the mang’onyi gold mining project singida ... gold...mr. idd mhina & mr. frank nnongi 5 | page...

60
THE MANG’ONYI GOLD MINING PROJECT SINGIDA REGION ENVIRONMENTAL IMPACT STATEMENT AND ENVIRONMENTAL MANAGEMENT & SOCIAL MONITORING PLAN (EM&SMP) PROPONENTS MR. IDD L. MHINA & MR. FRANK NNONGI Submitted to the Ministry for Energy and Minerals, With an Application for Mining Licence February, 2007 Prepared by: EGES Company (T) Limited, PO Box 72220, Dar es Salaam, TANZANIA

Upload: others

Post on 17-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

THE MANG’ONYI GOLD MINING PROJECT 

SINGIDA REGION 

 

ENVIRONMENTAL IMPACT STATEMENT 

AND  

ENVIRONMENTAL MANAGEMENT & SOCIAL MONITORING PLAN  

(EM&SMP) 

 

PROPONENTS 

 

MR. IDD L. MHINA & MR. FRANK NNONGI  

 

Submitted to the Ministry for Energy and Minerals, 

With an Application for Mining Licence 

 

 

February, 2007 

Prepared by: 

EGES Company (T) Limited, PO Box 72220, Dar es Salaam, TANZANIA  

Page 2: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

1 | P a g e     o f   E I S   a n d   E M & S P    

 

TABLE OF CONTENTS 

 1.  INTRODUCTION ................................................................................................ 4 

1.1.  Background of the Project .................................................................................................. 4 1.2.  Objective of the Report ...................................................................................................... 5 

2.  PROJECT DESCRIPTION ................................................................................... 6 2.1.  Location............................................................................................................................... 6 2.2.  Topography ......................................................................................................................... 7 2.3.  Exploration History ............................................................................................................. 8 2.4.  Geology of the Area ............................................................................................................ 8 2.5.  Project Life Span ............................................................................................................... 13 2.6.  Proposed Mining Equipment ............................................................................................ 13 2.7.  Mining Methods ................................................................................................................ 13 

3.  POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ................................... 17 3.1.  Overview ........................................................................................................................... 17 3.2.  National Policies ................................................................................................................ 17 3.3.  Legal Framework ............................................................................................................... 19 3.4.  Administrative Framework ............................................................................................... 21 

4.  BASELINE OR EXISTING CONDITIONS ........................................................... 23 4.1.  Physical Environment ........................................................................................................ 23 4.2.  Flora and Fauna ................................................................................................................ 24 4.3.  Social and Economic Environment .................................................................................... 24 

5.  ASSESSMENT OF IMPACTS AND IDENTIFICATION OF ALTERNATIVES ......... 30 5.1.  Impact Identification ......................................................................................................... 30 5.2.  Physical Impacts ................................................................................................................ 30 5.3.  Social‐Economic Impacts .................................................................................................. 32 5.4.  Evaluation of Alternatives ................................................................................................. 34 5.5.  Detailed Potential Environmental and Socio‐Economic Impacts ..................................... 36 5.6.  Environmental Impact Ratings for the Project ................................................................. 41 

6.  MITIGATION OF IMPACTS ............................................................................... 42 6.1  Mitigation of Physical Environmental Impacts ................................................................. 42 6.2  Mitigation of Socio‐Economic Impacts ............................................................................. 45 6.3  Measures to Mitigate Environmental and Socio‐Economic Impacts ................................ 46 

7  ENVIRONMENT AND SOCIAL MANAGEMENT PLAN ........................................ 50 7.1   Monitoring Activities ........................................................................................................ 50 7.2  Resource Evaluation/ Cost Benefit Analysis ..................................................................... 50 7.3   Decommissioning .............................................................................................................. 51 7.4  Detailed Summary of the Environmental Management Plan ........................................... 52 7.5  Detailed Social Monitoring Plan (SMP) ............................................................................. 57 

8  CONCLUSION AND RECOMMENDATIONS ...................................................... 58 8.1  Conclusion ......................................................................................................................... 58 8.2  Recommendations ............................................................................................................ 58 

BIBLIOGRAPHY .................................................................................................... 59 

 

Page 3: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

2 | P a g e     o f   E I S   a n d   E M & S P    

 

