TRANSCRIPT
The Punjab Masstransit Authority
MINUTES OF CLARIFICATION MEETING
Agenda TENDER FOR PROCUREMENT, OPERATIONS AND MAINTENANCE OF METRO
BUSES FOR LAHORE METROBUS SYSTEM (GAJUMATTA TO SHAHDARA)
Date: 06-07-2019
Venue Control Centre Lahore Punjab Metrobus Authority
Chair: Mr. Ozair Shah, General Manager Operations
,PMA.
List of Participants:
1. Ms. Nabila Javed, Secretary, PMA
2. Mr. Rizwan Aziz, Manager Operations (Technical), PMA
3. Ms. Anna Mumtaz, Assistant Manager (F&A), PMA
4. Mr. Adil Dyal, Assistant Manager (Operations), PMA
5. Mr. Abdur Rehman, COO, M/s Veda Transit Solution.
6. Mr. Abu Bakar Rashaid , PAE, M/s VPL Limited.
7. Mr. Adnan Qayyum, HOD- Bus Div, Foton Jv AutoPak (Pvt.) Ltd
8. Mr. Malik Alee, Master Motors
9. Mr. Arshad Bajwa, HOD, VPL
10. Mr. Yemen, Principal Officer, M/s Platform Tourizm
11. Mr. Hasnain Mian, Manager, M/s Platform Tourizm
12. Mr. Adil Noman, Director, Universal Auto Engineering
13. Mr. Khurram Mirza, GM, M/s Daewoo Pakistan
DECISIONS / DISCUSSIONS
The meeting started at 1100 hours. The General Manager Operations, PMA formally welcomed the
participants and started the meeting with recitation of Holy Quran. A presentation was then given
highlighting core Tender features. Question and Answer session was conducted afterwards including
the queries sent earlier by prospective bidders. Detailed Minutes of Meeting are attached as Annex
A. The list of participants is attached as Annex B. The meeting ended at 0400 Hours with a note of
“Thanks”
ANNEX- A
Sr. No QUERIES / COMMENTS PMA'S RESPONSE
A M/s Daewoo Pakistan
1. RFP
1.1. Tender Reserve Price
The Reserve Price for this Tender is PKR 310/- Per Kilometer
excluding Sales Tax on Services
1. Kindly share the cost breakdown of the reserve price of PKR 310 /
Km
Request denied. Please note that Reserve Price for this Tender is
revised and reflected in Addendum No 1.
2. Definition RFP
3.20 “VC/Venture Capitalist/Venture Capital firms” means A
person or investment firm that makes venture investments
This definition is not being used in any part of the RFP so can be
removed
Request denied.
3. Definition RFP
3.24 “Revenue Kilometers” means kilometer travelled during
operations when trips are scheduled for boarding and alighting
of passengers. Dead mileage shall be considered as Non-
Revenue Kilometers.
3.26 "Payable “Dead Mileage / Non Revenue Kilometers” means
those Dead Mileage / Non Revenue Kilometers as defined in
Section 3.25 (b) & (c) which will be paid according to the
specified schedule and conditions of Contract. The dead
mileage will be 23.85 Km for one-way trip to Shahdara Terminal
1. Yes. Dead Mileage will be part of Guaranteed Kms of 191.78
km/bus/day
2. PMA will pay dead mileage in case of trip cancellation due to any
strike or other emergency situation. Section 3.25 of RFP is amended
accordingly and reflected in Addendum No 1
3. Yes. They will be paid in accordance with Clauses 3.25 and 3.26
and 2.4 Km for one-way trip to Gajumatta Terminal
1. Payable Dead Mileage will be part of guaranteed Km of 192
km/bus / day, kindly confirm?
2. Other non-revenue Km should be included as payable dead
mileage, as an example of for any reason the trip is being cancelled
by strikes or riots or variation of routes etc. For the return to depot
buses from shahdara to Gajumatta will be paid or not?
3. For the return to depot buses from shadara to Gajumatta will be
paid or not?
4. Definition RFP
3.31 " Excess Kilometers" means Kilometers Plied exceeding
191.78 Km Per Bus Per Day
It is suggested the excess Kilometers to be calculated on monthly
basis rather than daily basis i.e 70,000/12 = 5,833.33 km
Request denied.
5. Definition RFP
Commencement of Operation date
1. Kindly clearly mention the commencement of operation date from
which the operator starts to raise invoices, please also include the
context as to how the deficient Kilometers working will be calculated,
if the start of operations could not be achieved in time.
Please refer to the delivery deadline as mentioned in Section 10.2.1 of
RFP and 32(4) of the Draft Contract in Addendum No 1, which is within
165 days after signing of the Contract. The commencement date will be
decided as follows:-
1. The commencement date will be within 10 days after the deadline as
deemed suitable by the Client. The payment will start from
commencement date.
2. In case the Operator shows its readiness before expiry of the
deadline, the Client will communicate the commencement date in
consultation with the Operator as deemed appropriate by the Client
but not exceeding aforementioned date in point no 1. The payment
will start from communicated commencement date.
3. In case Operator is ready after the deadline but corridor is not ready,
the Client will communicate the commencement date as deemed
appropriate by the Client. However in such case, payments to the
Operator will be made as per Section 10.1.23 of RFP
4. In case Operator is not ready or partially ready after the deadline but
corridor is ready, Liquidated damages will be invoked. The Client will
communicate the commencement date as deemed appropriate by
the Client based on operational readiness of the Operator.
For adjustments of deficient kilometers, time period will start from first
due payment whichever the case may be.
6. Reserve Buses
The RFP and the contract is silent on the reserve buses as a
percentage of the total kindly clarify
This will be Operator's decision in line with the terms and conditions of
the Contract
7. RFP
10.1.5 Client shall provide state of the art Masstransit stations
with AFC operation as well as elevated and/or fenced
Masstransit corridor
If there is any bumpy patch/track, the impact load will come on entire
bus structure especially on suspension system, tyres, rims, tie rods,
axel etc. ultimately causing severe damage of bus resulting in
increase of maintenance cost and recovery time. Does government
All previous reported defects in the corridor have been taken up and are
currently near to completion. PMA will put its best efforts in resolving any
corridor issues in the future.
As per SLA, Operator will be penalized in case of non-compliance solely
on his part. In case of any bus damages on part of the defected corridor
leading to inefficiency in operations, penalties will not be invoked to the
will compensate the operator this additional cost borne due to track
condition? Further, it is also suggested that operator shall
communicate the track condition to the Client on monthly basis and
the Client shall carry out track repair and maintenance work to
ensure smooth operations.
extent not on Operator's part. However in such cases, Government will
not provide any compensation in case of increase in costs such as
maintenance etc.
8. RFP
10.1.7 Arrange for provision of driver’s console in the buses;
and through the console the control centre will communicate to
the bus-driver the schedules regarding trips, routes, hour of
service, and timing at different station.
10.1.8 Equip every bus with GPS devices and relevant
components (on bus and off bus), that can gather location wise
data and transmit to central servers and related software
modules.
10.1.9 Provide Passenger Information System equipment and
software in buses
10.1.10 Provide depot for Parking of vehicle on at least one-side
of the LMBS Corridor with allied facilities such as washing, and
minor repairs (Civil works only).
All of these Items will be free of cost and no rental will be charged,
including cost of installation.
Yes. However for GPS devices and Passenger Information System
equipment in buses, the Client will arrange coordination between Bus
Operator and AFC-BSS Service Provide for their provisioning in the
buses. AFC-BSS Service Provider will be responsible for installation,
testing and commissioning of equipment in the buses.
9. RFP
10.1.14 For reconciliation of Guaranteed Kilometer, in every
12th invoice, all previous accumulated total kilometers plied
since start of the Contract shall be considered. In case the
Point wise answer to queries raised is as follows:-
1. Yes
2. Yes
3. Full rate cannot be paid for deficient kilometers as variable expenses
average Guaranteed Km/bus/year plied is less than committed
Guaranteed Kilometers for the corresponding time period, the
deficient kilometers will be treated as follows:-
1. The deficient kilometers will be bifurcated month wise for the
corresponding time period in chronological order.
2. For each bifurcated month, the Excess kilometers if available
will be converted to Guaranteed Kilometers. The rate applied
shall be the difference of Guaranteed Kilometer Rate and
Excess Kilometer Rate of the bifurcated month. In case the
Excess Kilometers are not available for the bifurcated month,
the Excess Kilometers will be borrowed from available month in
the chronological order. In that case the rate applied shall be
the difference of Guaranteed Kilometer Rate of the bifurcated
month and Excess Kilometer Rate of the borrowed month The
conversion of kilometers for the bifurcated months shall be
carried forward for onward reconciliations.
3. In case deficient kilometers still remain after following the
above procedure, the remaining deficient kilometers will be
paid according to the following formula:-
Rate / Km = (0.6485 x Bid Value) + previous Cumulative rate
adjustments up to the bifurcated month as per Annex-C
if the bifurcated month falls under the extended period of the
Contract the above formula shall be modified as follows:-
Rate / Km = (0.2109 x Bid Value) + previous Cumulative rate
adjustments up to the bifurcated month as per Annex-C
The deficient kilometers paid shall be treated as plied
Guaranteed Kilometers of the bifurcated month for onward
such as fuel, tires, lubricants and maintenance will not be incurred in
this case. The factor includes all fixed costs and profit. Please also
refer to Addendum No 1 as these factors have been modified due to
change in Reserve Price
4. For the extended period, it is assumed all capital costs would have
been paid before contract extension. Variable expenses such as fuel,
tires, lubricants and maintenance will not be incurred in this case.
The factor includes all fixed costs and profit excluding the capital
costs. Please also refer to Addendum No 1 as these factors have
been modified due to change in Reserve Price
reconciliations.
Our understanding of the revenue model is following
1) The guaranteed Km that the authority guaranteeing is total
KM over the life of the project
2) This, in case of deficient KM will also include the previous
paid deficient KM covered in to guaranteed KM by paying
differential of the rate paid earlier of respective months.
3) As per clause 3 after accounting for the above for total
guaranteed km, if less than 70k Km then Km will be paid at
0.6485 of the Bid rate. Why the authority will be paying less
than the guaranteed rate? It should be paid in full. Kindly
share the factor included in 0.6485.
4) For the extended period how the authority calculating 0.2109
factor? What is being included in this factor? it seems other
fixed cost our not included. It should at least be equal to the
sum of variable cost including salaries which as per annexure
C equals to 0.421.
10 RFP
10.1.19 Through AFC-BSS, provide the bus drivers the required
training of the use of the Driver Console.
Is this training free of cost?
Yes
11. RFP
10.1.22 Provide Bus operator the license to operate buses on
the LMBS corridor and the right to use the Depot so that Bus
Operator can perform its obligations in a timely manner.
