the value of post-combustion carbon dioxide capture and storage … · 2014. 9. 30. · the value...
TRANSCRIPT
-
IJGGC-120; No of Pages 10
The value of post-combustion carbon dioxide capture andstorage technologies in a world with uncertain greenhousegas emissions constraints
M.A. Wise *, J.J. Dooley
Joint Global Change Research Institute, Pacific Northwest National Laboratory, 8400 Baltimore Avenue, Suite 201, College Park,
MD 20740, USA
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x
a r t i c l e i n f o
Article history:
Received 1 November 2007
Received in revised form
11 June 2008
Accepted 18 June 2008
Keywords:
Carbon dioxide capture and storage
Pulverized coal
Post-combustion capture
Electricity production
East Central Area Reliability
Coordination Agreement
a b s t r a c t
By analyzing how the largest CO2 emitting electricity-generating region in the United States,
the East Central Area Reliability Coordination Agreement (ECAR), responds to hypothetical
constraints on greenhouse gas emissions, the authors demonstrate that there is an enduring
role for post-combustion CO2 capture technologies. The utilization of pulverized coal
generation with carbon dioxide capture and storage (PC + CCS) technologies is particularly
significant in a world where there is uncertainty about the future evolution of climate policy
and in particular uncertainty about the rate at which the climate policy will become more
stringent. The paper’s analysis shows that within this one large, heavily coal-dominated
electricity-generating region, as much as 20–40 GW of PC + CCS could be operating before
the middle of this century. Depending upon the state of PC + CCS technology development
and the evolution of future climate policy, the analysis shows that these CCS systems could
be mated to either pre-existing PC units or PC units that are currently under construction,
announced and planned units, as well as PC units that could continue to be built for a
number of decades even in the face of a climate policy. In nearly all the cases analyzed here,
these PC + CCS generation units are in addition to a much larger deployment of CCS-enabled
coal-fueled integrated gasification combined cycle (IGCC) power plants. The analysis pre-
sented here shows that the combined deployment of PC + CCS and IGCC + CCS units within
this one region of the U.S. could result in the potential capture and storage of between 3.2
and 4.9 Gt of CO2 before the middle of this century in the region’s deep geologic storage
formations.
# 2008 Elsevier Ltd. All rights reserved.
avai lab le at www.sc iencedi rec t .com
journal homepage: www.e lsev ier .com/ locate / i jggc
A growing body of literature is illuminating the significant
potential for the large-scale deployment of carbon dioxide
(CO2) capture and storage (CCS) technologies as central means
of reducing CO2 emissions across a broad swath of the global
industrial economy. This literature identifies coal-fired elec-
tricity production as an especially critical application for CCS
technologies and in particular the application of CCS coupled
with new purpose-built coal-fueled integrated gasification
combined cycle (IGCC) systems (IPCC, 2005). In an IGCC plant,
* Corresponding author. Tel.: +1 301 314 6770; fax: +1 301 314 6760.E-mail address: [email protected] (M.A. Wise).
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
1750-5836/$ – see front matter # 2008 Elsevier Ltd. All rights reserveddoi:10.1016/j.ijggc.2008.06.012
the CO2 emissions are captured prior to combustion of the
gasified fuel, and an IGCC with CCS (IGCC + CCS) can be
referred to as a pre-combustion CCS technology. IGCC + CCS is
a promising technology, and it may well turn out to be the best
or least-cost option for building new low-carbon fossil
capacity in many situations. However, there are critical
technical and economic reasons for maintaining research
and development in post-combustion CCS technologies for
pulverized coal (PC) technology (PC + CCS). Through its focus
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
.
mailto:[email protected]://dx.doi.org/10.1016/j.ijggc.2008.06.012http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Table 1 – ECAR modeling assumptions
Factor Assumption
Load growth Begins at 1.9%/year and tapers down to 1.4%/year by 2045
Delivered gas prices Increase from $4.60/mmbtu in 2015 to just over $6/mmbtu by 2045
Delivered coal prices Increase from $1.40/mmbtu in 2015 to $1.60/mmbtu by 2045
Nuclear power Grows with electricity demand to maintain share
Renewable power Accelerated growth from about 4% of total in 2005 to 10% by 2045
Existing capacity No fixed future retirement age is assumed. Electricity generation capacity is retired only if
fixed costs exceed revenues
Trade Imports and exports with neighboring regions remain at current fractions
Cost of CO2 transport, storage and
measurement, monitoring
and verification
Potential CO2 storage reservoirs in the ECAR region are modeled as a graded resource and the
cost of utilizing these storage reservoirs for the electric power sector is assumed to be
between $12–15/tonne CO2a
a As described in Wise et al. (2007), it is assumed that any value added CO2 storage reservoirs in this region will be fully utilized by higher
purity/lower cost of capture CO2 point sources such as ethanol plants and natural gas processing facilities by the time large CCS-enabled power
plants are built and commence operations. This then implies that the electricity generators in this region will be reliant on the abundant deep
saline formations found across the ECAR region.
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x2
IJGGC-120; No of Pages 10
on one heavily coal dominated electricity region in the United
States, this paper will seek to explore the largely under-
appreciated and potentially enduring role that PC + CCS
technologies could play in a greenhouse gas constrained world.
