the midland metro (wolverhampton city centre extension) … · adams’ view that the alternative...
TRANSCRIPT
1
Transport and Works Act 1992 Town and Country Planning Act 1990 Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006 Transport and Works (Inquiries Procedure) Rules 2004
The Midland Metro (Wolverhampton City Centre Extension) Order
CLOSING SUBMISISONS ON BEHALF OF THE APPLICANT
1. The fact that the inquiry has been short, and that there is little opposition to the
making of the order, is a clear indication that there is widespread recognition of the
benefits of the scheme.
2. There is no dispute that the scheme will deliver the key benefits which I set out in
my opening. I do not repeat that opening but do rely upon it, and ask you to
consider it when writing your report.
3. When making your report, you will wish to address the matters identified in the
Secretary of State’s statement of matters1. The evidence presented by the Applicant
addresses those matters2 and I do not intend to repeat it in these closing
submissions. I will provide brief submissions on each matter, but rely on the
unchallenged evidence, which I would ask you to consider in detail when writing
your report.
1. The aims and the need for, the proposed Midland Metro Wolverhampton City
Centre extension ("the scheme").
4. The aims of the scheme are identified in the concise statement of aims3.
5. The WCCE forms part of the wider Wolverhampton Interchange Project (“WIP”).
The WIP will deliver a multi-modal transport hub, commercial floorspace and
improve the strategic gateway to Wolverhampton and the Black Country.
1 INSP/4 2 Table 9.1 in Peter Adams PoE sets out where each matter is covered in the evidence. APP/P1.1/SCH 3 WCCE/A3
2
6. It is anticipated that the WIP will facilitate the development of 73,862 sq ft of
office/leisure/retail floor space providing 278 jobs. A further 321,000 sq ft of
floorspace will be created over subsequent years providing 1,590 jobs.
7. The need for the scheme is explained by Mr Adams in his proof of evidence4.
8. The lack of connectivity between Midland Metro Line 1 and the railway and bus
stations is a serious deficiency. That lack of connectivity disadvantages the travelling
public and undermines the Black Country LEP strategy of enhancing public transport
connectivity between the four strategic centres of Brierley Hill, Walsall, West
Bromwich, and Wolverhampton5.
9. The analysis conducted indicates that providing such linkages will prove attractive to
the travelling public and as a result patronage levels on Midland Metro will increase
by 4.6% by 2016 and by 5.4% by 20266.
10. There can be little doubt that there is a need to improve the connection between
the Metro and the existing bus and rail services. The WCCE will achieve that
connection and, as part of the WIP, will make a significant contribution towards
regeneration and job creation in Wolverhampton city centre.
11. I invite you to conclude that the need is established, and that the order if made will
enable that need to be met.
2. The main alternative options considered by Centro and the reasons for choosing
the proposals comprised in the scheme.
12. The environmental statement identifies the main alternatives considered by
Centro7.
13. A number of alternative means of linking the Metro and the railway station have
been considered since at least 1999.
14. In 2001 the Wolverhampton to Walsall via Wednesfied (5W’s) route was given
priority8.
4 Adams PoE 6.1-6.3 APP/P1.1/SCH 5 Adams PoE 6.1 APP/P1.1/SCH 6 Adams PoE 6.3 APP/P1.1/SCH 7 WCCE/A15 section 3.7 8 WCCE/A15 section 3.7.8
3
15. The 5W’s route was endorsed in the 2006 Local Transport Plan –the route envisaged
for Wolverhampton was a city centre loop9.
16. A series of plans showing the options considered was submitted to the inquiry. Mr
Adams explained those options. Options 1 and 4 are longer and affect more
stakeholders. Option 2 does not go to the station. Option 5 would also be longer,
would affect more stakeholders and would not interchange with the railway station.
17. In 2011/2012 the city centre loop proposals were replaced with the current more
direct twin track route along Piper’s Row10.
18. The May 2013 proposals would have required demolition of the Old Steam Mill.
That proposal was revised following objections from English Heritage and others11.
