the need for contracts management in reducing the risk of...
TRANSCRIPT
The Need for Contracts Management in Reducing the
Risk of Fraud in Public Expenditures
Dave Banarsee, CAMS-FCI
2019
1
Table of Contents
1. Executive Summary............................................................................................ 2
2. Background ........................................................................................................ 3
3. Public Sector Contract Formation Types ............................................................ 4
4. Public Sector Contract Management Maturity ................................................... 5
5. Public Sector Contract Management Deficiency and the Risk of Fraud ............. 9
6. Effective Public Sector Contract Management ................................................. 10
7. Conclusion ....................................................................................................... 12
References ....................................................................................................... 14
2
1. Executive Summary Post contract award, governments have fallen short in managing contracts to ensure timely
delivery, as per contractual specifications, quality and, within the agreed price. Contract
Management Practice Guidance, a document (2018) issued by the World Bank, stated that
“contract management also involves a level of flexibility by both parties and a willingness to adapt
the contract terms to reflect changing circumstances, as appropriate.” However, this flexibility
requires an approach that is more advanced than routine contract administration, and
governments may not necessarily emphasize, nor have the requisite governance structure to
achieve this. Therefore, without the capability to effectively and efficiently manage performance,
delivery, and payment, the risk of fraud and corrupt practices increases.
To minimize this risk, red flags are used to identify corrupt practices in public procurement, but,
where systemic corruption prevails, the task of anticorruption enforcement becomes difficult
because “many parts of the government that are supposed to prevent corruption have
themselves become corrupted—budgeting, auditing, inspection, monitoring, evaluation, and
enforcement” (Klitgaard, 2004). A research report (2014) issued by GIABA,1 an FSRB,2 presented
an analysis of how this crime feeds into money laundering, in a case study of Nigeria. The report
identified that insufficient and poorly implemented institutional safeguards and a lack of
transparency in the procurement process have allowed politicians and public officeholders to
award contracts and influence the process by relying on illicit acts that masquerade as legitimate
procedure. As a result, corrupt officeholders, particularly politically exposed persons (PEPs) in
conjunction with professional consultants and contractors with connections to the officialdom,
exploit both local and transnational financial networks and systems to manipulate the regulations
designed to prevent money laundering. However, the biggest contributory factor to the incidence
of fraud is the lack of internal controls or, where these controls exist, their deliberate flouting.
Notwithstanding this, contractors are essential to all governments from the perspective of the
economic ecosystem. They provide the resourcing necessary to complete mammoth
infrastructure projects, targeting the socio-economic goals of a nation while allowing
governments the opportunity to identify cost structure, realign competencies, reassess risk
exposure, and identify operational goals. However, with very little information available in the
public domain that speaks to typologies when combating procurement fraud, public officials may
grapple with the ability to understand and mitigate perceived risks. With the aid of targeted
actual situations, this paper is intended to discuss, with recommendations, the need for
governments to develop an adequate framework that complements proper contract
management practices as means to reducing the risk of fraud and mismanagement of funds in
the public sector.
1 Inter-Governmental Action Group against Money Laundering in West Africa, Money laundering related to fraud in public procurement in West
Africa: A case study of Nigeria. 2 Financial Action Task Force (FATF) Style Regional Body (FSRB)
3
2. Background A key finding from the government and public sector extract from PwC’s “Global Economic
Survey” reported that government and state-owned enterprises on average experienced a higher
incidence of fraud than did listed private entities. A case study of the Australian government and
state-owned enterprises taken from this survey, together with an ANAO3 report, indicated that
procurement and contract management fraud is one of the top fraud risks, and is more prevalent
when “power is centralized unduly: for example, when a single individual has the power to make
decisions on procurement, contracting, and approval.” As a consequence, standard contracting
procedures, together with policies and rules to minimize fraud and corruption, are bypassed. This
survey also reported that senior staff are more likely to commit fraud in government and state-
owned enterprises than in any other industry. However, without a governance structure that
reinforces management’s messages of honesty and integrity, together with inadequate
contracting management practices and flawed processes, there will be incomplete associated
records and insufficient evidence that can result in an unsuccessful investigation or prosecution.
