the phase one i-710 freeway rehabilitation project

66
The Phase One I-710 Freeway Rehabilitation Project: Initial Design to Performance After Six Years of Traffic Meeting with AAPA Study Tour Group UCPRC, CA 8/10/2010 Richmond Field Station, UC Berkeley

Upload: others

Post on 04-Oct-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

The Phase One I-710 Freeway Rehabilitation Project: Initial

Design to Performance After Six Years of Traffic

Meeting with AAPA Study Tour GroupUCPRC, CA 8/10/2010

Richmond Field Station, UC Berkeley

Presenter
Presentation Notes
Authors

I-710 Project - Partnered Effort(most recent participants)

• Caltrans§ T. Bressette, W. Farnbach, C. Suszko

• Industry § J. St. Martin,

• University of California PRC§ C. Monismith

I-710 Project - Partnered Effort(some earlier participants)

• Caltrans§ K. Herritt, R. Doty, J. Dobrowolski, S. Shatnawi

• Industry § L. Nawrocki, J. Copley, R. Smith, D. Chapman

• University§ J. Harvey, F. Long

Presentation• Mix designs• Structural section designs§ full-depth AC§ overlay on cracked and seated PCC

• Aspects of construction• Some lessons learned• Phase II structures

I-710March 2003

Presenter
Presentation Notes
Existing pavement constructed in 1952 Maintenance – isolated patching, crack sealing & slab replacement

Rehabilitation ofInterstate - 710

• Full-Depth Asphalt Concrete§ replacement under overpasses

• Overlay of PCC (cracked-seated)

Design & AnalysisTrial cross

section

Performance TestsTrial mix design

Conditioning(Aging & Water)

Analysis Performance Prediction

Final mix design & structural section

UnacceptableAcceptable

Long-Life Asphalt Pavement

• QC/QA specifications • Polymer modified binders• Improved aggregate requirements

• Modified mix design method

Trial Mix Design

• San Gabriel aggregate• Binders§ Conventional: AR-8000§ Polymer modified: PBA-6a*

• Hveem Stabilometer-to establish range of binder contents

Trial Mix Design

• Range of binder contents§ 4.2 - 5.7% (by wt of aggregate)

• Conventional dense-graded mix, Caltrans specs.

• All crushed materials

Final Mix Design - Rutting

Nsupply = M x NdemandNo

Input

NdemandTraffic

NsupplyPerformance test

Yes

³³

Shear Test

Ndemand - (PBA-6A)• Design ESALs - first five years§30 x 106 ESALs

• Ndemand = 660,000M x Design ESALs x TCF x SF§M = 5§ TCF = 0.116§ SF = 0.04

Design Binder Content

1,000

10,000

100,000

1,000,000

10,000,000

3 3.5 4 4.5 5 5.5 6

Asphalt content (percent by weight of aggregate)

N @

g p=

5 %

PBA 6AAR 8000

Temperature = 50 C

660,000 repetitions146,000 repetitions

HVS Rutting Study

Rutting Study Layout25 m section

33 tonnes AC

Placed on jointed PCC3 m

4 m

150 mm

K-barrier on one side of

section

Mix Performance Evaluation

0

5

10

15

20

25

30

- 50,000 100,000 150,000 200,000HVS Load Applications

Rut

Dep

th, m

m

38-mm ARHM-GG

62-mm ARHM-GG

75-mm DGAC AR-4000

76-mm PBA-6A

½ inch rut depth

< 20,000 reps ~ 170,000 reps

Presenter
Presentation Notes
Data from earlier studies which illustrate that Hveem stability does not capture permanent deformation response of modified binders/mixes. AR4000 – Stability ~ 43 ARHM – Stability ~ 23 PBA-6A – Stability ~ 37 20,000 reps - ~ 20 million ESALs 160,000 reps - ~ 200 million ESALs Ensure no more than ½ inch rutting - ~ 660,000 reps in shear

Thickness Design - Fatigue Analysis

Nsupply M x NdemandNo

Input

NdemandTraffic

NsupplyPerformance test

Yes

³

Design Considerations

• Fatigue in asphalt concrete• Deformation in unbound layers• Subsequently, design checked by CalME

Design Considerations

Asphalt Concrete

Base

Subgrade

et

ev

Input

• Structural section (full-depth)• Traffic (200 million ESALs)• Environment (T = 20°C)• Trial mixes & pavement section

Input

• Reliability (M=5) • f(traffic estimate & testing variability)

• Performance criterion§wheel path cracking £ 10%

Trial Pavement Sections

AR-8000

PBA-6A*

AR-8000(rich bottom)

subgrade

Fatigue

Fatigue Test Results

1.E+03

1.E+04

1.E+05

1.E+06

1.E+07

1.E+08

1.00E-04 1.00E-03Mean Strain

Nf

AR-8000, 4.7% AC, 6% AVAR-8000, 5.2% AC, 3% AVPBA-6A, 4.7% AC, 6% AVPBA-6A, 5.2% AC, 3% AV

Nsupply ³ M ´ Ndemand?

