the role of test closure activities in testing process

10
The Role of Test Closure Activities in Testing Process Crbtech.in

Upload: nikita-vyas

Post on 08-Feb-2017

51 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: The Role of Test Closure Activities in Testing Process

The Role of Test Closure Activities in Testing Process

Crbtech.in

Page 2: The Role of Test Closure Activities in Testing Process

Test Closure Activities.

l In the wake of verifying that test execution has been finished, the data received from various finished test exercises should be gathered and consolidated. You have to analyze the data to discover realities and numbers about the testing exercises amid the project cycle.

l Test completion tasks are done generally after the software is delivered, however there are different examples too where test closure is done like, if the venture got canceled or after support release is finished. Test conclusion exercises predominantly involve four sorts.

Page 3: The Role of Test Closure Activities in Testing Process

l Let’s See Them One By One:

Page 4: The Role of Test Closure Activities in Testing Process

1.Ensure completion of testing process:

l Ensuring that all the testing work has really been finished and closed. In case of complex projects it is likely that there can be a couple of things missed, so the test lead or manger needs to twofold check the test plan and ensure that all the planned tasks are really done. They have to ensure that all the decided test cases are either executed or skipped after the go ahead from stakeholders. Likewise every one of the defects in the venture ought to either be resolved and re-tested or conceded or acknowledged as perpetual confinements [such as, Technology limitations].

Page 5: The Role of Test Closure Activities in Testing Process

2.Handing Over Of Test Outcomes:

l Hand over the test artifacts to individuals who require it in future. After the release of the product, there are other individuals who will in any case be dealing with the project to maintain it, for instance teams like support and maintenance. These teams will require the test artifacts to make sense of if the reported bugs are as of now known defects or its another issue underway. Test artifacts are likewise required by support team to make sense of the steps to execute the diverse test scenarios or regression after any fixes are finished by maintenance engineers.

Page 6: The Role of Test Closure Activities in Testing Process

3.Project review:

l This is a critical activity of test conclusion, extend reviews are done to record the lessons learned in the project(both bad and the good). In these review meetings, it is examined that we keep on using best practices that worked truly well amid the venture and quit utilizing any unsuccessful practices.

l This was about the role of test closure activities, in the testing process. For more on this, and other testing related concepts, opt for software testing classes in Pune.

Page 7: The Role of Test Closure Activities in Testing Process

l There are numerous critical areas about project that should be talked about in review meetings, some of those areas include:

l Is the process followed in existing venture proficient or there are enhancements required in the process also.

l What was the pattern of defects found during the project. For instance, were the defects for the most part discovered late in light of the fact that we avoided a test level which would have recognized defects in advance and at a much lower cost.

Page 8: The Role of Test Closure Activities in Testing Process

Software testing

l We likewise need to discover was there any absence of skillset in the team because of which the team was not able to discover issues or it was a new technology because of which extensive number of bugs were found.

l Did the process of testing go smoothly as per plan? Or, were there any hiccups and diversions from the plan that need to be rectified in the upcoming projects? These and such questions need to be asked.

Page 9: The Role of Test Closure Activities in Testing Process

4.Record and maintain test work products:

l At last, all the test work products like test outcomes, test logs, test status reports, test cases, test plans and so on, ought to be preserved in configuration management system. The test plan and project plan ought to be put away in planning archive and have an unmistakable linkage to system and version they were utilized on, likewise the test execution reports ought to plainly be linked to the product version for which they were created.

Page 10: The Role of Test Closure Activities in Testing Process