits & Grants by

World Bank Borrowers" dated January 2011; and "Guidelines: Selection and Employment of

Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated

January 2011; Guidelines on Preventing and Combating Fraud and Corruption in Projects

Financed by IBRD Loans and IDA Credits and Grants, dated October 15, 2006 and revised in

January 2011; and the provisions stipulated in the Legal Agreement. For each contract to be

financed by the Credit, the different procurement methods or consultant selection methods, the

need for pre-qualification, estimated costs, prior review requirements, and time frame are agreed

between the Recipient and the Bank in the Procurement Plan. A separate Procurement Plan has

been prepared for the AF to take into account the methods and thresholds applicable. The

Procurement Plan will be updated at least annually, or as required, to reflect the actual project

implementation needs and improvements in institutional capacity. Procurement capacity

assessment for MoIC of the GoZ was carried out on April 6, 2011 and is presented in Annex 6.

24. The procurement performance of the project was rated moderately unsatisfactory during

the last supervision mission, due to some delays in implementing the agreed procurement plan.

However, with the recent spurt in procurement advances (due theoretically in part to the

Recipients‟ response to the moderately unsatisfactory (MU) rating) contracts that account for

some 96 percent of the credit amount are expected to be committed by June 2011 and hence the

original project is on track for rapid implementation and disbursement. Please refer to Tables 4

Page 18: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

8

and 5 of Annex 6 for the progress of procurement and actions and/or timing agreed in the

processing of each of the contracts included in the original procurement plan.

Social and Environmental Safeguards

25. Zanzibar airport taxiway and apron rehabilitation and extension: An Environmental and

Social Impact Assessment (ESIA) was prepared, approved by the Bank and was disclosed in

Zanzibar on January 18, 2011 and at the Bank‟s InfoShop on January 20, 2011. Environmental

impacts are standard such as air quality reduction due to noise and end equipment emissions

during construction, and the loss of vegetation in areas to be surfaced. Appropriate mitigation

measures have been included in the bidding documents. As most of the works included under the

additional financing involve the rehabilitation and improvement of existing facilities, the

possibility of construction activities affecting physical and cultural sites of national and

international importance is unlikely. However if any physical cultural resource such as burial and

archeological sites is identified during project implementation, the supervising engineers will

ensure that the contractor will implement appropriate measures. These would include informing

local authorities and the Antiquities Department; and preparing an appropriate mitigation plan,

which will be approved before commencing any works in that area, as provided in the

Operational Policy (OP) 4.11 procedure. Guidelines for “chance finds” procedure will be

integrated into the contracts for construction and road maintenance consultants. A Resettlement

Action Plan (RAP) has been prepared, was approved by the Bank and was disclosed in Zanzibar

on January 18, 2011 and at the Bank‟s InfoShop on January 20, 2011. Resettlement is only

triggered by the extension of the taxiway C, which would be done after the completion of the

taxiway rehabilitation and, apron extension and rehabilitation. Seventeen households with both

finished and unfinished houses and 27 small farms are affected. An appropriate relocation site

has been identified nearby. Estimates for the cost of the resettlement are TZS 2 billion and are to

be financed by GoZ. Relevant stakeholders in Zanzibar were consulted during the assessment

exercise. These include project proponent, Ministry of Water, Construction, Energy, Lands and

Environment; and communities surrounding the airport. Zanzibar Airport Management will

create an Environmental control Unit which will be responsible for monitoring the application of

the prepared Environmental Management Plan (EMP) as well as dealing with the mitigation of

unforeseen issues.

26. Improvement of the Songo Songo Island Jetty: There are no outstanding social safeguard

issues regarding the Songo Songo Island Jetty since the RAP for this component, which

originally was under Songo Songo Gas Extraction Project was fully implemented. An

Environmental Impact Assessment (EIA) study for the proposed extension and rehabilitation of

the jetty has been undertaken, reviewed, cleared and disclosed in line with Bank requirements

and procedures. As part of stakeholder consultations the draft EIA report was submitted to

stakeholders in a workshop held at Kilwas on March 26, 2011. Several stakeholders from Songo

Songo village, the district, the Ministry of Energy and Minerals and Songas attended the

workshop.

27. Overall responsibility with the implementation of Environmental Assessment/Social

Assessment (EA/SA) measures and the RAP is with TANROADS. TANROADS has an

experienced social and environmental unit being part of its Directorate of Planning. This unit

will be required to report, as part of the TSSP reports, progress of the implementation of EA/SA

Page 19: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

9

measures throughout the project period. Zanzibar Airport Management will appoint an

Environmental control Unit which will be responsible for monitoring the application of the

prepared Environmental Management Plan (EMP) as well as dealing with the mitigation of

unforeseen issues and produce quarterly implementation reports. The PMO-RALG shall

designate among its staff a representative to be the Environmental Control Officer on site to

provide day-to-day supervisory role during implementation as well as preparation of

implementation report.

28. The environmental assessments for the Songo Songo jetty and Zanzibar airport

rehabilitation did not find any real risks of impacts on physical cultural resources. As most of the

works included under the additional financing involve the rehabilitation and improvement of

existing facilities, the possibility of construction activities affecting physical and cultural sites of

national and international importance is unlikely. However, the project has triggered OP 4.11 on

a precautionary basis, given its proximity to cultural resources. If any physical cultural resource

such as burial and archeological sites is identified during project implementation, the supervising

engineers will ensure that the contractor will implement appropriate measures. These would

include informing local authorities and the Antiquities Department; and preparing an appropriate

mitigation plan, which will be approved before commencing any works in that area, as provided

in the OP 4.11 procedure. Guidelines for “chance finds” procedure will be integrated into the

contracts for construction and road maintenance consultants. "

Disbursements

29. The first disbursement under the project was to cater for the six months cash flow

forecast - January 2011 to June 2011 - for the project based on an approved work plan and

budget. Follow up disbursements would be based on submittal of withdrawal application to the

Bank. The original disbursement forecast for the FY11 was US$50 million; however, the project

has disbursed US$43.74 million to-date as per the agreed work plan and budget.

Closing Date

30. The activities to be funded out of the additional financing will not require an extension of

the credit closing date. The project closing date remains June 30, 2015.

31. As the TSSP has been under implementation for less than 12 months and per OP/BP

13.20, the Bank provides additional financing only when it is satisfied that implementation of the

project, including substantial compliance with loan covenants, is satisfactory, it was necessary to

seek the Regional Vice President‟s (RVPs) approval to proceed with the additional financing.