1. Background and objective
A recently published analysis (Wise et al., 2007) detailed an
economic modeling assessment of the potential adoption of
CCS in response to hypothetical CO2 reductions policies in
each of the North American Electric Reliability Council (NERC)
regions of the continental United States over a 40-year period
that spanned 2005–2045. That paper attempted to illuminate
the impact of the differing regional electricity market
characteristics (such as current capacity, fuel prices, and
growth rate) along with significant differences in geologic CO2storage cost and availability on each region’s response to a CO2policy. In addition to expanding nuclear and renewable
capacity as a means of reducing CO2 emissions in the face
of the imposed climate policy, between 180 and 580 GW of
IGCC + CCS generation capacity was brought on-line before
2045 to meet demand growth while simultaneously meeting
the imposed increasingly stringent CO2 emissions constraint.1
In this previous analysis, investment in PC + CCS was
relatively small, and limited to retrofits of some of the most
efficient existing coal generating units in regions where
conditions were favorable, such as the East Central Area
Reliability Coordination Agreement (ECAR) region in the upper
Midwest. But no new (i.e., post 2005 construction) PC + CCS
capacity was built in these scenarios; the use of post-
combustion CO2 capture was limited to only existing units.
The goal of that paper was to illustrate the potential large-
scale commercial deployment of CCS systems within the U.S.
1 The East Central Area Reliability Coordination Agreement inthe upper Midwestern U.S. and the South Eastern Reliability Coun-cil in particular were regions where the intensive use ofIGCC + CCS was seen in this previous analysis. Other regions inTexas and the Rocky Mountains could also be significant regionsfor the deployment of this class of low-carbon electricity genera-tion technologies.
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
electric power sector and to assess whether there was
sufficient geologic storage capacity in U.S. to meet this
potential demand.2 The previous paper (Wise et al., 2007)
was not intended to be an analysis of the relative merits of
future IGCC + CCS versus PC + CCS technologies, a point that
was stressed in the paper’s conclusions.
The present analysis is designed to more explicitly focus on
the relative performance of IGCC + CCS and PC + CCS systems
in a competitive, CO2 emissions constrained electricity
market. At the outset, it is important to acknowledge that
the choice between these two technologies is a deterministic
result of input cost and technology performance assumptions,
which are in reality uncertain. Future CO2 emissions reduc-
tions policy is also highly uncertain. Here, we will make the
case for the continued development of post-combustion CCS
systems and demonstrate with new modeling analyses of the
economic conditions that the availability of a post-combus-
tion technology is a valuable technology option.
2. Approach
To explore the impact of advanced post-combustion CCS
technologies, we modeled two scenarios of future technology
improvements in PC + CCS systems based on work by Rao et al.
(2006). We also modeled the impact of future CO2 emissions
price paths on investment choices by varying both the shape
of the price path and the extent to which the owners and operators
of the electricity generation system are knowledgeable about how the
future price path will evolve. This last point is a critical new
insight brought forward in the present analysis; expectations
of future CO2 emissions prices is a critical determinant in any
decision about the relative merits of near term investments in
post-combustion CO2 capture technologies. In order to avoid
duplicating work that has already been completed and to
2 Between 12–40 Gt CO2 of geologic storage was needed to meetthe demands of the cases modeled in Wise et al. (2007). Thisdemand, while significant and orders of magnitude larger thanthe cumulative global experience to date with CCS technologies,can be accommodated by the large and widely distributed geologicstorage capacity within the U.S.
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Fig. 1 – The ECAR region, its large, heterogeneous potential geologic storage capacity and large existing (greater than 0.1 Mt
CO2/year) stationary CO2 emissions point sources by type.
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x 3
IJGGC-120; No of Pages 10
facilitate comparisons across a wider range of potential
pathways for decarbonizing the U.S. electricity sector, we
have – except where explicitly noted – adhered to the same
assumptions about technologies, demand growth, fuel prices,
geologic storage cost and availability that were employed in
Wise et al. (2007).3 Table 1 summarizes the key ECAR modeling
assumptions for this study.
This analysis has employed two research tools developed at
Battelle: the Battelle CO2-GIS (Dahowski et al., 2005) to determine
the regional capacity and cost of CO2 transport and geologic
storage, and the Battelle Carbon Management Electricity Model
(CMEM) (Wise and Dooley, 2005), an electric system optimal
capacity expansion and dispatch model, to examine the
3 Assumptions of costs and performance of new electric tech-nologies for this exercise are from DOE/EIA (2005). Regional elec-tric demand load profiles and growth forecasts for this exerciseare taken from FERC filings (2005) for the near term. The authorshave decreased these region-specific growth assumptions afterthe first decade to be conservative about future demand growthand the corresponding amount of new capacity required. Regionaldelivered coal and natural gas prices for this scenario correspondto the Energy Information Administration (EIA) 2005 AnnualEnergy Outlook Reference Case (EIA, 2005) to 2025 and are extra-polated thereafter. All costs here are given in 2005 US$.
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
investment and operation of electric power technologies with
CCS against the background of other options. The dispatch
model is used because it is important to consider numerous
factors that extend beyond simple comparisons of the static,
levelized costs of competing power plant technologies. The
heterogeneous nature of the existing regional electric generat-
ing capacity must be considered; the fuel mix, age, plant
efficiencies, operating and maintenance costs, and emissions
rates are critical determinants of the economic response to a
CO2 emissions policy. The characteristics of electricity demand
are also crucial: both the varying nature of the electricity load
profile (from baseload to peaking) as well as future demand
growth. The competing technologies for new electricgenerating
capacity, their capital costs, efficiencies, operating and main-
tenance costs, and emissions must be weighed in building for
load growth and for replacing existing capacity.
