the national highway authority of india (nhai) and the...
TRANSCRIPT
Chapter 3
The National Highway Authority of India (NHAI) and the Project
Highway
3.1 Introduction.
3.2 Establishment.
3.3 Functions.
3.4 Projects of the NHAI.
3.5 The NHAI and the Project Highway.
3.5.1 The location of the Project Highway.
3.5.2 Clearances.
3.5.3 The Build – Operate – Transfer (BOT) Project.
3.5.4 The Model Concession Agreement (MCA).
3.5.5 Grant of Concession.
3.5.6 Construction Aspects of the Project Highway.
3.5.7 Obligations of the NHAI.
3.5.8 Completion of the Project Highway.
3.5.9 Tests of the Project Highway.
3.5.10 Operation and Maintenance of the Project Highway.
3.5.11 Financing Arrangements.
3.6 The Provisional Completion Certificate.
27
Chapter 3
The National Highway Authority of India (NHAI) and the Project
Highway
3.1 Introduction
The National Highway Authority of India (NHAI) is an autonomous agency of the
Government of India, responsible for management of a network of over 60,000 km of
National Highways in India. The Authority is a nodal agency of the Ministry of Road
Transport and Highways (MoRTH).
3.2 Establishment
The NHAI, a statutory body, was created under the provisions of the National
Highways Authority of India Act, 1988. In February 1995, the Authority was formally
made an autonomous body. It succeeded the erstwhile Ministry of Surface Transport
(MOST).
It’s principle office is at G-5 and 6, Sector 10, Dwarka, New Delhi – 110075.
3.3 Functions
It is responsible for the development, maintenance, management and operation of
National Highway totalling over 70,548 km in length.
28
3.4 Projects of the NHAI
The NHAI has the mandate to implement the National Highway Development Project
(NHDP). The NHDP is one of the most ambitious projects launched in the
independent India. The NHDP comprises following phases:
Phase I: Approved in December 2000. It includes 5,846 km. Golden
Quadrilateral (GQ) connecting the four major cities of Delhi, Mumbai,
Chennai and Kolkata, portions of the NS – EW corridors and connectivity of
four major ports to National Highways.
Phase II: Approved in December 2003. Estimated cost of Rs. 34,339 Crores
(At 2002 prices). It included the completion of the NS – EW corridors and
other 486 km highways. It links Kashmir in the North to Kanyakumari in the
South including spur from Salem to Kochi and Silchar in the East and
Porbandar in the West.
Phase III A: Approved in March 2005. Estimated cost Rs. 22,207 Crores (At
2004 prices). It included up gradation and 4-laning of 4,035 km of National
Highways on the BOT basis.
Phase III B: Approved in April 2006. Estimated cost Rs. 54,339 Crores. It
includes up gradation and 4-laning of 8,074 km National Highways.
Phase V: Approved in October 2006. It includes upgrades to 6-lanes for 6,500
km of which 5,700 km is on Golden Quadrilateral (GQ). This phase is
entirely on a Design, Build, Finance and Operate (DBFO) basis.
Phase VI: Approved in November 2006. It includes development of 1,000 km
of Expressways at an estimated cost of Rs. 16,680 Crores.
Phase VII: Approved in December 2007. It will develop ring roads, by-passes
and flyovers to avoid traffic bottlenecks on selected stretches at an estimated
cost of Rs. 16,680 Crores.
29
3.5 The NHAI and the Project Highway
3.5.1 The Location of the Project Highway
Mumbai – Agra road, National Highway No. 3 is one of the most important highways
in the network of National Highways that carries heavy long distance commercial
traffic.
The Ministry of Road Transport and Highways (MoRTH) decided to improve this
road on the BOT basis. The National Highway Authority of India (NHAI) is the
implementing authority for this project.
For the purpose of project preparation, the selected length of this corridor is divided
into convenient sections based on their traffic generation and attraction potential,
geographic location and other considerations.
One such section that falls in Maharashtra between Vadape (km 539/500) to Gonde
(km 440/000) is chosen for implementation. (Ch 0.00 is at Indore and increases
towards Mumbai).