The RVPs approval was granted on April 20, 2011.

Page 20: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

10

Annex 1: Results Framework and Monitoring

TANZANIA – TRANSPORT SECTOR SUPPORT PROJECT

Table 1: Revisions to Results Framework

Revisions to the Results Framework Comments/

Rationale for

Change

PDO

Current (PAD) Proposed

The development objectives of the project are: (i) to

improve the condition of the national paved road

network; (ii) to lower transport cost on selected

roads; and (iii) to expand the capacity of selected

airports.

Same but reworded to better focus the objective

of the project.

The reworded objective is to: (i) improve the

condition of the national paved road network,(ii)

to lower transport cost on selected roads and to

Songo Songo Island, and (iii) to expand the

capacity of selected airports.

Slight change in

wording to better

focus on the project

objectives.

PDO indicators

Current (PAD) Proposed change*

1. Average vehicle operating costs on (a) Korogwe-

Same and (b) Arusha – Minjingu roads; No change

2. Roads in good and fair condition as a share of

total classified roads (Core Indicator); No change

3. Passenger volume at (a) Bukoba, (b) Kigoma and

(c) Tabora airports; Passenger volume at (a) Bukoba; (b) Kigoma;

(c) Tabora; and (d) Zanzibar airports;

To add one new

airport (Zanzibar).

4. Direct Project beneficiaries (number) of which

female (%)

Figures remains as is for other components but

number of beneficiaries increases with those of

Zanzibar airport and the Songo Songo Island

Jetty. The Indicator has now been modified to

include female (%).

Increase in the

number of

beneficiaries due to

scale up.

Intermediate Results indicators

Current (PAD) Proposed change*

A.1 Roads rehabilitated –non rural (km) (Core

Indicator).

(a) Korogwe – Same (172 km)

(b) Arusha – Minjingu (98 km)

A.2 Design and bidding documents for rehabilitation

prepared (911 km).

No change

B.1 Kigoma runway paved

B.2 Tabora runway paved

B.3 Bukoba runway paved, terminal building as well

as new access road and car parking constructed.

B.1 Kigoma runway paved

B.2 Tabora runway paved

B.3 Bukoba runway paved, terminal building as

well as new access road and car parking

constructed.

B.4 Zanzibar taxiways and apron

rehabilitated and extended. (new)

To include Zanzibar

airport.

C.1 National Road Safety Agency (NRSA)

established and operational

C.2 Driver and Vehicle Examination and Licensing

Agency (DVELA) established and operational

C.3 Road Accident Information System (RAIS)

No change

Page 21: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

11

Revisions to the Results Framework Comments/

Rationale for

Change established and operational.

D. Number of transport sector PPP transactions

which have reached bidding stage.

No change

E. Number of national road/bridge sections

improved.

No change

F. Songo Songo Island Jetty rehabilitated New component.

Page 22: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

12

TABLE 2: REVISED PROJECT RESULTS FRAMEWORK

The development objectives of the project are: (i) improve the condition of the national paved road network,(ii) to lower transport cost on selected roads and to Songo Songo

Island , and (iii) to expand the capacity of selected airports.

PDO Level Results Indicators

Co

re UOM

Baseline

Original

Project

Start

(2008)

Progress

To Date

(2011)

Cumulative Target Values

Frequency

Data

Source/

Methodology

Responsibility

for Data

Collection

Comments 2011/12 2012/13 2013/14 2014/15

Average vehicle operating cost on

Korogwe-Same road

US cents

per km

34

-

-

-

23

Completion

report (CR)

HDM-4 TANROADS No change

Average vehicle operating cost on

Arusha – Minjingu road

US cents

per km

45

-

-

-

25

CR

HDM-4 TANROADS No change

Roads in good and fair condition as a

share of total classified roads1 % 66 67 68 69 70 70

Bi annual

Progress

Report

(BPR)

TANROA

DS

quarterly

report

TANROADS

and PMO-

RALG No change

Annual passenger volume at Bukoba

airport2 No. 26,628 34,000

BPR

TAA

Quarterly

Report

TAA No change

Annual passenger volume at Kigoma

airport No. 28,859 40,000

BPR

TAA

Quarterly

Report

TAA No change

Annual passenger volume at Tabora

airport No. 22,912 30,000

BPR

TAA

Quarterly

Report

TAA No change

Annual passenger volume at

Zanzibar airport No.

0.5

million

0.66

million

BRP

Directorate

of Civil

Aviation

Report

MoIC New (Scale up)

Beneficiaries No Direct project beneficiary by the end of project 5.7 million, out

of which 50 % are female CR

Revised from 5.15

million to 5.7 million

Zanzibar airport users: 0.5

milion, Songo Songo Island Jetty

Number

(%)

Direct project beneficiary by the end of project of which 50 %

are female CR

Completion

Survey

PMO-RALG

and MoIC

1 Supplemental Information: Total length of classified road network 86,472 at appraisal of TSSP

2 The figures for 2011 has not been updated as the airports rehabilitation has not started.

Page 23: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

13

users: 2500 (of which female)

Intermediate Results and Indicators

Intermediate Results Indicators C

ore

Unit of

Measur

ement

Baseline

Original

Project

Start

2009/10

Progress

To Date

2010/11

Target Values

Frequency Data Source/

Methodology

Responsibility

for Data

Collection

Comments 2011/12 2012/13 2013/14 2014/15

Intermediate Result 1: Rehabilitation and preparation of design for the rehabilitation of paved trunk roads

Roads Rehabilitated – non rural

Korogwe – Same rehabilitated km 0 0 30 110 172 BPR

TANROADS

quarterly

report

TANROADS No change

Roads Rehabilitated – non rural

Arusha – Minjingu rehabilitated km 0 0 20 60 98 BPR

TANROADS

quarterly

report

TANROADS No change

Design and bidding documents for

rehabilitation prepared km 0 0 0 911 BPR

TANROADS

quarterly

report

TANROADS No change

Intermediate Result 2: Improvement of airports

Bukoba runway paved, terminal

building as well as new access

road and car parking constructed

Yes/No Not done No No Yes BPR

TAA

Quarterly

Report

TAA No change

Kigoma runway paved Yes/No Not done No No Yes BPR

TAA

Quarterly

Report

TAA No change

Tabora runway paved Yes/No Not done No No Yes BPR

TAA

Quarterly

Report

TAA No change

Zanzibar taxiways and apron

rehabilitated and extended Yes/No Not done No No Yes BPR MoIC Report

MOIC New (Scale up)