19. A summary assessment of the options is set out at page A17 of the Business Case
for the WIP12. As Mr Adams13 explained it was considered disproportionate to
prepare a full business case for each option (with resultant BCR). However it is Mr
Adams’ view that the alternative options would be likely to have a lower BCR as
benefits would be similar whereas the route would be longer (and therefore cost
more).
20. The alternatives considered have not been restricted to the route. Examination of
alternatives has also included detailed consideration of the stops on Piper’s Row,
and in particular the northbound stop. Mr Gardner produced the Aecom technical
note which considered such options14.
21. There can be little doubt that there has been a thorough consideration of
alternatives including extensive consultation over a considerable period, and that
there is no preferable alternative to the scheme now proposed.
22. Alternatives are often relevant in decision making when the preferred scheme is
held to cause some harm or has some other disadvantage. In those circumstances it
can be appropriate to consider whether the aims of the scheme could be achieved
without causing the harm complained of. This is not such a case, as there is no
9 WCCE/A15 section 3.7.12 10 WCCE/A15 section 3.7.14 11 WCCE/A15 section 3.7.16 12 WCCE/D1 table 2.1 page A-17 13 Oral explanation 14 Gardner Ap.3 APP/P3.3
4
suggestion that the proposals will cause such harm that it becomes desirable or
necessary to search for alternative means of achieving the desired objective.
23. To the extent that the scheme does cause harm, such as the less than substantial
harm to the setting of certain heritage assets, it is not suggested by any objector
that such harm could be overcome by an alternative alignment or other alternative.
24. I ask you to report to the Secretary of State that:
a. any harm is not such as to require alternatives to be considered any further.
b. there has been careful and detailed consideration of alternatives
c. there is no realistic alternative means of achieving the desirable outcomes
that the scheme will bring.
3. The extent to which the scheme would be consistent with the National Planning
Policy Framework, national transport policy, and local transport, environmental
and planning policies.
25. There is no dispute that the proposals are consistent with, and will advance the
objectives of the NPPF, national transport policy, and local transport, environmental
and planning policies.
26. All the relevant policies are identified in the evidence of Mr Ellingham. Mr Ellingham
also considers whether the scheme proposals comply with those policies. He
concludes that they do15. I do not repeat that analysis in these submissions, but I do
rely on it, and ask that you accept it.
27. Mr Young, in his representation, does allege conflict with Core Strategy policy
TRAN4 which seeks to create coherent networks for cycling and for walking.
28. There is no conflict with that policy.
a. Specific consideration has been given to impact on cyclists.
b. As explained by Mr Gardner crossing facilities have been provided allowing
cyclists to cross the tram tracks.
c. Further as demonstrated by Mr Gardner’s plan there are alternative
convenient and safe routes are available for cyclists enabling them to avoid
15 Ellingham PoE 6.58-6.59 APP/P7.1/TOW
5
using Pipers Row16. Those routes form part of the coherent network desired
by TRAN4, and provide safe, direct links for cyclists.
29. The clear conclusion that I invite you to draw is that the proposals accord fully with
the objectives of national and local transport and planning policies.
4. The adequacy of the Environmental Statement submitted with the application
for the TWA Order, having regard to the requirements of the Transport and Works
(Applications and Objections Procedure) (England and Wales) Rules 2006, and
whether the statutory procedural requirements have been complied with.
30. In considering this issue it is necessary to consider the environmental statement
(“ES”) as submitted together with the further environmental information contained
in the April 2015 Addendum17.
31. Mr Ritchie has considered whether the requirements contained in the 2006 Rules
have been complied with. He concludes that not only have the rules been complied
with but good practice has also been followed18. No other party contests Mr
Ritchie’s conclusion or makes any submission alleging a failure to comply with the
requirements.