Therefore, to combat a proliferation of fraud and corruption, and successfully prosecute such
individuals with fiduciary responsibilities that commit those acts, countries around the world are
increasing and tightening regulation and legislation. Without a global change in attitudes toward
this offense, it becomes impossible to instigate any civil recovery action, and damage inflicted
can be more than just economic cost, but there will be collateral damage as well. This damage
can be defined as careers being ruined and negative media coverage that can deter suppliers and
customers, and affect global standing on the world stage.
In a CIPS November 2018 article,4 “a lack of contractor control has been blamed in an auditor’s
report for California’s bullet train project seeing billions of dollars of cost overruns and significant
delays.” It was stated that in an effort to beat deadlines for spending federal grant funds, the
California High-Speed Rail Authority began awarding contracts long before it had finished
planning or assessing potential risks to cost and schedule. In addition, lack of oversight of
contractors was “firmly blamed” for pushing the cost upward by $49 billion over and above
secured funding of $28 billion. This can be viewed as a classic example that reinforces the impact
that contract management has in deriving value for money in the public sector in pursuit of a
socio-economic goal. That is, the train was debated as an alternative to expanding airports and
building new freeways to meet growing demand; however, the auditor’s report identified that
the authority needs to improve its contract management to control soaring costs, and without a
schedule to monitor contract managers’ compliance, it becomes difficult to hold contract
managers accountable for performing the duties assigned by the authority.
Specific areas of concerns identified in managing contracts within the public sector include:
Contract managers assigned to projects do not serve in contract management roles full time.
3 Australian National Audit Office Annual Reports 4 Chartered Institute of Procurement and Supply (CIPS); see article at https://www.cips.org/en/supply-
management/news/2018/november/contract-management-must-improve-on-bullet-train-to-nowhere
4
External consultants provided much of the oversight for large contracts.
There is limited evidence for reviewing the accuracy of monthly invoicing.
Contract managers do not maintain tracking logs of deliverables and could not demonstrate
quantity and quality of the contracted work.
Contract Management Support Unit(s) established to oversee contracting “performs only
weak and inconsistent oversight.”
Amendments to contracts for additional time and funding are usually based on contractors’
own estimates and projections of associated costs and delays.
It is important to recognize that these areas of concern can also be used as indicators when
identifying, assessing, and understanding the risks to which contract management exposed. As
stated by ACAMS,5 “although there is no exhaustive list of tried-and-true suspicious activity
indicators for business, there are many common indicators of financial crime, money laundering,
and terrorist financing” that an entity can be ready for.
3. Public Sector Contract Formation Types Understanding the risks begins with identifying and assessing mitigating strategies from the start
of procurement planning to formation of contract types to close out. A wide range of contract
types within the public sector, regardless of the terminology in any specific country and within
the confines of policy and law, are usually categorized under the umbrella known as Public-
Private Partnership (PPP). For example, in the United Kingdom, government pays PPPs for new
assets known as private finance initiative (PFI), while existing assets (hospitals, railways) are
franchises. In Brazil, Chile, and France, the term concession6 is used. Also, CIPS has recommended
as best practice to consider the use of cooperative procurement contracts, on a case-by-case
basis and only after proper due diligence has been performed. These contract types combine the
requirements of two or more public procurement entities as a means to leverage supply chain
advantages, reduce expenses, and allow other government entities to piggyback on the same
pricing and terms of the originating contract. This practice achieves economies of scale that
would not otherwise be possible, if each entity competed on its own, and allows for increased
due diligence in monitoring potential instances of fraud.
Not all government entities would necessarily identify or agree on the most suitable approach
when entering into contracts for the delivery of public services. For both PPPs and cooperative
contracts, policy makers must identify that the demand for the services delivered by the project
will be sustained over the life of the contract; the private party should be able to accept
responsibility for service delivery over its term; and the availability of conditional financing should
influence contractual arrangements. However, poor or unlawful procurement practice from the
onset can eventually be compounded with poor contract management and result in fraud. For
example, a September 2017 article7 published by CIPS reported that the Wales Audit Office found
5 Association of Certified Anti-Money Laundering Specialists, Study Guide, sixth edition. 6 PPP Knowledge Lab; see https://pppknowledgelab.org/guide/sections/6-ppp-contract-types-and-terminology 7 CIPS’s Supply Management; see https://www.cips.org/en/supply-management/news/2017/september/welsh-health-board-refers-contracts-
to-corruption-watchdog/
5
that Cardiff and Vale University Health Board (UHB) failed to comply with its own procurement
procedures when awarding contracts to a consulting firm, making both the contract and
subsequent payments potentially unlawful, and leaving UHB open to unnecessary financial and
reputational risk.