Rather than model a hypothetical or overly simplified
aggregate market, we have chosen to look at a specific market
and use it to gain real-world insights that can hopefully be
generalized to other markets. For this analysis, we have
chosen to focus on the ECAR regional electricity system which
spans all or most of Ohio, Indiana, Michigan, Kentucky, and
West Virginia as well as the western parts of Virginia,
Maryland, and Pennsylvania. Fig. 1 depicts the ECAR region:
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Fig. 2 – ECAR Year 2005 modeled electric dispatch curve.
6 Cost and performance parameters for IGCC + CCS are derivedby the authors from cost and energy requirement specificationsfor CO2 capture technologies specified David and Herzog (2000).While there are too many technical parameters involved to detailhere, for comparison purposes we note that the resulting costs forCO2 capture (i.e., exclusive of the cost of transport and storage in asuitable deep geologic storage reservoir) realized in our modelingare approximately $18 to $20/tonne CO2 for new IGCC plants,depending on the energy efficiency and the capacity factor ofthe underlying plant. These are our calculations, dependent onseveral scenario-specific factors, and the reader should refer tothe paper by David and Herzog for original technology data.
7 As noted in Table 1, the cost of CO2 transport, storage, mea-surement monitoring and verification for these potentially largepower plants that would utilize CCS and would be built in ECAR is
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x4
IJGGC-120; No of Pages 10
the large number of coal and other fossil-fired power plants as
well as the significant number of large stationary CO2 point
sources from the chemical, refining, steel, ethanol and other
industries that are also potential users of CCS technologies.
Fig. 1 also shows the abundant and widely distributed
theoretical deep geologic storage potential in the ECAR
region.4 The ECAR region is interesting both because it is
one of the largest regions in terms of electrical demand and
because it has been dominated historically by coal-fired
capacity. As a consequence, it represents the largest electric
power generation CO2 emitter of all the NERC regions.
Fig. 2 is an electricity generation dispatch curve for the Year
2005 from our modeling of ECAR. From this figure, it is clear
that ECAR is dominated by coal capacity, extending beyond
the baseload into the intermediate load. A relatively small
amount of renewables and nuclear power, and a moderate
amount of gas combined cycle (gas CC) and gas peaking
capacity round out the region’s current generation capacity.
Much of the gas CC capacity has been built in the last decade
and is therefore comprised of very efficient units.
Electricity generation dispatch curves provide an informa-
tive graphical depiction of the capacity mix, dispatch order,
capacity factors, and electricity prices. Using Fig. 2 as an
example, the dispatch cost is plotted on the vertical axis
versus the cumulative capacity available at each level of
dispatch cost on the horizontal axis. Dispatch cost is defined
as the variable operating and fuel cost (and therefore does not
include sunk costs such as capital or fixed operating and
maintenance).5 With vertical lines on the figures indicating
different points on the load duration curve, the dispatch
curves provide some insight into the capacity factors of the
different types of plants as well as price levels. Specifically, all
capacity to the left of the point where the load line intersects
4 In Wise et al. (2007), we estimate that there is potentially 169 GtCO2 of theoretical geologic storage capacity in the ECAR region.
5 It is important to stress the distinction between the dispatchcost, which is the appropriate basis for determining electricitygeneration and corresponding emissions, and the capital costs,which are considered only in determining the investment in newcapacity. Decisions relating to what electricity generation capacityshould be built in a region and which generation capacity isoperated on a given day are obviously linked, but they arenone-the-less distinct.
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
the supply curve is economical to operate to serve the load at
that point, and the electricity price at that point (at least at the
wholesale level before any tariffs or distribution costs are
incurred) is equal to the marginal cost of generation—the
dispatch cost of the capacity at that intersection point.
3. Scenario definitions
We construct four scenarios by pairing two assumptions about
future developments in post-combustion CCS technologies
with two paths of future CO2 emissions prices. We use the
CMEM model to explore the potential impact of these sets of
assumptions on ECAR over an approximately 40-year time
horizon.
Our assumptions about future costs and performance of
PC + CCS technologies are based on work by Rao et al. (2006).6
From their paper, we have derived two sets of assumptions for
PC + CCS technologies for use here:
� Base technology assumption: PC + CCS technology performs atlevel resulting in a cost of roughly $47/tonne CO2 (depending
on assumed capacity factor and cost of coal) to capture,
dehydrate compress and otherwise ready for pipeline-based
transport off the site of the power plant facility, and
� Improved technology assumption: cost of capture from PC + CCStechnology is reduced by 35% (i.e., to roughly $30/tonne CO2)
to similarly prepare the captured CO2 for pipeline-based
transport.7
We combine these post-combustion technology assump-
tions with two paths of future CO2 emissions prices:
� CP2 path (as named in the earlier study): a smooth CO2 priceincrease starting at $12/tonne CO2 in 2015 and increasing at
5% per year in real terms, with that price increase known
with certainty to investors.8
assumed to be an additional $12–15/tonne CO2.8 The earlier Wise et al. (2007) paper included a CP1 case as well,
where CO2 emissions prices started at the same $12/tonne CO2 butrose at a lower 2.5% per year, reaching about $25/tonne CO2 by2045. No PC + CCS units were built in ECAR under this less strin-gent CP1 case and therefore we will put this case aside in thepresent analysis. We will retain the CP1/CP2 terminology from theearlier paper to facilitate comparisons across the two analyses. Forthe current study, the CP2 path is a more relevant case as it issufficiently high to induce a large-scale investment in CCS duringthe 40-year time horizon.