32. I invite you, in your report, to endorse Mr Ritchie’s view.
5. The likely impact on the public, businesses and the environment of constructing and operating the scheme, including:
(a) impact of the proposed works on storage, access and servicing arrangements to premises;
(b) effect on Piper’s Row and Fryer Street car parks and the City ring road;
(c) impact on pedestrian, cycle and motor traffic during construction and
operation; and
(d) ecological impacts and whether any licences are likely to be required
16 WCCE/C2 paragraph 4.2, and Gardner Ap.2, APP/P3.3/ENG 17 WCCE/A15/6 18 Ritchie PoE 5.9 APP/P5.1/ENV
6
from Natural England.
5(a)
33. Control of road closures during construction is provided for by Article 43 of the draft
order. Article 43(2) could be relied upon to put in place temporary traffic regulation
measures – they can only be exercised with the consent of the traffic authority (the
City Council).
34. Impact of the proposed works on storage, access and servicing arrangements to
premises are considered in the transport assessment19 and by Mr Gardner in his
proof of evidence20. Specific construction impacts are considered by Mr Gardner at
paragraphs 5.13 to 5.22.
35. The inspector raised questions in relation to access to premises on Piper’s Row, in
particular access to the courts and to the Wulfrun Hotel. As explained by Mr
Adams, during construction:
a. It is proposed that alternative arrangements be made for Judges’ parking at
the Combined Court Centre.
b. It is proposed that vehicles transporting those in custody to the court will be
able to access the court from the bus station.
c. Alternative loading arrangements are available in Queen Street which allow
the Wulfrun Hotel to be serviced.
36. The access to the alleyway adjacent to the Wulfrun Hotel will not be accessible for a
limited period during the construction works. However the disadvantage to the
operation of the hotel is not great as alternative servicing is available using the
Queen Street loading bay.
37. Mr Lunt also considers transportation impact during construction (section 4) and
addresses matter 5 at his section 521.
19 WCCE/C7 section 10 20 APP/P3.1/ENG 21 APP/P4.1/TRA
7
38. The conclusion of the transport assessment is, that with the mitigation proposed,
the proposals are not considered to have an unacceptable impact on the accessing
and servicing requirements of existing operations and businesses22.
39. During operation of the tramway existing operations and businesses may be
affected by changes to traffic regulation. Those changes are made in schedule 7 to
the order; these include controlling the use of Railway Drive23 (as raised by the
inspector during the course of the inquiry). Physical measures will be put in place to
restrict the use of eastbound traffic over Railway Drive by use of rising bollards.
40. I invite you to conclude that, on the basis of the construction activities envisaged,
the changes to traffic regulation and other changes during operation, and the
assessment of those activities and changes to traffic regulation set out in the
evidence, there will be no unacceptably adverse impact.
5(b)
41. Impacts on Piper’s Row and Fryer Street car parks and on the road network are also
considered by Mr Lunt. Access to both car parks will be maintained during
construction24 and operation25.
42. Agreement has been reached with NCP in relation to the Piper’s Row car park and
the Fryer Street Car Park.
43. The Applicant has agreed not to exercise its powers in relation to the Fryer Street
Car Park (Plot 25).
44. In relation to Piper’s Row car park, the Applicant has agreed that the new car park
entrance on to Tower Street will be opened simultaneously with the closure of the
current Piper’s Row access. At the same time new signage will be provided to direct
people to the Tower Street entrance.
22 WCCE/C7 paragraph 10.4 23 Draft order Schedule 7 Part 2 Table 7 No. 7.1 24 Lunt PoE 5.4 APP/P4.1/TRA 25 Lunt PoE 5.8-5.10 and 5.11 APP/P4.1/TRA
8
45. The proposals will lead to a reduction in the number of parking spaces at the Piper’s
Row car park, however the reduction in number (15) is not significant when
compared to the approximately 3,800 parking spaces in the WV1 postcode area26.
46. The benefit to be derived by siting the northbound tramstop in Piper’s Row in such a
position as to avoid impeding right turning bus movements out of the bus station27
far outweighs any minor detriment arising as a result of the loss of 15 parking
spaces.
