the windsor woods drainage project club house road project ...€¦ · early construction project...
TRANSCRIPT
-
The Windsor Woods Drainage ProjectClub House Road Project
CIP 7-028
February 2019
-
• To Inform Residents
• Seek Input/Comments
• Provide Opportunity for One-On-One Dialog
Objectives
17
-
18
Project
-
Early Construction ProjectClub House Road Drainage Improvements
19
STORMWATERPOND
BOW CREEK
GOLF COURSE
PROPOSED STORM DRAIN
POND
▪ Finalizing Design
▪ Construction Start: No later than February 2020
▪ Estimated Construction Cost: $3.3M
-
20
-
• Redirects a portion of the stormwater flows from Rosemont Road east along Club House Road to Bow Creek Golf Course to Bow Creek
• Storm drain length is 1,400 feet• 80 feet across Rosemont Road right-of-way
• 700 feet within Club House Road right-of-way
• 620 feet Club House Road to Bow Creek Golf Course and within the golf course
• Pipe Diameter is 15-inch to 60-inch
1. 21
Club House Road Project Description
21
-
• Construction time: 14 months
• Contractor required to comply with City’s Noise Ordinance
• The following will be maintained:• Water and sanitary sewer service• Access to homes• Access to Police, Fire, EMS,
school buses, and trash pick-up• Access to US Postal service
22
Club House Road Project Construction
22
-
• Contractor required to restore lawns and driveways
• Club House Road to be repaved upon completion of work
• A City Inspector will be assigned to the project and work directly with residents throughout the project
23
Club House Road Project Construction
23
-
• Rosemont Road heavily traveled major roadway
• Contractor required to maintain one lane north and one lane south
• Four lanes of Rosemont Road open during peak hours
• Night time construction may be required
• Neighborhood detours and one-lane traffic will likely be required; traffic will be allowed in both direction with flaggers 24
Club House Road Project Constructionat Club House Road and Rosemont
24
-
Rosemont Road Construction Phasing
25
Construction Phase 1
Construction Phase 2
Construction Phase 3
-
• A new stormwater pond will be constructed within the golf course to receive the new stormwater
• A new pond is necessary to comply with water quality regulations
• Construction work will be coordinated with Parks & Rec and the course operator
• Goal is to keep the golf course open and to minimize adverse impacts to players
26
Club House Road Project ConstructionInside the Bow Creek Golf Course
26
-
Bow Creek Golf Course Construction
27
-
• For questions, comments or additional information, please contact us at:
• PLEASE be sure to enter your name and contact information when you e-mail us so that we can follow up with you.
28
mailto:[email protected]
-
PUBLIC WORKS SERVICE REQUESTS
(757) 385-1470
www.vbgov.com/service-requests
29
https://na01.safelinks.protection.outlook.com/?url=http://www.vbgov.com/service-requests&data=02|01|[email protected]|3bb9978479054c67e0db08d6911dcb7e|4e1ee3db4df64142b7b9bec15f171ca4|0|0|636855954488785866&sdata=3saxOGgDGzEMyE2czgr82HO3BrQF46hQrwB7CqcO6y4%3D&reserved=0
-
Public Works and Michael Baker staff are availableto further discuss the Club House Road Project
Table 1 – Windsor Woods, Princess Anne Plaza and The Lakes Combined Drainage Project and Concept Map
Table 2 – Club House Road Drainage Project Maps
Table 3 – Club House Road Project Engineering Plans
30