Village Gonde is about 25 km south of Nashik and Vadape is at the end of 4-lane
wide Bhiwandi By-pass toll section, about 20 km. north of Thane.
The Ministry appointed Consulting Engineering Services (India) Private Limited
(CES) as the Consultant for providing necessary technical service to prepare Detailed
Project Report (DPR).
The Project Road length runs in North-South direction and passes through Nashik and
Thane district. Out of the 100 km road length, 30% lies in the Nashik district and
remaining in the Thane district. Alignment traverses through Igatpuri Taluka in
Nashik district and Shahapur and Bhiwandi Talukas in Thane district. There are in all
52 number of villages through which the alignment passes.
30
The important towns on way are Ghoti (km 453) in Igatpuri Taluka, Igatpuri (km
463), Khardi (km 493) and Shahapur (km 513).
There are six major roads (State Highways) that join or cross the National Highway.
In addition there are 73 more road junctions of village roads joining the highway.
3.5.2 Clearances
For construction of the Project Highway following clearances were obtained.
i) Environment Clearance from Ministry of Environment and Forest
(MoEF).
ii) Forest Clearance from Regional Forest Office, Bhopal.
iii) Road Over Railway Bridge from Central Railway.
iv) Permission from Tree Authority for tree cutting.
The clearances from above authorities were required because –
1) The project affects forest lands. In some places it needed acquisition of the
forest land.
2) The Noise level along the Project Road was already high and was expected
to increase progressively. It also causes air pollution.
3) For 4-laning, transplanting the existing trees to the extent possible was
planed but still cutting the existing trees was unavoidable.
4) The Project Highway crosses various streams, rivers, gorges and railway
tracks.
31
3.5.3 The Build, Operate, Transfer (BOT) Project
The BOT Documents were prepared and offers were called by the Ministry. The BOT
i.e. Build, Operate, Transfer arrangement means the private investor (Concessionaire)
builds, operates and transfers the project back to the Government at the end of a
specified period, called the ‘Concession Period’.
3.5.4 The Model Concession Agreement (MCA)
The Model Concession Agreement for this Project Highway was signed on 14th
October 2005 between the National Highway Authority of India (NHAI) and the
Concessionaire i.e. M/s. Mumbai Nasik Expressway Limited, a company incorporated
under the provisions of the Companies Act 1956. It has its registered office at
Gammon House, Veer Savarkar Marg, Prabhadevi, Mumbai – 400 025. The NHAI
was keen to implement a project envisaging Improvement, Operation and
Maintenance, Rehabilitation and Strengthening of the existing 2-lane NH-3 and
widening it to 4-lane divided highway of Vadape to Gonde section of NH-3 from km
539.50 to km 440.00 in the State of Maharashtra on the BOT basis.
The MoRTH invited the Request for Proposals on the BOT basis on 19th September
2003 and subsequent to that the NHAI issued and prescribed the technical and
commercial terms and conditions vide its letter no. NHAI/BOT/11019/1/2003 dated
28th February, 2004 (the Tender Notice) and invited Bids from the BOT
Entrepreneurs.
The NHAI received the BID from the Consortium Members, Gammon India Limited
(having its registered office at Gammon House, Veer Savarkar Marg, Prabhadevi,
Mumbai – 400 025) as the Lead Member, Sadbhav Engineering Limited (having its
registered office at Sadbhav House, Opposite Law Garden Police Chowki, Ellis
Bridge, Ahmadabad) and B.E. Billimoria and Company (having registered office at
Wankhede Stadium (North Stand) ‘D’ Road, Churchgate, Mumbai – 400020).
32
After evaluation of the Bids so received, the NHAI accepted the Bid of the
Consortium and issued its Letter of Acceptance No. NHAI/BOT/ 11019/1/2003/227
dated 16th June, 2005 (LOA) to the Consortium, requiring its confirmation of
acceptance of LOA, the execution of the Concession Agreement within thirty days of
the date of acceptance of LOA and furnishing of Performance Security before signing
of the Concession Agreement.