Intermediate Result 3: Improvement of road safety management

Page 24: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

14

Intermediate Results and Indicators

Intermediate Results Indicators

Co

re

Unit of

Measur

ement

Baseline

Original

Project

Start

2009/10

Progress

To Date

2010/11

Target Values

Frequency Data Source/

Methodology

Responsibility

for Data

Collection

Comments 2011/12 2012/13 2013/14 2014/15

National Road Safety Agency

(NRSA) established Yes/No Not done No Yes BPR

MoW Annual

Report MoW No change

Driver and Vehicle Liscening

Agency (DVELA) established

Yes/No

Not done No Yes BPR

MoW

Quarterly

Report

MoW No change

Road Accident Information System

established and operational

Yes/No

Not done No Yes BPR

MoW

Quarterly

Report

MoW No change

Intermediate Result 4: Promotion of public private partnerships

Transport sector PPP transactions

that have reached bidding stage Number None None None 1 2 BPR

MoT

Quarterly

Report

MoT No change

Intermediate Result 5: Emergency road and bridge repair

National road sections repaired

and financed through component

E

Number None 106 BPR

TANROADS

Quarterly

Report

TANROADS No change

Intermediate Result 6: Rehabilitation of Songo Songo Island Jetty

Songo Songo Island Jetty

improved Yes/No No No Yes BPR

PMO RALG

Quarterly

Progress

Report

PMO-RALG New (Scale up)

Page 25: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

15

Annex 2: Operational Risk Assessment Framework (ORAF)

TANZANIA TRANSPORT SECTOR SUPPORT PROJECT

Project Development Objective(s)

The project development objectives (PDOs) are as follows: to improve the condition of the national paved road network, to lower transport cost on

selected roads and to Songo Songo Island, and to expand the capacity of selected airports.

PDO Level Results

Indicators

1. Average vehicle operating costs on (a) Korogwe-Same and (b) Arusha – Minjingu roads.

2. Roads in good and fair condition as a share of total classified roads (Core Indicator);

3. Passenger volume at (a) Bukoba, (b) Kigoma, (c) Tabora, and (d) Zanzibar airports;

4. Direct Project beneficiaries (number) of which female (%)

Risk Category Risk Rating Risk Description Proposed Mitigation Measure

1. Project Stakeholder

Risks

1.1 Airport Users Medium - I

Risk of the improvement of the

airports airside infrastructures may

not result with increase in demand

1. GoT plans to increase the autonomy of the TAA through enacting its

own Bill. This will attract more PPPs in aviation and enable TAA become

more commercial. 2. In parallel to the IDA financing, the GoZ has received funds from

China Exim Bank for construction of new passenger terminal for the

Zanzibar Airport. GoZ will improve the airport management by continuing to implement

reforms as indicated in the Zanzibar transport master-plan approved in

September 2009.

1.2. Donor relation and

Program Co-ordination Low

Risk of improper coordination with

other Donors financing the Transport

sector.

The Works program and interests of Donors in the Transport sector is to

be coordinated through the Transport Donor Group, Joint Technical

Committee (JTC) and the annual Joint Infrastructure Sector review.

Page 26: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

16

2. Implementing Agency

Risks Medium - I

Risks are associated with capacity,

Governance, coordination, and fraud

and corruption associated with

procurement and contract

implementation.

A number of measures have been included under the project to enhance

the capacity of implementing agencies; TANROADS is to coordinate

project activities; Contracts implementation information to be made

available to the Construction Sector Transparency initiative (CoST) for

review whenever required.

3. Project Risks

3.1. Design

Medium - L

Large number of components are

likely to complicate the project

implementation.

Severe disruption of traffic during the

implementation of the project.

1. Still remain with one overall implementing agency.

2. Bid documents for road works rehabilitation to allow limited „works-

in-progress‟ lengths.

3. Airport works contractors to produce an agreed program of works that

minimize closures and where needed some works to be executed during

the night.

3.2. Social &

Environmental

Medium - L

Risk of encroachment to resettled

road corridors and airport areas.

Risk of inadequate and unreliable

funding of the environmental and

social mitigation measures.

1. The implementing agencies to conduct regular inspection tour of road

corridor and airport boundaries to ensure no new settlement are

established. Reserved area to be properly demarcated

2. The two roads and three airports in Tanzania mainland have no

resettlement needs. GoZ will allocate Tshs 2 billion in FY11/12 for

Resettlement Action Plan (RAP) implementation at the Zanzibar airport.

An ESIA for the Zanzibar airport taxiway and apron rehabilitation and

extension has been prepared, consulted upon, and disclosed in January

2011. An EIA study for the proposed extension and rehabilitation of the

jetty has been undertaken, reviewed, cleared and disclosed in line with

Bank requirements and procedures..

3.3. Delivery Quality

Low

Risk of delivery of substandard

quality infrastructure by

contractors/vendors.

All the Works to be supervised by qualified international consultant

monitored by TANROADS, TAA, PMO-RALG and MoIC. Reasons for

all premature failures of pavement to be studied.

3.4. Procurement Medium-I Risk of procurement failure and

increase of construction prices.

Post-qualification (open bidding) to be considered for procurement of

works contracts

Page 27: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

17

Overall Risk Rating

at Preparation

Overall Risk Rating

During Implementation Comments

Low Medium-L

The Zanzibar airport component is ready for implementation and there are no major unresolved issues thus

the risk for this component is Low. At the same time Songo Songo Island Jetty component is to be

implemented by PMO-RALG through the Kilwa District Council which is not very conversant with Bank

procedures therefore the risk rating for this component is High. However, since the proposed allocation for

Zanzibar airport is US$57 million while the Songo Songo Island Jetty has an allocation of US$2 million,

the overall risk rating is Medium - L as the risks have high likelihood of materializing but with low impact

towards the achievement of the PDO. The major risks associated with high cost of construction under the

original project are no more relevant as the Bids for most of the works are within appraisal estimates. Other

project related risks are either Medium or Low as shown above.

