Project ManagementProject Management9. Performance Management9. Performance Management
![Page 2: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/2.jpg)
Week 9
![Page 3: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/3.jpg)
Performance management
![Page 4: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/4.jpg)
Once you have selected a project
![Page 5: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/5.jpg)
Once you have selected a project
And planned it
![Page 6: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/6.jpg)
Once you have selected a project
And planned it
And hired the team
![Page 7: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/7.jpg)
Once you have selected a project
And planned it
And hired the team
And started the work
![Page 8: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/8.jpg)
Once you have selected a project
And planned it
And hired the team
And started the work
How do you stay on track?
![Page 9: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/9.jpg)
How do you even know if you are progressing to plan?
![Page 10: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/10.jpg)
Gray & Larson, 2006, Ch 13.
![Page 11: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/11.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 12: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/12.jpg)
What is a Project Monitoring System?What is a Project Monitoring System?
![Page 13: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/13.jpg)
It involves determining what data to collect, how, when an who will collect the data; analysis of the data; and reporting progress
It involves determining what data to collect, how, when an who will collect the data; analysis of the data; and reporting progress
Monitoring SystemMonitoring System
GatherGather AnalyseAnalyse ReportReport
![Page 14: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/14.jpg)
You need to know what information is needed to satisfy you and your stakeholders.
![Page 15: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/15.jpg)
Think about the Information System Structure
![Page 16: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/16.jpg)
What data are collected?
![Page 17: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/17.jpg)
current status of project (schedule and cost)
current status of project (schedule and cost)
remaining cost to compete project
remaining cost to compete project
date that project will be complete
date that project will be complete
potential problems to be addressed now
potential problems to be addressed now
out-of-control activities requiring intervention
out-of-control activities requiring intervention
Cost and/or schedule overruns & their reasons
Cost and/or schedule overruns & their reasons
Forecasting overruns at time of completion
Forecasting overruns at time of completion
What data are collected?What data are collected?
![Page 18: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/18.jpg)
Collecting data and analysis
who will collect project data?
how will data be collected?
when will the data be collected?
who will compile and analyze the data?
who will receive the reports?
how will the reports be transmitted?
when will the reports be distributed?
Photo by germanium
![Page 19: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/19.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 20: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/20.jpg)
Progress Report FormatProgress since last report
Current status of project
ScheduleCostScope
Problems and issues since last report
Actions and resolution of earlier problems
New variances and problems identified
Corrective action planned
![Page 21: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/21.jpg)
How long should a project status report be?
![Page 22: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/22.jpg)
1 page
![Page 23: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/23.jpg)
<example>
![Page 24: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/24.jpg)
office.microsoft.com/en-us/templates/TC011417231033.aspx
http://saulcarliner.home.att.net/idbusiness/statusreport.htm
http://www.projectperfect.com.au/info_status_report.php
More info
www.ic.arizona.edu/~profcomm/writing/samples/stat_samp_s1.htm
www.projectconnections.com/knowhow/subsets/sample-templates/StatusReports.doc
![Page 25: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/25.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 26: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/26.jpg)
Project Control Process
![Page 27: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/27.jpg)
The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action
Pensiero
![Page 28: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/28.jpg)
Project Control Steps
Set and baseline a
plan
Measuring progress and performance
Comparing the plan to the facts
Taking Action
![Page 29: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/29.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 30: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/30.jpg)
Monitoring Time Performance
![Page 31: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/31.jpg)
Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:
![Page 32: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/32.jpg)
Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:
Tracking and baseline Gantt charts
show expected, actual, and trend data for event duration performance
![Page 33: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/33.jpg)
Figure 13.1 Baseline Gantt Chart(Gray & Larson, 2006, p414)
Time
A Gantt Chart
![Page 34: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/34.jpg)
Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:
Tracking and baseline Gantt charts
show expected, actual, and trend data for event duration performance
Control chartsplot the difference in
scheduled time on the critical path with the actual point on the critical path
![Page 35: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/35.jpg)
Figure 13.2 Project Schedule Control Chart(Gray & Larson, 2006, p415)
A Control Chart
![Page 36: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/36.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 39: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/39.jpg)
Corrects the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget
Picture by Pensiero
![Page 40: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/40.jpg)
Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule
Picture by Pensiero
![Page 41: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/41.jpg)
Earned Value Cost/Schedule System
An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs
Picture by airgap
![Page 42: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/42.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 43: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/43.jpg)
Earned Value ManagementEarned Value Management
![Page 44: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/44.jpg)
What is Earned Value Management (EVM)?