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Fig. 3 – CO2 emissions price paths.
Fig. 4 – ECAR 2045, dispatch curve. Base PC + CCS, CP2 CO2price path, ECAR 2045.
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x 5
IJGGC-120; No of Pages 10
� ‘‘Jump to CP2’’ path: a scenario in which the price of CO2emissions remains relatively low to moderate (although
certainly not negligible) for the next few decades and then
rises steeply to the CP2 by 2045, with that price increase
being a surprise to the owners and operators of power
generation assets.
The difference in expectations is a key point here. In our
modeling of the CP2 path, investment is done on an
intertemporally optimal basis. That is, investment decisions
made in each period are done with full knowledge of
conditions, including CO2 prices, of all future periods. This
assumption is fairly typical in optimization modeling, and it
provides useful insight into what the rational investment
decisions would be. This assumption, also called perfect
foresight, is one extreme. We constructed the Jump to CP2 case
to explore the other extreme: one in which investors do not
know how the climate policy will unfold in future years. In the
Jump to CP2 case, investors do not foresee the steep increase in
CO2 prices when making investment decisions and are forced
to react to it given the generation assets that exist at the time
of the spike in CO2 permit prices.
A likely reality would lie somewhere between these two
extremes of perfect foresight and complete nearsightedness,
but modeling them as such provides useful insights into
economic investment for long-lived assets such as electric
power plants. Fig. 3 shows the two CO2 price paths graphically.
4. Results and analysis
Before turning to examining the changes in ECAR’s fossil-fired
generation mix across these four scenarios, it is important to
reiterate the point made in Table 1 that underlying all of these
scenarios is an explicit assumption of significant growth in
nuclear and renewable power that is a necessary complement
to the potential large scale deployment of CCS-enabled coal-
fired power plants.
For each of these cases, it is assumed that an additional
4400 MW of nuclear capacity comes on line in ECAR between
now and 2045. That would imply the construction and
commissioning of approximately one new large nuclear power
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
plant in ECAR every 5 years starting in 2015. In terms of
renewable power, it is assumed that 16,600 MW of new
renewable generation capacity is brought on line between
now and 2045. To meet this growth would require hundreds to
thousands of new large wind turbines coming on line every
decade starting immediately.
A key point, and we will return to this later, is that
significant generation capacity will be built in ECAR, regardless
of what climate policy is imposed, simply to serve expected
load growth. The question at hand is to attempt to shed light
on how climate policy and the state of CCS technologies will
impact this new generation capacity and to also examine the
extent to which existing generation assets are impacted.
Dispatch curves will be used to illustrate many of the scenario
results and analysis.
4.1. The role of PC + CCS in a well-defined future CO2emissions controlled environment
First, we will compare the results of changing the post-
combustion technology assumptions under the CP2 CO2 price
path, i.e., the smoothly escalating price that is known with
certainty. Figs. 4 and 5 compare dispatch curves depicting the
ECAR generation mix in the Year 2045, for both the Base
Technology and Improved Technology Scenarios against the
CP2 policy background.
As seen in Figs. 4 and 5, the new builds in ECAR from the
present to 2045 under the CP2 path are comprised mainly of
IGCC + CCS, and gas combined cycle (labeled New Gas CC to
distinguish from capacity already in place in 2005). In these
two scenarios where it is clear that an increasingly
significant climate policy will be put in place (e.g., on the
level of the CP2 path), no new PC capacity is built in ECAR
after 2005 regardless of whether an improved post-combus-
tion CO2 capture technology is available. The main differ-
ence between these two cases is that under the Improved
PC + CCS assumptions, about 20 GW of existing PC capacity
(i.e., built before 2005) is retrofitted with CCS, while under
the Base PC + CCS assumption, none of this capacity is
retrofitted.
Under the Base PC + CCS assumptions (Fig. 4), the most
efficient existing PC capacity, which today serves as baseload
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Fig. 5 – ECAR 2045, dispatch curve. Improved PC + CCS, CP2
CO2 price path, ECAR 2045.
Fig. 6 – ECAR 2035, dispatch curve. Improved PC + CCS, CP2
CO2 price path.
9 These 2035 dispatch curves are nearly identical to the BasePC + CCS technology cases as the CO2 prices are not yet highenough in 2035 to induce and new build or retrofits of PC + CCSin these scenarios.
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x6
IJGGC-120; No of Pages 10
capacity, is pushed back in the dispatch order by the CO2 prices
behind gas CC capacity, operating less than 50% of the year.
The least efficient PC capacity is pushed even further back,
some to the point where they would likely be retired. However,
under the Improved PC + CCS assumptions (Fig. 5), the most
efficient PC capacity is retrofitted with CCS and continues to
operate at or near baseload capacity factors, while only the
less efficient PC capacity is displaced by gas CC in the dispatch
order. Also evident from Figs. 4 and 5 is that dispatch costs are
lower between the minimum dispatch and 50th percentile
points with the retrofit PC + CCS in place, which indicates
lower off-peak electricity prices for consumers and businesses
in the ECAR region due to the ability to reduce emissions in a
more cost effective manner, made possible by the presence of
the Improved PC capture technology.