Page 28: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

18

Annex 3: Detailed Description of New Project Activities

A. Component B2: Improvement of Zanzibar airports: Zanzibar

A1. Background

1. The proposed rehabilitation and expansion of taxiways and apron is a follow up of the

rehabilitation and extension of the Zanzibar airport runway which was financed and completed

under the Second Central Transport Corridor Project (CTCP2). The runway rehabilitation and

extension was originally planned under the International Development Association‟s (IDA‟s)

Second Integrated Roads Project (IRP2). However, the contractor failed to perform and the

contract was terminated in 2005. IRP2 closed on December 31, 2006 and the component was

transferred to CTCP2. Prior to approval of CTCP2, new bids for rehabilitation and extension of

the runway were issued and received in January 2008. However, the lowest bid was more than

100 percent above the engineer‟s estimate and the bidding process was cancelled due to

insufficient funding. As proposed in the Airport Master Plan study, it was decided to change the

airport development strategy by initially (through CTCP2) repairing of the runway thereby

providing it with an additional life of about six years. Concurrently, design a new parallel

runway that would be built and the existing one would become a taxiway. However the full

rehabilitation and extension of the airport runway was carried out as originally planned based on

the request from GoZ. With approval of the Bank, bids were restated and the contract was

awarded. The selected contractor concluded the works ahead of the contractual time (15

months) in July 2010, within the contract amount and to good quality.

2. The rehabilitation works improved the riding quality and increased the bearing capacity

of the runway, while the extension increased the length of the runway by 560 meters to 3,021

meters allowing for the use of wide-body aircrafts. This has enhanced the potential of Zanzibar

as a tourist destination by attracting direct services from north European and far eastern

markets. The cost of this component by the end of the defect liability period is estimated to be

US$35 million, and includes the cost for both works and supervision contracts.

3. The results of economic analysis showed that the runway was viable even with only the

operational profits and departure tax. When other value additions are included in the analysis,

the proposed investment becomes more justified from both a financial and economic standpoint.

However, the benefits of this rehabilitation and extension of the runway could not be fully

realized as a result of the existing taxiways and apron pose capacity, quality and safety

constraints.

A.2 Proposed Rehabilitation and expansion of taxiways and apron

4. In view of the expected growth of air traffic at Zanzibar airport (expected to grow from

0.5 million passengers in 2010 to 1.3 million by 2030) and the deteriorated condition of the

taxiways and apron their rehabilitation and expansion is now urgent. The bottlenecks with

regards to the current apron and taxiway can be seen in operations even at today's capacities.

Since the longest taxiway (taxiway C) has deteriorated to the extent that it can no longer be used

Page 29: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

19

by large aircraft, and the taxiway to the northern end of the runway (taxiway A) is too close to

surrounding buildings, only one remaining taxiway (taxiway B) is usable. Often the apron gets

so filled up with aircraft that additional arriving aircraft have to park on the taxiway. At this

point the runway becomes inaccessible to larger aircraft on the apron, until taxiway B has been

cleared. Additionally, the Revolutionary Government of Zanzibar (GoZ) has secured a loan

from the China Exim Bank to finance an urgently needed new terminal building. Both these

scale up investments will assist to achieve the chosen indicator for the component which is

satisfactory rating of the Zanzibar airport by both airlines and passengers. For location of the

proposed works see Figure 1 below.

Figure 1: Location of Proposed Works at the Zanzibar Airport

5. Over a planning period of 20 years, from 2010 to 2030, passenger demand will increase

from 482,062 passengers in 2010 to nearly three times as much at 1,285,901 passengers.

Growth assumes an annual domestic rate of four percent. For international passengers an initial

growth rate of 10 percent until 2015 is being used, reflecting the immediate effect of an

improved airport, followed by a long term growth rate of four percent. Recognizing the need for

expansion to meet future growth, GoZ has secured finance from China Exim Bank for the

construction of a new, third terminal. However, the construction of the third terminal does not

address the airside shortcomings of the airport, and makes their remedy even more necessary

and urgent.

6. The works have been logically divided into four phases starting with the most critical

activities for the operation of the airport. Phase 1 includes the extension of the current apron

along the runway, with an additional new link taxiway to relieve pressure from taxiway B and

reduce aircraft taxing time on the runway. Phase 2 includes the rehabilitation of taxiways A and

B, and the existing, aged portion of the apron. Phase 3 includes the complete reconstruction of

taxiway C, which is suffering from sub-base failure and would have to be closed if not rebuilt,

nearly doubling runway occupation time for a northern departure (or southern arrival) from 3

minutes and 22 seconds to 6 minutes and 27 seconds. Phase 4 includes the extension of current

taxiway C to the full length of the southern part of the runway, in order to decrease the amount

of taxi time for aircraft on the actual runway.

Extension of

Taxiway C

Rehabilitation of

existing Taxiway C

Extension of

Apron

Rehabilitation of

existing apron Rehabilitation of existing

taxiway A and B

Page 30: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

20

A3. Description of Works

7. Phase 1, would extend the current apron from 21,323 m

2 by 48,237 m

2 to a total of

69,560 m2. Phase 1 also includes the new much needed taxiway link of 153m x 25m between

the apron and the runway. Since the apron extension will be along taxiway C, 675 m of taxiway

C, with a shoulder of 9.5 m towards the runway, will be reconstructed. The estimated cost for

phase 1 is US$29.561 million.

8. Phase 2 will rehabilitate taxiways A (120 mm overlay) and B (50 mm overlay). Both

taxiways will have their width increased from 23 m to 25 m, and additional partial shoulder of

areas of 9.5 m on each side. The shoulders for taxiway A will be partial due to existing

structures, such as the original historic terminal one now used for administrative purposes. The

estimated cost for this phase is US$3.53million, and includes new signage and aeronautical

ground lighting systems (AGL) for the taxiways.

9. Phase 3 will reconstruct, and provide shoulder for 640 m of the existing taxiway C at an

estimated cost of US$12.41 million. As with the other taxiways, the width will be increased

from 23 m to 25 m. This phase includes updating signage and lighting systems for the new

dimensions.

10. Phase 4 will extend the taxiway C an additional 650 meters along the runway to its

southern turning bay, and provide additional signage and AGL. The extension will cut on-

runway taxi time from an average of 3.5 minutes to roughly 30 seconds, allowing for a peak rate

of three departures or landings per five minutes. The estimated cost for the extension works is

US$8.77 million.

11. The design aircraft for the airport for establishing apron sizes, taxiways widths, and other

design parameters such as pavement has been determined to be the Airbus 330, which is an

International Air Transport Association (IATA) code E type wide-body aircraft.

12. An ESIA was prepared, approved by the Bank and was disclosed in Zanzibar on January

18, 2011 and at the Bank‟s Infoshop on January 20, 2011 under project ID P124114.

Environmental impacts are standard such as air quality reduction due to noise and end

equipment emissions during construction, and the loss of vegetation in areas to be surfaced.

Appropriate mitigation measures have been included in the bidding documents.