![Page 45: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/45.jpg)
What is Earned Value Management (EVM)?
A project performance measurement technique that integrates scope, time, and cost data.
![Page 46: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/46.jpg)
What is Earned Value Management (EVM)?
A project performance measurement technique that integrates scope, time, and cost data.
Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.
You must enter actual information periodically to use EVM.
![Page 47: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/47.jpg)
What is Earned Value Management (EVM)?
A project performance measurement technique that integrates scope, time, and cost data.
Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.
You must enter actual information periodically to use EVM.
![Page 48: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/48.jpg)
Terms to learn
PV
AC
EV
Planned Value
Actual Cost
Earned Value
CV Cost Variance
SVSchedule Variance
CPICost Performance Indicator
SPISchedule Performance Indicator
![Page 49: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/49.jpg)
(Also called the budget)
This is that portion of the approved total cost estimate planned to be spent on an activity during a given period
PV Planned Value
![Page 50: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/50.jpg)
The total of direct and indirect costs incurred in finishing work on an activity during a given period
AC Actual Cost
![Page 51: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/51.jpg)
An estimate of the value of the physical work actually completedEV Earned Value
![Page 52: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/52.jpg)
Earned value minus the actual cost. Shows the difference between the estimated cost of an activity and the actual cost of that activity
TABLE 13.1
CV Cost Variance
![Page 53: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/53.jpg)
Earned value minus the planned value. Shows the difference between the schedule completion of an activity and the actual completion of that activity
TABLE 13.1
SVSchedule Variance
![Page 54: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/54.jpg)
The ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project.
If the CPI is equal to 1 or 100% then the planned and actual costs are equal, or the costs are as budgeted.
If the CPI is less than 1 or less than 100%, the project is over budget.
If the CPI is greater than 1 or more than 100%, the project is under budget
CPICost Performance Indicator
![Page 55: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/55.jpg)
The ratio of earned value to planned value and can be used to estimate the projected time to complete the project.
Similar to the CPI, an SPI of 1 or 100% means the project is on schedule.
If the SPI is greater than 1 or 100% then the project is ahead of schedule.
If the SPI is less than 1 or 100%, the project is behind schedule
SPISchedule Performance Indicator
![Page 56: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/56.jpg)
TABLE 13.1
Quick EVM quiz
What can we say if CPI > 1
![Page 57: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/57.jpg)
Quick EVM quiz
What can we say if CPI > 1
If the CPI is greater than 1 or more than 100%,
the project is under budget
![Page 58: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/58.jpg)
Quick EVM quiz
What is EV minus AC?
![Page 59: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/59.jpg)
Quick EVM quiz
What is EV minus AC?
EV – AC = SVEarned Value (what was done)
MinusActual Cost (what has been
paid)=
Schedule Variance
![Page 60: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/60.jpg)
![Page 61: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/61.jpg)
Scenario Example
![Page 62: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/62.jpg)
“Purchasing & Installing Web Server”
Duration 1 week,
Budget $10,000.
Scenario Example
![Page 63: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/63.jpg)
“Purchasing & Installing Web Server” Duration 1 week, Budget $10,000.