The Consortium accepted the said LOA and the terms and conditions therein and
issued its acceptance of the LOA vide its Letter No. VG/PKU/VSK/2005/31 dated
29.06.2005.
Subsequently the Consortium has promoted and incorporated the Concessionaire
(M/s. Mumbai Nasik Expressway Limited) to enter into the Concession Agreement
for undertaking the design, engineering, financing, procurement, construction,
operation and maintenance of the Project Highway on the BOT basis.
The Consortium also submitted the Performance Security of Rs. Seventeen Crores and
Thirty Seven Lakhs for the Project vide its Letter No. VG/PKU/VSK/20O5/43 dated
27th July, 2005.
3.5.5 Grant of Concession
Subject to and in accordance with the terms and conditions of the Concession
Agreement, the concession period of 20 years commencing from the Appointed Date
(means the date, 180 days from signing of the Concession Agreement [Date of
Signing 14th October, 2005]) was granted by the NHAI.
According to the Concession Agreement, the Concessionaire is entitled to develop,
design, engineer, finance, procure, construct, operate and maintain the Project
Highway during the Concession Period and after completion of the Project Highway
and during the Operations Period to manage, operate and maintain the Project
Highway. The Concessionaire according to the MCA is entitled to levy and collect
33
Fees from the users of the Project Highway and refuse entry of any vehicle to the
Project Highway if the due fee is not paid.
The overall estimated cost of the project was estimated approximately Rs. 536 Crores
(a base cost including the Kasara Ghat Bypass) and the Financial Internal Rate of
Return (FIRR) is worked out to 15.48%.
The Concessionaire is entitled to suggest locations of Toll Plazas and the Project
Monitoring Unit Complex and pay for acquisition of lands for it.
The NHAI and the Concessionaire will jointly appoint Independent Consultant and
the Project Monitoring Unit to supervise the progress of the work.
The construction programme will be of 5 years, divided into 2 stages. In the 1st stage
of 3 years duration, most of the priority works will be completed. The 2nd stage of 2
years will attend to residual works like service roads, drains, amenities and
arboriculture etc.
3.5.6 Construction Aspects of the Project Highway
As the major work has to be completed within an initial limited period of 3 years, all
the sections should remain in progress simultaneously and there are no intersay
priorities in between them.
Each section will have two major components, that is, improvement of the existing
road and construction of second (new) carriageway. It will be necessary to construct
the new carriageway, divert traffic on it and then switch over to improvement of the
existing highway. For this purpose eccentric widening of the roadway is preferred to
symmetrical widening of the existing road, which will ensure minimum hindrance to
traffic plying on the existing road. As far as possible, it will be preferable to keep the
construction vehicles separated from the main traffic flows. Concessionaire has to use
34
his ingenuity in planning and implementing construction methodology and adopt
traffic control methods accordingly.
The overall prioritization of component sub-works comprise of preconstruction and
during construction activities. The sequence of such construction activities is
suggested below.
A) Pre Construction Activities :
1) Obtaining ‘No Objection Certificates’ (NOCs).
2) Environment Clearance.
3) Land Acquisition.
4) Relocating Utilities.
5) Felling of Trees.
6) Appointment of the BOT Agencies.
B) During Construction :
1) Construction of new road starting with construction of culverts and
bridges and service roads, including construction of New Kasara Ghat
road. It is possible to take up construction of about 15 km of road length
between Ghoti and Kasara within available ROW i.e. till additionally
required land is acquired in other stretches.
2) New road embankment and pavement (including Ghat bypass).
3) Diverting traffic to new road (in sub-sections if possible).
4) Construction of culverts and bridges if any, on the existing road.
5) Improvement to existing road, camber correction and pavement.
6) Road furniture, side drains, median.
7) Toll plaza, amenities, land scaping.
35
3.5.7 Obligations of the NHAI
The NHAI agrees to observe, comply and perform the following:
1) Enable access to the Site to the Concessionaire, free from Encumbrances, in
accordance with the MCA.
2) Permit peaceful use of the site by the Concessionaire as licensee under and in
accordance with the provisions of the MCA without any let or hindrance from
the NHAI or person claiming through or under it.