Some of the red flags that procurement specialists may consider as indicators to mitigate risks at
the pre–contract formation stage may include:
Procedure was not followed, e.g., procurement code of conduct, when dealing with a
shortened time span or accelerated tender process.
There may be connections between bidders so as to influence winning bid and thwart
competition.
Bids were still accepted, even after admission deadline.
Due diligence was bypassed when determining the existence of (artificial) bids from
companies that do not exist.
There were complaints (formal and informal) from nonwinning bidders.
Effectively managing this process when applying the basic tenet of agency theory to contract
management in the public sector, whereby the government (principal) contracts with the agent
(contractor) to perform a specified task, mixed with differing and conflicting objectives, various
levels of motivation and incentivization (or lack of), can give rise to a complex and
insurmountable situation. For example, a conference paper8 issued by the Project Management
Institute (July 2014) found that the U.S. Department of Defense (DoD) manages millions of
contract actions annually (obligated approximately $258 billion in contracts in 2013). However,
both the DoD Inspector General and the Government Accountability Office have issued multiple
reports on deficiencies in the DoD contract management processes, identifying poor contract
planning, contract administration, and contractor oversight as some of the critically deficient
areas in DoD contract management. Hence, to fully assess the underlying issues and develop a
road map for process improvement initiatives, regardless of project size or contract value, it is
necessary to explore and benchmark contract management maturity in the public sector.
4. Public Sector Contract Management Maturity It is important to recognize that the decision to contract and the contract monitoring and
implementation stages tend to receive less attention, although they are prone to corruption as
well (Kenny and Musatova, 2011). Therefore, the extent to which the level of maturity of contract
management achieved within the public sector can be assessed and its impact on the governance
framework is reliant on three critical factors.
The first is the process capability of government to achieve planned results. The second hinges
on the characteristics of the types of contracts executed by public bodies. These two factors are
interrelated when focused on effective contract management. Contract process maturity is
neither dependent on the tenure of service of staff nor the passage of time, but on the
8 Project Management Institute; see https://www.pmi.org/learning/library/
6
progression toward continuous improvement in process capability. As a government(s)
implements measures to gradually improve its process capability, organizational competence
increases, and organizational processes become more mature (Ahern, et al., 2001). Maturity can
be defined as “a measure of effectiveness in any specific process” (Dinsmore, 1999).
Similarly, competence is defined as the underlying characteristics of the contracts that will
eventually determine effective and measurable performance. The characteristics can be
categorized under two main contract types used by public entities. Neoclassical contracts
(Domberger, 1998) are short in duration (3–7 years), detailed, legally binding, limited in flexibility,
and specify performance provisions. Relational contracts are longer in duration (10–15 years),
have defined general purpose, omitted penalties, agreed control through cooperation,
encouraged sharing of benefits, and flexibility achieved by sharing information.
The third factor is not given sufficient attention by public entities and pertains to the level of
contract management maturity of contractors when delivering projects. Without a foundation
on which improvements can be built upon—and a framework for assessing the capability of the
contractor in delivering contractual objectives as specified by the other two critical factors—the
risk of fraud and mismanagement of public expenditures increases. A good reference point to
where it can all go wrong was encapsulated in the (previously mentioned) U.S. DoD conference
paper, whereby “the combination of the increasing defense contracting workload and the
decreasing size of the defense procurement workforce, along with the complexities of an arcane
and convoluted government contracting process and deficient contractor oversight, have created
the perfect storm—an environment in which complying with government contracting policies
and adopting contract management best practices has not always been feasible”. In December
2018, the Office of the U.S. Under Secretary of Defense for Acquisition and Sustainment issued a
report on defense and contracting fraud that encompassed 1,059 cases and resulted in criminal
convictions of 1,087 defendants. The Deputy Director for Public Sector Fraud of the U.K.
Government estimated that £31 billion to £49 billion of public sector money is lost to fraud each
year.
Following on from the example above, some of the red flags that procurement specialists may
consider as indicators to mitigate risks at the contract implementation and monitoring stage may
include:
Items not included in bid specifications are included in awarded contracts.
