MILESTONES 14 AUGUST 2018 Collapse of the Morandi bridge 28 JUNE 2019 Explosion of the Morandi remains CONSULTING ENGINEERING 220,000 hours of engineering work 80 people dedicated to supervising the project 3,200 technical documents 2,000 inspections DECEMBER 2018 beginning AUGUST 2020 ending THE NEW BRIDGE FOR GENOA RINA was the Project Management Consultant for the Commissioner’s team and in charge of the Works Supervision, Quality Assurance and Health and Safety during both phases of demolition and construction of the viaduct THE BRIDGE IN NUMBERS 1,000 workers employed 24,000 tonnes of steel and metalwork 20 construction sites simultaneously 18 piles ~ 1,500 meters total height (over and below ground) 67,000 cubic metres of concrete 95% of the energy consumption covered by renewable sources 100% excavation material recycled 15 APRIL 2019 Construction officially begins 3 AUGUST 2020 Opening of the new Genoa bridge 350 companies involved 60,000 vehicles each day 1,067 meters bridge length Viewing and reviewing 10,500 project documents

Upload: others

Post on 08-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE NEW BRIDGE FOR GENOA · 2020. 7. 31. · Morandi bridge 28 JUNE 2019 Explosion of the Morandi remains CONSULTING ENGINEERING 220,000 hours of engineering work 80 people dedicated

MILESTONES

14 AUGUST 2018

Collapse of the Morandi bridge

28 JUNE 2019

Explosion of theMorandi remains

CONSULTING ENGINEERING

220,000hours of engineering work

80 people

dedicated to supervising the project

3,200 technical documents

2,000 inspections

DECEMBER 2018 beginning

AUGUST 2020 ending

THE NEWBRIDGE FOR

GENOARINA was the Project Management Consultant for

the Commissioner’s team and in charge of the Works Supervision, Quality Assurance and

Health and Safety during both phases of demolition and

construction of the viaduct

THE BRIDGE IN NUMBERS

1,000 workers employed

24,000 tonnes of steel and metalwork

20 construction sites simultaneously

18 piles ~ 1,500 meters total height(over and below ground)

67,000 cubic metresof concrete

95% of the energyconsumption covered by renewable sources

100% excavationmaterial recycled

15 APRIL 2019

Construction officially begins

3 AUGUST 2020

Opening of the new Genoa bridge

350 companiesinvolved60,000 vehicles

each day

1,067 meters bridge length

Viewing and reviewing

10,500 project documents