13. A Resettlement Action Plan (RAP) has been prepared, was approved by the Bank and

was disclosed in Zanzibar on January 18, 2011 and at the Bank‟s Infoshop on January 20, 2011

under P124114. Resettlement is only triggered by Phase 4 of the works, the extension of the

taxiway. Seventeen households with both finished and unfinished houses and 27 small farms are

affected. An appropriate relocation site has been identified nearby. Estimates for the cost of the

resettlement are TZS 2 billion and are to be financed by GoZ.

Page 31: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

21

Table 1: A Description of the Proposed Pavement Works

Works Section Surface Treatment Proposed Construction Finished Level

Above Existing

mm

Apron Existing Mill 50mm

surfacing

60 + 40mm bituminous 50mm

Extension Excavate to

required formation

New construction

(200 + 200 mm granular + 150 +

60 + 40mm bituminous = 650mm)

50-450mm

Taxiway A

Including link

taxiway

Mill 40mm

surfacing (reduced

milling because of

thin current

construction)

Overlay construction (60 + 60 +

40mm) bituminous

120mm

B

(link taxiway)

Mill 50mm

surfacing

60 + 40mm bituminous 50mm

C

(Existing)

Including link

taxiway

Break out existing

construction &

excavate to

required formation

New construction

(200 + 200 mm granular + 150 +

60 + 40mm bituminous = 650mm)

50-450mm

C

(Extension)

Including link

taxiway

Excavate to

required formation

New construction

(200 + 200 mm granular + 150 +

60 + 40mm bituminous = 650mm)

50-450mm

D

(maintenance

hangar)

Break out existing

construction &

excavate to

required formation

New construction

(200 + 200 mm granular + 150 +

60 + 40mm bituminous = 650mm)

50-450mm

Runway

Link

Taxiways

- Excavate to

required formation

New construction

(200 + 200 mm granular + 150 +

60 + 40mm bituminous = 650mm)

0-450mm

B. Component F: Improvement of the Songo Songo Island Jetty

B.1 Background

14. The proposed rehabilitation of the Island Jetty on Songo Songo Island is not only

essential to the transport facilities to and from the island but also a recommended social

mitigation measure for the closed Bank financed Songo Songo gas extraction project

(P002797). During the implementation of the Songo Songo gas extraction project, the existing

jetty on Songo Songo Island was taken over by the project and a new jetty was constructed on

the western shoreline of the island for the use of the Songo Songo villagers. This new jetty has

not been providing satisfactory services for the villagers, as it is being overtopped during very

Page 32: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

22

high tides and the length of the jetty is not enough for arriving boats to approach it during low

tides. Furthermore, lightering facilities such as stairs and rails are inappropriate and the jetty is

too narrow. Since the Songo Songo Energy Project closed on December 31, 2010 it was decided

that this component would be attached to TSSP.

B.2 Proposed Rehabilitation, Widening and Extension of Jetty and Breakwater

Construction.

15. The jetty was constructed on the western shoreline of the island using pre-cast concrete

blocks, however in a structural oversight the height of the jetty at +4.05m Chart Datum (CD)

became submerged during seasonal high tides which have a maximum of +4.5m CD, and is

subject to considerable wave overtopping during the South East Monsoon. Consequently the

jetty use during this period is largely restricted and in addition to the jetty rehabilitation a

protective breakwater will be constructed to protect the jetty. Use of the jetty at low tides is also

restricted as, despite its 30m length, the existing jetty fails to extend beyond the low water mark

thereby preventing users from gaining access the jetty until the water returns, forcing passengers

and traders to transport their goods over the exposed coral.

Figure 2: Jetty and Breakwater Construction

A3. Description of Works

16. To ensure that access to the jetty is largely unrestricted it is necessary to extend both the

height and the length of the jetty. This will be undertaken in two phases, as there are two clearly

defined stages of construction and in an attempt to minimize the time during which the jetty will

be inaccessible. The first phase is to extend the height of the jetty by 0.8m, thereby insuring that

17. To ensure that access to the jetty is largely unrestricted it is necessary to extend both the

height and the length of the jetty. This will be undertaken in two phases, as there are two clearly

defined stages of construction and in an attempt to minimize the time during which the jetty will

be inaccessible. The first phase is to extend the height of the jetty by 0.8m, thereby insuring that

the platform extends beyond the highest astronomical tide. The width of the jetty will also be

Increase the width and height

of existing jetty

Increase the length

of the jetty by 20m

Construct a rubble

mound breakwater

Page 33: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

23

increased by 2.0m by introducing 1m wide sections to the sides of the existing jetty, as the

current width of 3.5m is inadequate for the volumes of goods and passengers at peak periods

and increases the risk of accident/injury. Four sets of concrete stairs, two on either side of the

jetty, will extend down to the sea bed. The stairways will be provided at berthing faces for

access to and from small vessels. Landings will be provided at 0.75m above mean high, mean

and mean low water levels and will be 1.5m long. Recessed mooring rings will be provided at

each level.

18. Once the rehabilitation of the existing structure is complete, an additional 20m will be

added to jetty in an effort to ensure access to the jetty is not regulated by tidal conditions. The

sea floor will be dredged to a depth of -3.25CD before the extension can be added, ensuring that

large coral features are carefully relocated and damage to the surrounding environment is

minimized. A rubble foundation at least 1.0m thick will be placed on top of the foundation

stratum and the base should extend at least 1.0m on each side of the wall base to accommodate

any construction tolerance and to spread the load.

19. The extensions will be in the form of multiple layers. The south side will continue at the

new height of +4.85CD for the length of the extension, whilst the North half will step down 1m,

followed by another 1m step down 10m along the jetty. The reduced height will ensure that

access to the jetty platform will be possible at low tide, while the continuous level will

guarantee the jetty structure is visible at high tide. A hand rail will be positioned between the

sections to ensure a safe working environment. To prevent accidental grounding/collision with

the submerged sections a 500mm x 500mm concrete column shall be constructed at the corner

of the reduced section of the jetty, extending to the top level of the jetty. Two sets of ladders

will be installed on either side of the jetty to ensure that access to the jetty from the water is

possible at all times. Ladders will be fabricated from steel and positioned in such a way that

they will not be obstructed by mooring lines

20. General public lighting shall be provided at intervals not exceeding 10m, ensuring that

the positioning of the structures does not cause an obstruction. Where lighting poles cannot be

deployed on both sides of the jetty, a single central pole shall be used with extended

overhanging lights. In order to identify the extremity of the jetty a single jetty light shall be

positioned at the centre point of the jetty.