47. Mr Lunt considers impact on the City Ring Road during construction28 and
operation29.
48. Impact during construction will depend upon whether the Corn Hill access to the
railway station car park has been opened; this access is likely to be provided at an
advanced stage of the works, even if not already in place as a result of the WIP
project. Mr Lunt’s judgement on this issue is set out at his Table 4.130.
49. Based on the modelling report, Mr Lunt concludes that impact attributable to the
WCCE during operation is likely to be negligible31. The most appropriate
information to consider (in relation to northbound and southbound journey times)
is that in Tables 4.5 and 4.6 in Mr Lunt’s Appendix 3 as that is the product of the
average of 15 model runs.
50. On the basis of Mr Lunt’s evidence I invite you to conclude that there will be no
unacceptably detrimental impact on the Ring Road, whether during construction or
operation.
5(c)
51. Matter 5(c) is also considered by Mr Lunt. He considers impact during construction
to be acceptable32.
26 Applicant’s rebuttal to NCP paragraph 29, APP/R1/1/OBJ10 27 Gardner PoE 2.11-2.12 APP/P3.1/ENG 28 Lunt PoE 5.5, APP/P4.1/TRA 29 Lunt PoE 5.12, APP/P4.1/TRA 30 Lunt PoE page 11 APP/P4.1/TRA 31 Lunt PoE 5.12, APP/P4.1/TRA, and see Lunt Appendix 3 Tables 4.5 and 4.6 32 Lunt PoE 5.6, APP/P4.1/TRA
9
52. Mr Lunt has based his assessment during operation on the outputs of a VISSIM
micro simulation model as reported in the Transport Assessment33. The conclusion
of the traffic impact section of the TA is that the proposals are acceptable34. The
same conclusion is reached in relation to pedestrians35. The TA concludes that, with
mitigation, impact on cyclists will be negligible36.
53. During the course of the inquiry Mr Lunt explained the model outputs. It is clear
from the average delay times to all traffic37 that the delays attributable to the WCCE
(as distinct from the wider WIP project) cannot be described as unacceptable. The
reference to an average masks the fact that there will be an improvement to bus
journey times. Furthermore, even if there is some delay attributable to the WCCE it
has to be balanced against the advantages of the scheme; those advantages far
outweigh the delays identified.
5(d)
54. Matter 5(d) is considered by Mr Ritchie in his proof of evidence38. When the ES was
prepared it was not possible to gain access to the tunnel and void at the Old Steam
Mill and therefore there was some uncertainty as to whether bats were present.
That uncertainty has been resolved. A survey has been conducted, as reported in
the ES Addendum at paragraphs 1.5.4-1.5.839. It was discovered that the void space
and tunnel are not suitable for bats. As a result the prohibitions imposed by Article
12 of the Habitats Directive are not engaged and no European Protected Species
licence will be required.
55. The evidence I have referred to has not been contradicted and should be accepted. I
invite you to conclude that there will be no unacceptable impact on impact on the
public, businesses and the environment of constructing and operating the scheme.
33 Lunt PoE 5.7, APP/P4.1/TRA 34 WCCE/C7 paragraph 5.6 35 WCCE/C7 paragraph 7.2.7 36 WCCE/C7 paragraph 7.3 37 Lunt PoE Table 3.3, APP/P4.1/TRA 38 Ritchie PoE 5.10-5.15 APP/P5.1/ENV 39 WCCE/A15/6
10
6. The effects of the scheme on statutory undertakers and other utility providers,
and their ability to carry out undertakings effectively, safely and in compliance
with any statutory or contractual obligations.
56. Article 45 and schedule 8 of the draft order make provisions relating to statutory
undertakers. The standard provisions are included which enable, in relation to land
acquired under the order, statutory undertakers rights to be extinguished subject to
payment of compensation.
57. Mr Gardner considers the effects of the scheme on statutory undertakers at section
4 of his proof of evidence40. I rely upon, but do not repeat, that evidence.