Given the cost assumptions for both the Base and Improved
PC CO2 capture systems, it might seem that the CO2 price in
CP2 is sufficiently high by 2045 to induce retrofits of PC to
PC + CCS for either technology scenario, but the analysis must
consider other factors. One factor is the additional cost of CO2transport, storage, measurement, monitoring and verification
which as noted in Table 1 is assumed to be $12–15/tonne CO2for these large power plants in ECAR. A second factor is the
initial energy efficiency of the PC capacity to be considered for
retrofit. Capturing CO2 from an existing PC can be thought of as
a parasitic energy requirement, so a plant that generates
electricity less efficiently to start with will result in a higher
CO2 capture cost. Finally, a perhaps more subtle factor that
requires a dispatch model to consider fully is the resulting
capacity factor of the retrofit capacity. Technical specifications
of CO2 capture cost are typically presented at a fixed, baseload
capacity factor. Lower capacity factors mean fewer units of
output for amortizing the capital costs, resulting in higher per
unit costs of capturing CO2. And, as seen when comparing
across Figs. 4 and 5, it cannot be assumed that retrofit PC + CCS
will be able to compete with other baseload capacity in the
system and operate at a baseload capacity factor. In these
scenarios, the Improved PC CO2 capture technology is needed
to allow for retrofitted PC + CCS unit to compete with new
capacity being built and therefore justify the cost of the
retrofit.
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
4.2. The role of PC + CCS in an ill-defined future climatepolicy environment
We now examine the impact of the steep and unforeseen
increase in CO2 emissions prices which characterizes the Jump
to CP2 case on how ECAR would decarbonize its generation
capacity. Before moving to examine the changes at the end of
the study period (i.e., in the Year 2045), it is first instructive to
examine the extent of changes in the ECAR system in the Year
2035 immediately before this spike in CO2 permit prices is
introduced. From Fig. 3, the CO2 price is about $32/tonne CO2 in
the CP2 path in 2035, with the increase to $52/tonne CO2 by
2045 known, while the CO2 price is about $13/tonne CO2 in 2035
in the Jump to CP2 path, with the increase to $52/tonne CO2 by
2045 not known. Figs. 6 and 7 show electric dispatch curves for
the Year 2035 under the CP2 and the Jump to CP2 CO2 price
paths, respectively, both with the common assumption of
Improved PC + CCS technology for comparison purposes.9
Fig. 6 shows the same scenario as in Fig. 5 previously, but
here for the Year 2035 and can therefore be used to shed light
on the temporal evolution of changes in ECAR’s generation
mix in the well-defined CP2 case. From Fig. 6, it can be seen
that the CO2 price is already sufficient by 2035 to induce
investments in about 20 GW of IGCC + CCS, in addition to the
expansion of renewables, nuclear, and gas CC capacity.
Although the CO2 price path is too high to allow builds of
new venting PC plants, it is not so high that the existing PC
plants are yet pushed behind gas CC in the dispatch order, as
they will be in 2045. In fact, most of the PC capacity still serves
as baseload power even with this CO2 price. This result is
important in that it highlights both the continued value, along
with the continued CO2 emissions, from today’s PC capacity
even under a CO2 policy. The CO2 price does result in a higher
operation cost, which can be seen by comparing to the 2005
dispatch curve in Fig. 1, resulting in lower margins than they
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Fig. 7 – ECAR 2035, dispatch curve. Improved PC + CCS,
jump to CP2 CO2 price path, ECAR 2035.
Fig. 8 – ECAR 2045, dispatch curve. Base PC + CCS, jump to
CP2 CO2 price path, ECAR 2045.
Fig. 9 – Dispatch curve. Improved PC + CCS, jump to CP2
CO2 price path, ECAR 2035.
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x 7
IJGGC-120; No of Pages 10
would without a CO2 price. So the value to the owners of the
capacity is certainly affected by the CO2 policy.
Comparing Fig. 6 with Fig. 7, the most striking difference is
that there are no power plants capturing CO2 in ECAR in the
Year 2035 under the Jump to CP2 case (Fig. 7). The Jump to CP2
policy in place in 2035 and expectations of how it will unfold in
the future are insufficient to warrant the investment to build
let alone operate CCS-enabled units as a means of decarboniz-
ing ECAR’s fossil-fired electricity generation. To draw out this
point more explicitly, the main difference is that almost the
same amount of new capacity that was IGCC + CCS under the
CP2 path is instead new PC capacity under the Jump to CP2
path. The growing electrical load in ECAR is still largely being
served by coal-fired generation in both cases. However, in the
Jump to CP2 case it is still economic to construct and operate
new PC capacity that vents CO2 emissions to the atmosphere
at these CO2 price levels. In 2035, the existing PC capacity has
lower dispatch costs and will earn higher margins relative to
the dispatch costs of the gas capacity that will be setting the
electricity price much of the time. Therefore even though a
penalty must be paid for every tonne of CO2 vented to the
atmosphere (whether it be from a coal plant or a natural gas
fired facility) there is no reason to engage in massive fuel
switching to natural gas.
4.3. In an uncertain policy environment, it is better to havemore options
We now shift our focus to explicitly examine the value of
advanced PC-based CO2 capture systems in the Jump to CP2
case during the interval 2035–2045 where CO2 permit prices are
increasing rapidly. Figs. 8 and 9 are electricity dispatch curves
for 2045 under the Jump to CP2 path with Base PC + CCS
technology and Improved PC + CCS technology, respectively.