21. The breakwater will be constructed some 25m to the South and parallel to the existing

jetty. It will be constructed with a core of 1-3 ton rock segments covered with 3 ton armor

segments and will have a height of +5.3 CD. At its crest the breakwater will have a width of 1m.

The breakwater shall extend seaward as far as the existing jetty, making it approximately 75m

long. The newly extended section of the jetty will protrude beyond the protected region,

however as this section is expected to be used predominantly in low tide, and thus calmer,

conditions, it has not been deemed necessary to extend the breakwater level with the extension.

Page 34: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

24

Annex 4: Revised Project Costs

TANZANIA: TRANSPORT SECTOR SUPPORT PROJECT

Total IDA GoT

A. Rehabilitation and preparation of designs for rehabilitation of paved trunk roads 186.5 186.5

A.1 Korogwe – Same (172 km) 101.4 101.4

A.2 Supervision of Korogwe – Same 3.5 3.5

A.3 Arusha town border – Minjingu (98 km) 72.0 72.0

A.4 Supervision of Arusha – Minjingu 2.6 2.6

A.5 Design and preparation of bidding documents for 911 km of road rehabilitation 4.7 4.7

A.6 Office equipment for TANROADS 0.5 0.5

A.7 Training for TANROADS and TAA 1.3 1.3

A.8 Additional operating cost for TANROADS 0.5 0.5

B. Improvement of regional airports 126.20 114.5 11.7

B.1.1 Works at Bukoba Airport 20.4 16.9 3.5

B.1.2 Works at Kigoma Airport 26.7 22.2 4.5

B.1.3 Works at Tabora Airport 19.1 15.9 3.2

B.1.4 Supervision 3.0 2.5 0.5

B.2.1 Works at Zanzibar Airport 55.5 55.5 -

B.2.2 Supervision of Zanzibar airport works 1.5 1.5 -

C. Improvement of road safety 6.0 6.0

C.1 Equipment for NRSA, DVELA and DSE 1.5 1.5

C.2 Services for the establishment of the Road Accident Information System 1.0 1.0

C.3 TA for NRSA, DVELA and DSE 1.5 1.5

C.4 Training for road safety 1.0 1.0

C.5 Initial operating cost of NRSA and DVELA 1.0 1.0

D. Promotion of public-private partnerships in the transport sector 5.0 5.0

D.1 Civil Aviation Masterplan and PPP options 0.7 0.7

D.2 Kisarawe Freight Centre feasibility study and transaction advisor 0.8 0.8

D.3 Study for the removal of bottlenecks on local government roads with PPP 0.5 0.5

D.4 Assistance to RAHCO to develop bankable central rail upgrading program 0.5 0.5

D.5 Other feasibility studies and transaction advise 1.7 1.7

D.6 TA for DPP of MoID 0.3 0.3

D.7 Training for PPP staff at MoID, TANROADS, TAA,TPA, PMO-RALG, MoFEA 0.5 0.5

E. Emergency road and bridge repair 15.0 15.0

F. Songo Songo Island Jetty rehabilitation 2.0 2.0

TOTAL 340.7 329.0 11.7

Page 35: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

25

Annex 5: Revised Economic Analysis

Component B2: Zanzibar Airport

1. The overall cost for the airport, including the work already done on the runway surface

and extension, is broken down in the table below:

Table 1: Overall Cost for Zanzibar Airport

Description Note Amount (US$)

Apron extension not including work financed by Exim Bank 21,709,400

Rehabilitation of existing apron Phase 1 6,288,093

New link taxiway Phase 1 1,568,236

Rehabilitation of taxiways A and B Phase 2 3,525,234

Rehabilitation of taxiway C Phase 3 12,408,323

Extension of taxiway C Phase 4 8,771,794

Subtotal of new additions to project 54,271,794

Runway rehabilitation and extension Works completed under CTCP2 35,468,048

New apron in front of new terminal Exim Bank financed 14,858,658

Total Airport Investments Including external parties (MS/BCEG) 104,597,786

2. The estimation of the actual costs for the new additions to the project is about US$57

million out of which US$54.27 million is for the base construction cost as noted above allowing

for a six percent contingency. Another US$1.23 is provided for price contingency making the

total requirement for the works contract to US$55.5 million. The supervision costs are estimated

at about US$1.5 million.

3. Moving data from the 2004 Tanzania Tourism Sector Survey forward, with an annual

income growth rate of two percent representing the growth in spending per tourist, it was

estimated that tourism expenditure in Zanzibar per passenger will rise from US$248.82 in 2013

to US$624.90 in 2032, with additional income due to the added passenger flows created by the

project, growing from an annual total of US$14,304,226 in 2013 to US$190,068,604 annually in

2032. Measuring the local benefits estimated to be gained in fishing, agriculture, and other

business ventures, a gain of US$744,497 to US$8,604,180, in between the same periods, is

estimated. The total estimated benefit for the period is US$1,680,575,018.

4. The entire project investment was then discounted against revenues for the 20 year period

between 2012 and 2030. The results show an internal rate of return of 12.3 percent, above the

World Bank threshold of 12 percent, and at a discount rate of 12 percent, a positive net present

value of US$198,230,912.

Page 36: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

26

Annex 6: Procurement

1. Procurement for the proposed Additional Financing (AF) would be carried out in

accordance with the World Bank‟s "Guidelines: Procurement of Goods, Works and Non

Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers"

dated January 2011; and "Guidelines: Selection and Employment of Consultants under IBRD

Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011; Guidelines on

Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA

Credits and Grants, dated October 15, 2006 and revised in January 2011; and the provisions

stipulated in the Legal Agreement.

2. Procurement activities for contracts that account for about 97 percent of the AF will be

carried out by the procurement staff of the Procurement Management Unit of the Ministry of

Infrastructure and Communications of the Revolutionary Government of Zanzibar with the

support of the Coordination of Donor Aided Projects (CODAP) staff and two Consultants

attached to CODAP.

3. An assessment of the capacity of the ministry to implement procurement actions for the

Additional Financing was carried out on April 6, 2011. The assessment reviewed the

organizational structure for implementing the activities under the AF and the interaction between

the staff responsible for procurement and other relevant central units for administration and

finance. The key issues and risks concerning procurement for implementation of the procurement

activities have been identified and mitigation measures agreed with the ministry. The main risk is

lack of experience with the Bank‟s procurement procedures including records keeping among the

project management unit (PMU) staff.

4. Training in basic and advance procurement will be required especially for the ministry

staff in order to ensure that they are knowledgeable about Bank and government procurement

procedures.