58. As the majority of the construction works will take place within existing public
highways, the New Roads and Street Works Act 1991 regime applies, and the stages
set out under that regime have been and will continue to be followed.
59. Notice of the TWA order was served on all the statutory undertakers and other
utility providers and no objections were made41. It should be noted that no utility
company objected.
60. There will be no undue impact on statutory undertakers and in cases where there is
an impact, appropriate measures are in place to protect the interests of statutory
undertakers.
7. The effects of the scheme on the statutory obligations, waterway operations
and navigational management of the Canal and River Trust, and proposals to
mitigate these effects.
40 APP/P3.1/ENG 41 Gardner PoE 4.6, APP/P3.1/ENG
11
61. No significant works are anticipated to be required to the existing bridge over the
Birmingham Canal. The arch bridge over the Birmingham Canal will have its
waterproofing renewed as part of the project42.
62. Agreement has been reached with the Canal and River Trust, who have withdrawn
their objection.
63. The protective provisions which the Applicant requests are included in the order will
protect the Canal and River Trust’s interests. The protective provisions prevent the
Applicant from exercising certain powers conferred on it by the order, unless
consent is given by the Trust.
64. I invite you to report to the Secretary of State that the order contains appropriate
and adequate provisions to mitigate impact upon, and to afford protection to, the
Canal and River Trust.
8. The implications for rail users, train operators, Network Rail and businesses
located at Wolverhampton Railway Station of works to the station in connection
with the scheme (including safety, parking, staff facility, and access issues).
65. The effect on rail users, train operators, Network Rail and businesses located at
Wolverhampton Railway Station is considered in the evidence of Mr Adams43.
66. The fact that Network Rail, the station facility owner, the train operating companies,
and businesses located at the station have reached agreement with the Applicant
can and should be taken as indicating that, so long as the relevant protective
provisions are included in the order, adequate arrangements are in place to protect
those interests.
67. Any scheme to improve facilities at a railway station is likely to cause some degree
of interference with existing arrangements. As a result all works have to be carried
out with care so as to avoid unnecessary disruption to rail operators and
passengers.
68. The main protection for rail interests is that works will be undertaken in accordance
with the agreements reached with rail companies, which provide for standard
42 Gardner PoE 5.12, APP/P3.1/ENG 43 Adams PoE 10.6-10.37 APP/P1.1/SCH
12
template rail industry agreements regulated by the Office of Rail and Road (ORR) to
be entered into at a later date, and by the inclusion of protective provisions in the
TWA order. The rail companies will have the ability to exercise control so as to
ensure that the works are carried out in such a way as to avoid undue interference
with their interests. Those agreements will also ensure that passengers can access
and exit the station safely and efficiently while construction works are underway.
69. The WCCE will have no impact on operational train services44.
70. On completion of the works:
a. The new tram stop at the railway station will provide a significant benefit to
rail station accessibility and interchange45.
b. The environment for rail users accessing the station will be improved by the
changed arrangements for traffic; vehicular access will be relocated from
Railway Drive to Corn Hill46.
c. There is likely to be a positive impact on the business of West Coast Trains47.
71. I invite you to conclude that, subject to the inclusion of the proposed protective
provisions, the interests of rail users, train operators, Network Rail and businesses
located at Wolverhampton Railway Station will be adequately protected.
9. The effects of the scheme on the Old Steam Mill (though noting that listed
building consent has been sought separately and granted for this element of the
works).
72. The alignment of the proposed tramway in the vicinity of the Old Steam Mill was the
subject of careful consideration. In May 2013 consultation was undertaken on a
proposed alignment which would have required demolition of the Old Steam Mill.
English Heritage (now Historic England) and others raised objections48.