There are substantial changes to project costs and project scope after contract is awarded.
Audit certificates may be issued by unknown auditors with no professionally recognized
credentials.
The National Audit Office of the United Kingdom (NAO) indicated that better contract
management could derive savings and value for money; however, a lack of resources to manage
contracts and a shortage of qualified skilled personnel have been major contributing factors. CIPS
refers to an NAO study which found the central government spent an estimated £240 million in
2007–2008 managing service contracts. In its simplest form, the U.S. DoD conference paper
7
identified the main areas along the contract management process areas where problems can be
identified and which, in conjunction with the use of a maturity model, can be used to “assess
organizational contract management process and provide a road map for implementing process
improvement initiatives” (Table 1). In this scenario, the contract management maturity model
(CMMM) assessment tool used was a web-based survey, and the problem areas were contract
administration and contract closeout process areas, procurement process integration issues, and
contract management training and knowledge sharing.
Table 1
Contract Management Processes
Source: (Rendon, R.G. 2014, U.S. Army)
Procurement Planning The process of identifying which organizational needs can be best met by procuring products or services outside the organization. This process involves determining whether to procure, how to procure, what to procure, how much to procure, and when to procure.
Solicitation Planning The process of preparing the documents needed to support the solicitation. This process involves documenting program requirements and identifying potential sources.
Solicitation The process of obtaining bids or proposals from prospective sellers on how organizational needs can be met.
Source Selection The process of receiving bids or proposals and applying evaluation criteria to select a contractor.
Contract Administration (problem area)
The process of ensuring that each contract party’s performance meets contractual requirements.
Contract Closeout (problem area)
The process of verifying that all administrative matters are concluded on a contract that is otherwise physically complete. This involves completing and settling the contract, including resolving any open items. Contract closeout also includes contract termination.
Ideally, public entities should strive to achieve a contract management maturity level that
enables continuous management process improvements with the use of performance indicators
that evaluate the quality, efficiency, and effectiveness of existing processes. Similar to project
management, programs should be established to capture lessons learned and benchmark against
best practices and quality standards. However, if government entities are able to achieve this
optimal state, there would still be an issue of managing differing or conflicting objectives with a
potential contractor of a different level of maturity. For example, a white paper on ”Contractor
Management Strategy” was issued by ISN Analytics and a five-stage contractor management
process maturity framework, together with the attributes of leading contractor organizations, as
per Figure 1, demonstrates that attributes which characterize leading contractor organizations
are, for the most part, very similar to those of an optimal state achieved in public entities.
8
Figure 1
Five-Stage Contractor Management Process Maturity Framework
Source: (ISN Analytics, 2017)
5. Leading
3. Managing
2. Reactive
1. Start of Journey
4. Proactive
Attributes of Leading Contractor Organizations
1. Documented strategic plan.
2. Risks are well understood.
3. Risks of using third-party contractors are
well managed.
4. Leading metrics of performance are reported
to corporate level executives.
5. Communication regarding setting clear
expectations with contractors is the top area
for driving continual improvement in the
contractor management process.
6. Drive a safety-first culture.
7. They do not have a significant number of
disconnected internal business processes.
They integrate HSE, procurement, security,
and other internal processes for end-to-end
risk management practices.
8. Improvement of business continuity and
operational excellence is a key priority over
the next 12–18 months.
9. Regulatory requirements are the minimum
requirements to be satisfied.
10. Shortage of qualified contractor companies
and shortage of a skilled and competent
workforce are key challenges.
11. They do not see a lack of management
support and commitment as a key challenge.
12. They identify economic, political, and
regulatory uncertainties as challenges.
9
5. Public Sector Contract Management Deficiency and the Risk of
Fraud Armed with the knowledge that poor contract management practices can lead to an array of legal
challenges, fraud, and loss of public trust, there still seems to be a great deal of confusion and
inertia by governments to effect change. Thus far, this white paper has provided numerous
situations that identified poor contract management practices that led to fraud and corruption;
however, many governments still do not prioritize this area of deficiency as a source of major
concern.