TABLES

Table 2.1: Location Co‐ordinates of Applied Area ......................................................................... 6 

Table 2.2: Equipments and Machinery to be Procured ............................................................... 13 

Table 5.1: Source of Fugitive Dust and Smoke ............................................................................. 31 

Table 5.2: Potential Impacts of the Project ................................................................................. 36 

Table 5.3: Impact Rating of the Project ....................................................................................... 41 

Table 6.1: Mitigation Measures ................................................................................................... 46 

Table 7.1: Environmental Management Plan (EMP) ................................................................... 52 

Table 7.2: Social monitoring Plan (SMP) ...................................................................................... 57 

Page 4: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

3 | P a g e     o f   E I S   a n d   E M & S P    

 

PLATES AND FIGURES

Plate 2.1: Topographic view of Mining Licence Applied Area (Google Earth) ................................. 6 Plate 2.2: Typical Topography of the Mining Licence Applied Area ................................................ 7 Plate 2.3: Typical Topography with Exploration Pits in the Applied Area ....................................... 7 Plate 2.4: Gold Searching Using Metal Detector. Small Scale Mining Effects ................................. 8 Plate 2.5: Typical Bulldozer ........................................................................................................... 14 Figure 2.1: Different Ways of Doing Gold Concentration ............................................................. 15 Figure 2.2: Schematic Drawing of gold Process Plant ................................................................... 16 

 

Page 5: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

4 | P a g e     o f   E I S   a n d   E M & S P    

 

1. INTRODUCTION 

The area applied for mining  licence has been  licensed to Mr. Idd L. Mhina & Mr. Frank 

Nnongi  of  P.O.  Box  1513  SINGIDA  ‐  TANZANIA.  The  proponents  were  granted  several 

primary mining  licences  covering a  total  surface area of about 146 hectares; and  located 

near Mang’onyi  village  in  the  Singida  region.  Following  various  studies  and  discoveries 

within  these  primary mining  licences,  the  proponents  intends  to  convert  these  primary 

mining licences into mining licences in order to be able to carry out mining and processing 

of gold ore efficiently and effectively. 

Obtaining a mining licence requires that the applicant fulfil specific conditions under the 

various  statutes;  particularly  the mining  law  and  the  environment  laws,  and  that  their 

application be accompanied by certain documents. Among the documents the applicant  is 

required  to  attach  is  the  Environmental  Impact  Statement  and  Management  Plan  in 

accordance with the Mining Act of 1998 and Mining Regulations of 1999. 

This  report  therefore  is  part  of  the  requirements  that  the  applicant  has  prepared  to 

meet conditions required by the Mining Act of 1998 and also meets the requirement of the 

Environmental Management Act, of 2004. The statement covers issues ranging from project 

background,  existing  environmental  conditions  through  to  environment  and  social 

management  plans,  in  accordance  with  Environmental  Management  Regulations  and 

Guidelines. 

1.1. Background of the Project 

The project proponents  started gold mining activities on  their primary mining  licence 

early  in 2007. The mining operation took place under sixteen primary mining  licences (16 

PMLs) issued by the ministry of Energy and Minerals, the licensing authority. 

The PMLs  issued were Nos. 0008581  to 0008594 and 0010376  to 0010377 covering a 

total of 146 hectares equivalent to 1.46 square kilometres. Due to  limited security that  is 

offered by owning primary mining licence, the fact that the area has huge potential to be 

mined at  larger scale operation and from the fact there  is a possibility of  importing  large 

machinery hence the need for long term licence tenure; the partnership opted to convert 

these primary licences into mining licences (ML).  

This move ensured that the partnership could enjoy entering into joint venture with any 

other entity regardless of its nationality. It also meant that they can secure more funds and 

get loans easily. 

Page 6: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

5 | P a g e     o f   E I S   a n d   E M & S P    

 

During  the course of  initial mining operation,  the proponent discovered  that  the area 

might offer more  resources  than anticipated earlier after  finding out  that  there might be 

gold bearing zones within the area. These  findings prompted  the proponent to reconsider 

and  instead of mining  the area under primary mining  licenses,  they now opted to convert 

them into a mining licence (ML). This option is in agreement with the prevailing mining law; 

the Mining Act of 1998 and its regulation of 1999. 