Yes, PMA will charge license cost to bus operators which is very
minimal i.e. up to PKR 2000/- per bus
Is there any cost of acquiring this License? If yes what are the
charges / fee
12. RFP
10.1.23 Before start of operations, in the eventuality that all 64
buses are fully ready to operate to be legally plying on the
corridor, but the corridor is not operational; during such period,
the Client will pay the Operator at the rate per kilometer for
191.78 km/bus/day, which shall be computed as follows
Rate / Km = (0.5501 x Bid Value) + previous Cumulative rate
adjustments as per Annex-C
The period of payment under this Clause shall commence fifty
(50) days from the date of application by the Operator for
vehicle inspection as per following allowances for time to fulfill
all legal requirements:
1) 0.5501 represents what factors of the cost?
2) 50 days seems really high as there is no wait for corridor
completion. In the previous similar RFP the time was 5
days.it is suggested to keep it same to 5 days as additional
cost like interest, salaries utilities etc will be incurred by the
operator.
3) Kindly clearly mention the commencement of operation date
from which the operator starts to raise invoices, please also
include the context as to how the deficient Kilometers
working will be calculated, if the start of operations could not
Point wise answer to queries raised is as follows:-
1. This factor includes only fixed costs excluding variable costs and
profit. Please also refer to Addendum No 1 as these factors have
been modified due to change in Reserve Price.
2. What is referred as previous RFP is RFP for Multan Metrobus
System. There is no change in number of days. Please refer to
the Addendum to RFP for Multan Metrobus System.
3. Please refer to answer to the query at Serial No A(5).
be achieved in time.
13. RFP
10.1.20 Upon completion of the contract period, the Client shall
re-advertise the RFP for procurement of bus operator.
Just as the case in Multan Metro RFP, the existing Bidder should be
given the first right of refusal
The first right of refusal was deleted in the Addendum to RFP for Multan
Metrobus System. Request denied.
14. RFP
10.1.24 During the operations, in the eventuality that all 64
buses are fully ready to operate, but the corridor is not
operational for more than 30 consecutive days; during such
period, the Client will pay the Operator at the rate per kilometer
for 191.78 km/bus/day, which shall be computed as follows:-
1. All previous Excess kilometers shall be converted into
Guaranteed Kilometers. The rate applied shall be the difference
of applicable monthly Guaranteed Rate and paid Excess Rate of
the month in the chronological order from which the Excess
Kilometers are borrowed. The conversion of kilometers will be
carried forward for onward reconciliations as per Clause
10.1.14.
2. After adjustment of excess kilometers, the new rate shall be
computed as follows:-
Rate / Km = (0.5501 x Bid Value) + previous Cumulative rate
Point wise answer to queries raised is as follows:-
1. The factor 0.5501 includes only fixed costs excluding variable
costs and profit. Variable costs such as fuel, tires, lubricants and
maintenance will not be incurred in this case. The Factor 0.1413
is for the extended period. It is assumed all capital costs would
have been paid before contract extension. The factor includes
all fixed costs excluding the capital costs, variable costs and
profit. Please refer to Addendum No 1 as these factors have
been modified due to change in Reserve Price
2. Request denied.
adjustments as per Annex-C
If the period falls under extended period of the Contract the
above formula shall be modified as follows:-
Rate / Km = (0.1413 x Bid Value) + previous Cumulative rate
adjustments as per Annex-C
The kilometers paid shall be treated as plied Guaranteed
Kilometers for particular period for onward reconciliations as
per Clause 10.1.14.
1. Kindly share the component of costs for 0.5501 in
operation period and 0.1413 in the extended period.
2. Instead of 30 consecutive days the payment from the
authority should be based on 3 consecutive days of
nonoperational corridor.
15. RFP
10.2.3 In addition to these buses, the operator may be directed
within first year after commencement of operations to add up to
25% more buses as per requirement of the client/passenger
demand. Beyond one year, such addition of buses will be
mutual consent.
At the end of first year if the authority asks for additional buses then
remaining payback period for additional buses will be lower than the
older buses therefore the rate should be higher
Yes. The bidders may build the said rate in their bids.
16. RFP
10.2.48 Supply and hand over to the Client before
commencement of operations, 65 infrared thermometers of
fixed standing hand free type with non-contact face recognition,
minimum 8 inch display, HD camera, accurate measurement in
degree Celsius and Fahrenheit, high sensitivity, clear digital
display and sound working for outdoor, industrial durability,
long service life, AC and rechargeable battery powered, audible
alarm beep in outdoor and temperature threshold settings.
What will be the specs for the equipment demanded? Is this one
time cost?
Yes it is one time cost. The Operator will hand over these equipment to
Client before commencement of operations. The generic specifications
to comply with are already defined in the referred Clause.
17. RFP
12.11 Regular third-party audit (financial as well as technical) to
be made an integral part of the Operation. The Client will
arrange and bear the costs of third-party audits.
Does this means that the project will have separate financial
statements? As audits are done on company basis not project basis
Further the audit is already conducted by internal audit department
every month before making every payment
The referred clause deals with PMA audits from a third party. There is
no requirement of separate financial statements for this project on part
of the Operator. However, in case of any data requirements raised by
auditors pertaining to the Operator, the Operator shall facilitate them.
18. Clause 10.2.19
Provide maintenance plan of metro buses in consultation with
the Client, and implement it. The plan must cover procedures
and parameters for preventive and break-down maintenance, as
well as maintenance review procedures. During running
operations, the operator shall submit monthly bus maintenance
The estimated costs associated with maintenance of buses will be
submitted by the Operator in compliance to the referred clause. The
maintenance of bus includes fuel, tires, lubricants and spare part
replacements.
plan along with estimated associated costs in advance to the
Client for its approval.
This clause need to be clarify regarding ‘estimated associated
costs in advance’.
19. Clause 10.2.34
May replace any or all buses in the fleet at its own cost in case
the he buses are no longer capable of meeting the operational
requirements stated in this RFP. The replaced buses shall have
the same brand with compliance to bus specification stated in
this RFP.
What if the same brand stop manufacturing the buses of the same
specifications?
The matter may be covered under Force Majeure clause of the contract.
However, in such case, compliance to the bus specifications shall not be
compromised.
20. Clause 10.2.44
Install surveillance cameras as specified in the bus
specifications. Make necessary arrangements for the extraction
on daily basis, and storage of audio and video data for a period
no less than seven (15) days. The Digital Video Recorder (DVR)
should be provisioned and placed in such a way that it ensures
its safety and keep it intact during accidents especially
including collision of buses. Provide data to the Client upon
receiving his directions within the specified time frame. In case
Operator is unable to provide data, penalties will be invoked as
per Service Level Agreement (SLA).
The data storage period should be 10 days as heavy data will store
Request denied
on daily basis, each bus realized lots of trips in a day. So, it is
requested to keep it up to 10 days. Further there is no hard to
provide guarantee that DVR will work properly in case of bus
collision despite keeping it safe. A single electric fluctuation may
stop working of DVR and this happened in case of collision.
21. Clause 10.2.26
It is expected that driver must possess preferably graduate
degree and shall be tested and declared capable of reading
English instruction/tabs. The drivers hired before start of
operations will be trained once for the use of the Driver Console
by the Client through AFC-BSS; however, the qualification of
driver’s is mandatory for understanding the system parameter
and discipline of the system.
The condition of drivers’ graduation should be removed as it is not
possible in Pakistan to search graduate drivers in such a large
number.
The graduation of drivers is only preferred and not a binding on Operator
in the referred Clause.
22. Shelter facility at end terminal of LMBS corridor
It is requested and proposed to provide shelter facilities at start and
end of LMBS corridor for the Operator’s staff including dispatchers
and drivers as same is provided in Multan Metro Bus Service.
Request denied. Operator is responsible to arrange shelter facilities at
both terminals.
23. RFP
18.5.19 Properly arranged Scanned copy of entire Technical Bid
Scanned copy of Financial Bid shall not be provided in the USB.
in USB.
It has been clearly mentioned in the RFP that scanned copy of
technical copy shall be provided in USB. However, the RFP is silent
regarding the scanned copy of financial proposal. Kindly clarify
whether scanned copy of financial proposal is to be provided or not
in USB.
24. RFP
15 b. One partner will be designated the lead partner and would
enter into legal contract with Client and would be liable to incur
liabilities, receive payments and receive instructions for and on
behalf of any or all partners. A power of attorney to that effect,
legally executed, signed by all the partners shall be submitted
with the Tender
It is requested that in case of JV an AOP should sign the contract
and all the payments should be mode to the AoP directly rather than
the lead partner only.
The Client after due diligence may facilitate the Operator in case
Operator requires the Client to issue the payment cheque in the name of
AOP or JV company.
25. RFP
15 c. There must be at least one locally registered company
(Partner) of good repute and proven track record, in the joint
venture that must be the lead partner.
Any member of the JV can become Lead Member? Does the lead
member have to have relevant operational experience or an
investment company can also become a lead member?
Please refer to Section 15(c) of RFP
26. Contract Request denied
The Client shall pay the amount verified in the Certificate of
Payment within twenty one (21) days inclusive of seven days of
issuance of Certificate of Payment. Payment shall not be made
in advance. The Client shall make payment for the Services
provided, to the Operator, as per Terms of the Contract, in Pak
Rupees, through crossed cheque.
If the authority delays the payment then there should be some
penalty on the authority as well Or Assignment of receivable clause
may be included to eliminate delay in payment or working capital
gap.
27. Contract
Indexation
There is no Kibor indexation applicable in annexure C. It is
suggested to add Kibor indexation as well in the contract.
Request denied
28. Annexure C
For adjustments in Lubricants, base value considered shall be of the month of bid submission.
For adjustments in Tires, Maintenance and Salaries, base values considered shall be of the first complete calendar month after bid submission.
For Lubricant the rates will be average of the whole month or starting
price in the month or ending price in the month as the fluctuation in
pricing varies largely.
Additionally it is suggested to start the indexation from the Bid date
rather than monthly values.
The monthly Whole Sale Price Index as published by Pakistan
Statistical Bureau shall be considered for adjustments. The month
considered as base shall be the month of bid submission.
29. Annexure C
CT The Tires cost will be adjusted every year on January 1; on the basis of Wholesale price index variation in Auto Tires mentioned in Price Statistics published by Pakistan Bureau of Statistics, Government of Pakistan
It is suggested that the indexation of tire cost to be done on quarterly
bases rather than annual basis.
Request denied
30. Annexure D
5.2 Lighting Passenger Comfort
300 lux intensity of light in all areas of bus is only possible if main
source of light has intensity 900 lux or more. Practically, it has been
observed that it 100-150 lux in various internal areas and nooks.
Agreed. The light intensity is modified as 200 lux up to the passenger
seat level and reflected in the Addendum No 1 to the RFP
31. FINES FOR DEFICIENCIES RELATED TO USER OPERATION
Failure to deliver bus camera video to The Client (The penalty will be 500 Km if the video demanded is expected to reveal critical incident such as accident or Operator is unwilling to share the video for his own vested interest)
The penalty of 500 KM should not be there because the DVR
recording may be missing and sometimes it missed (as experienced
in pervious practice) due to multiple reasons like, malfunction of the
hard disk, virus, electric fluctuation, bugs, etc. So it will become hard
to judge the intentions of the operator.
Request denied.