3) Assist and provide all reasonable support to the Concessionaire in obtaining
Applicable Permits.
4) Upon written request from the Concessionaire, assist the Concessionaire in
obtaining access to all necessary infrastructure facilities and utilities,
including water, electricity and telecommunication facilities at rates and on
terms no less favourable to the Concessionaire than those generally available
to commercial customers receiving substantially equivalent services.
5) Procure that no barriers are erected or placed by the Government of
Maharashtra or any Governmental Agency on the Project Highway except on
account of any law and order situation or upon national security
considerations.
6) Enter into the State Support Agreement with the Concessionaire and the
Government of Maharashtra.
7) Assist the Concessionaire in obtaining necessary assistance to regulate traffic
on the Project Highway subject to and in accordance with the Applicable
Laws.
8) Assist the Concessionaire in obtaining Police assistance from the Government
of Maharashtra against payment of prescribed costs and charges, if any, for
36
traffic regulation, patrolling and provisions of security on the Project
Highway.
9) Operate and maintain the Project Highway during the Development Period, at
its own cost and expenses, in a manner that the level of service is at no time
inferior to the level prevailing on the date when bids were received for this
Concession.
10) Observe and comply with its obligations set forth in this Agreement.
11) Take all necessary steps towards accomplishment of acquisition of additional
land. The NHAI shall bear the cost of additional land.
12) Coordinate with the Government of Maharashtra authorities for completing
the legal requirements and maintaining law and order during removal of
encroachment by the Concessionaire.
13) Provide necessary support to the Concessionaire in obtaining necessary
clearances / permissions / permits in respect of environmental clearances, tree
cutting, compensatory afforestation, shifting of all types of utility services,
construction of ROB/RUB on Railway lines and rehabilitation and
resettlement.
14) Bear all expenses as per demand note raised by the concerned Government
or other concerned agencies in respect of environmental clearances, tree
cutting, compensatory afforestation, shifting of all types of utility services,
construction of ROB/RUB on Railway lines and rehabilitation and
resettlement.
15) Arrange to issue fee notification to get legal opinion from a legal counsel to
the concessionaire.
37
3.5.8 Completion of the Project Highway
According to the MCA, the Project shall be deemed to be complete and
open to the traffic only when the Completion Certificate or Provisional
Certificate is issued.
Commercial Operation Date (COD) of the project shall be the date on
which the Independent Consultant has issued the Completion Certificate or
the Provisional Certificate, as the case may be, under the MCA and the
Concessionaire shall not levy and collect any Fee until it has received such
Completion Certificate or Provisional Certificate.
The Concessionaire guarantees that the Project Completion shall be
achieved in accordance with the provisions of the MCA on a date not later
than 36 months from the Appointed Date.
If the Project Completion is not achieved by the Scheduled Project
Completion Date for any reason, the Concessionaire shall pay the NHAI as
Weekly Damages for delay in the achievement of Commercial Operation
Date [COD] an amount calculated at the rate of 0.01% of the Total Project
Cost per week or part thereof.
If the COD does not occur within 12 months from the Scheduled Project
Completion Date, the NHAI shall be entitled to terminate the MCA.
3.5.9 Tests of the Project Highway
‘Tests’ means the tests to be carried out to determine the Project
Completion and its certification by the Independent Consultant for
commencement of Commercial operation of the Project Highway. The
NHAI shall designate a NHAI Representative to witness and observe
Tests.
38
The Independent Consultant shall monitor the results of the Tests to
determine the compliance of the Project Highway with the Specifications
and Standards. The Concessionaire shall provide to the Independent
Consultant and the NHAI with copies of all Test data including detailed
Test results.
At least 30 days prior to the likely completion of the Project Highway or
each of (a) a continuous stretch of at least 50 km of the Project Highway
and (b) the balance stretch of the Project Highway (if the length of the
Project Highway is more than 50 km), the Concessionaire shall notify the
Independent Consultant and the NHAI of the same and shall give notice of
its intent to conduct any final Tests. The Concessionaire shall give to the
NHAI and the Independent Consultant at least 10 days prior notice of the
actual date or which it intends to commence the Tests and at least 7 days
prior notice if the commencement date of any subsequent Tests. The
Independent Consultant shall have the right to suspend or delay any Test
that the performance of the Project Highway or any part thereof does not
meet the Specifications and Standards.
