The SecondNew Caledonian Nickel Conference

Building effective resource development partnerships for the next generationChris PointonPresident BHP Billiton Stainless Steel Materials

Page 2: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 2

We are successful in creating value when:

• Our shareholders are realising superior return on their investment

• Our customers and suppliers are benefiting from our business relationships

• The communities in which we operate value our citizenship

BHP Billiton’s Charter states: ‘Our purpose is to create value through the discovery, development and conversion of natural resources…’

Page 3: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 3

First fundamental: build and consolidate robust, enduring partnerships with local business

We have been working with New Caledonia since 1986

We purchased 2.3 million tons of lateritic ore in 2003 CY, earning New Caledonia nearly CFP5 billion (27 million tonnes to QNI since 1986)

We have relationships with small and large New Caledonian companies and we are actively increasing our number of suppliers

We have developed the ‘Environmental Manual for Mining’ with our partners, to make work practices more efficient and improve environmental performance

Our business accounts for nearly 90% of activity of the East Coast Mining Centers

Page 4: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 4

0123456789

10

1985

1987

1989

1991

1993

1995

1997

1999

2001

2003

0

500

1000

1500

2000

2500

3000Nickel Price NominalQNI NC Ore Imports

Nickel price vs New Caledonia ore imports

Source: Brook Hunt/BHP Billiton

Maintaining strong partnerships despite the vagaries of the market

ktpaUS$/lb

Page 5: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 5

Second fundamental: bring significant development experience and a proven track record of successful project delivery and technological innovation• 17 growth projects delivered since July 2001• On-time delivery providing savings for shareholders and certainty

for regional stakeholders

Page 6: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 6

BHP Billiton has a strong pipeline of new developments• In BHP Billiton “major” capital projects are those where BHP

Billiton’s investment share is USD100M or greater.• As at start July 04 the major project portfolio contained:

– 5 projects in “Feasibility”– Total project amount = USD 3.2B

– 14 major projects in “Execution”– Total project amount = USD 5.1B

Page 7: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 7

Major Project Delivery – the key is doing the “Front End Loading” before you start to build anything.At BHP Billiton we have a rigorous approach to major projects,

based on:– A disciplined capital investment process, which specifies all steps

required to ensure a project is ready for efficient delivery.– A rigorous internal Independent Peer Review Process, with reviews at

specified points (or “tollgates”)– Independent external assessment at end Feasibility against best

practice, using Independent Project Analysts Inc. (IPA)– Focus on Front End Loading through Key Leading Indicators.

Page 8: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 8

Key Elements of capital effectiveness:managing the project inputs

Source: Independent Project Analysts Inc

Page 9: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 9

Front End Loading Index for BHP Billiton project since 1991 – the benefits of a rigorous process

2

3

4

5

6

7

8

9

10

11D

ec-9

1

Dec

-92

Dec

-93

Dec

-94

Dec

-95

Dec

-96

Dec

-97

Dec

-98

Dec

-99

Dec

-00

Dec

-01

Dec

-02

Dec

-03

Dec

-04

FEL

Inde

x

No Tollgating Tollgating & Independent Review Authorised (Not Complete)

Scr

eeni

ngP

oor

Fair

Go

odB

est

Industry Average (IBC 2004)

Top Quintile Performance (IBC 2004)

Pre Tollgating Ave = 7.7

Post Tollgating Ave = 5.4

Page 10: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 10

We have developed, and operate, leading technologies:• Atmospheric leaching of nickel• BioCop – tank bioleaching copper sulfide• Bioheap Leaching – enhanced copper heap recovery• Falcon™ – gravity gradiometer for airborne minerals exploration• MAC™ dust• Mine optimisation – open pit strategic planning

BHP Billiton operates an impressive inventory of technologies. We are able to match technology to the specific orebody.

Page 11: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 11

A proven technology suite for nickelCerro Matoso – rotary kiln + submerged arc electric furnaceYabulu – reduction roast + ammonia leachRavensthorpe – EPAL, AL & PALSouth Africa/Chile – Bio-leaching and heap leaching

Page 12: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 12

Third fundamental: bring the highest international standards in environment, community engagement and business practice

QNI operates a fully ‘zero discharge’ site. Its “world’s best practice”water recycling project helped earn the approval of Government to expand its operations, even though it is located adjacent to the Great Barrier Reef Marine Park (WHA)

Page 13: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 13

The host country must provide clear guidelines, allowing investor to obtain fair return for risk and capital investment.

Fourth Fundamental: Partnership is a two-way process providing value creation opportunity for both host country and investor

Page 14: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 14

Cerro Matoso in Colombia• 20 years of operation• Remote agricultural host community• Stable fiscal regime respected by both operator and Government• Funded by equity and commercial project finance• Sustainable development effort a joint venture between company,

church and community

Cerro Matoso SA: a successful partnership with Government and Community

Page 15: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 15

Cerro Matoso’s sustainable development programme is designed to build a long term diversified local economy

The focus of Cerro Matoso’s sustainable development programme is on the long term:

– Education – developing a skilled new generation– Governance – embedding planning skills in the local municipalities– Micro-economy – working capital and training for local businesses and

entrepreneurs– Health – family health and clean water programmes– Service industries – recycling, transport, clothing, agribusiness and

forestry– Skills development – training and pre-qualifications

Page 16: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 16

A fair and stable fiscal regime, matched by high operating and project delivery standards, and by a commitment to invest in sustainabledevelopment of the host community will:

– Guarantee stability and security of operations, and attract sound investment– Enable communities to ensure that they obtain sustainable benefits– Give a better ability to strategically plan for the longer term– Encourage improved operational performance and efficiency

In conclusion: long term relationships between resource companies and host communities need stability and mutual responsibility

Page 17: The Second New Caledonian Nickel Conference

NoumeaSeptember 2004Page 17

Current Ore SupplyCurrent Ore Supply

Active SuppliersPotential Suppliers