The NBS BIM Toolkit

The NBS BIM Toolkit

Introduction1. Dave Philp, BIM Task Group - The Level-2 BIM journey

2. Stephen Hamil, NBS - Digital plan of work

3. Steve Lockley, BIM Academy - Verification

1. The Level-2 BIM journey

2011

2015

How to traditionally describe construction data PLQ: How Many Legs Do I Have?

LOD

The focus brought about by the requirement

of the UK Government to mandate BIM

Level 2 BIM by 2016 has necessitated clarity

as to how data is:

• Defined,

• Tested

• Effectively used by both the supply chain

and the public client

The DPOW helps support how this new

‘digital’ data is procured at ‘Level 2’

enabling clear definitions of need to the

supply chain and use full data detailed to the

client for use.

ENSURE EVERYONE CAN PLAY THEIR PART (OPEN DATA)

The selected supply base supplying data upto the tier one who is responsible for itscoordination use and submission to theemployer must be employed consistently toensure data can be created and re-used,rather than repeatedly re-typed.

Clearly it is incumbent on the employer to only ask for information that is needed ateach stage of the project

The rate of this growth must be driven by theamount of information needed to answer each Key Client Question. Any more and we are incurring waste, any less and we cannot effectively answer the questions.

These questions are known as the ‘Plain Language’ Questions.

As the project progresses the data “Progressively Grows”

Key ‘anchors’ for the dPoW

Plain language questions

(PLQ’s) to inform key

client decisions

COBie Data

2D PDF’s

(Native models)

Plain

language

questions

(PLQ’s) to

inform key

client

decisions

Putting too much information into the model too

soon may restrict both the design and supply

chain options for others in the team and leads to

other forms of waste with the inherent costs

incurred by both the supplier and the client.

It also places constraints on the supply chain to

offer compliant alternative designs, offering better

asset or value performance.

DPOW = Goldilocks Principle

2. Digital plan of work

The Level-2 BIM package

How will the BIM Toolkit benefit those working within the level-2 BIM process?

Standards are freely available at - http://shop.bsigroup.com/BIM

Assessment and needProcurement

Post-contract award and mobilisation

Production

Maintenanceand use

Figure taken from PAS1192-2:2013 – Copyright Mervyn Richards

Assessment and need

Assessment and need

Assessment and need

Overview• Client determines their plain language questions

(determines the need)

• Client produces their employer’s information requirements(Required information to meet the needs as defined in PLQs)

• Information requirements aligned to the project stages

• This is part of the tender documentation

A collectionof projects

Information at a project level

Information at astage level

At the start of the project the client has not assembled their

team

At strategy/brief stage it is possible to

determine information needs

Template tasks can be modified, removed and

added to

These projects can be refined and reused on

future projects

Tasks and deliverables are assigned to roles prior to

the team being assembled

This information may be exported

Export to MS Excel for inclusion within the EIR

document (PDF)

…and export to IFC/COBie for digital

re-use

All information can exported and manipulated either in

buildingSMART or MS Excel format

At a basic level – it can easily be inserted into an MS Word EIR

Procurement

Procurement

Procurement

Overview• Bidders respond with their pre-contract BIM execution plan

• Proposed responsibility of bidders supply-chain is provided

• The client can compare these against their original information requirements

• Selection can take place

The proposed roles have been assigned

The proposed project team has

been addedEach item, at each stage has a party

responsible

The bidder

Export to MS Excel for inclusion within the BEP document (PDF)

…and export to IFC/COBie for digital

re-use

Pre-contract award and mobilisation

Post-contract award and mobilisation

Production

Production

Production

Overview• The federated Project Information Model begins to grow

• dPOW defines the what, the when and who

• Information exchanges between supply-chain

• Information delivery to the client as agreed in EIR

• Documented classification and data structure allows for verification

Moving into the design phases the team is now assembled and the information requirements

grow

Level of detail guidance can be defined for each deliverable

Level of information guidance can be defined for each deliverable

A definitions library of over 5,000 items across all construction disciplines will be provided

At concept stage – the operations phase should be considered

At the technical design stage more geometric detail is required

The level of information grows through the bandings too

LOI-6 contains the standard COBie properties for transfer to the asset management systems

The definitions library covers infrastructure in addition to

buildings

RICS were part of the core team and have provided classification

mappings to NRM1

Rules of measurementfrom RICS NRM1

Benchmark costsfrom RICS BCIS

Filter by Uniclass 2015 classification tables

At an early stage space requirements may be

specified

Classification – Uniclass 2015

Advanced search technology is used to take the complexity

away from classification

What hasbeen asked for

What hasbeen provided

Maintenance and in use

Maintenanceand use

- ID- ParentSpace- Level- Manufacturer- Model- ExpectedLife- O+M-Manual

Verification & Validation of BIM Submissions

Prof. Steve Lockley

Overview & Background

R&D funded by Innovate UK

Built on the xBIM platform

Open source toolkit for open BIM

Led by BIM Academy at Northumbria

Developed by the XbimTeam

Collaborative BIM development

Built on BuildingSmart data model – IFC

Community based, royalty free.

Objectives

Information Requirements

Development

Information Submission

Validation

Close the loop

Automate validation

Minimise error and misunderstanding

BIM platform neutral

IFC based

COBie compliant

Support widely used industry

classifications and properties

Open and extensible

Scope – Current phase

Verify that data required has been submitted

Integrated with the BIM Toolkit

Works across all project stages

Employers, design team and contractors

Handles Documents and BIMs

Understandable process

Built on Open Standards

110% COBie Structure

Two way IFC exchange

IFC -> COBie

COBie -> IFC

Computer

Human

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

BIM Platform neutral

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

COBie Requirements & Submission

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

In-Cloud + In-House

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

Simple Submission Report

COBie, IFC

COBieSubmission COBie, IFC

COBie Requirements

Community support needed

xBIM is an Open Platform• Royalty free, open source

Several key organisations actively engaged• 4Projects, NBS, AEC3, Metz Architects, eDocuments, B&ES

Designed and built on, and for, IFC• No Compatibility or portability issues

Construction & IT industry engagement welcomed

[email protected]

www.OpenBIM.orgwww.github.com/xBimTeam

Summary

The NBS BIM Toolkit

Summary1. A clear central strategy for information procurement

2. A free-to-use digital plan of work tool for UK Level-2 BIM

3. Verification of information using well-structured open data

The NBS BIM Toolkit

theNBS.com/Toolkit