1.2. Objective of the Report 

This report is prepared for presentation to the Ministry of Energy and Minerals (MEM), 

as one of the requirements of issuance of a Mining Licence in order to allow the proponents 

undertake mining operations  in  the area  they own at a  larger  scale. Therefore,  the main 

objective of the report is to identify current and future environmental issues, their impacts 

and  how  they  can  be mitigated  in  relation  to  intended mining  activities  in  the Mining 

Licence being sought by the Proponent.  

Some of the specific objectives are:‐ 

To identify sensitive areas that might be affected by the proposed mining activities; 

To identify socio – economic issues related to the project through consultation with 

the surrounding communities; 

To identify and analyse potential impacts of the undertaking; and 

To propose appropriate mitigation measures based on collected data/ information. 

 

Page 7: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

6 | P a g e     o f   E I S   a n d   E M & S P    

 

2. PROJECT DESCRIPTION  

2.1. Location  

The area for which the mining licence is being sought is near Mang’onyi Village, South‐East of  Singida  Town,  the Administrative Headquarters  for  Singida Region. Currently,  the proponents holds a total of sixteen  (16) primary mining  licenses over the area granted on 5thth April 2007, pursuant to the Mining Act, 1998. 

The  area  is  defined  by  lines  of  latitude  and  longitude  having  the  corner  coordinates shown below. The current PMLs cover an area of approximately 146 hectares.  

Table 2.1: Location Co­ordinates of Applied Area 

Corner  Latitudes (S) Longitudes (E)

A  05º 15′ 00.00″ 35º 00′ 00.00″B  05º 15′ 00.00″ 35º 01′ 21.20″C  05º 15′ 05.73″ 35º 01′ 21.27″D  05º 15′ 06.21″ 35º 00′ 48.72″E  05º 15′ 12.86″ 35º 00′ 48.73″F  05º 15′ 12.77″ 35º 00′ 25.40″G  05º 15′ 19.35″ 35º 00′ 25.40″H  05º 15′ 19.20″ 35º 00′ 48.64″I  05º 15′ 25.81″ 35º 00′ 48.63″J  05º 15′ 25.82″ 35º 00′ 40.43″K  05º 15′ 32.45″ 35º 00′ 40.51″L  05º 15′ 32.41″ 35º 00′ 00.00″

. The coordinates are located on Topographic sheets 123/3 and the location of the licence is shown in map below. 

 Plate 2.1: Topographic view of Mining Licence Applied Area (Google Earth) 

Page 8: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

7 | P a g e     o f   E I S   a n d   E M & S P    

 

To reach the area from Singida a road on the northern‐east of the licences can be used, which is passable throughout the year. 

2.2. Topography  

The project area is dominated by flat plains which are spacious populated with trees and shrubs. The general topography of the area can be seen on plate 2.2 and plate 2.3 below. 

 

Plate 2.2: Typical Topography of the Mining Licence Applied Area 

 

 

Plate 2.3: Typical Topography with Exploration Pits in the Applied Area 

 

Page 9: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

8 | P a g e     o f   E I S   a n d   E M & S P    

 

2.3. Exploration History  

The project area consists of various small scale mining operations that has commenced for the past three to four years. There are some primary mining licences held by small scale miners in addition to other prospecting licences owned by various companies that surround this applies area.  

Artisanal miners have been mining gold in the area since late nineteen nineties. Various means of searching for minerals, particularly gold have been used as depicted on Plate 2.4, below where metal detector is used. 

 

Plate 2.4: Gold Searching Using Metal Detector. Small Scale Mining Effects 

Intensive  and  systematic  exploration  activities  were  carried  out  immediately  after acquiring  the  Primary  Mining  Licence.  Mineral  exploration  activities  are  still  being undertaken in other areas surrounding the project area.  

2.4. Geology of the Area 

The  Archaean  crystalline  rocks  outcropping  in  the  area  represent  an  extension 

westwards of the synorogenic granitic rocks mapped on the adjacent quarter degree sheet 

124,  Kelema.  These  rocks  are  quite  extensively  covered  by  superficial  deposits,  mainly 

residual sandy soils and "mbuga" deposits. In the south‐west, the Precambrian rocks are 

almost entirely obscured by  the Kilimatinde "Cement" which attains a  thickness of over 30 

metres. The crystalline rocks are cut by north‐easterly‐striking dolerite dykes and two small 

kimberlite pipes have so far been found in them. 