Upon the Independent Consultant determining the Tests to be successful,
then that stretch of the Project Highway can be legally, safety and reliably
placed in commercial operations, the Independent Consultant issues
Completion Certificate to the Concessionaire and the NHAI in respect of
that stretch. When all the stretches of the Project Highway receives
Completion Certificate for all the stretches, a final Completion Certificate
certifying the Project Completion is issued.
The Concessionaire shall bear all the expenses relating to the Tests.
39
3.5.10 Operation and Maintenance of the Project Highway
The Concessionaire shall operate and maintain the Project Highway by itself, of
through O & M Contractors (O & M Contractor means the person or entity with
whom the Concessionaire has entered into an O&M Contract for discharging
Operation and maintenance functions for and on behalf of the Concessionaire) or if
required modify, repair or otherwise make improvements to the Project Highway to
comply with Specifications and Standards such as:
Permitting safe, smooth and uninterrupted flow of traffic during normal
operating conditions.
Charging, collecting and retaining the fees in accordance with the MCA.
Minimizing disruption to traffic in the event of accidents or other incidents
affecting the safety and use of the Project Highway by providing rapid and
effective response and maintaining emergency services.
Undertaking routine maintenance including prompt repairs of potholes,
crocks, concrete joints, drains, line markings, lighting and signage.
Undertaking major maintenance such as resurfacing of pavements, repairs
to structures, repairs and refurbishment of tolling system and hardware and
other equipments.
Carrying out periodic preventive maintenance to Project Highway including
tolling system.
Preventing with the assistance of concerned law enforcement agencies,
unauthorized encroachment on the Project Highway including site and
preserve the right of way (ROW) of the Project Highway.
Maintaining Public Relations Units to interface with and attend to
suggestions from users of the Project Highway, the media, the Government
Agencies, and other external agencies.
40
In case of unsafe conditions, vehicle breakdowns and accidents; the
Concessionaire shall follow up temporary traffic cones and lights, removal
of obstructions and debris etc.
The Concessionaire shall ensure that any diversion or interruption of traffic
is remedied without delay. The Concessionaire’s responsibility for rescue
operation on the Project Highway shall be limited to the removal of
vehicles or debris or any other obstruction, which may endanger or interrupt
the smooth traffic flow on the Project Highway.
The Concessionaire shall be responsible for the maintenance of the
approach roads to and underpasses and overpasses upto 100 meters from
the Project Highway.
3.5.11 Financing Arrangements
a) Financial Close :
The Concessionaire shall provide to the NHAI, a copy of Financing Package
furnished by it to the prospective Senior Lenders. (Senior Lender means the financial
institutions, banks, funds and agents or trustees of debenture holders, including their
successors and assignees, who have agreed to provide finance or guarantee facility to
the Concessionaire under any of the Financing Documents for meeting costs of all or
any part of the Project). As and when such Financing Package is approved by the
Senior Lenders, with or without modifications, a copy of the same shall be furnished
by the Concessionaire to the NHAI.
The Concessionaire shall achieve Financial Close within 180 days from the date of
the MCA. If the Concessionaire fails to achieve the Financial Close within 180 days
period, the Concessionaire shall be entitled to a further period of 180 days subject to
an advance weekly payment by the Concessionaire to the NHAI of a sum of
41
Rs. 1,00,000/- per week or part thereof for any delay beyond the said first 180 days
period as Damages on account of such delays.
‘Financing Close’ means the date on which the Financing Documents providing for
funding by the Senior Leaders have become effective and the Concessionaire has
immediate access to such funding under the Financing Documents.
‘Financing Documents’ means the documents executed by the Concessionaire in
respect of financial assistance to be provided by the Senior Lenders by way of loans,
guarantees, subscription to non-convertible debentures and other debt instruments,
security agreements and other documents relating to the financing (including
refinancing) of the Project.