32. KPI In case of Punctuality the margin will be as follows
Punctuality & Travel Time Regularity
In case of Punctuality and Travel Time Regularity there should be a
margin of +/- 30% of the given schedule head. This should be written
in RFP as it is written in case of Schedule Adherence in the RFP.
1. + 30% of the scheduled headway up to 3 minutes
2. +54 seconds for scheduled headways beyond 3 minutes
In case of Travel Time Regularity, the margin will be +60 seconds. The
changes are reflected in the Addendum No 1 to RFP
33. KPI
Reliability of Buses/ No. of Breakdowns
In case of No. of Breakdowns the standard per month of maximum 2 should be for first three years of the contract period and for the remaining five years it should be maximum 10. The buses got depreciate after three years to an extent that the chance of breakdown increase due to multiple technical and mechanical reasons.
Request denied
34. FINES FOR DEFICIENCIES RELATED TO USER OPERATION
Failure to follow or acknowledge instructions issued by the Control Center, operations personnel OR Any act/instance which is non-conforming to Authority's Rules/Regulations/Contract/Instructions , not covered in other sections of SLA
30 x A ( Where A = 1 to 100 depending upon sensitivity of event and decision from the Client
The above given clause of the contract should not be generalize; it
should be specific and if it is compulsory to keep it in generalize form
Request denied.
than there should be a penalty of 30 KM only without factor as all
the serious violations already covered in SLA.
35. FINES FOR DEFICIENCIES RELATED TO USER OPERATION
Injury caused to the passenger due to negligence in operations including but not limited to improper docking, improper dwell time, improper door operations, improper vehicle acceleration and deceleration etc. In addition to the penalty the case will be dealt as per RFP clause 10.2.37 ( 1000 kms)
As the said penalty is the highest penalty given in SLA; it should be
written in SLA that in order to invoke the above penalty client will
provide medical certificate duly sign and stump by a govt. hospital as
an strong evidence as it is written in the contract that client will
provide strong evidence before invoking any penalty.
Agreed. The modifications are reflected in the Addendum No 1 to RFP.
36. SANCTIONS AGAINST DRIVERS
To drive above speed limits
In this clause a margin of 10 sec should be in written form. For
example if driver drive the bus above speed limit for 10 seconds is
acceptable. This often happens while moving down from elevated
area of the track.
Agreed. The modifications are reflected in the Addendum No 1 to RFP.
37. SANCTIONS AGAINST DRIVERS
To move the bus without fully closing the bus doors
This clause needs to be specific on the part of drivers’ negligence.
For example if bus move without fully closing the bus doors due to
drivers’ negligence than the above penalty should invoke but if bus
In case of mechanical failure leading to improper closing of doors, the
bus is not allowed to continue its trip keeping in view passenger's safety.
In such cases, penalty will be invoked to the extent on Operator's part.
move without fully closing or partially closing of bus doors due to
mechanical reasons than 20 km’s penalty should invoke which is at
page 49
“Inadequate operation of passenger access doors, either due to
damage or incorrect operation including nonfunctional door cameras
and display units which affects boarding and alighting times or safety
of passengers”
38. PENALTIES
MONTHLY ACCUMULATED PENALITES IN KM’S
Less than 100 kms
100-250 Km’s – 70% of Accumulated Penalties in Km’s
251-500 Km’s – 80% of Accumulated Penalties in Km’s
501-750 Km’s – 90% of Accumulated Penalties in Km’s
751-1000 Km’s – 100% of Accumulated Penalties in Km’s
Above 1000 Km’s – 200% of Accumulated Penalties in Km’s
It is proposed and requested to revise penalties chart
Less than 100 kms
100-250 Km’s – 70% of Accumulated Penalties in Km’s 251-500 Km’s – 80% of Accumulated Penalties in Km’s 501-750 Km’s – 90% of Accumulated Penalties in Km’s 751-1000 Km’s – 100% of Accumulated Penalties in Km’s
Request denied
1001-1500 Km’s – 125% of Accumulated Penalties in Km’s 1501-2000 Km’s – 150% of Accumulated Penalties in Km’s 2001-2500 Km’s – 175% of Accumulated Penalties in Km’s Above 2501 Km’s – 200% of Accumulated Penalties in Km’s
B. Volvo Pakistan Limited (VPL)
1. 10.2.1 Procure 64 Brand New, Air Conditioned (AC), 18m, Diesel
operated buses as per prescribed specification to be delivered
to Lahore Metrobus Depot at Nishter, within 135 calendar days
from signing of the Contract henceforth called the dead line.
Owing to COVID-19 pandemic, the global supply chain network is
highly affecting especially shipping lines are not under control of any
manufacturer/operator of buses. The stingent requirements at port
requesting for qurantine of shipments may result in additional days
on shipment of Buses to Pakistan. Further to above, the banking
channels are being extra vigilent during these tough times therefore,
taking extra precautions while issuing LCs which take additional time
as regular days.
To ensure quality of product and meeting of all internatioanl and
national standards of buses, we recommend to provide grace period
in Shipment timelines and extend 135 days to 150 days minimum.
The deadline is modified as 165 days and reflected in the Addendum No
1 to RFP
2. 10.2.2 Ensure compatibility with the existing AFC-BSS. It is clarified that AFC-BSS equipment is owned by PMA. The Contractor will be required to ensure compatibility of AFC-BSS equipment in coordination with the bus man The equipment details of AFC-BSS and their respective locations to
be installed in the buses are missing in the tender documents and so
Client will share such details after the issuance of LOA to successful
bidder
are the details of AFC-BSS Contractor to retreive the required
information. The details regarding availability of such equipment are
also missing that whether such equipment will be installed in
Pakistan or Country of Origin of buses as it depends upon the
procurement timelines of such equipment.ufacturer and the AFC-
BSS Contractor
The locations and details of AFC-BSS contractor may be shared and
made part of tender document so that relevant wiring provisions can
be kept inside the buses.The equipment may be made avaialable at
the factory location so that clean installation can take place without
any retrofitting locally in Pakistan.
3. 10.1.7
Arrange for provision of driver’s console in the buses; and
through the console the control centre will communicate to the
bus-driver the schedules regarding trips, routes, hour of
service, and timing at different station.
The equipment details (Dimensions) of driver console equipment are
missing in the tender documents whereas it is critical to operations
and the preferred location of such equipment is also lacking as the
provision have to be kept while designing the bus to ensure the
installation of such equipment. The details regarding availability of
such equipment are also missing that whether such equipment will
be installed in Pakistan or Country of Origin of buses as it depends
upon the procurement timelines of such equipment.
The details of driver console equipment and contractor may be
shared and made part of tender document so that relevant wiring
provisions can be kept inside the buses.The equipment may be
Driver consoles are already installed in existing buses and these
consoles will be shifted to new buses upon their arrival in Pakistan.
Client will share other details after the issuance of LOA to successful
bidder
made avaialable at the factory location so that clean installation can
take place without any retrofitting locally in Pakistan.
4. 10.2.29
Ensure that air-conditioning facility continues uninterrupted
during operation in case of a mechanical break-down of the bus
except in case of engine failure
Mechanical break-down can also include air-conditioning
system break-down and number of other breakdowns such as
blown out fuse that can result in malfunctioning of air-
conditioning inside bus not limited to Engine failure
We recommend to change this clause to allow for other mechanical
breakdowns as well that doesn't allow movement of bus and
specifically Air-conditioning system breakdown
Request denied
5. 10.2.44
Install surveillance cameras as specified in the bus
specifications. Make necessary arrangements for the extraction
on daily basis, and storage of audio and video data for a period
no less than seven (15) days. The Digital Video Recorder (DVR)
should be provisioned and placed in such a way that it ensures
its safety and keep it intact during accidents especially
including collision of buses. Provide data to the Client upon
receiving his directions within the specified time frame. In case
Operator is unable to provide data, penalties will be invoked as
per Service Level Agreement (SLA).
It a typographic error which is corrected and reflected in the Addendum
No 1 to RFP
There is a discrepancy in words and numeric digit mentioned for the
least number of days of data storage
Clarification required as to which requirement to follow
6. 10.2.48
Supply and hand over to the Client before commencement of
operations, 65 infrared thermometers of fixed standing hand
free type with non-contact face recognition, minimum 8 inch
display, HD camera, accurate measurement in degree Celsius
and Fahrenheit, high sensitivity, clear digital display and sound
working for outdoor, industrial durability, long service life, AC
and rechargeable battery powered, audible alarm beep in
outdoor and temperature threshold settings
The use/function of such devices are required to further propose a
solution and meet compliance requirement.
These devices will be placed in stations and not buses. Please also refer
to answer to queries at Serial No A(16).
7. Annexure-D12.2
Each bus shall be equipped with a self disinfectant system with
a liquid tank of sufficient capacity and pressure pump as option
available to a driver with push button to spray the whole bus at
the end of each trip. The system shall generate a mist of a
suitable chlorox type non-flamable self evaporating disinfectant
in the entire bus prior to start of a trip. As a safeguard, the
pump system shall remain disabled while the bus speed is non-
zero i.e. in a moving bus. The mist shall be used to disinfect the
bus in the direction from roof to floor and its discharge points
shall be placed proportionally to cover the entire inside of a
bus.
UV Light is not accepted. However instead of suitable chlorox type non-
flammable self evaporating liquid disinfectant, the Operator may use any
other liquid disinfectant in compliance with available international
standards to fulfill the purpose. The modifications are reflected in the
Addendum No 1 to RFP
There are number of ways in which buses can be disinfected for
potential infections inside bus and mist is one of them.
Repeated use of disinfectant can have long term impact on the
buses interior which may fade and wirin of buses can also get
damaged as PVC is not very soluble in ethanol or isopropanol
(Disinfectnat Mixutre), but prolonged exposure may cause
crazing or stiffening resulting in breakdowns. The damage can
also be done to paint job inside the bus such as fading of seat
colors.
we recommend allowing operators to use other types of disinfectants
as well such as UV lights are being used to treat to interior/exterior
of buses in China. The same UV light disinfectants are being used in
Hospitals as well as they provide better disinfection of equipment
and area. Since the disinfection has to be done while no passengers
are on board, therefore, UV light can be one of the best modes of
disinfectant.
C. M/s PLATFORM TURIZUM
1. Bid Submission Date Extended
Under post Covid 19 circumstances, Bid submission activities are
taking little extra time. You are hereby requested to extend Bid
Submission deadline/date by at least one week.
Agreed. The bid date and time is extended to 27.07.2020 at 1100 hours.
The changes are reflected in the Addendum No 1 to RFP.
2. 1.4 Type of Tender Page # 5
Whether Foreign companies which don’t have local presence in
Pakistan, can participate in the Tender as per clause 13.3 of RFP?
They can participate in a JV with lead member as a locally registered
company.
3. 6(1) Tender Scope Page # 9 The decision is solely on Operator's part. There is no binding in the RFP
Whether Tow-away Trucks needs to be procured by the Bidder or
Bidder can arrange the Tow-away Trucks on Rental basis?
4. Clause 9 Page 11 & Annexure-C Page # 55 & 56
Rate of payment for extra kilometers needs to be rationalized. Rates
mentioned are very less. Only 42 percent of Non-Excess Km Rate
can’t cover variable cost of operating one extra kilometer along with
little profit margin therein.