Page 10: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

9 | P a g e     o f   E I S   a n d   E M & S P    

 

The  hill  country  lying  between  Kwa  Mtoro  and  Sanzawa,  the  Kwa  Mtoro  block,  is 

demarcated along the south‐west by the north‐westerly‐striking Sanzawa boundary fault.  In 

the south‐east of the sheet, the rocks are affected by the north‐easterly‐striking Bubu fault; 

and  in  the west of  the area by  the generally northerly‐striking Mpondi  fault;  the  last  two 

faults  form  part  of  the  Gregory  Rift  system.  Structurally‐controlled  helium‐bearing  hot 

springs occur at four localities, three in the west of the area and one on the south‐east. 

2.4.1  Archaean. 

Synorogenic  granitic  rocks  outcrop  over  most  of  the  area.  They  are  dominantly 

migmatitic  granites,  but  adamellitic,  granodioritic  and microgranitic  varieties  also  occur. 

Variation between the types is frequent and apparently haphazard, and differences have 

been  indicated on  the map by  symbols only. Cataclasites derived  from  these  rocks  form 

linear zones  striking approximately 300° and with similarly‐striking  shear  zones where  the 

granite is granulated, they form a conspicuous geological feature bounding the Kwa Mtoro 

block to the north; this direction is parallel to a coarse foliation observed in the un‐sheared 

granitic rocks. 

The  typical  synorogenic  granite  is  often  porphyroblastic,  and  either  altered  sodic 

plagioclase  or  fresh microcline,  or  both, may  form  the  porphyroblasts.  These  larger 

crystals  are  surrounded  by  a  finer‐grained mosaic  of microcline,  sodic  plagioclase  and 

quartz.  Biotite  and  epidote  occur  interstitially  as  the  chief mafic  constituents,  the  latter 

frequently replacing the plagioclase. Biotite is often altering to chlorite. Fine grains of iron‐

ore  are  often  disseminated  throughout  the  rock.  Allanite  and  sphene  occur  as minor 

accessories.  Not  uncommon  are  rounded  remnants  of  twinned  plagioclase  within 

developing porphyroblasts of microcline perthite. All  types of  replacement  textures are 

encountered, and  in  the majority of  rocks examined microcline and quartz appear  to be 

replacing  previous  minerals.  Sericitization  of  the  sodic  feldspar  is  common.  Xeijoliths, 

skialiths,  dark  streaks  and  irregular  basic  patches  occur  throughout  the  synorogenic 

migmatitic  granite,  but  are  particularly  common  in  the  north‐west  of  the  area.  In  the 

north‐east corner of the sheet, granulated synorogenic granitic rocks represent the extension 

westwards of  the Bubu Cataclasites which  in  the Kelema area  (sheet 124) mark  the  thrust‐

zone  boundary  between  the metasediments  of  the  Kelema  Group  and  the  synorogenic 

granite. 

Migmatitic biotite and hornblende gneisses occur as small patches  in the granite. These 

are considered to be remnant patches of host rocks which were not completely assimilated 

during the formation of the granite. Outcrops of this gneiss large enough to be represented 

on the map were found only in the north‐west of the area. 

Page 11: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

10 | P a g e     o f   E I S   a n d   E M & S P    

 

A  belt of migmatite with  hornblende‐rich  and  trondhjemite bands  is  indicated  to  the 

south‐west  of  the  Sanzawa  boundary  fault.  The  relationship  with  the  granite  is  not 

certain. The northern boundary is obscured by superficial deposits and that in the south‐

west by  the Kilimatinde  "Cement"  as well  as by pegmatitic  injections which have broken 

through the banded migmatites along their contact with the granite. 

The best outcrop of the migmatites is found in a river exposure south of Sanzawa. Here, 

the main rock‐type is a banded migmatitic gneiss in which the hornblende‐rich and quartzo‐

feldspathic  bands  vary  from  a  few  inches  to  many  yards  in  thickness.  The  leucocratic 

trondhjemitic  bands  consist  of  quartz  and  oligoclase  with  subordinate  hornblende  and 

sphene.  The  orientation  of  the  quartz  and  hornblende  defines  the  foliation.  The  sodic 

feldspar is often altered to sericite and epidote and in places replacement by epidote is so 

great that epidotites are formed. The hornblendic bands contain up to 80 per cent, of blue‐

green hornblende, with oligoclase, quartz and  the usual accessory minerals and alteration 

products. Amphibolites and biotite gneisses occur infrequently. 