44 Adams PoE 10.26, APP/P1.1/SCH 45 Lunt PoE 3.16, APP/P4.1/TRA 46 Gardner PoE 2.22, APP/P3.1/ENG 47 Adams PoE 10.28, APP/P1.1/SCH 48 WCCE/A15/2 ES Main volume paragraph 3.7.16
13
73. In response to those objections the alignment of the tramway in the vicinity of the
Old Steam Mill was revised and the current alignment put forward. That change of
alignment was endorsed by English Heritage49.
74. Some 727 sq m of land will be taken to provide space for the new access to the
revised Network Rail car parking spaces and for the new taxi drop off and
turnaround area50.
75. The 20th century steel clad north-west corner of the Old Steam Mill will be
demolished (for which listed building consent has been obtained), and the
remainder of the building will be stabilised and made safe51.
76. The current scheme has been considered by English Heritage who have stated that
they are fully satisfied by the amendments which have been made to address their
concerns about the alignment of the extension adjacent to the Old Steam Mill and
Corn Hill52. The fact that EH now raise no objection, and have expressed their
satisfaction with the changes should be given considerable weight.
77. The heritage impacts are considered by Mr Surfleet who concludes that the
proposals will have a positive effect on the significance and setting of the Old Steam
Mill53.
78. I ask that you report Historic England’s position, and the views of Mr Surfleet to the
Secretary of State and that you conclude that the impact on the Old Steam Mill will
be positive.
10. The measures proposed by Centro for mitigating any adverse impacts of the
scheme, including:
(a) the proposed Code of Construction Practice;
(b) any measures to avoid, reduce or remedy any major or significant adverse
environmental impacts of the scheme; and
49 WCCE/A15/2 ES Main volume paragraph 3.7.17 50 Gardner PoE 7.6, APP/P3.1/ENG 51 Gardner PoE 7.6, APP/P3.1/ENG 52 WCCE/A16 53 Surfleet PoE 8.1(6) APP/P6.1/CUL
14
(c) whether, and if so, to what extent, any adverse environmental impact would
still remain after the proposed mitigation.
79. A draft Code of Construction Practice has been prepared54, and the imposition of
condition 6 would ensure that a code in substantial accordance with the draft is
adhered to.
80. Mr Gardner describes the construction process in section 5 of his proof of evidence.
81. The measures to avoid, reduce or remedy environmental impacts of the scheme and
an analysis of the residual effects are described in the environmental statement in
each of the specialist chapters. The mitigation measures are summarised in chapter
16 of the ES. The proposed mitigation measures are also identified and described,
and an assessment of the significance of any residual effect provided, in Mr Ritchie’s
table at his Appendix 255.
82. The conclusions to be drawn are that:
a. A range of appropriate mitigation measures are proposed, and where
appropriate will be secured by the conditions proposed or by the terms of
the order.
b. The residual effects are, in the main neutral, negligible or beneficial.
c. Where residual effects are adverse, they are slight or minor save in the case
of views during construction activity56, and in relation to construction noise
and vibration which will be short term and can be regulated by the code of
construction practice.
d. The environmental effects are acceptable.
11. Whether there is a compelling case in the public interest for conferring on
Centro powers compulsorily to acquire and use land for the purposes of the
scheme, having regard to the guidance on the making of compulsory purchase
54 WCCE/A15/3 55 APP/P5.3/ENV 56 Major adverse effect on the view from Wolverhampton Railway Station is identified during construction in
scenario B, Ritchie Ap.2 page 55 of APP/P5.3/ENV, and Item 9 in Table 16.4 of the ES WCCE/A15/2
15
orders in ODPM Circular 06/2004, paragraphs 16 to 23; and whether the land and
rights in land for which compulsory acquisition powers are sought are required by
Centro in order to secure satisfactory implementation of the scheme.
83. The need for the scheme is established in Mr Adams’ evidence.
84. For the reasons set out above there are no realistic alternatives.
85. Mr Adams also identifies the transport benefits57 and the regeneration benefits58.
86. The scheme is an integral part of the WIP, which is predicted to deliver commercial
development which will result in the provision of over 1,500 jobs59.