Due to revision in the Reserve Tender Price, Non-Excess Km rate has
been modified and reflected in the Addendum No 1 to RFP
5. 9 Contract Type and duration Page # 11
Per km rates for Non-excess and Excess Km’s for the probable
extended period of one year are very low. Kindly rationalize the said
rates as per above-clause.
Due to revision in the Reserve Tender Price, the rates for the extended
period have been modified and reflected in the Addendum No 1 to RFP.
The rates as published in the Addendum No1 to RFP will not change,
however, the bidder may adjust its bid price accordingly.
6. 10.1.11 Services Required Page # 11
Kindly elaborate the term “suspension/stopped on Operator’s part”?
What kind of events may fall under the said term?
These include events which lead to suspension or stoppage of
operations and are attributable on Operator's part such as strike from
Operator's staff etc.
7. 10.1.23 Services Required Page # 13
It is stated in the said clause that “The period of payment under this
Clause shall commence fifty (50) days from the date of application
by the Operator for vehicle inspection as per following allowances for
time to fulfill all legal requirements”
Kindly amend the portion of the clause because Operator have to
pay the lease installment’s to the bank and any delay in the
commencement of payment in the absence of any mobilization
advance will make it difficult to the Operator to manage the finance
Request denied. Please refer to the answer to queries at Serial No A(12)
issues
8. 10.2.1 Services Required Page # 15
Kindly enhance the time period for induction of the buses within 135
days and make it 175 days from the contract signing date while
considering the facts that current Covid 19 situation is making it
difficult to meet stringent timelines and also client must understand
that in all its previous 3 BRT projects, supply timeline could not be
met by any operator because of practical limitation involved therein.
It would not be rational to stick to non-practical/too ambitious
timelines to cause loss of operators as well as client.
Please refer to the answer to queries at Serial No B(1)
9. 10.2.19 Services Required Page # 16
Kindly delete the portion of the clause related to “submission of
estimated associated costs to the Client for its approval”. This will
not only delay the maintenance work but also basic purpose of
service level parameters and relevant penalty mechanism for not
compliance will be undermined. Also sharing such information
means sharing of competitive information of bidder
Request denied.
10. 10.2.26 Services Required Page # 16
Requirement of Graduate Degree for Bus Driver:-
Kindly delete the word “must” from the said clause and make it
preferably to facilitate hiring of suitable drivers who may not possess
graduate degree.
Agreed. The changes are reflected in the Addendum No 1 to RFP
11. 10.2.31 Services Required Page # 17
Kindly modify the said clause and response time should be specified
The response time shall be specified to the Operator in the Operational
SOP's based on location of tow-away trucks and other factors.
with mutual consent of both the Client and the Operator
12. 10.2.34 Services Required Page # 16
What will be the specific parameters to consider that buses are not
capable of meeting the operational requirement as per this clause?
or it will be sole discretion of Operator?
It will be sole discretion of the Operator.
13. 10.2.38 Services Required Page # 17
Who will be responsible for the Security of the Metro Buses on the
Corridor?
Bus Operator shall be responsible for the security of the buses.
14. 10.2.45 Services Required Page # 18
Kindly remove the said clause because it is difficult for the Operator
to arrange the security for the buses on immediate notice for any
place mentioned by PMA. Further in presence of the depot for
parking of the buses, placing expensive assets at any place other
than depot is attracting too much risk for such expensive assets.
Request denied.
15. 10.2.46 (2) Services Required Page # 18
Kindly rephrase the said clause as all activities at the end of each
trip may not be practical/economical.
Request denied.
16. 10.2.48 Services Required Page # 18
Kindly remove the requirements mentioned in this clause from the
RFP Documents and Client either itself can purchase the said
equipment or instruct the winning bidder to purchase the said
equipment under a work order from PMA and get the one time
reimbursement accordingly.
Request denied.
17. 10.2.49 Services Required Page # 18
This is tantamount to calling our basic competitive information. You
are hereby requested to kindly limit this clause only to Bill of Lading
and certificate of origin and any certificate endorsing Brand New
status of Buses.
Request denied. However, for Operator's facilitation, all indicated
information will be received from the Operator under a Non-Disclosure
Agreement (NDA). The information if shared with any other Government
organization shall be treated as strictly confidential. The modifications
are reflected in the Addendum No 1 to RFP.
18. 12.11 Revenue collection and Payment Page # 19
Kindly delete the said clause because in the presence of penalty
mechanism and performance guarantee, client is already ensuring
that operator maintains technical and financial worth 24/7 to achieve
principal objectives of PMA for smooth operations.
The referred clause comes under the scope of Client and not the
Operator. The said request is invalid.
19. 20 Tender Security Page # 25
Where to place the Tender Security in the “Technical Envelope” or
“Financial Envelope”?
The bidder will submit the original Tender Security with Financial Bid
and copy of the Tender Security with the Technical Bid.
20. 15 of GCC (Payment) Page # 34
It is written in the said clause that “The Client may withhold a
Certificate of Payment on account of defects/shortcomings in the
services provided”. This is an open ended close kindly limit the time
period for such an instance.
Further Delayed payment by the authority to the Operator should
bear late payment charges as per prevailing KIBOR for the delayed
period.
Request denied
21. 24 of GCC (Termination for Convenience) Page # 38
Kindly amend the said clause and take the market value of the
Paying an allowance as compensation for overheads and anticipated
profit to the Operator has been modified from 5% to 7.5%. Other
buses while paying to the Operator. Secondly kindly enhance the
rate of anticipated profit to the Operator and make it 20%. Thirdly
kindly specify the maximum number of days within which
client/operator may settle their payable obligations falling under this
clause.
requests are denied.
22. 25 of GCC (Force Majeure) Page # 39
We are facing force majeure situation currently and client is handling
it very well. Current response of PMA to force majeure situation
should be added in force majeure clause to add clarity therein.
It has been already included. Please refer to Section 10.1.24 of RFP and
Addendum No 1 to RFP.
23. Annex-A Page # 44
Calling of financial information via “Form Tech-8” instead of
“Form Tech-4” at page number of 44 seems typo error. Kindly
amend the same.
This is a typographical error which is corrected and reflected in the
Addendum No 1 to RFP
24. Annex-C Page # 55 & 56
Kindly enhance the Fuel Factor Rate and align it with current fuel
rates along with taking its impact to excess/non-excess etc Km
rates.
Agreed. All factors have been modified due to change in Reserve Price
after incorporating current fuel rate. Please refer to the Addendum No 1
to RFP
25. Key Performance Indicators (Breakdowns) Page # 48
It is suggested that before declaring an incident at corridor as
“Breakdown” a minor reasonable time
(Max 15 Minutes) should be provided to resolve the issue up to
satisfaction of PMA. In case of failure to resolve the issue within the
specified time frame, incident should be declared as Breakdown.
Breakdown for clarity is defined as an event in which a bus encounters a
failure in its system making it incapable of continuing the scheduled trip
and leading to disembarking of passengers. The modifications are
reflected in the Addendum No 1 to RFP
Addendum 01 to Tender Document
PROCUREMENT, OPERATION, AND MAINTENANCE OF METRO BUSES FOR LAHORE METROBUS SYSTEM
(GAJJUMATTA TO SHAHDARA)
THE PUNJAB MASSTRANSIT AUTHORITY Government of the Punjab
5th Floor, Arfa Software Technology Park (ASTP) 346-B, Main Ferozepur Road, Lahore, Pakistan. Phone: +92 42 99028000 Fax: +92 42 9923 2541
URL: www.pma.punjab.gov.pk
Addendum No.1 to the Tender Document Due to some clarifications required in the RFP document, the following addendum is hereby issued; which shall form a part and parcel of the original document titled " PROCUREMENT, OPERATION, AND MAINTENANCE OF METRO BUSES FOR LAHORE METROBUS SYTEM (GAJJUMATTA TO SHAHDARA)"
,issued and uploaded on July 11, 2020. The contents of this addendum shall supersede/replace pages 05, 06, 08, 09, 11, 13, 14, 15, 16, 18, 19, 38, 42, 44, 45, 46, 51, 52, 55, 56, 60 and 66 of the original RFP document, and shall be read as part of the RFP document uploaded on the following websites:
www.pma.punjab.gov.pk
www.ppra.punjab.gov.pk
The aforementioned modified pages are hereby attached with this addendum with changes as highlighted text.
1. Invitation to Bid
Punjab Masstransit Authority, Government of the Punjab (GoPb) invites bids for the Tender for “PROCUREMENT, OPERATION, AND MAINTENANCE OF METRO BUSES FOR LAHORE
METROBUS SYSTEM (GAJJUMATTA TO SHAHDARA)” The Tender Number is PMA-TNDA-LMBS-L1/02/2020
1.1. Tender Reserve Price
The Reserve Price for this Tender is PKR 310/- 328/- Per Kilometer excluding Sales Tax on Services.
The estimated Contract Price can be calculated according to the following Formula:-
Contract Price = Rate per Kilometer x Minimum Guaranteed Kilometers per bus per year x
Number of buses x Contract Life
= 310 328 x 70,000 x 64 x 8 = PKR 11,110,400,000 / - 11,755,520,000/-
It may be noted here that
a) The Reserve Price is an estimated price based on Diesel rate of PKR 101.46/- per liter, as notified by
Pakistan State Oil (PSO) on their official website (www.psopk.com), prevalent on advertisement
date of Addendum No 1 to this RFP which is. 10.07.2020. All bidders are required to submit their
bid values based on the aforementioned Diesel rate.
b) The total contract value can only be estimated based on the aforementioned formula due to possible
variation in kilometers plied and adjustments on account of factors such as fuel, lubricants, spare
parts, salaries, taxes etc. during the currency of the contract.
1.2. PPRA Rules to be followed Punjab Procurement Rules 2014, as modified from time to time ,will be strictly followed. These may be
obtained from PPRA’s website:
http://ppra.punjab.gov.pk/PublicPages/prorules1.aspx
In this document, unless otherwise mentioned to the contrary, "Rule" means a Rule under the Punjab
Procurement Rules 2014.
1.3. Mode of Advertisement(s) As per Rule 12, 12(1), and 12 (3) this Tender is being placed online at PPRA's website, as well as being
advertised in print media. The bidding document carrying all details can be downloaded from websites
www.pma.punjab.gov.pk and www.ppra.punjab.gov.pk, for information only.