Details of the Procurement Arrangements Involving International Competitive Bidding

(ICB) and Other Methods

5. List of contract packages to be procured following ICB/direct contracting and other

methods under the additional financing:

Table 1: Works and Goods 1 2 3 4 5 6 7 8 9

Ref.

No.

Contract

(Description)

Estimated

Cost

($’000)

Procure

ment

Method

Prequal

(yes/no)

Domestic

Preference

(yes/no)

Review

by

Bank

(Prior

/Post)

Expected

Bid-

Opening

Date

Comment

Works 1 Civil works contract for

Zanzibar Airport

54,200 ICB NO NO YES October

26, 2011

2 Civil works contract for

Songo Songo Jetty

1300 NCB NO NO NO March 15,

2012

Page 37: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

27

6. List of consulting assignments with short-list of international firms and other selection

methods:

Table 2: Consulting Services

1 2 3 4 5 6 7

Ref.

No.

Contract Description Estimated

Cost

($‟000)

Selection

Method

Review

by Bank

(Prior /

Post)

Expected

Proposals

Submission

Date

Comments

1 Supervision services for Zanzibar

Airport

1500 SSS* YES August 2,

2011

There is a

supervision

consultant

for prior

activities

2 Supervision Services for Songo

Songo Jetty

200 QCBS YES December

2011

*Subject to the approval of the Bank based on the review of the evidence to be provided to justify the SSS.

(a) Shortlists composed entirely of national consultants: Short lists of consultants for

services estimated to cost less than US$200,000 equivalent per contract may be composed

entirely of national consultants in accordance with the provisions of paragraph 2.7 of the

Consultant Guidelines.

Advertising

7. All works and goods contracts to be procured under ICB and consultancy services

contracts estimated to cost US$200,000 and more equivalent per contract shall be advertised in

United Nations Development Business (UNDB) online in addition to advertising in national

newspaper(s) of wide circulation.

Thresholds for Procurement Methods and Prior Review

8. Thresholds for procurement methods and for prior review are presented in the Table 3

below.

Page 38: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

28

Table 3: Thresholds for Procurement Methods and for Prior Review

Expenditure

Category

Contract Value

Threshold (US$)

Procurement /

Selection Method

Contracts Subject to

Prior Review

Works

≥5,000,000 ICB All <5,000,000

NCB

None (Post review) unless

specified in the PP

<50,000 Shopping None (Post review) All values Direct Contracting All

Goods

≥500,000 ICB All <500,000

NCB

None (Post review) unless

specified in the PP

<50,000 Shopping None (Post review) All values Direct Contracting All

Consulting

Services - Firms1

≥ 200,000 QCBS/ Other

3

(QBS/FBS/LCS) All

< 200,000 CQS/ Other

4

(QBS/FBS/LCS) None (Post Review)

All values SSS All

Consulting

Services –

Individuals (IC)

≥100,000 IC - Qualification All

<100,000 IC - Qualification None (Post review)

All Values IC - SSS All

(a) Review of Terms of References: Terms of Reference for all contracts will be cleared by

the Bank.

Risks and Mitigation Measures Additional Financing

9. Procurement risk for the Additional Financing is assessed as Medium - I. The following

measures were agreed to mitigate the risks:

Inadequate Legal and Regulatory Framework: The World Bank Guidelines, Standard

Bidding Documents and Standard Forms of Evaluation to be used for the procurement of the

contracts under the Additional Financing.

Weak Procurement Capacity: Train procurement staff within PMU so as to upgrade their

procurement skills

3 Shortlists for consultancy services for contracts estimated to cost less than US$200,000 equivalent per contract may be

composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4 QBS, FBS, and LCS for assignments meeting requirements of paragraphs 3.2, 3.5, and 3.6 respectively, of the Consultant

Guidelines.

Page 39: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

29

Risk Assessment of the Original TSSP

10. The procurement risk associated with the original project at this stage is Low as with the

recent spurt in procurement advances there are evidences that contracts that accounts for some 96

percent of allocations of the original credit amount are expected to be committed by end of June

2011.

Page 40: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

30

Agreed Procurement Plan during the Appraisal of the TSSP, updated Procurement Plan and the Current Status

Works, Goods and Non Consulting Services

Table 4: List of Contract Packages to be Procured Following ICB

1 2 3 4 5 6 7 8 9 10 12

Ref.

No.

Contract

(Description)

Estimated

Cost (including

contingencies)

US$m

Procurement

Method

P-Q

Domestic

Preference

(Yes/No)

Review

by Bank

(Prior /

Post)

Expected

Bid-Opening

Date

Actual Bid

Opening

Date

Revised Bid

Transmission

Status

1 Civil Works contract for

Korogwe – Same –

Mkumbara in two lots;

(172km)

101.4 ICB N N Prior July 15, 2010 Feb 3, 2011 N/A Comment s on

BER sent on

April 28, 2011

2 Civil works contract for

Arusha town border –

Minjingu (98 km)

72.0 ICB N N Prior July 15, 2010 Dec 1, 2010 N/A No-objection

for the award of

the contract was

given on March

8, 2011.

Contract Signed

on May 12,

2011..

3 Civil works contract for

Bukoba airport

20.4 ICB N N Prior July 15, 2010 Feb 25,

2011

N/A

Comment s on

BER sent on

April 20, 2011

4 Civil works contract for

Kigoma airport

26.7 ICB N N Prior July 15, 2010 Feb 25,

2011

N/A

5 Civil works contract for

Tabora airport

19.1 ICB N N Prior July 15, 2010 Feb 25,

2011

N/A

Page 41: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

31

2. Consulting Services

Table 5: List of Consulting Assignments with Short-list of International Firms 1 2 3 4 5 6 7 8 9

Ref.

No.