87. The economic case is established by Mr Chadwick. The Benefit Cost Ratio of 2.5:1
demonstrates that the scheme is high value for money60. Although such a BCR is
simply stated it is the product of detailed analysis, and clearly establishes the
economic benefits of the proposals. Those economic benefits cannot be secured
unless the order is made.
88. Mr Gardner produces a schedule in which he identifies each plot of land and
explains the purpose for which it is to be acquired or used61. It is clear from Mr
Gardner’s schedule that each plot of land is required in order to carry the scheme
into effect.
89. The disadvantages of the scheme (e.g. some less than substantial harm to the
significance of heritage assets as a result of impact on setting), such as they are, are
minor (although that less than substantial harm should be given considerable
weight and importance when considering whether to direct that planning
permission be deemed to be granted62).
90. The very significant economic, transport, and regeneration benefits cannot be
secured unless the order is made and compulsory acquisition of land and rights is
authorised. Those benefits far outweigh any negative impact.
57 Adams PoE 6.4-6.13 APP/P1.1/SCH 58 Adams PoE 6.14-6.16 APP/P1.1/SCH 59 Adams PoE 6.14-6.15 APP/P1.1/SCH 60 Chadwick PoE 2.52 APP/P2.1/ECO 61 Gardner Ap.4, APP/P3.3/ENG 62 Surfleet Ap. 5 Barnwell Manor v. East Northamptonshire [2014] EWCA Civ 137 at paragraph 29,
APP/P6.3/CUL
16
91. To the extent that the rights afforded by Article 1 Protocol 1 of the European
Convention on Human Rights are engaged, the deprivation of possessions is clearly
justified in the public interest, and I invite you to so find in making your report.
92. There is a compelling case in the public interest for the order to authorise the
promoter to acquire the necessary land and rights and to use land temporarily,
without such authorisation the very many benefits will not be realised in the public
interest.
12. Having regard to section 25 of the TWA, whether the relevant Crown authority
has agreed to the compulsory acquisition of interests in, and/or the application of
provisions in the TWA Order in relation to, the Crown Land identified in the book
of reference.
93. I repeat the submissions made in opening.
94. The Wolverhampton Combined Courts Centre is land held by the Ministry of Justice
(“MoJ”) and is land in which there is a Crown interest for the purposes of section 25
of the Transport and Works Act 1992 (“TWA”). The Crown land can be acquired
compulsorily under a TWA order if the appropriate authority agrees. In this case the
appropriate authority is the MoJ who are the government department having
management of the land.
95. The MoJ, through their solicitors63, have indicated that whilst a legal agreement has
not yet been entered into the MoJ have agreed in principle to the acquisition of
those parts of the Crown land which will form new public highway. The MoJ have
also indicated that they agree in principle to measures to mitigate impact during
construction. The applicant requests that, when making your recommendations to
the Secretary of State, you proceed on the basis that, in due course, the agreement
which has been given in principle, will result in formal agreement.
63 Letter from Michelmores to the programme officer dated 27th May 2015
17
13. Centro’s proposals for funding the scheme.
96. As required64 the application was accompanied by an estimate of the costs of the
works65 and a funding statement66.
97. The total outturn cost of the Wolverhampton Interchange Project is stated to be
£39.4m, which includes the £18m67 cost of the WCCE.
98. The approach to capital funding is set out in the Financial Case section of the
business case and the funding position is as follows68:
LTB Major Schemes (BCLEP) £9m
ITB £3m
BCLEP (SEP) £4.5m
Wolverhampton City Council £1m
Prudential Borrowing £21.9m
-----------
Total £39.4m
99. As the expenditure on the WCCE is planned to fall towards the end of the overall
construction programme for the WIP it is likely that the majority of its funding will
come from the prudential borrowing funding stream.
100. It is anticipated that Centro will use the income derived from the station car
park to finance the loan repayments.