1.4. Type of Tender This is a National Tender with response time not less than 15 days as per Rule 14.
1.5. Type of Open Competitive Bidding
As per Rule 38(2), Single Stage - Two Envelope Procedure shall be followed. This is as follows: i. The bid shall comprise of a single package containing two (2) separate envelopes.
ii. The envelopes shall be marked in bold and legible letters to avoid confusion, as follows:
a. “ENVELOPE-NO. 1:TECHNICAL PROPOSAL”
b. “ENVELOPE-NO. 2:FINANCIAL PROPOSAL”
iii. Initially, only the ENVELOPE-NO. 1 marked TECHNICAL PROPOSAL shall be opened;
iv. ENVELOPE NO 2 shall be retained in the custody of the Client without being opened;
v. The technical proposal will be evaluated in a manner as per the clauses mentioned in this
document; and proposals which do not conform to the specified requirements as listed in said
document will be rejected.
vi. During the technical evaluation no amendments in the technical proposal shall be permitted;
Page 5 of 82
vii. The ENVELOPE-NO. 2: FINANCIAL PROPOSAL of technically qualified bidders shall be
opened publicly at a time, date and venue announced and communicated to the bidders in
advance;
viii. After the evaluation and approval of the technical proposal the Client shall, at a time within the
bid validity period, publicly open the ENVELOPE-NO. 2: FINANCIAL PROPOSAL of the
technically accepted and qualified bids only.
ix. The technically qualified bidder with lowest financial bid will be the successful bidder.
x. PMA will invite the successful bidder to enter into an Agreement.
2. Bidding Details (Instruction to Bidders)
In line with PPRA Rule 27, the bid security fixed for this Tender is PKR 20/- Million. All bids must be
accompanied by a Demand Draft / Pay Order/ Bank Guarantee of PKR Twenty (20) Million (See Price
Schedule of General Condition of Contract) as bid security in favor of “Punjab Masstransit
Authority” issued by a scheduled bank allowed carrying financial transactions in PAKISTAN. Clause
20 gives details on Tender Security.
The bids along with the Demand Draft / Pay Order/ Bank Guarantee, Tender Forms, Affidavits, etc.,
must be dropped in Tender Box placed at the Office of the Punjab Masstransit Authority, 5th Floor, Arfa
Software Technology Park (ASTP), Lahore, PAKISTAN, on or before 1100 hours on 27th July, 2020.
The Technical bids will be publicly opened in the Committee Room of the Punjab Masstransit Authority,
5th Floor, Arfa Software Technology Park (ASTP), at 1130 hours on 27th July, 2020.
The Punjab Masstransit Authority shall hold a clarification meeting at 1100 hours on 06th July, 2020; at
the Committee Room, loor, Punjab Masstransit Authority, 5th Floor, Arfa Software Technology Park
(ASTP), Lahore, PAKISTAN. Bidders in case of any queries for seeking clarifications regarding the
specifications of the services may send their queries in writing at the office of Punjab Masstransit
Authority, 5th Floor, Arfa Software Technology Park (ASTP), Lahore, PAKISTAN, or email to the
designated address on or before 29th June, 2020 or raise them during the Clarification Meeting. All
queries shall be responded to within due time. No query shall be responded if received after the
Clarification Meeting. The minutes of Clarification Meeting shall be considered as part of this RFP.
The bidder must submit bids on the basis of complete fulfillment of requirements. Failure to meet this
condition will cause disqualification of the bidder. The bidder shall submit bids which comply with the
Bidding Document. Alternative bids will not be considered. The attention of bidders is drawn to the
provisions of Clause on “Determination of Responsiveness of Bid” regarding the rejection of Bids,
which are not substantially responsive to the requirements of the Bidding Document.
The contact detail for all correspondence in relation to this bid is as follows:
Email: [email protected]
Punjab Masstransit Authority
5th Floor,
Arfa Software Technology Park (ASTP),
Lahore, PAKISTAN
Page 6 of 82
Services submitted by a bidder in response to RFP.
3.14 “RFP” means Request for Proposals, including any amendments that may be made by the
procuring entity for the selection of bidder.
3.15 “SBD” means Standard Bidding Documents.
3.16 “SCC” means the Special Conditions of Contract.
3.17 “Services” means the tasks to be performed by the bidder pursuant to the Contract as listed under RFP Section 10.2
3.18 “TEC” means the Technical Evaluation Committee, constituted for the purpose of evaluating
the Proposals received.
3.19 “Terms of Reference” or “TOR” means the document which explains the objectives, scope of
work, activities, task to be performed, respective responsibilities of the procuring entity and the
bidder, and expected results and deliverables of the assignment.
3.20 “VC/Venture Capitalist/Venture Capital firms” means A person or investment firm that makes venture investments
3.21 "Works" means work to be done by the Operator under the Contract.
3.22 “GoPb” means Government of the Punjab
3.23 “GoP” means Government of Pakistan
3.24 “Revenue Kilometers” means kilometer travelled during operations when trips are scheduled
for boarding and alighting of passengers. Dead mileage shall be considered as Non-Revenue
Kilometers
3.25 “Dead Mileage / Non Revenue Kilometers” means kilometer travelled when trips are not
scheduled for boarding and alighting of passengers. The examples of Dead Mileage are
a) Kilometers travelled outside the LMBS Corridor for any reason whatsoever.
b) Kilometers travelled from Depot Exit to Station/Route terminal to start a trip.
c) Kilometers travelled from Station / Route terminal to Depot Entrance, after completing the
trip or after cancellation of a trip due to emergency situation as directed by Control room.
d) Kilometers travelled from corridor to Depot in case of any maintenance work / fueling /
breakdown during operations
e) Kilometers travelled by an empty bus inside the corridor which is unable to board
passengers during operations due to any reason whatsoever.
f) Kilometers travelled that are unassigned by the Client.
g) Kilometers travelled in violation of the schedule or conditions/instructions of the schedule.
Schedules are further clarified in Clause 10.2.4
3.26 "Payable “Dead Mileage / Non Revenue Kilometers” means those Dead Mileage / Non
Revenue Kilometers as defined in Section 3.25 (b) & (c) which will be paid according to the
specified schedule and conditions of Contract. The dead mileage will be 23.85 Km for one-way
Page 8 of 82
trip to Shahdara Terminal and 2.4 Km for one-way trip to Gajumatta Terminal
3.27 "Non Payable “Dead Mileage / Non Revenue Kilometers” means those Dead Mileage / Non
Revenue Kilometers as defined in Section 3.25 (a), (d), (e), (f) & (g) which will be not be paid
according to the conditions of Contract.
3.28 "Penalty Kilometers” means accumulated kilometers for each month which will be fined due
to lapses and non-conformances as per Service Level Agreement. The fines shall be computed
as per Clause 10.1.25 and deducted from monthly payments.
3.29 "Guaranteed Kilometers / Non Excess Kilometers" means Kilometers Plied up to 191.78
Kilometers Per Bus Per Day
3.30 "Guaranteed / Non Excess Kilometer Rate" means Bid Value subject to adjustments as per
Annex-C
3.31 " Excess Kilometers" means Kilometers Plied exceeding 191.78 Km Per Bus Per Day
3.32 "Excess Kilometer Rate" means (Bid Value x 0.4258) subject to adjustments as per Annex-C
3.33 "Bus Breakdown" means an event in which a bus encounters a failure in its system making it
incapable of continuing its scheduled trip and leading to disembarking of passenger(s).
4. Headings and Titles In this document, headings and titles shall not be construed to be part thereof or be taken into
consideration in the interpretation of the document and words importing the singular only shall
also include the plural and vice versa where the context so requires.
5. Notice
5.1 In this document, unless otherwise specified, wherever provision is made for exchanging notice,
certificate, order, consent, approval or instructions amongst the Bus Operator and the Client, the
same shall be:
5.1.1 in writing;
5.1.2 issued within reasonable time;
5.1.3 served by sending the same by courier or registered post or by hand to their principal
office in Pakistan or such other address as they shall notify for the purpose; and
5.1.4 The words "notify", "certify", "order", “consent”, “approve”, "instruct", shall be
construed accordingly.
6. Tender Scope
Punjab Masstransit Authority, GoPb, invites/requests Proposals (hereinafter referred to as “the
Tenders”) for the Procurement, Operation and Maintenance of buses, as outlined in this
document. In the first phase, PMA is looking for induction of 64 Brand New 18-m Articulated
Air conditioned (AC) Diesel buses.
The Bus Operator’s scope of work is as follows;
1. Procurement of buses and tow-away trucks including payment of all applicable taxes,
insurance, and transportation to Lahore Metrobus Depot.
Page 9 of 82
• There are station amenities such as water coolers, water motors, washrooms, ticket booths,
Ticket Vending Machines, Announcement System, Surveillance Cameras, Passenger
Information screens, gensets, transformers, turnstiles etc. Washrooms, water motors and
transformers are located outside the station at varying accessible distances from the stations
• Automated Fare Collection (AFC): Two types of electronic fare media are used i.e. token and
smart card which are validated at turnstiles before entering into the platforms
• Intelligent Transportation System (ITS) at intersections providing Metrobus Signal Priority.
• Terminal stations i.e. Shahdara and Gajjumatta have bus turnarounds and bus parking space
• Operations is monitored and controlled through Command & Control Center located in Arfa
Karim Software Technology Park (ASTP), 5th Floor, Ferozpur Road, Lahore
9. Contract Type and Duration
Contract will be for procurement, operations and maintenance of buses for a period of 8 Years
from commencement of operations. The duration may be extended based on running condition
of buses as mutually agreed between the Parties.
In case if at the expiry of the Contract, new operator has not been engaged, deployed and ready
to take over the operations, the duration of the Contract will be automatically extended till
successful engagement, deployment and take over by the new Operator; however such automatic
extension shall not exceed 01 year after the expiry of the Contract.
In case of any extension in the Contract after 08 years from commencement of operations, the
new payment rate shall be computed as follows:-
Guaranteed / Non-Excess Rate per Km = (0.5625 0.5978 x Bid Value) + previous Cumulative
rate adjustments as per Annex-C
Excess Rate per Km = (0.4258 0.4752 x Bid Value) + previous Cumulative rate adjustments as
per Annex-C
Sponsorship of Operation: Punjab Masstransit Authority– GoPb
Technical Evaluation: Punjab Masstransit Authority, GoPb.
Contract Signing: Formal Contract will be signed between technically qualified bidder with the
lowest financial bid, and the Client (Punjab Masstransit Authority, GoPb).
10. Services Required
Contractual obligations Roles and Responsibilities shall be as under:
10.1 The Client Shall:
10.1.1 Undertake and complete a competitive and transparent bidding process to select the successful
bidder.
10.1.2 Follow PPRA Rules 2014, as revised from time to time, and procedures for bidding process to
ensure transparency and economically efficient outcome.
10.1.3 Advertise the project to initiate the procurement process and conduct evaluation of bids
(technical and financial) submitted against this tender document.
10.1.4 Select only one operator for operation of LMBS.
Page 11 of 82
3. In case deficient kilometers still remain after following the above procedure, the remaining
deficient kilometers will be paid according to the following formula:-
Rate / Km = (0.6485 0.6077 x Bid Value) + previous Cumulative rate adjustments up to
the bifurcated month as per Annex-C
if the bifurcated month falls under the extended period of the Contract the above formula
shall be modified as follows:-
Rate / Km = (0.2109 0.2055x Bid Value) + previous Cumulative rate adjustments up to the
bifurcated month as per Annex-C
The deficient kilometers paid shall be treated as plied Guaranteed Kilometers of the
bifurcated month for onward reconciliations.
10.1.15 Develop and notify detailed specifications of the Metrobuses. All Buses to be introduced under
this project would have to conform to these specifications. The detail of Urban Bus
Specifications is attached as (Annexure-D) with this document. The buses shall have system
brand name and brand color only.