In the public sector, the risks of corruption are threefold at the contract implementation stage
(Ferwerda, Deleanu, Unger, 2016).9 First, changes to an awarded contract may be made and go
unnoticed because of failure by the procurement section to track records of its procurement
process. This allows public officials to request additional services over and above tender requests,
but this can also allow the chosen bidder to reduce the project scope. At this point, it is imperative
to investigate any changes in project scope compared to original design and any changes in
quoted prices to original quotations. Della Porta and Vannucci (2002) explained that
modifications of contracts and price alterations post-contract allocation are indicators of
corruption.10 Second, it is important to scrutinize audit assessments and compare these to
relevant media coverage. This is important as the monitoring entity can be corrupt or negligent
such that poor contractor performance is not recorded. Third, audit irregularities due to
suppliers’ poor performance should be classified as high risk. At this point, the supplier is assigned
the risk of corruption, as costs may be faked11 to recoup a bribe.
There is no way to measure the tangible benefits of good contract management, and this is
mainly because contract management is not well understood. It is still misconstrued that contract
management focuses on the terms and conditions of contracts and agreements. However,
contract management focuses on both value and risk arising from contracts. This is where
governments should become more adept at distinguishing, for example, the need for relational
versus neoclassical contract types, but this introduces the need for a complex skill set. There is a
lack of adequate planning at the pre-procurement stage which leads to chaotic decision-making
during the post-contract award phase. The NAO stated that contract management needs to be
improved, and there is a lack of skilled contract managers in the public sector, whereby, 64
percent of government agencies did not have a contracts management department; 45 percent
did not have the job title consisting of contracts management; and 65 percent were not
professionally qualified and trained in contracts management. In most governments, this skill set
is usually dispersed throughout various departments, and challenges arise with this disperse d
and diverse function that may not communicate and project-manage effectively. Therefore,
appropriating public monies toward a dedicated contract management function within
9 Jose Ferwerda, Ioana Deleanu, & Brigitte Unger, “Corruption in Public Procurement: Finding the Right Indicators,” 2016. 10 Laffont and Tirole (1990) argue that while renegotiation of contracts can be socially beneficial, malevolent public officials and companies can
abuse this provision for the purpose of rent collection (refer Note 9 above). 11 Phantom companies can provide best coverage for fake invoices, and, therefore, the real existence of the subcontracting firms and the other
team members, and their persistence in the market, is important (refer Note 9 above).
10
government is not prioritized; there is general lack of compliance and due diligence; lack or
nonexistent policies and procedures; and opportunities for fraud begin to manifest among
corrupt officials.
6. Effective Public Sector Contract Management This paper has discussed that fraud and corruption can occur at every process and at any stage
of the procure-to-pay process. Hence, managing the risk of fraud should not be viewed as
ancillary to developing a robust framework that includes managing performance, delivery, and
payment, and addressing the capability and competency of a contract management team. This is
a major failure by most public entities and also, to a certain degree, in the private sector. Many
public authorities become restrictive in managing contracts and contractors during the contract
term if a sound foundation of systematic and effective planning is not performed during the
procurement process.
It is important that after the drafting of project specifications, but during the tender
documentation and before determining appropriate award criteria, a robust performance
management plan is established. This performance management plan can then be included in
the contract and will be used for measuring and monitoring performance, so as to identify any
defaults to contractual obligations. Performance measurement in the form of indicators and
targets is now an integral part of government’s machinery when allocating funds and
demonstrating commitment to mandate to the public. An important point of note is that formal
introduction of performance targets was introduced by the New Public Management movement
in the 1980s, and, by 1999, the NAO concluded that performance targets of government agencies
were too outcome focused on impact to society, satisfying all different stakeholders and various
interest groups. This resulted in a large volume of targets being created, and resulted in
difficulties when executing and managing contracts. Also, additional targets had to be built into
contract clauses, with hidden costs that could be viewed as mismanagement of funds or could
lead to potential fraud. An oversight that many public entities experience is not considering any
potential amendments to a future contract at the point of pre-procurement.
Because this was not considered at an early stage of the process, there is usually an omission of
any inclusion of an express provision within the contract to address possible modifications. As a
result, situations like this can give rise to possible probity issues on public officers with fiduciary
responsibilities, approval authority, and vulnerability to fraud and/or corruption (Contract
Management Practice, World Bank, 2018). Probity involves more than just avoiding corrupt or
dishonest conduct, it involves ensuring that often complex public sector processes—such as
procurement—are conducted in a manner that is fair, impartial, accountable, and transparent,
and always in the public interest. Probity plans should factor a greater prominence in the
planning process.