‘Financing Package’ means financing package of the Project furnished by the
Concessionaire along with its Bid indicating the Total Project Cost and the means of
financing thereof and shall be deemed to have been modified to the extent as
submitted to the Senior Lenders and as approved by the Senior Lender for the purpose
of funding of the Projects.
Notwithstanding anything to the contrary contained in the MCA, the NHAI shall be
entitled to terminate the MCA.
b) Grant :
The NHAI agrees to provide to the Concessionaire cash support by way of Grant
equal to the sum as set forth in the Bid of Consortium and accepted by the NHAI
aggregating to Rs. 159.00 Crores and the Concessionaire agrees to provide to the
NHAI cash payment (the Negative Grant) equal to the sum as set forth in the Bid of
the Consortium and accepted by the NHAI, aggregating Rs. 120.00 Crores during the
Concession Period.
Negative Grant shall be paid in advance within 90 days of the commencement of the
year for which it is due and payable.
42
The Grant shall be applied by the Concessionaire for meeting the Capital Cost of the
project and expenditure during the Operations period and shall be treated as part of
the shareholders’ Funds i.e. the ‘Equity Support’.
c) Revenue Shortfall Loan :
If the Realisable Fees (means all the Fees due and realisable under the MCA but does
not include fees that the Concessionaire has not been able to realise after due
diligence and best effort) in any Accounting year during the Concession Period shall
fall below the Subsistence Revenue Level (means the total amount of Fee revenue that
is required by the Concessionaire in an Accounting Year to meet the sum of (a) the O
& M Expense subject to an annual ceiling of 1.5%. Operations year, to be revised
each year to reflect the variations in the WPI in each subsequent years and (b) Debt
Service Payments due to the Senior Lenders in an Accounting Year) as a result of an
Indirect Political Event (i.e. an act of war, invasion, armed conflict or act of foreign
enemy blockade, riot, terrorist or military action etc. which prevent collection of Fees
by the Concessionaire for a period of exceeding a continuous period of 7 days in an
Accounting Year) or a Political Event (means change in law, expropriation or
compulsory acquisition by any Government Agency of any Project Assets or rights of
the Concessionaire or of the Contractors, etc.) agrees to provide to the Concessionaire
such shortfall support by way of a loan called “Revenue Shortfall Loan” with interest
thereon @ SBI PLR per annum.
‘SBI PLR’ means the prime lending rate per annum for loans with one year maturity
as fixed from time to time by the State Bank of India, and in the absence of such rate,
the average of the prime lending rates for loans with one year maturity fixed by the
Bank of India and failing that any other arrangement that substitutes such prime
lending rate as mutually agreed between the Parties.
43
d) Escrow Account :
‘Escrow Account’ means an Account which the Concessionaire shall open and
maintain with a Bank in which all inflows and outflows of cash on account of capital
and revenue receipts and expenditure shall be credited and debited, as the case may
be, in accordance with the provisions of the MCA.
According to the MCA, the Concessionaire shall within 60 days from the date of the
MCA open and establish the Escrow Account with a Bank and all funds constituting
the Financing Package for meeting the Total Project Cost shall be credited to such
Escrow Account. During Operation Period all fees collected by the Concessionaire
from the users of the Project Highway shall be exclusively deposited therein. In
addition, all fees collected by the NHAI in exercise of its right under this MCA during
the Concession Period and all disbursements or payments by the NHAI shall also,
subject to the rights of deductions and appropriations therefrom of the NHAI, should
be deposited by the NHAI in the Escrow Account.
e) The State Support Agreement :
The “State Support Agreement” means the agreement to be entered into between the
Government of Maharashtra, the NHAI and the Concessionaire substantially are fully
described in the draft State Support Agreement set forth as Schedule ‘R’ of the
Concession Agreement for provision of support, backup and services required from
the Government of Maharashtra for the performance of Concessionaire’s obligations
under this MCA.
f) Insurance :
The Concessionaire is required to take Insurance during the Construction Period as
well as the Operation Period, at no cost to the NHAI up to maximum sums required in
accordance with the Financing Documents and Applicable Laws.