10.1.16 Open an escrow account jointly operated by authorized representatives of the Client and the
Bus Operator.
10.1.17 The Client may consider allowing advertisements inside the bus, in which case it will define the
size, nature, etc of the advertisements. Revenue proceeds of such advertisements or any non-
fare activity , if allowed, will be credited to Metrobus Authority Fund Account.
10.1.18 Be responsible for the conduct and functioning of all staff employed in the PMA. The PMA
staff shall provide efficient services, polite and courteous behavior towards operator, and
passengers. The Client shall be liable for any misconduct or unreasonable offense of its
employees and shall take prompt and appropriate action.
10.1.19 Through AFC-BSS, provide the bus drivers the required training of the use of the Driver
Console.
10.1.20 Upon completion of the contract period, the Client shall re-advertise the RFP for procurement
of bus operator.
10.1.21 Provide and notify fare structure and business rules for Bus operation
10.1.22 Provide Bus operator the license to operate buses on the LMBS corridor and the right to use the
Depot so that Bus Operator can perform its obligations in a timely manner.
10.1.23 Before start of operations, in the eventuality that all 64 buses are fully ready to operate to be
legally plying on the corridor, but the corridor is not operational; during such period, the Client
will pay the Operator at the rate per kilometer for 191.78 km/bus/day, which shall be computed
as follows
Rate / Km = (0.5501 0.5010 x Bid Value) + previous Cumulative rate adjustments as per
Annex-C
The period of payment under this Clause shall commence fifty (50) days from the date of
application by the Operator for vehicle inspection as per following allowances for time to fulfill
all legal requirements:
Page 13 of 82
i. Two (2) days for vehicle inspection by the Transport Department and
ii. Three (3) days for registration by the Excise and Taxation Department
iii. 45 days to make the corridor operational
It is clarified that after the Operator has met all the aforementioned requirements then this payment shall be made upon invoicing and is not to be withheld on account of procedural or any other delays.
The kilometers paid shall be treated as plied Guaranteed Kilometers for particular period for
onward reconciliations as per Clause 10.1.14.
10.1.24 During the operations, in the eventuality that all 64 buses are fully ready to operate, but the
corridor is not operational for more than 30 consecutive days; during such period, the Client
will pay the Operator at the rate per kilometer for 191.78 km/bus/day, which shall be computed
as follows:-
1. All previous Excess kilometers shall be converted into Guaranteed Kilometers. The rate
applied shall be the difference of applicable monthly Guaranteed Rate and paid Excess
Rate of the month in the chronological order from which the Excess Kilometers are
borrowed. The conversion of kilometers will be carried forward for onward
reconciliations as per Clause 10.1.14.
2. After adjustment of excess kilometers, the new rate shall be computed as follows:-
Rate / Km = (0.5501 0.5010 x Bid Value) + previous Cumulative rate adjustments as
per Annex-C
If the period falls under extended period of the Contract the above formula shall be
modified as follows:-
Rate / Km = (0.1413 0.1314 x Bid Value) + previous Cumulative rate adjustments as
per Annex-C
The kilometers paid shall be treated as plied Guaranteed Kilometers for particular
period for onward reconciliations as per Clause 10.1.14.
10.1.25 Implement the Service Level Agreement and levy penalties in case of deficiencies in
performance. For purpose of this Sub-clause it is clarified that penalty shall be computed as
follows:
Penalty Amount (PKR) = R x ∑K
Where:
R = Adjusted Non Excess Km Rate (Refer to Annexure-C)
∑K = Total penalty kilometers in the invoiced month
10.1.26 If any of the tracker devices becomes irresponsive or non-functional due to any reason, keeping
in view the public convenience, the operation of buses shall not be terminated and bus will
complete its trips. In such an eventuality the Client will validate the manual log book entries of
the Operator / Service Provider to calculate the actual plied kilometers through manually
generated reports by the AFC-BSS after taking into account the system generated data of the
relevant period in the previous month, and such validation will be acceptable to the Operator /
Service Provider.
Page 14 of 82
10.2 The Operator shall:
10.2.1 Procure 64 Brand New, Air Conditioned (AC), 18m, Diesel operated buses as per prescribed
specification to be delivered to Lahore Metrobus Depot at Nishter, within 135 165 calendar
days from signing of the Contract henceforth called the dead line.
10.2.2 Ensure compatibility with the existing AFC-BSS. It is clarified that AFC-BSS equipment is
owned by PMA. The Contractor will be required to ensure compatibility of AFC-BSS
equipment in coordination with the bus manufacturer and the AFC-BSS Contractor
10.2.3 In addition to these buses, the operator may be directed within first year after commencement
of operations to add up to 25% more buses as per requirement of the client/passenger demand.
Beyond one year, such addition of buses will be mutual consent.
10.2.4 Must ensure to ply the buses and follow the specified schedules and instructions by the Client.
The specified schedule from the client will include at least daily assignment of Revenue Trips,
Payable Non Revenue Trips, Headways, Speed Limits, Dwell Time Limits, Number of buses to
park along with parking locations and parking timings. Failure to complete the assigned jobs
would result in deductions of unassigned kilometers and penalties as per Agreement.
10.2.5 Only one operator shall carryout LMBS operation on the Green-line.
10.2.6 Must employ adequate, well-trained staff including at least two Transport Engineers to perform
all duties and responsibilities stated in this RFP ; including all roles/duties to be performed on
the LMBS corridor, Depot, fueling operation, and general fleet management. Operator must
deploy at least one representative to be stationed at the LMBS Command and Control Center
during the operational hours. The representative will act as a liaison for coordination between
PMA and Contractor for effective monitoring and control of bus operations.
10.2.7 Obtain all necessary permits under all applicable Laws of Pakistan required to procure the
buses. Also obtain all necessary permits/licenses/certificates required to run the
operations of buses.
10.2.8 Obtain route license from The Client and vehicle fitness certificates as prescribed in the Punjab
Motor Vehicle Ordinance
10.2.9 Carry out all responsibilities laid out in this document.
10.2.10 Cooperate with all other LMBS service providers and to the extent possible facilitate their
operations in the LMBS system.
10.2.11 Engage and deploy suitably skilled personnel for procurement, operation and maintenance of
the Buses, and maintenance/replacement of all related equipment/components in buses in a
timely manner and at its own cost, and participate in all meetings, committees, etc, as directed
by the Client from time to time.
10.2.12 Be responsible for the conduct and functioning of all staff employed in the Operation. The bus
operator shall ensure efficient services, polite and courteous behavior towards passengers and
representatives of the Client and other related departments/entities of the GoPb. The bus
operator shall be liable for any misconduct or unreasonable offense of its employees and shall
take prompt and appropriate action.
Page 15 of 82
10.2.13 Prior to procuring, the bus operator shall submit detailed specifications, documentation, and
manuals of related buses being procured for operation and maintenance.
10.2.14 Adhere to timelines of the Operation implementation specified in this RFP.
10.2.15 Provide monthly reports on progress of the Operation implementation as per scope defined in
this RFP
10.2.16 Impart meaningful and timely training to all Driver/staff associated with the Operation.
Operator will train the drivers for all kind of operational requirements including but not limited
to Trip Efficiency, Punctuality, schedule adherence, precision docking, Headway Regularity,
Travel Time Regularity, Avoidance of Bus Bunching, Minor Repair Works, emergency
handling including breakdowns / accidents, customer dealing, safe and comfortable driving,
reading and understanding English instructions/tabs of On Board Units (OBU), cooperation
with PMA staff, Driver actions that can invoke penalties etc. Operator will ensure that these
trainings are conducted prior to implementation of operations as well as on time to time basis.
Operator will submit the training plans and records if desired by the client. The client may
proceed to check and evaluate the results of the training.
10.2.17 Operator will make sure that all hired drivers have valid PSV licenses. For this purpose the
Operator shall ensure at its own costs the validity of licenses before hiring any driver.
10.2.18 Guarantee smooth operations and functioning of all buses during the entire contract period
10.2.19 Provide maintenance plan of metro buses in consultation with the Client, and implement it. The
plan must cover procedures and parameters for preventive and break-down maintenance, as
well as maintenance review procedures. During running operations, the operator shall submit
monthly bus maintenance plan along with estimated associated costs in advance to the Client
for its approval.
10.2.20 Implement the maintenance plan of metro buses
10.2.21 Allow authorized Punjab Masstransit Authority staff (and other authorized Government
personnel) for inspection of buses at depot and corridor during operation
10.2.22 Take prompt and reasonable action for resolution of each complaint – including complaints
received from the Client related to the operation of buses.
10.2.23 Bear the cost of license/Route permit and that for the registration of the buses.
10.2.24 Comply with the provisions of the applicable Motor Vehicles Ordinance / Act, the regulations
and rules framed in the standards and all other applicable local, provincial, and federal laws.
The Inability of the bus Investor(s) / Operator(s) to comply with rules, regulations and
procedures will be penalized as per penalty mechanism.
10.2.25 Comply, complete, and follow all reasonable commands, directions, and requirements of the
Client in respect of the operation, including directions and requirements that ensure public
safety and security. The inability of the Operator to comply will be penalized as per penalty
mechanism.
10.2.26 It is expected that driver must possess preferably graduate degree and shall be tested and
declared capable of reading English instruction/tabs. The drivers hired before start of operations
Page 16 of 82
10.2.40 Establish workshop and spare parts inventory in the provided Depot. The availability of spare
parts should be sufficient enough to maintain the quality of operations.
10.2.41 Maintain and manage all available utility connections in Depot and at other locations such as
rotaries, terminals etc. for facilitation of Operator's staff. Arrange, maintain and manage new
connection where required.
10.2.42 Arrange, maintain and manage shelter facilities for its staff if required at any Station / route
terminals / rotaries etc.
10.2.43 Provide and install up to Twenty Five (25) stickers per bus as per instructions/format provided
by the Client. Service Provider shall also be responsible for their periodic maintenance.
10.2.44 Install surveillance cameras as specified in the bus specifications. Make necessary
arrangements for the extraction on daily basis, and storage of audio and video data for a period
no less than seven fifteen (15) days. The Digital Video Recorder (DVR) should be provisioned
and placed in such a way that it ensures its safety and keep it intact during accidents especially
including collision of buses. Provide data to the Client upon receiving his directions within the
specified time frame. In case Operator is unable to provide data, penalties will be invoked as
per Service Level Agreement (SLA).
10.2.45 Follow the instructions of the Client Regarding Night - Parking of Metrobuses. For purpose of
this Clause if and when such instructions are given, the security of the buses shall be the
responsibility of the Service Provider.
10.2.46 Perform the following activities in the bus at the end of each trip
1. Dry mobbing and litter picking.
2. Disinfection with self disinfectant system as specified in bus specifications. Arrange for the
supply of disinfectant liquid at terminals if required.