101. When Mr Adams wrote his proof of evidence, the arrangements necessary to
allow the car parking income to fund the borrowing were still dependent upon the
Secretary of State giving his agreement. On 29th May 201569 the Secretary of State
64 Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006, Rule
10(3)(b)(ii) –estimate of costs. Rule 10(3)(a) proposals for funding 65 WCCE/A5 66WCCE/A6 67 Adams PoE APP/P1.1/SCH Table 7.1 68 Adams PoE APP/P1.1/SCH Table 7.2 69 Appendix 1 to Peter Adams’ Supplementary Proof of Evidence APP/P1.4/SCH
18
confirmed his support of the arrangements proposed. The Secretary of State’s
support for that agreement provides significant additional grounds for concluding
that the funding streams relied upon are likely to deliver the necessary funds to
ensure that the scheme proceeds.
102. No objector has sought to question the fact that funding will be forthcoming
to allow the scheme to be delivered.
14. The conditions proposed to be attached to the deemed planning permission
for the scheme, if given, and in particular whether those conditions satisfy the six
tests referred to in Planning Practice Guidance, Use of Conditions (Section ID:21a).
103. The proposed planning conditions are those set out in Mr Ellingham’s
evidence70 (with amendments discussed at the inquiry) and accord with established
TWA precedent.
104. The relevant policy test for use of conditions is that set out at paragraph 206
of the NPPF, namely that conditions should be necessary, relevant to planning and
to the development to be permitted, enforceable, precise and reasonable in other
respects.
105. Both the City Council and Mr Ellingham conclude that the relevant policy
tests are met71.
15. Any other relevant matters which may be raised at the inquiry.
106. Mr Young has raised concerns about the impact of the scheme on cyclists.
The Applicant has provided a written response to Mr Young’s points72.
70 APP/P7.3/TOW Appendix 1 71 Ellingham PoE 6.83 APP/P7.1/TOW 72 APP/GEN7
19
107. Mr Gardner has produced a plan which shows two alternative routes for
cyclists73.
108. In their letter of support74 Wolverhampton City Council expressed the view
that: “At this stage, Centro, in partnership with Wolverhampton City Council (WCC),
have done everything reasonable to accommodate cyclist’s needs within the WCCE
proposals……”
109. I invite you to endorse the comment made by the City Council and to find
that Mr Young’s criticisms, whether in relation to alleged lack of information or
failure to make adequate provision for cyclists are wholly unjustified.
Conclusions
110. There is no serious challenge to the Applicant’s case75 (supported by the
evidence of the witnesses including Mr Ellingham76) that the WCCE will deliver the
following key benefits:
a. Improved integration between Metro, bus and rail modes providing new and
improved journeys for the travelling public.
b. Encouraging modal shift from private to public transport.
c. Enhancing railway station accessibility.
d. Providing a connection between the bus station and the railway station and
to all areas along the Metro line 1 route.
e. Facilitating access to HS2 in the future via line 1 and the proposed Metro
Birmingham Eastside Extension to Curzon Street Station.
f. Improving access to investment opportunities in the Black Country and more
widely in the West Midlands region.
g. Encouraging and facilitating the regeneration of land either side of Railway
Drive and the rail station as part of the WIP leading to the provision of over
73 Gardner Ap.2 APP/P3.1/ENG 74 quoted and repeated in SUPP/1/GEN6 75 Centro Statement of Case paragraph 14.1 76 Ellingham PoE 4.24 and 4.34 APP/P7.1/TOW
20
1,500 jobs and the provision of mixed leisure and commercial facilities for
Wolverhampton.
111. The WCCE is deliverable, there is no challenge to the feasibility of introducing
it, and funds are in place.
112. This scheme will deliver very significant benefits to Wolverhampton without
causing any unduly adverse impacts. I urge you to recommend to the Secretary of
State that he should make the order with the modifications put forward and give
the associated planning direction.
Landmark Chambers, Neil Cameron QC
180, Fleet Street,
London EC4A 2HG 9th June 2015