44
g) Accounts and Audit :
The Concessionaire shall maintain full accounts of all Fees including Realisable Fees
(means all the Fees due and realisable under the MCA but does not include fees that
Concessionaire has not been able to realise after due diligence and best efforts) and
other revenues derived / collected by it from and on account of use of the Project
Highway and of O&M Expenses and other costs paid out of the Project Escrow
Account and shall provide to the NHAI copies of these accounts duly audited and
certified by the Concessionaire’s Statutory Auditors within 120 days of the close of
each Accounting Year.
The ‘Statutory Auditors’ means an independent, recognized and reputable firm of
Chartered Accountants duly licensed to practice in India acting as independent
statutory auditors of the Concessionaire under the provisions of the Companies Act
1956.
3.6 The Provisional Completion Certificate
Sheladia Associates Inc. in association with M/s. Artefact Projects acted as
Independent Consultants on the Project “4 laning of Vadape to Gonde from km
440/000 to km 539/500, section of NH-3 in the State of Maharashtra, India” on the
BOT basis.
M/s. Mumbai Nasik Expressway Limited is the Concessionaire in the Project which
signed the Concession Agreement dated 14th October, 2005 with the NHAI.
The Independent Consultants provided the Provisional Completion Certificates, one
on 23rd December, 2009, the second on 11th May, 2010 and the third on 11th July,
2011.
The first Provisional Certificate dated 23rd December, 2009 mentioned that 4 numbers
of ROB’s and 2 numbers of major bridges along with approaches are still incomplete
45
and competent Authority of the NHAI has approved their deletion from 1st Milestone
COD. Approximately 3 km. length is incomplete between km 440/000 to km 490/000.
In this regard the Concessionaire has completed upto km 493.000 to compensate for
the incomplete 3 km between km 440/000 and 490/000 and to complete the required
50 km length for the 1st Milestone.
The second Provisional Completion Certificate dated 11th May, 2010 was issued for
the stretch from km 493/000 to 508/000 deducting 1.00 km length on account of
incomplete status of ROB at 494+767 resulted in a total completed length of 14 km.
The Third Provisional Completion Certificate dated 11th July, 2011 was issued for the
stretch from km 508+000 to km 539+500 (2nd Milestone) and for excluded sectional
lengths of Milestone – 1. The certificate certifies that all works have been completed
on 31st May, 2011, excluding 2 numbers ROBs and items appended in Punch list. It
also states that the Competent Authority in NHAI HQ has approved the deletion of
these two numbers of ROBs from 2nd Milestone COD.
Receiving such Provisional Completion Certificate, the Concessionaire is permitted
that all parts of the Project Highway can be legally, safely and reliably placed in
Commercial Operations.
Chapter 4
Financing Procedures and Rules for the Road Projects of the
National Highway Authority of India (NHAI) Using
the Public Private Partnership (PPP) Scheme
4.1 Introduction.
4.2 Meaning and Definition of the PPP Project.
4.3 Reasons for opting to use the PPP Scheme.
4.4 The PPPs in National Highways.
4.5 Framework for the PPPs in National Highways.
4.6 The PPP Database.
4.7 The Model Concession Agreements (MCA).
4.8 The Public Private Partnership Approval Committee (PPPAC).
4.9 Finance for the PPP Projects.
4.9.1 Meaning of India Infrastructure Project Development Fund (IIPDF).
4.9.2 Purpose of the IIPDF.
4.9.3 The Viability Gap Funding Scheme.
4.9.4 Eligibility Criteria for getting support under VGF Scheme.
4.9.5 Procedure for getting the VGF.
4.9.6 Disbursement of the VGF.
4.10 India Infrastructure Finance Company Limited (IIFCL).
4.11 the BOT variants used in National Highways Projects.
4.11.1 Meaning and Definition of the BOT.
4.11.2 Parties to the BOT Projects.
4.11.3 The BOT (Toll) Model.
4.11.4 The BOT (Annuity) Model.
4.11.5 Applicability of the BOT Models.
4.11.6 Advantages of the BOT Projects.
4.12 Issues Limiting Greater Participation of the Private Sector in the
PPP.