Government agencies should conduct an internal analysis of the contracts management function
to determine its contracts management capacity. This capacity consists of the influence and
resources of managers to influence contract management issues, together with management
imperatives to develop and manage contracts successfully, when delivering public service (Brown
11
and Potoski, 2003). Emphasis should be placed on recruiting experienced contract management
individuals and should be outsourced if not available within the public sector. These individuals
should be able to negotiate contracts, monitor and evaluate contractors’ performance, manage
budgets, and clarify performance targets (Figure 2). Requisite training should be conducted in
developing contract management individuals and pursue professional designations. A lack of
contract management competency is a key factor for losses experienced in contract management
when deriving value for money in public expenditures.
Figure 2
Contract Manager Responsibilities
Source: (Contract Management Practice, the World Bank, 2018)
The slowing down of the global economy over the past 10–12 years has placed a spotlight on the
use of public funds in the delivery of goods and services provided by government, and moreover,
ensuring that value for money is achieved. Traditionally, there was no distinction between
contract administration and contract management, and any value for money achieved during
tendering and negotiation was viewed as a procurement function. Today, there are many
government officials that still hold this view. Attaining an optimal level of contract management
maturity becomes difficult as contract management processes or standards that may be
established at a basic level are not institutionalized, and there is no government policy requiring
the consistent use of these contract management processes. Contract administration
professionals ensure government enters into legally sound, mutually advantageous contracts
that ensure value for money is achieved. This work is performed before contract formation and
Monitor and measure
output/outcomes.
Control payments for
successful delivery. Report to
governance
group.
Provide
relationship
management.
Prioritize risk
management.
Control changes
and contract
variations.
Organize
contract admin
and record
keeping.
Monitor
compliance with
contract terms.
Analyze reporting.
CONTRACT
MANAGER
12
involves sourcing potential contracting partners via requests for proposals and working with
prospective partners to finalize price, schedule, and performance expectations. Contract
management occurs after contract formation and requires appropriate utilization of government
resources. This involves compliance with contractual obligations, managing relationships, and
facilitating modifications to the contract.
It is imperative that procurement, contract administrators, and contract managers remain in
close communication throughout the life of the contract, as during the pre-procurement planning
process all parties should have been involved. A strategic procurement approach facilitates a
“cradle-to-grave” approach utilized in the private sector as a combined function called
procurement and contracts management. When dealing with PPPs and PFIs, this approach is
critical to identifying fraud. For example, these arrangements are large projects that usually
require a new company to be formed to facilitate a PPP/PFI agreement. This company is
established, there are no controls in place, and there is a high level of disorganization. This can
create an environment for potential fraud to become embedded in the design phase. However,
with a public entity that already has established contract management processes that are fully
integrated with other organizational core processes such as financial management, schedule
management, performance management, and systems engineering, the entity can use metrics
to measure various aspects of the contract management process and to make contracts-related
decisions. This planning requires skill sets from all three—procurement, contracts administration,
and management. Therefore, reducing fraud would involve reviewing fraud strategies and
policies, risk registers, and fraud investigation log. Procurement fraud controls should also be
enforced by auditing contractors and subcontractors, implementing an efficient procure-to-pay
process, and introducing fraud training during the planning stage.
7. Conclusion As a means to improving the contract management function in the public sector, with the primary
purpose to reduce instances of fraud and corruption, a more modern and progressive
interpretation should be considered. Contract management is a subset of the procurement life
cycle, and this life cycle is a hotspot for fraudulent activities because it is one of the primary areas
of expenditure for government organizations. This area is very difficult to investigate because
governments do not view contract management as an investment but rather a cost, especially
when building mechanisms to prevent fraud and achieve value for money. In addition, state-
centric anti-corruption organizations have failed to make any appreciable changes in the fight
against corruption of this nature, due to the paucity of evidence in corruption cases and a lack of
capacity for tracing financial crimes—more-so in developing countries.
