the old and the new...the old and the new the story of an integrated chilled water plant kelley...

27
THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley Cramm, P.E. [email protected]

Upload: others

Post on 04-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

THE OLD AND THE NEW

The Story of an Integrated Chilled Water PlantKelley Cramm, P.E.Kelley Cramm, P.E.

[email protected]

Page 2: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

The IRS Processing Facility

• Old Post Office – Offices – 500,000 sq. ft.• New 70,000 sq. ft. warehouse• New processing facility – 600,000 sq. ft.• Approximately 1.2 million total square feet of space

Page 3: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 4: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 5: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 6: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

The TeamA Cast of Thousands

•General Services Administration

•The Developer (under contract with GSA)

•The Architect (a joint venture between 2 firms) – under contract with the developer

•The Construction Manager•The Construction Manager

•The Commissioning Agent

•The Test and Balance Contractor

•The Mechanical Design/Build Contractor –4 MEP consulting firms

•The Electrical Design/Build Contractor –Another MEP consulting firm

•Lots of additional consultants

Page 7: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

DP

VSCHILLER

CHILLERCOOLING COIL

DP

PRIMARY SECONDARY SYSTEM

DECOUPLER

Size decouple pipe for very low pressure drop(It does not need a check valve)

Page 8: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Controls for Primary/Secondary

• Primary pumps are constant speed – matched to chillers• Secondary pump speed controlled to maintain remote

delta P• Chillers controlled to maintain leaving water temperature• Chillers staged on/off to maintain LWT• Chillers staged on/off to maintain LWT• Excess chilled water will bypass using the decouple pipe• Low delta T can be a problem, resulting in more water

required than what the operating chillers can flow• Consider resetting remote delta P based on coil valve

position

Page 9: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

100%LOAD

100 FT.

75%LOAD67 FT.

50%LOAD42 FT.

25%LOAD26 FT.

SUPPLYRETURN

P: 20 FT.

DIFFERENTIAL PRESSURE TRANSMITTER MUST BE LOCATED AT FAR END OF SYSTEM

PRESSURE GRADIENTS

PRESSURE VARIATIONS IN A CHILLED OR HOT WATER SYSTEM

(COILS AND CONTROL VALVES NOT SHOWN)

Page 10: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

CHILLER

DP

VS

VS

DP

DP

COOLING COIL

CHILLER

DP

VARIABLE PRIMARY SYSTEM

BYPASS VALVE

Page 11: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Controls for Variable Primary

• Pump speed controlled to maintain remote delta P• Bypass valve controlled to insure minimum chiller

evaporator flow• Use evaporator delta T to determine chiller flow – works

better than a flow meterbetter than a flow meter• Chillers controlled to maintain leaving water temperature• Chillers staged on/off on load (flow + delta T)• Consider resetting remote delta P based on coil valve

position

Page 12: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Important Design Points

• Size of bypass line and valve– Must flow difference between min. load and min. chiller flow

• Valves– slow chiller isolation valves don’t cause upset– Bypass valve must be actuated open and closed– Bypass valve must be actuated open and closed

• Chiller selection – Select evaporator near peak flow and list the minimum in the equipment

schedule

• Hard wire remote delta P to same controller as pump VFD

• Need tight controls specification

Page 13: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Advantages/Disadvantages

• Lower first cost• Fewer pumps• Smaller footprint• Lower energy cost• Helps combat low Delta T syndrome

• Operator unfamiliarity

• Helps combat low Delta T syndrome

MUST HAVE GOOD CONTROLS AND SAVVY OPERATORS

Page 14: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Existing Plant in Old Post Office

• 2 water cooled centrifugal chillers – 500 tons each – converted to R134A• 17 years old when design started (2003)• Constant flow system with 3-way valves at air handlers

Page 15: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 16: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

• Needed a total of 2500 tons• Originally planned to replace old chillers• 3 new chillers – variable primary flow• Why replace machines with life remaining?• Can we vary the flow through the old chillers?

Page 17: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

• Flow on old chillers could be reduced to 30% of • Flow on old chillers could be reduced to 30% of original design flow

• Obtained evaporator pressure drop curves• Settled on a minimum of 40% of design flow• Limited rate of change of flow when an old

chiller was running

Page 18: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

• Installed 2 new 850 ton machines• Variable frequency drive on one of the new chillers• Flow could drop as low as 25% of max evaporator flow• Made selections near peak of evaporator flow capability

Page 19: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 20: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 21: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 22: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Lessons Learned

• Communicate Communicate Communicate

• Just because someone says they did it doesn’t mean it’s done. Double Check

Page 23: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Communication is a two way streetCommunication is a two way street

Page 24: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Communication

• A Woman: without her, man is nothing.

Page 25: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Communication Take 2

• A woman, without her man, is nothing.

Page 26: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 27: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

"I know that you believe you understand what you think I said, but I'm not sure you realize that what you heard is not what I meant."

Robert McCloskeyRobert McCloskey