From Figs. 8 and 9, the new PC capacity built in the period
between 2005 and 2035 under the assumption of a continua-
tion of relatively low and slowly increasing CO2 permit prices
that characterize the pre-2035 Jump to CP2 scenario is
retrofitted to PC + CCS under either set of assumptions about
the cost of CO2 capture technology. Of significance to the
owners and operators of these new PC units is that the ability
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
to utilize the Improved PC + CCS technology results in lower
dispatch cost and therefore higher margins than if they are
limited to using only the Base CO2 capture technology shown
in Fig. 7.
These scenarios differ also in the extent of retrofitting pre-
existing PC capacity (i.e., that already operated in ECAR by
2005). Under the Base PC + CCS technology assumptions, it is
not economic to retrofit any of this capacity, and all existing
pre-2005 PC plants are pushed behind gas CC in the dispatch
order. However, under the Improved PC + CCS assumptions,
the most efficient existing PC capacity is retrofitted and
continues to dispatch at or near the baseload.
Table 2 summarizes key points across these four scenarios.
In all but the CP2/Base PC + CCS case, there appears to be a
significant rationale for the continued development of PC-
based CO2 capture systems in managing the costs of reducing
CO2 emissions within ECAR. In a case in which CO2 prices are
known with certainty, it is critically important to develop
IGCC + CCS technology. But it is also important to develop
advanced PC-based CO2 capture systems for deployment
centering on existing PC units. But in perhaps the more likely
case that future CO2 prices are not known, a robust, proven
and cost effective PC + CCS technology is a hedge that allows
new PC capacity to be built and later retrofit and continue to
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Table 2 – Summary of scenario results
CP2 price pathwith base
PC + CCS capturetechnology
CP2 price pathwith improved
PC + CCScapture
technology
Jump to CP2price pathwith base
PC + CCS capturetechnology
Jump to CP2price path
with improvedPC + CCS capture
technology
CO2 emissions price $/tonne
2035 ($) 32 32 14 14
2045 ($) 52 52 52 52
Pre-2005 PC retrofit to CCS by 2045 0 22 0 22
New (post-2005 builds) PC + CCS by 2045 0 0 0 17.7
IGCC + CCS by 2045 (GW) 81 70 72 57
Cumulative CO2 stored in ECAR
by 2045 (million tonnes)
4300 4900 3200 3600
Fig. 10 – Dispatch curve. IGCC + CCS not competitive,
improved PC + CCS, CP2 CO2 price path, ECAR 2045.
Fig. 11 – Dispatch curve. PC + CCS not competitive, jump to
CP2 CO2 price path, ECAR 2045.
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x8
IJGGC-120; No of Pages 10
serve as baseload power. The ability to deploy improved
PC + CCS technologies also helps to contain the escalation in
baseload electricity prices that would be caused by such a
rapid increase in CO2 permit prices and therefore is a means
for protecting the larger macro economy if there is a need to
rapidly reduce CO2 emissions.
4.4. IGCC + CCS and PC + CCS as options to manageuncertainty in technology development
In each of the preceding four scenarios, there was an explicit
assumption that the IGCC + CCS technology is a lower-cost
option than PC + CCS for building new electric generating
capacity with CCS. That is an input assumption, not a result of
our analysis. This assumption was employed to allow for a
clearer focus on the role of post-combustion CCS in the event
that IGCC + CCS does in fact succeed.
Here we relax this assumption and briefly examine a
scenario in which PC + CCS turns out to be a lower-cost option.
Fig. 10 shows the dispatch curve for a hypothetical scenario in
which the CP2 CO2 price path is followed but IGCC + CCS is not
competitive. Here, we have also assumed the Improved
PC + CCS assumptions, but the same point could be made
with the Base PCC + CCS assumptions. As can be clearly seen
from Fig. 10, the electricity system in ECAR responds to the
imposed climate policy with a large scale deployment of new
PC + CCS capacity, along with substantial retrofits of pre-
existing PC capacity to PC + CCS. These units serve to provide
baseload power under such a scenario.
And in the last scenario analyzed here, Fig. 11 shows the
dispatch curve in the Year 2045 under the Jump to CP2 CO2price path but now assuming for whatever reason a viable PC-
based CO2 capture technology does not exist. The combination
of the significant spike in CO2 permit prices and no viable
means for capturing CO2 from the vast PC infrastructure built
out between 2005 and 2035 in the Jump to CP2 case, results in
massive changes in ECAR’s generation mix in the relatively
short interval 2035–2045. From Fig. 11, it is clear that one
immediate response is the rapid build out of new IGCC + CCS
units (more than in any of the previous cases) as the CO2 prices
are too high to operate the large numbers of post 2005 PC units
at high capacity factors. The new PC units built in the
preceding decades are pushed back behind new gas CC in the
dispatch order, providing much less power and value than its
investors had anticipated. Interestingly, this leaves little need
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
for the pre 2005 existing PC capacity to operate, and most of it
is retired as a result. Admittedly, this last case represents an
extreme scenario, and the real world response would probably
not be as quick or drastic. However, it does highlight the
enormous economic pressure that would be placed on the
system if something like this path is followed without the
ability to utilize improved PC-based CO2 capture technologies.
One key result evident in all of these cases is the vast
amount of IGCC + CCS or PC + CCS that is built within the ECAR
region. Although most of the capacity additions are due to
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
Fig. 12 – ECAR power sector CO2 emissions, by scenario.