A major setback with most governments is the inability to complete a long-term strategy within
the time frame that representatives are in elected office. Hence, any loss of control due to the
introduction of new elected players can result in a breakdown of any relationship management
that was nurtured in the not-too-distant past, which can jeopardize successful completion of
earmarked projects. In developing countries, procurement corruption is exacerbated due to
institutional weaknesses, bureaucratic-decision making, a lack of enforced accountability
13
mechanisms (law enforcement), and a culture of silence in relation to public sector
malfeasance.12
In summary, most instances of fraud committed during the contract management phase could
be prevented or detected early if the government entity possesses a complete understanding,
with a view to institutionalizing, the following:
Policies, procedures, and controls embedded within the procurement framework. This would
be the first line of defense and is foundational to any successful compliance program,
especially in detecting risks and outlining how the government organization is fulfilling its
regulatory requirements.
There should be list of red flags and typologies for corruption along the procurement cycle
that government officers in both procurement and contract management should be aware of
and continually trained on.
Data analytics should be considered in detecting insider-enabled contract management
fraud. Analytical techniques can measure areas that have an increased chance of corruption
and can assist law enforcement by focusing on targeted investigations.
Contract management should not be viewed from a purely legalistic manner, and as such,
governments should consider more usage of relational type contracts. This would enable
strategic alliances and allow for more cooperation, especially given that the majority of
modern contracts are subject to volatility in technology, prices, and competition.
When conducting strategic planning exercises, public sector organizations should introduce
objectives that target savings and an approach for generating value for money. This would
entail contractors becoming motivated, enabled, and empowered to achieve extra value over
and above original specifications, but still accessible against the original contract criteria.
Long-term contracts should include accrued benefits to contractors via incentivization for
achieving savings and developing innovation. This would cause contractor and government
objectives to become more aligned, share common interests, minimize the desire for fraud
or misappropriation of funds, and work towards the broader social and economic objectives
Contract management is an important part of the procurement process, but one that receives
the least focus and attention in the legislative framework on procurement. This paper is not a
panacea to all the ills of corruption in contract management but, rather, demonstrates how
effective contract management practices can lay the foundation for detecting and reducing the
risk of fraud in public expenditures.
12 Journal of Public Procurement, 2018, “Systemic corruption and public procurement in developing countries: Are there any solutions?”
14
References
THE WORLD BANK, 2018. Contract Management Practice. First Edition
RENDON, R.G., 2014. Benchmarking Contract Management Process Maturity
Retrieved from:
https://www.pmi.org/learning/library/benchmarking-contract-management-process-maturity
SMITH, PETER, 2017. Public Spend Forum
Retrieved from:
https://www.publicspendforum.net/blogs/peter-smith/2017/03/20/contract-management-
europe-challenge-public-sector-procurement/
PUBLIC MATTERS NEWSLETTER, 2017. Solving Contract Management in Public Sector
Retrieved from:
https://www.brownejacobson.com/training-and-resources/resources/legal-
updates/2017/12/top-tips-for-contract-management-in-public-procurement
ANDREW ALLEN, 2018. Chartered Institute of Procurement and Supply
Retrieved from:
https://www.cips.org/en/supply-management/news/2018/november/contract-management-
must-improve-on-bullet-train-to-nowhere/
CHURCHILL FRANCIS, 2017. Chartered Institute of Procurement and Supply
Retrieved from:
https://www.cips.org/en/supply-management/news/2017/september/welsh-health-board-
refers-contracts-to-corruption-watchdog/
ISN ANALYTICS, 2017. Contractor Management Strategy White Paper
PWC, 2011. Fighting Fraud in the Public Sector
HARRIS MILTON, 2013. The Impact of Contracts Management in the Public Sector
NATIONAL FRAUD AUTHORITY, OCTOBER 2011. Procurement Fraud in the Public Sector
WILLIAMS-ELEGBE SOPE, JUNE 2018. Systemic corruption and public procurement in developing
countries: are there any solutions?
FERWERDA JORAS, DELEANU IOANA, UNGER BRIGITTE, MAY 2016. Corruption in Public
Procurement: Finding the Right Indicators
INTER-GOVERNMENTAL ACTION GROUP AGAINST MONEY LAUNDERING IN WEST AFRICA, GIABA
RESEARCH REPORT, FEBRURAY 2014. Money Laundering Related To Fraud in Public Procurement
in West Africa: A Case Study of Nigeria
ASSOCIATION OF CERTIFIED ANTI-MONEY LAUNDERING SPECIALISTS. Study Guide, Sixth Edition.