3. Spraying air freshener
4. Collection of any leftover passenger belonging and hand it over to Station Security
Manager
10.2.47 Provide Controller Area Network (CAN) module in buses capable of providing data including
acceleration, deceleration, breaking (All kinds of Break), gear shifting, fuel information, engine
RPM, bus speed, doors control (open/close) information, bus saloon temperature
data/information, engine temperature data/information, battery data/information. The CAN
module manual shall be in English with proper identification of wire and terminal
numbers/tagging as per actual installed in the bus. Provide detailed information on the protocol
used in CAN module and its compatibility factor. Arrange a translator with technical support if
required, in case of any understanding of the system required by the Client or its representative
10.2.48 Supply and hand over to the Client before commencement of operations, 65 infrared
thermometers of fixed standing hand free type with minimum 01 year warranty, non-contact
face recognition, minimum 8 inch display, HD camera, accurate measurement in degree Celsius
and Fahrenheit, high sensitivity, clear digital display and sound working for outdoor, industrial
durability, long service life, AC and rechargeable battery powered, audible alarm beep in
outdoor and temperature threshold settings,
10.2.49 Submit the following documents before commencement of operations
Page 18 of 82
1. The copies of Letters of Credits (LCs) for Import of Buses & Equipment
2. The Commercial Invoices for Purchase/Import of Buses.
3. The Bill of Ladings
4. Certificate of Origin.
5. The Goods Declaration notes (GDs) for Import filled with Pakistan Customs
For Operator's facilitation, all indicated information will be received from the Operator under a
Non-Disclosure Agreement (NDA). The information if shared with any other Government
organization shall be treated as strictly confidential.
11. Key Service-level Parameters The performance indicators for provision of service are attached as Annexure-B.
12. Revenue Collection and Payment
12.1 The Client will open a Masstransit Authority Fund Account (MAFA) in a suitable branch of the
Bank of the Punjab (BOP) in Lahore.
12.2 An escrow account shall be opened by the Client in the same branch of BOP. The escrow
account will be jointly operated by authorized representatives of the Client and the Bus
Operator.
12.3 The AFC-BSS contractor shall arrange printing of the cards/tokens, based on card/token design
specified by The Client
12.4 Sale of tickets (cards/tokens) shall be the responsibility of the AFC-BSS contractor.
12.5 For activation and subsequent recharging of cards (Smart cards) and tokens/throwaway media,
the AFC-BSS contractor shall arrange “Bulk Initialization Machines (BIM)”,and place BIMs at
premises specified by The Client.
12.6 BIMs, and/or top-up/Point of Sale (POS) machines will only initialize/top-up media if there is
sufficient balance available. AFC-BSS Contractor must first transfer sufficient balance amount
into the Government Escrow Account, and the BOP will subsequently generate an instruction to
the E-ticketing solution provider to issue equivalent credit for loading in the BIM/POS machine.
12.7 The revenue collected each month will be disbursed to the Operator, and any shortfall will be
arranged by the Client through MAFA.
12.8 Payments from the Escrow Account will be made to the Bus Operator based upon agreed
policies, formulas, and reconciliation reports from AFC-BSS as per terms and conditions of this
RFP
12.9 If there is surplus balance in the Escrow Account, the amount will be retained by the Client. If
there is deficit in the Escrow Account (that is, all service providers cannot be paid) then The
Client will arrange for the deficit amount through MAFA and make payments that are due.
12.10 Payment to the Bus Operator shall be made against actually plied Kilometers according to the
schedule on monthly basis subject to clause 3.24 to 3.32
12.11 Regular third-party audit (financial as well as technical) to be made an integral part of the
Operation. The Client will arrange and bear the costs of third-party audits.
Page 19 of 82
23. TERMINATION FOR INSOLVENCY
If the Operator, or any member in case of JV, becomes bankrupt or otherwise insolvent, the
Client may, at any time, without prejudice to any other right or action / remedy it may have, by
written notice served on the Operator, indicate the nature of the insolvency and terminate the
Contract, in whole or in part.
24. TERMINATION FOR CONVENIENCE
24.1. The Client may, at any time, by written notice of 30 days served on the Operator, terminate the
Contract, in whole or in part.
24.2. The Services which are complete, or are scheduled to be completed by the Operator, within thirty
working days after the receipt of such notice, shall be accepted by the Client. For the remaining
services, the Client may elect:
24.2.1 To have any portion thereof completed and delivered; and
24.2.2 To cancel the remainder and pay the Operator by:
1. Purchasing all buses, toe-away vehicles, repairing vehicles, and workshop
equipments like tools, equipments, spare parts, furniture, and construction of diesel
station provisioned till date by the Operator (taking into consideration depreciated
values). For the purposes of this clause the price of buses, vehicles and workshop
equipments will include taxes, custom duties, freight charges, registration charges
and the interests charged by the financing institutions.
2. Paying an allowance as compensation for overheads and anticipated profit to the
Operator, 5% 7.5% of value of rest of the contract value calculated at the rate of
70,000 km per year per bus.
24.3. For purposes of calculations of payments, the Client and the Operator shall appoint a reputed
firm of Chartered Accountants through mutual agreement who will follow the methodology of
calculation which is just, even and fair to both parties.
24.4. All of the accounts or remaining payables under this clause, on the part of either of the parties,
shall be paid / adjusted within thirty (30) days (or such longer period as the Client may allow in
writing) from the day on which notice of termination under clause 24.1 shall come into effect.
Page 38 of 82
receiving new bank guarantee shall return the previous bank guarantee in lieu of Performance Security to the Operator.
3 Signing of Contract The Client shall, after receipt of the Performance Security from the successful Bidder, send the Contract provided in the Tender Document, to the successful Bidder. Within ten working days of the receipt of such Contract, the Bidder shall sign and date the Contract and return it to the Client.
4 Start operation of buses
The induction of buses shall be as per following program;
64 Air Conditioned, 18 m , Brand New, Diesel Operated, Articulated buses to be delivered within 135 165calendar days from signing of the Contract to Lahore Metrobus Depot at Nishter, henceforth called the deadline
5 Liquidated damages for failure / configuration of Services by the Operator
If and when applicable, liquidated damages (LD) shall be levied as follows:
LD (PKR) per day in case of buses = (Factor F x 191.78 x Number of Buses x Bid Price) LD (PKR) per day in other cases = (Factor F x 100 x Bid Price) For 0 – 10 days Factor F = 0.25 For 11– 20 days Factor F = 0.50 For 21 – 30 days Factor F = 0.75 For 31 days and above, Factor F =1.00 However, the amount so deducted shall not exceed, in the aggregate, the value of the performance security. The Liquidated Damages are attributable to such part of the Services as cannot, in consequence of the failure / delay, be put to the intended use, for every day between the scheduled delivery date(s), with any extension of time thereof granted by the Client, and the actual delivery date(s) (This penalty will also be invoked on the failure on the part of the Operator to meet commitments given by him in the technical proposal and failure in compliance to the bus specifications). It is clarified that LDs stated in this clause may be levied until such time the Operator has failed/delayed the start of operation as per conditions described in this document. After the start of the operation any further service/performance related failures/delays shall be penalized as per Service Level Agreement (Annexure-B).
6 Legal Status to Work in Pakistan
The Bidder must be allowed and meet all conditions set forth by the GoP to work with all concerned parties of the private, public, and not for profit sectors.
7 Contract Duration The duration of this Contract will be 08 years starting from commencement of operations.
Page 42 of 82
ANNEXURE-A: TECHNICAL EVALUATION CRITERIA
It is mandatory to score minimum 70 marks and non-zero marks in criteria at Serial No 1,2,4,6,7&8 In case of JV, marks shall be evaluated jointly for all member unless stated otherwise.
Sr No.
Criteria
Max. Marks
Comment/Description Evidence Required
1
Number of implementations of successful Bus operations for a period of no less than 01year (Urban/Intercity Public routes)
15
Number of Routes Operated :- Less than 1 = 0 Points 1 to 2= 5 Points 3 to 5= 10 Points 6 or more =15 Points
Copy of Route Permits OR Contract Document OR Letter of Award OR Any other valid document for evidence
2
Maximum bus fleet maintained and operated currently
15
Less Than 10 = 0 Points 10 to 20= 4 Points 21 to 30= 8 Points 31 to 50 = 12 Points 51 or more =15 Points
Registration Certificates in case of Buses owned OR Lease Agreement (for a period of not less than one year of which at least three months have been completed as of the date of bid) in case of Buses on Lease OR Any other valid document for evidence
3 At least one year Operational Experience of Bus Rapid Transit
5 Yes = 5 Points No = 0 Points
Copy of Route / License Permits OR Contract Document OR Letter of Award OR Any other valid document for evidence
4
Total number of human resource managed by the company
10
Less than 30 = 0 Points 30 to 50 = 4 Points 51 to 100= 6 Points 101 to 300= 8 Points 301 or more =10 Points
List of Human Resources Employed stating Designation and numbers
5
Number of years of bus operations (Bus Operations including but not limited to Urban and Intercity)
10
Number of years:- Less than 5 = 0 Points 5 to 6 = 2 Points > 6 to 7= 4 Points > 7 to 8= 6 Points > 8 to 9= 8 Points > 9 to 10= 10 Points
Copy of Route Permits OR Contract Document OR Letter of Award OR Any other valid document for evidence (In case of JV, applies to any one single member with maximum years of experience)
6
Average Annual Turnover of Transport Business in last three years in PKR Millions
20
< 800 = 0 Points 800 to 1000 = 5 Points >1000 to 1250= 10 Points >1250 to 1500 = 15 Points >1500 = 20 Points
Form Tech-8 TECH 4 along with its attachments
7
Net Worth of Transport Business in Last Year in PKR Millions (Total Assets - Total Liabilities)
10
Less than 150 = 0 Points > 150 to 200 = 3 Points >200 to 300 = 6 Points >300 = 10 Points
Form Tech-8 TECH 4 along with its attachments
Page 44 of 82
8
CURRENT RATIO (Ratio of current assets of the firm to its current liabilities in the last Fiscal Year)
10
1 and More = 10 Points 0.9 to less than 1 = 8 Points 0.8 to less than 0.9= 6 Points 0.7 to less than 0.8 = 4 Point 0.6 to less than 0.7 = 2 Point Less than 0.6 = 0 Marks
Form Tech-8 TECH 4 along with its attachments
9
DEBT RATIO (ratio of total liabilities to total assets in the last Fiscal Year)
5
0.5 and Less = 5 Points More than 0.5 to 0.6 = 4 Points More than 0.6 to 0.7= 3 Points More than 0.7 to 0.8= 2 Points More than 0.8 = 0 Marks
Form Tech-8 along with its attachments
TOTAL 100 Minimum Passing Marks = 70
Page 45 of 82
ANNEXURE-B: SERVICE LEVEL AGREEMENT (SLA)
In case of breach of SLA parameters, penalties will apply supported by concrete evidence.
Scope:
• The SLA describes target performance levels which the bidder shall aim to deliver for the Services
outlined in this RFP. It also lists the procedures for managing unavailability of Services / negligence /
inefficiency on part of the Operator, and associated penalties which will be applied if bidder fails to
deliver any service performance targets in accordance with this Agreement.
• The Operator will be exempted from delays or slippages on SLA parameters arising out of delays in
execution or due to delay in approval or review from the Client's side. Any such delays will be notified
in writing.