Fig. 13 – Installed coal-fired capacity in ECAR by vintage
and plant type.
11 Compare this path to the CP1 emissions path in Wise et al.(2007). With a CO2 emissions price rising to $25/tonne, ECAR powersector CO2 emissions peak and decline to just under 2005 levels by2045.12 The primary reference for data on new coal builds in ECAR isNETL (2007). The authors also relied on press accounts and otherpublicly available information to update (in all cases to delete or
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x 9
IJGGC-120; No of Pages 10
continued load growth, some of the new CCS-enabled coal-
fired capacity is needed to replace capacity losses due to
retrofits of existing units, as well as some retirements. The
amount of this CCS-enabled coal-fired capacity whether IGCC-
or PC-based appears large, but the scale of growth required for
any of these technologies, including renewables, nuclear, and
natural gas-fired capacity is also large.10 With continued load
growth, a great deal of new generation capacity will be built
within the ECAR region; the real question is what the mix of
technologies will be.
4.5. Resulting CO2 emissions for ECAR
Fig. 12 summarizes the impact of these CO2 emissions price
path and technology assumptions on the region’s CO2emissions. From the figure, it is clear that the CP2 price path
is a substantial policy that would result in deep emissions
reductions, and have a profound impact on the way electric
10 We believe we are being conservative by assuming lowerfuture growths than historical and by not presuming any fixedretirement ages for current capacity. If we were to assume thatcurrent capacity would be forced to retire at a certain age, muchmore new capacity would be required than shown here.
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
power is generated.11 Differences in prices through 2025 do not
result in significant deviations in emissions levels. CO2 prices
are not sufficiently high to change investment decisions
between coal and gas, or high enough to invest in CCS. In 2035,
emissions reductions are much greater under the CP2 path
than the Jump to CP2 path, but by 2045 the emissions are fairly
consistent.
The Jump to CP2 case also results in an additional 2900
million tonnes of CO2 released to the atmosphere. This is
notable for at least two reasons. First, it is clear that these
policies while ending up with the same emissions levels on
2045 are not equivalent in terms of cumulative emissions
reductions to the global environment. Second, from Table 2
the difference in the amount of CO2 stored between the CP2
and Jump to CP2 cases is significantly less, approximately 1300
million tonnes of CO2, and thus in the CP2 cases less coal is
built and the coal plants are operated less while generation
from gas increases.
As noted, the drop in emissions in the Jump to CP2 path
would be a shock to the system and would likely be more
difficult to realize than what any model might suggest.
5. Discussion
According to publicly available documents, there are currently
plans to build approximately 9200 MW of new coal-fired
capacity in ECAR over the next decade.12 Approximately
5100 MW of new natural gas-fired capacity could be on line by
2010 (EIA, 2006). The majority of this planned coal-fired
capacity, 6800 MW, will be PC units, with the remaining
2400 MW of the announced capacity slated to be IGCC-based
units. While it is difficult to know which planned or
announced power plants will actually get built, it is important
to note that a handful of these units are already under
construction and one relatively small PC unit (less than
300 MW) could come on line by 2010.13 It is therefore worth
reflecting upon what the foregoing analysis says about this
large potential investment in coal-fired generation capacity.
Fig. 13 shows installed and planned coal-fired generation
capacity within ECAR by vintage and by plant type. While it is
clear that the most of the existing coal-fired capacity in ECAR
is already at least 35 years old, it is also clear that there is
substantial capacity of a much more recent vintage. This data
also shows there is a substantial amount of coal capacity that
has been operating for more than 40 or 50 years.14
delay) coal plants that were contained in the NETL (2007) report.13 East Kentucky Power Cooperative’s 278 MW PC-based Spurlock#4 Unit is scheduled to come on line in the Spring of 2009. http://www.ekpc.coop/Generation/EKPCGeneratingProjects3.htm.14 This point provides support for our modeling assumption thatexisting plants may continue to operate and have value in thecoming decades, rather than simply retiring at a fixed lifetime.
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://www.ekpc.coop/Generation/EKPCGeneratingProjects3.htmhttp://www.ekpc.coop/Generation/EKPCGeneratingProjects3.htmhttp://dx.doi.org/10.1016/j.ijggc.2008.06.012
-
i n t e r n a t i o n a l j o u r n a l o f g r e e n h o u s e g a s c o n t r o l x x x ( 2 0 0 8 ) x x x – x x x10
IJGGC-120; No of Pages 10
At present, there is more than 20 GW of installed coal-fired
capacity in the ECAR region that is of fairly recent vintage and
which has been fitted with both SOx and NOx controls. Given
the significant investment entailed in installing these emis-
sions control devices, it is perhaps fair to assume that these
are highly efficient units that their owners/operators believe
will still be productive assets for decades to come. Further the
significant investment in SOx and NOx controls at many of the
newer plants is germane to any discussion of the potential for
PC + CCS to deploy in ECAR as most amine-based CO2 capture
systems would require that SOx and NOx be removed before
CO2 is sent to the CO2 scrubber to minimize solvent losses
from the reaction with these acid gases (IPCC, 2005). This is not
to say that these plants will or will not be retrofitted with CCS
at some point in the future but rather to suggest that there is at
least some basis in reality for thinking that substantial PC-
based generating capacity could still be operational well into a
climate constrained environment and therefore there is
potentially significant value in the continued development
of post-combustion CO2 capture technologies.