Fatigue

Check vertical subgrade strain ! ! ! (controlled total thickness)

Final Design

AR-8000 (4.7%)PBA-6A (4.7%)

AR-8000 (5.2%)(rich bottom)

subgrade

AR-OGFC 25 mm75

150

75

6% air voids6%

3%

Overlays

Jointed PCC

Cement treated Base

Subgrade

Asphalt ConcreteFabric

Leveling Course

150 – 250 mm

200 mm

150 mm

30 mm

Calculated Configuration

Traffic loads applied staticallysymmetrical boundaries

p =725 kPa250 mm

Cracks @ 1 m

AC

Finite Element Mesh~ 12,000 elements, NIKE2D

Bending Strains in Mix just above Fabric

-120

-80

-40

0

40

80

120

160

-4 -2 0 2 4 6DISTANCE FROM CENTER (ft)

BEN

DIN

G S

TRA

IN (u

s)

5"@900, 4"@150 ksi3"@900, 5"@150 ksi3"@900, 3"@150 ksi

Composite OverlayFinal overlay thickness

25 mm OGFC

Fabric

225 mm75 mm PBA-6A

125 mm AR-8000

Broken and seated PCC

Full-Depth AC Comparisons

• The Asphalt Institute• United Kingdom• Australia• Asphalt Pavement Alliance-U.S.

Perpetual Pavement Design Concepts

Max Tensile Strain

Pavement Foundation

High ModulusRut Resistant Material4.5 - 6”

Flexible Fatigue ResistantMaterial 3 - 4”

1.5 - 3” SMA, OGFC or Superpave

}4”to6”

ZoneOf High

Compression

Construction Specifications• Performance requirements based on shear and fatigue testing

• More stringent compaction requirements

• Tack coat between layers§Asphalt cement (AR- 4000)

Construction• Six stages• Stages 1 and 2 preliminary to rehab. of trafficked sections

• Stages 3-6 - rehab. of trafficked sections in 8 - 55 hr. weekend closures (vs. 10 originally planned)

• Use of CA4PRS (construction management program)

Construction

• Stages 3 -6§Traffic closure§Crack, seat, and overlay (CSOL)§Full depth AC construction (FDAC)§Traffic opening

Contractor Staging Plan

Crack, Seat, and Overlay (CSOL) = 2.8 centerline - km Full - Depth AC Replacement (FDAC) = 1.6 centerline - km

Stage 4A (2 nd ) N N

Stage 3A (1 st ) Stage 4B and 4C (3 rd and 4 th )

Stage 6A (8 th ) Stage 5A and 5B (5 th and 6 th )

FDAC: 362m CSOL: 1,259m

FDAC: 406m CSOL: 1,035m FDAC: 840m

CSOL: 480m

FDAC: 342m CSOL: 760m FDAC: 321m

CSOL: 959m FDAC: 840m CSOL: 1,160m

Stage 5C (7 th )

Crack, Seat, and Overlay (CSOL) = 2.8 centerline - km Full - Depth AC Replacement (FDAC) = 1.6 centerline - km

Stage 4A (2 nd ) N N N

Stage 3A (1 st ) Stage 4B and 4C (3 rd and 4 th )

Stage 6A (8 th ) Stage 5A and 5B (5 th and 6 th )

FDAC: 362m CSOL: 1,259m

FDAC: 406m CSOL: 1,035m FDAC: 840m

CSOL: 480m

FDAC: 342m CSOL: 760m FDAC: 321m

CSOL: 959m FDAC: 840m CSOL: 1,160m

Stage 5C (7 th )

N

Placement of Leveling Course

Installation of Pavement Fabric

Placement of PBA-6A* Mix

Digout and Placement of Aggregate Base – Working Platform

Rich Bottom Layer Construction

Monday, March 30, 2003 05:00am

Some Lessons Learned

• Pre-bid conference mandatory for all potential bidders

• For projects of this importance a “partnering” meeting at the outset is mandatory§ Partnering on the technical

aspects extremely important!

Some Lessons Learned (cont.)

• For new test procedures included in Special Provisions insure that all involved groups perform tests and analyze resulting data the same way:§ equipment calibration essential§ preliminary testing of comparable

specimens

Some Lessons Learned (cont.)

• Improved specification requirements based on statistical considerations desirable

• For QC/QA activities adequate staffing imperative (large quantities of materials, up to 15,000 tonnes per weekend)

Some Lessons Learned (cont.)