Description of Assignment

Estimated

Cost

(including

contingencies)

US$m

Selection

Method

Review

by Bank

(Prior /

Post)

Expected

Proposals

Submission

Date

Actual

Proposal

Opening Date

Revised

Proposal

opening

date

Status

1 Supervision of the Korogwe – Same 2 lots 3.5 QCBS Prior na na N/A Contract signed

2 Supervision of Arusha – Minjingu 2.6 QCBS Prior June, 2010 Feb 24, 2011 N/A No-objection on TER

was given on April

23, 2011

3 Supervision of works at three airports 3.0 QCBS Prior May, 2010 Dec 17, 2010 N/A No-objection on TER

was given on April

20, 2011

4 Detailed design for Same – Himo (80km), Himo

– Marangu (13km) and Mombo – Lushoto

(32km)

0.6 QCBS Prior June, 2010 Mar 8, 2011 N/A

TER underway

5 Detailed design for Mtwara – Masasi (200km) 0.9 QCBS Prior June, 2010 Mar 15, 2011 N/A TER underway

6 Detailed design for Makambako – Songea

(295km)

1.2 QCBS Prior June, 2010 Jan 21, 2011 N/A No objection on TER

was given on April

12, 2011

7 Detailed design for Lusahunga – Rusumo

(91km) and Kobero – Nyakasanza (58km)

0.6 QCBS Prior June 2010 Mar 15, 2011 N/A TER underway

8 Detailed design for Mafinga - Makambako –

Igawa (142km)

0.7 QCBS Prior June 2010 Jan 21, 2011 N/A No objection on TER

was given on April 1,

2011

9 Establishment of Road Accident Information S. 1.0 QCBS Prior September 2010 August

19, 2011

No Objection of the

TOR was given on

April 5, 2011

10 Preparation of a civil aviation master plan

including PPP options

0.7 QCBS Prior September 2010 - August

10, 2011

11 Kisarawe Freight Center feasibility study 0.5 QCBS Prior September 2010 - NYD

12 Study for the design of a program for the

removal of bottlenecks on the local government

road network

0.5 QCBS Prior September 2010 - July,8,

2011

13 Assistance to RAHCO to develop bankable

central rail upgrading program

0.5 QCBS Prior November 2010 -

14 TA for DPP in MoID 0.3 IC Prior July 1, 2010 - July 6,

2011

15 TA for DSE - MoW 1.5 QCBS Prior September 2010 August

19, 2011

No Objection of the

TOR was given on

April 5, 2011

Page 42: The World Bank FOR OFFICIAL USE ONLYdocuments.worldbank.org/curated/en/584941468341086125/...P. O. Box 9111 Dar es Salaam - Tanzania Fax: +255 22 2117790 Agencies: Tanzania National

Yalova

Kaliua

KasuluKondoa

Manyoni

KibondoKahama

Nzega

Buoen

Njombe

Mpui

Mpanda

Tunduma

Same

Tunduru

Masasi

Utete

Kilwa Kivinje

Wete

Lindi

Mbeya

Koani

Tanga

Moshi

Songea

Mtwara

Iringa

Kibaha

Mkoani

TaboraKigoma

Arusha

Mwanza

MusomaBukoba

Singida

Morogoro

Zanzibar

Mkokotoni

Shinyanga

Sumbawanga

Babati

DODOMA

Dar es Salaam

A R U S H A

MANYARA

M A R A

R U V U M A MTWARA

KILIMANJARO

I R I N G A

L I N D I

D O D O M A

K I G O M A

M WA N Z A

S H I N YA N G A

R U K W A

M B E Y AP WA N I

TA B O R A

ZANZIBARNORTH

PEMBANORTH

PEMBASOUTH

ZANZIBARSOUTH &CENTRALZANZIBARWEST

DAR ES SALAAM

KAGERA

SINGIDA

TA N G A

MOROGORO

K E N Y AUGANDA

ZAMBIA

MOZAMBIQUE

RWANDA

BURUNDI

DEM

. RE

P. O

F CO

NGO

Korogwe

Mkumbara

Minjingu

Yalova

Kaliua

KasuluKondoa

Korogwe

Mkumbara

Minjingu

Manyoni

KibondoKahama

Nzega

Buoen

Njombe

Mpui

Mpanda

Tunduma

Same

Tunduru

Masasi

Utete

Kilwa Kivinje

Wete

Lindi

Mbeya

Koani

Tanga

Moshi

Songea

Mtwara

Iringa

Kibaha

Mkoani

TaboraKigoma

Arusha

Mwanza

MusomaBukoba

Singida

Morogoro

Zanzibar

Mkokotoni

Shinyanga

Sumbawanga

Babati

DODOMA

Dar es Salaam

Songo Songo Island

See inset

30° 35°

30° 35°

40°

40°

10°

10°

A R U S H A

MANYARA

M A R A

R U V U M A MTWARA

KILIMANJARO

I R I N G A

L I N D I

D O D O M A

K I G O M A

M WA N Z A

S H I N YA N G A

R U K W A

M B E Y AP WA N I

TA B O R A

ZANZIBARNORTH

PEMBANORTH

PEMBASOUTH

ZANZIBARSOUTH &CENTRALZANZIBARWEST

DAR ES SALAAM

KAGERA

SINGIDA

TA N G A

MOROGORO

K E N Y AUGANDA

ZAMBIA

MOZAMBIQUE

RWANDA

BURUNDI

DEM

. RE

P. O

F CO

NGO

Mbemkuru

Matandu

Rufiji

Great

Ruaha

Rungwa

Wam

i

Simiyu

Ruvuma

Mara

Kagera

Moyow

osi Ugalla

Pangani

Kilo

mbe

ro

INDIAN

OCEAN

Lake

Tanganyika

LakeMalawi

Lake Rukwa

Lake Natron

Lake Victoria

LakeEyasi Lake

Manyara

To Nakuru

To Malindi

To Kasama

To Kasama

To Kasungu

To Lichinga

To Marrupa

To Chiúre

To Nakuru

To Tororo

To Kampala

To Kampala

To Kama

TANZANIA

This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other informationshown on this map do not imply, on the part of The World BankGroup, any judgment on the legal status of any territory, or anyendorsement or acceptance of such boundaries.

0 50 100 150

0 50 100 150 Miles

200 Kilometers

IBRD 38586

MAY 2011

TANZANIATRANSPORT SECTOR SUPPORT PROJECT

ADDITIONAL FINANCINGCIVIL WORKS & SUPERVISION OFREHABILITATION/UPGRADING OF ROADS

REHABILITATION/PAVING OF AIRPORTRUNWAYS AND APRONS

PROJECT AIRPORT (ZANZIBAR)

SONGO SONGO JETTY

DETAILED DESIGN OFREHABILITATION OF PAVED ROADS

MAIN CITIES AND TOWNSPROVINCE CAPITALSNATIONAL CAPITALMAIN ROADSRAILROADSPROVINCE BOUNDARIESINTERNATIONAL BOUNDARIES

ZanzibarZanzibar

ZANZIBARISLAND

Mangapwani

Bweleo

Mkokotoni

Nungwe

Matemwe

Pongwe

Pingwe

Uroa

Paje

Chwaka

Mtegani

INDIANOCEAN

ZanzibarChannel

0 5 10 15

KILOMETERS