• Penalties shall be levied as per the following formula:-
Penalty Amount (PKR) = R x ∑K
Where:
R = Adjusted Non Excess Km Rate of the invoiced month (Refer to Annex-C)
∑K = Total penalty kilometers in the invoiced month
• The total monthly penalty amount shall not exceed more than 10% of same monthly payment to the
Operator.
• Successful bidder / Operator must notify the vehicle defect to the Authority affecting daily operations ,
via email, fax, and/or telephone, as soon as it becomes aware of the fault, and must also keep the
monitoring cell informed of progress towards resolution in a timely manner.
• For measurement of Trip Punctuality described at Serial 2 of the table "Key Performance Indicators",
the minimum acceptable limits of the gap between actual and scheduled bus time will be as follows:-
o + 30% of the scheduled headway up to 3 minutes
o +54 seconds for scheduled headways beyond 3 minutes
• For measurement of Travel Time Reliability described at Serial 3 of the table "Key Performance
Indicators" minimum acceptable limit of the gap between actual and scheduled bus time will be taken
as + 60 seconds
• For measurement of Schedule Adherence / On Time Performance described at Serial 4 of the table
"Key Performance Indicators", the following criteria shall apply:-
o Minimum number of locations other than route terminals for measuring arrivals / departure times
is three
o Minimum acceptable limits of the gap between actual and scheduled bus time is +30% of the
schedule headway.
o The number, location and acceptable limit is subject to change as per requirement of the client
keeping in view the minimum criteria.
• For execution of KPI regarding Bus Bunching at serial 5 of table "Key Performance Indicators",
Bunching shall be established if headway between two successive buses dispatched in the same
direction reduces to 10% (or less) of the scheduled headway measured at any point along the route.
Page 46 of 82
Delaying operation without cause. 15
Stopping bus at station for a time lesser than specified in the schedule 50
Overtaking vehicles of the same service without the authorization of PMA /
Client
25
To run out of fuel during trip 50
Interrupting traffic light crossings due to congestion of the station. 25
Air Conditioning not as per the prescribed bus specifications 35
Response time to tow away the stalled vehicle more than specified by the
PMA / Client
100
Failure to deliver bus camera video to The Client (The penalty will be 500 Km if the video demanded is expected to reveal critical
incident such as accident or Operator is unwilling to share the video for his own
vested interest)
50
Tow away trucks deployed are not as per numbers and/or on locations
described in the plan provided by the PMA / Client. (Fine will be for each
tow away truck non-compliant to this criteria x No of days of non-
compliance)
200
Failure to follow or acknowledge instructions issued by the Control Center,
operations personnel OR Any act/instance which is non-conforming to
Authority's Rules/Regulations/Contract/Instructions , not covered in other
sections of SLA
30 x A
Where A = 1 to 100 depending
upon sensitivity of event and
decision from The Client
Failure to arrange repairs of the damages to PMA Property caused by the
Operator within the prescribed time frame.
25 x No of days delayed
Injury caused to the passenger due to negligence in operations including but
not limited to improper docking, improper dwell time, improper door
operations, improper vehicle acceleration and deceleration etc. In addition
to the penalty the case will be dealt as per RFP clause 10.2.37
1. Minor Injury
2. Major Injury / death
In case of major Injury / death, evidence will include medical report from
the hospital.
1. 50
2. 1000
Page 51 of 82
SANCTIONS AGAINST DRIVERS
CONDUCT DESCRIPTION FINE (NO. OF KMS)
Failure to carry personal and/or vehicle identification. 5
Using non-personal On Board Unit (OBU) Driver Card 50
Communicating with passengers without any purpose or authorization
during normal operations.
35
Refusal to provide information 10
Slight infringement with other buses 10
To cross a red light 50
To reverse in trunk routes, stations or portals without authorization 20
To carry weapons of any kind 10
Disobedience to authorities 20
Drunkenness on duty or smoking while driving 20
To cause an accident due to irresponsible behavior 20
Incorrect approach to platforms and/or alignment between bus and station
doors. Driver has to maintain minimum gap between bus and station doors
as specified by the PMA / Client
30
To drive above speed limits for sustained ten (10) seconds 50
Stopping bus ahead of the stop bar 10
To take Passengers illegally 5
Abandoning and/or alighting from vehicle without cause and/or
authorization from the PMA / Client
100
Verbal or physical ill-treatment of passenger (referring to driver) Termination of the Driver
To charge tariffs inside the vehicles of the trunk route system 10
To move the bus without fully closing the bus doors 500
FINES OF INSTITUTIONAL OR ADMINISTRATIVE NATURE
Description of the infraction Fine (No. of
KM’s)
Failure delivers information required by the PMA / Client, or delivers same
outside the terms which for this purpose the PMA / Client may establish.
25
Page 52 of 82
ANNEXURE-C: ADJUSTMENT OF THE RATE PER KM OF MBS ROUTE AND PAYMENTS
There are two categories of plied kilometers as follows:-
I. Non Excess Kilometers = Kn = Kilometers Plied up to 191.78 Kilometers Per Bus Per Day II. Excess Kilometers = Ke = Kilometers Plied exceeding 191.78 Km Per Bus Per Day
Similarly there are two categories of rates applicable to plied Kilometers as follows:-
I. Rate for Non Excess Kilometers = Rn = Bid Value (subject to adjustment if any) II. Rate for Excess Kilometers = Re = (Bid Value x 0.4258) (subject to adjustment if
any)
PAYMENTS Payment for Non Excess Kilometers = Pn = Rn x Kn Payments for Excess Kilometers = Pe = Re x Ke
Total Gross Monthly Payment(PKR) = PT = Pn + Pe Non Excess and Excess Rate Adjustment
• The relative weighting within the cost structure of the bid value is described in the table and shall
be used to calculate the variation of cost per Kilometer .
• Calculation of adjustments is subjected to variation in base values, which for various categories
shall be taken as follows:-
o For adjustments in Fuel, base price considered shall be of that which prevailed on the day
of bid submission advertisement date of Addendum No 1 to RFP i.e. 10.07.2020
o For adjustments in Lubricants, base value considered shall be of the month of bid
submission.
o For adjustments in Tires, Maintenance and Salaries, base values considered shall be of
the first complete calendar month after bid submission.
The adjustments in the rate per km will be subjected to subsequent variations in the base values
and procedures laid down in the coming sections.
Page 55 of 82
• The parameters established for calculating the cost basket are estimates and therefore, failure to
actually meet the same will not entitle any party to request adjustments in the calculation
procedure of tariffs nor in the economic compensation of any kind.
• The Adjusted Bid Rate Rn for monthly payment of Non Excess Kilometers shall govern
irrespective of whether it is higher or lower than the original Bid Rate.
Categories Factor Per Km
Fuel = F 14.54 17.4
Tyres = T 3.89 3.68
Lubricants = L 2.64 2.50
Maintenance = M 12.41 13.79
Salaries = S 8.62 8.37
Percent increase or decrease applicable to all categories = PI
Where,
PI = [(New Value – Previous Value) / Previous Value] x 100
∆CF ∆CF = (PI Fuel x F x Bid Value) / 10,000
Fuel increase / decrease as per notification of the GoP. The source for prices of High Speed Diesel (HSD) shall be of Pakistan State Oil (PSO)
∆CT The Tires cost will be adjusted every year on January 1; on the basis of Wholesale price index variation in Auto Tires mentioned in Price Statistics published by Pakistan Bureau of Statistics, Government of Pakistan
∆CT= (PI Tires x N x Bid Value) / 10,000
∆CL The cost increase in lubricants will be adjusted Monthly on the basis of Wholesale price index variation in Mobil Oil mentioned in Price Statistics published by Pakistan Bureau of Statistics, Government of Pakistan
∆CL= (PI Lubricants x L x Bid Value) / 10,000
Page 56 of 82
3.2 Ergonomics a Interior Free Standing Height (Front) 2.1 m - 2.4 m b Floor Height from road level Exactly 900 mm (High Floor - Level Boarding )
Section 4: Passenger Safety 4.1 Introduction
Passenger safety, speed and security of movement while boarding, accessing and leaving seated positions and alighting is paramount to the provision of a service that is attractive and timely to the public, and one in which they can have confidence.
4.2 Stanchions/handrails and Grab Handles
Stanchions/handrails and Grab handles should be high-visibility contrasting color from either floor to ceiling or seatback to ceiling, as locations indicates, should be fitted throughout the length of the bus and close to the aisle. The height of grab handles should facilitate passenger in having comfortable standing position.
4.3 Over hang hand rails should not be higher than 1900 mm.
4.4 Knurling is not encouraged for general cleanliness and hygiene reasons.
4.5
Safety and Emergency exit provisions should be fully compliant to acceptable international standards including but not limited to signs, safety instructions, emergency roof exits, fire extinguishers, emergency hammers, emergency bells, switching of pneumatic doors to manual operations, door cameras etc.
Section 5: Passenger comfort and Use 5.1 Seating a Passenger Area 0.202 m2 Area per passenger
b Seat design & material
Seats should be ergonomically designed, placed keeping in view the passenger comfort & durability to withstand daily wear & tear. Seats should be covered with water and dust proof fire retardant material.
c Provisions for specially challenged people
Provision for minimum one wheel chair with provision for seat belt, wheel chair anchorage etc. Minimum four Color coded seats near access doors for specially challenged passengers
5.2 Lighting Passenger Comfort Energy efficient lights which should provide light intensity of min 300 200 LUX in all internal areas up to the passenger seat level
Section 6: Design Features of Bus 6.2 Bus Drive Right Hand Driven bus (Steering on the right side)
6.3 Bus Design
The bus will be designed to carry daily commuters and shall be suitable for daily operation of 16 to 20 hours in an urban passenger transport system with peak load (Each passenger weighing 68 Kg average) of about 120% of bus capacity, average journey speed of about 18 km/h with frequent stops/starts. The maximum attainable speed would be in the range of 80 Km/hr with speed limiting device. Components used in the bus would be of heavy duty design
Page 60 of 82
in CAN module and its compatibility factor.
Section 12: Additional Features to safeguards against COVID-19 and associated strain of viruses:-
12.1 Air Flow System of the bus
The air-system of the bus shall be specially designed with option available to the driver with push button to collect all breath air from the roof and exhaust it without recycling during passenger trip. Meanwhile fresh dust free / filtered air of equal proportion is to be pumped in from the driver side of the bus for normal breathing of passengers
12.2 Self Disinfectant System
Each bus shall be equipped with a self disinfectant system with a liquid tank of sufficient capacity and pressure pump as option available to a driver with push button to spray the whole bus at the end of each trip. The system shall generate a mist of a suitable chlorox type non-flamable self evaporating disinfectant or any other liquid disinfectant in compliance with available international standards to fulfill the purpose in the entire bus prior to start of a trip. As a safeguard, the pump system shall remain disabled while the bus speed is non-zero i.e. in a moving bus. The mist shall be used to disinfect the bus in the direction from roof to floor and its discharge points shall be placed proportionally to cover the entire inside of a bus.