PV – Planned Value – for that activity for that week = $10,000
AC – Actual Cost – suppose it actually took 2 weeks and cost $20,000. Assume $15,000 were incurred in week 1, and $5,000 in week 2. These costs are the actual costs for that activity each week
EV – Earned Value – earned value after one week is $7,500. (10,000 * 75%)
Example: CP829_Lecture_Week9_EarnedValue.xls
Scenario Example
![Page 64: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/64.jpg)
![Page 65: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/65.jpg)
![Page 66: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/66.jpg)
Earned Value Chart for Project after 5-MonthsEarned Value Chart for Project after 5-Months
![Page 67: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/67.jpg)
![Page 68: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/68.jpg)
Max WidemanMax Wideman
![Page 69: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/69.jpg)
Rules for Earned Value Numbers
Negative numbers for cost and schedule variance indicate problems in those areas
The project is costing more than planned or taking longer than planned
CPI and SPI less than 100% indicate problems
![Page 70: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/70.jpg)
Table 13.3 Interpretation of Indexes(Gray & Larson, 2006, p429)
![Page 71: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/71.jpg)
An alternative
Source: http://www.mountaingoatsoftware.com/release_burndown
![Page 72: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/72.jpg)
Week 2 lecture
Week 2 lecture
![Page 73: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/73.jpg)
So, what do you do when your plan changes?
![Page 74: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/74.jpg)
There are methods used to revise estimates of future project costs
EVM allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate
EVM uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable
![Page 75: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/75.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 76: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/76.jpg)
Developing an Integrated Cost/Schedule System
![Page 77: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/77.jpg)
Compute
Calculate
Collect
Schedule
Resource plan
WBS
Budget
Pla
nM
on
itor
![Page 78: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/78.jpg)
Define the work using a WBS
ScopeWork packagesDeliverablesOrganization unitsResourcesBudgets
Develop work and resource schedules
Schedule resource to activities
Time-phase work packages into a network
Photo by shimonkey
![Page 79: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/79.jpg)
Develop a time-phased budget using
work packages
included in an activity.
Accumulate budgets (PV)
At the work package level, collect the actual costs for the work performed (AC)
Multiply percent complete times original budget (EV)
Compute the schedule variance (EV-PV) and the cost variance (EV-AC)
![Page 80: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/80.jpg)
Figure 13.3 Figure 13.3 Project Management Information Systems OverviewProject Management Information Systems Overview(Gray & Larson, 2006, p419)(Gray & Larson, 2006, p419)
Integrated Cost/ Schedul
es
![Page 81: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/81.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 82: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/82.jpg)
Project Baselines
![Page 83: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/83.jpg)
Week 4 lecture
Week 4 lecture
![Page 84: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/84.jpg)
a Baseline is an anchor point for measuring performance
Photo by _Robert C_ @
flickr
![Page 85: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/85.jpg)
a planned cost and expected schedule against which actual cost
and schedule are measured
Gold by Куртис Перри
![Page 86: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/86.jpg)
a basis for cash flows and awarding progress payments
Photo by quaziefoto @ flickr
![Page 87: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/87.jpg)
a summation of time-phased budgets (cost accounts as summed work packages) along a project timeline
Picture by Network Osaka @ flickr
![Page 88: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/88.jpg)
![Page 89: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/89.jpg)
What Costs Are Included in Baselines?LaborEquipmentMaterialsProject direct overhead costs (DOC)
![Page 90: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/90.jpg)
Figure 13.14 Scope Changes to a Baseline(Gray & Larson, 2006, p436)
![Page 91: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/91.jpg)
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management – a silver bullet?
Integrated Cost/Schedule System
Project Baselines
![Page 92: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/92.jpg)
ReviewProject monitoring system include; data collection; analysis and reporting.Project control steps include; baseline plan, progress measurement, comparing actual against projected plan, and actions.Performance can be monitored using tools such as; tracking Gantts, control charts, baseline plans and earned value management.Earned value management (EVM) is a technique which incorporated scope, time and cost data to determine the health of the project.Integrated Cost/Schedule systems are developed creating; WBS, work/resource schedules, budget, and EVM.Project baselines are an anchor point for measuring performance.
![Page 93: The Project Management Process - Week 9 Performance Management](https://reader033.vdocuments.us/reader033/viewer/2022061105/54422450afaf9ff3098b457d/html5/thumbnails/93.jpg)
ReferencesHorodyski, K. (1995). Managing and developing teams. Footscray, Vic.: Open Training Services.Greenberg, J. & Baron, R. (1993). Behavior in organizations (4th ed.). Syd., NSW: Allyn and Bacon. Robbins, S., et al. (1998). Organisational behaviour (2nd ed.). Sydney: Prentice-Hall