The potential significant build out of new coal-fired
capacity depicted at the right of Fig. 13 within this one region
of the U.S. is instructive and provides perhaps an important
insight into expectations for how climate policy will unfold
and the impact of future climate policy on these generation
assets. In particular, the significant 6800 MW build out of PC-
based units in ECAR is suggestive that something less
stringent than the modeled CP2 case is expected by many
participants. On the other hand, the announced 2400 MW of
IGCC capacity would seem to indicate that at least some
participants in the ECAR market are preparing for a more
significant climate policy.
If nothing else, these data about the differing approaches
being taken just within ECAR in terms of building PC units or
IGCC units is suggestive of a lack of certainty in the real world.
Given that the forgoing analysis would strongly suggest that
the continued development of advanced PC-based CO2 capture
systems is an important complement to continued develop-
ment of IGCC and IGCC + CCS technologies. Advanced post-
combustion CO2 capture technologies serve as a hedge against
the significant risk associated with uncertainty centered on
future climate policy as well as a hedge against uncertainty in
success of development of IGCC. But to be clear on this point,
PC + CCS still has value even if IGCC + CCS is successful. This is
true for the ECAR region studied here and likely also other
NERC regions in the U.S. It is also true for regions like China
that are growing rapidly and whose electricity generation
Please cite this article in press as: Wise MA, Dooley JJ, The value of
in a world with uncertain greenhouse gas emissions constraints, Int. J.
infrastructure is and apparently continues to be dominated by
pulverized coal power plants.
r e f e r e n c e s
Dahowski, R.T., Dooley, J.J., Davidson, C.L., Bachu, S., Gupta, N.,2005. Building the cost curves for CO2 storage: NorthAmerica. Technical Report 2005/3. IEA Greenhouse Gas R&DProgramme.
David, J., Herzog, H., 2000. The cost of carbon capture. In:Proceedings of the Fifth International Conference onGreenhouse Gas Control Technologies (GHGT-5), Cairns,Australia.
IPCC, 2005. In: Metz, B., Davidson, O., de Coninck, H.C., Loos, M.,Meyer, L.A. (Eds.), IPCC Special Report on Carbon DioxideCapture and Storage. Prepared by Working Group III of theIntergovernmental Panel on Climate Change. CambridgeUniversity Press, Cambridge, United Kingdom and NewYork, NY, USA, 442 pp.
Rao, A., Rubin, E., Keith, D., Morgan, M.G., 2006. Evaluation ofpotential cost reductions from improved amine-based CO2capture systems. Energy Policy 34 (2006). Elsevier, pp. 3762–3772.
U.S. Department of Energy, Energy Information Agency (EIA),2005. Assumptions for the Annual Energy Outlook 2005.DOE/EIA-0554 (2005).
U.S. Department of Energy, Energy Information Agency. (EIA),2006. Electric Power Annual. Table 2.4 Planned NameplateCapacity Additions from New Generators, by Energy Source.http://www.eia.doe.gov/cneaf/electricity/epa/epat2p4.html(October 4, 2006).
U.S. Department of Energy, National Energy TechnologyLaboratory (NETL), 2007. Tracking New Coal-fired PowerPlants: Coal’s Resurgence in Electric Power Generation.http://www.netl.doe.gov/coal/refshelf/ncp.pdf (May 1,2007).
United States Federal Energy Regulatory Commission (FERC),2005. Form 714, Annual Electric Control and Planning AreaReport Data. http://www.ferc.gov/docs-filing/eforms/form-714/data.asp (updated December 2005).
Wise, M.A., Dooley, J.J., 2005. Baseload and peaking economicsand the resulting adoption of carbon dioxide capture andstorage systems for electric power plants. In: Rubin, E.S.,Keith, D.W., Gilboy, C.F. (Eds.), Greenhouse Gas ControlTechnologies, vol. I. Elsevier Science, pp. 303–311.
Wise, M.A., Dooley, J.J., Dahowski, R.T., Davidson, C.L., April2007. Modeling the impacts of climate policy on thedeployment of carbon dioxide capture and geologic storageacross electric power regions in the United States.International Journal of Greenhouse Gas Control 1 (2), 261–270, doi:10.1016/S1750-5836(07)00017-5.
post-combustion carbon dioxide capture and storage technologies
Greenhouse Gas Control (2008), doi:10.1016/j.ijggc.2008.06.012
http://www.eia.doe.gov/cneaf/electricity/epa/epat2p4.htmlhttp://www.netl.doe.gov/coal/refshelf/ncp.pdfhttp://www.ferc.gov/docs-filing/eforms/form-714/data.asphttp://www.ferc.gov/docs-filing/eforms/form-714/data.asphttp://dx.doi.org/10.1016/S1750-5836(07)00017-5http://dx.doi.org/10.1016/j.ijggc.2008.06.012
The value of post-combustion carbon dioxide capture and storage technologies in a world with uncertain greenhouse gas emissions constraintsBackground and objectiveApproachScenario definitionsResults and analysisThe role of PC+CCS in a well-defined future CO2 emissions controlled environmentThe role of PC+CCS in an ill-defined future climate policy environmentIn an uncertain policy environment, it is better to have more optionsIGCC+CCS and PC+CCS as options to manage uncertainty in technology developmentResulting CO2 emissions for ECAR
DiscussionReferences