• Timely QA results required• Human resources – 3 to 5 weekend closures in a row maximum; if more required, allow 1 to 2 weekend interval

Some Lessons Learned (cont.)

• In digout areas (FDAC) :§Exploratory testing imperative§Exact location of underground utilities

Some Lessons Learned (cont.)

• Contingency plan important§ Digout areas - working platform; materials easily accessible§ Standby HMA plant(s)

• Meteorologist for contractor(construction in digout areas)

Performance Evaluation• FWD Deflection testing (2003 through 2008)

• Back calculation of layer moduli and strains in HMA layers using MLEA

• Condition surveys• Longitudinal and transverse profile measurements

• Noise measurements• Laboratory testing of cores (RSST-CH)and slabs (Fatigue)

Performance Evaluation

• Non-destructive HWD tests§11/03, NB and SB§9/04, NB; 2/5, SB§12/05, NB; 2/06, SB

CENTER DEFLECTIONS LANE 3 I-710 SOUTHBOUND (ADJUSTED TO 19C)

0

100

200

300

400

500

600

700

800

0 50 100 150 200 250 300 350

LOCATION

DEF

LEC

TIO

N (M

ICR

ON

S)

2003

2004

2005

2008

Section 1(FD) Section 2(CSOL) Section 3(FD) Section 4(CSOL) Section 5(FD) PCH 405

Deflections – SB Lane 3

X

03030508

Presenter
Presentation Notes
Pacific Coast Hwy – no granular base 2008 deflections fairly consistent; lower in crack, seat & OL sections Construction began on SB lanes at Pacific Coast Hwy towards 405

CENTER DEFLECTIONS LANE 3 I-710 NORTHBOUND (ADJUSTED TO 19C)

0

100

200

300

400

500

600

700

800

900

1000

0 50 100 150 200 250

LOCATION

DE

FLE

CTI

ON

(MIC

RO

NS

)

2003

2004

2006

2008

Section 1(FD) Section 2(CSOL) Section 3(FD) Section 4(CSOL) Section 5(FD)

PCH 405

Deflections – NB Lane 3

X

03030508

Presenter
Presentation Notes
Pacific Coast Hwy – has granular base!

I-710 Northbound Lane 3 Full Depth Sections - Layer Moduli with Time

0

3,000

6,000

9,000

12,000

15,000

2002 2003 2004 2005 2006 2007 2008 2009

Year Tested

Modulus (MPa)

Section 1AC

Section 3AC

Section 5AC

Section 1Base

Section 3Base

Section 5Base

NB Lane 3 – Layer Moduli

Presenter
Presentation Notes
AC moduli fairly consistent Base moduli fairly high; recall that in the full-depth sections the base is crushed PCC, some cementation took place

Tensile Strain, Underside HMA Layer, in/in x 10-6

Section NB SB

1 18 49

3 17 18

5 16 8.5

Presenter
Presentation Notes
Calculated from back-calculated moduli Very small strains based on fatigue endurance limit (70 to 100 micro-strain) – IDOT Sam Carpenter Fatigue cracking should be minimal Also, the vertical compressive strains were low. AI criterion threshold is ~ 190 micro-strain. SectionMicro-strain 1151 3 82 5 73

Rut Depth MeasurementsSB Lane 3

0

3

6

9

12

15

0+00 5+00 10+00 15+00 20+00 25+00 30+00 35+00 40+00 45+00

Station (m)

Rutting (mm) Left WP Right WP

12.5 mm

Presenter
Presentation Notes
5-years of traffics, 30million ESAls, 12.5mm max

Rut Depth MeasurementsNB Lane 3

0

3

6

9

12

15

0+00 10+00 20+00 30+00 40+00

Station (m)

Rutting (mm) Left WP Right WP

12.5 mm

Presenter
Presentation Notes
5-years of traffics, 30million ESAls, 12.5mm max

I-710 Traffic

I-710 Traffic

I-710, Phase II

• Modifications§Design traffic: - 330x106 ESALs§Thickness of HMA base layer [PG 70-10 (AR-8000)] increased§Surface course: RAC-G instead of RAC-O

Concluding Thoughts• Implementation of New Technology for Mix &

Structural Design• Strict Attention To Pavement Construction• Constructability Considerations - Use of

CA4PRS• Successful partnering – agency, contractor and

academia.• Paving performing as expected.

Presenter
Presentation Notes
Phase I under review by Caltrans; likely available ??? Contact Carl. Opened to construction in June 2003. As of Dec 2008, maintenance costs were ~ $30k. Limited to two small areas of the open-graded mix – marginal construction.

Summary

• Implementation of SHRP developed technology

• Strict attention to pavement construction

• Constructability considerations; (CA4PRS)