To the north the rocks are sheared and a band of mylonitic augen‐gneiss (ya) represents 

the sheared junction of the granite with the banded migmatites. The Sanzawa fault would 

appear to follow this structural zone along most of its length. 

Other outcrops  in  this belt of banded migmatites between  the  Sanzawa  fault  and  the 

Mpondi Rift  fault  are obscured by  the  "Cement"  except where  this has been  eroded  away 

along  the Mpondi  River  and  on  the  fault‐scarp west  of  Sambaru.  Coarse mica  gneisses, 

sheared basic rocks and garnetiferous gneisses in the Mpondi River valley are included within 

the  same  group of migmatites.  These have been  altered  somewhat by  later mica‐bearing 

pegmatites and gneissose quartzo‐feldspathic segregations which have been intruded in the 

Isanga,  Maganzase  and  Msangasugh  areas.  The  pegmatites  are  thought  to‐  have  been 

emplaced  along  another  shear  zone which marks  the  junction  of  the migmatites with  the 

granite in the south‐west. Fine‐grained basic Cataclasites and phyllonites outcropping on the 

fault‐scarp  west  of  Sambaru  are  thought  to  be  the  sheared  equivalents  of  the  banded 

migmatites. 

Cataclasites also outcrop  south of  Sambaru, mylonite at  Sambaru and eataclasites and 

sheared vein quartz on Mzale Hill north of Sambaru. 

There  are  few metamorphosed  igneous  rocks. A  variolitic metadolerite  outcrops  three 

miles  and  a  half  north  of  Mzale  Hill  and  further  to  the  north‐west  an  interesting 

metamorphosed porphyritic dolerite  (now a  '‐porphyritic" amphibolite) outcrops on  the 

Mpondi fault‐scarp. This latter rock is quite unique in Tanganyika. Chlorite‐tremolite schists 

which outcrop seven miles west of Kwa Mtoro represent a small metamorphosed ultrabasic 

intrusion. Neogene.—The  Kilimatinde  "Cement"  is  dominantly  a  silcrete,  but  small  areas 

Page 12: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

11 | P a g e     o f   E I S   a n d   E M & S P    

 

and pockets of calcrete and ferricrete occur. On the Mpondi fault‐scarp and in the banks of 

the Mpondi River  in the vicinity of  Isanga, where the "Cement" has been eroded to expose 

Precambrian rocks, the deposit is between 15 and 30 metres thick. 

The Kilimatinde "Cement" shows considerable variation  in  lithology from place to place 

depending  on  its mode  of  formation  and  if  is  considered  that  alluvial  fans,  sandy  river 

alluvium, shallow lake deposits and colluvial material have all contributed to its origin. 

The "Cement" was formed  in a shallow basin developed on a nearby planed land surface 

with residual hills. The larger of these inselbergs were not completely buried by the deposit 

and now protrude through the "Cement"; a good example is Kilinga Hill in the south‐west of 

the area. It is suggested that the Sanzawa fault‐scarp acted as a barrier on the north of the 

basin of deposition, thus limiting the northerly extent of the Kilimatinde "Cement". If this is 

so, then the Sanzawa boundary fault is pre‐"Cement" in age, and initial erosion of the fault‐

scarp may well have supplied an amount of material for the deposit. 

Perhaps the most common rock‐type is silicified sandstone. Sub‐angular to sub‐rounded 

quartz grains are  contained  in an opaline matrix. This  siliceous matrix appears  to have 

increased  its  growth  at  the  expense  of  the  original  quartz  grains,  for  where  it  is  well 

developed  the quartz grains are more  rounded,  fewer  in number  and  show  replacement 

borders  with  the  matrix.  Only  rarely  does  the  sandstone  contain  feldspar  grains. 

Conglomeratic horizons are quite common. 

Another common rock‐type  found  in  the Kilimatinde "Cement"  is an unsorted colluvial 

arkose; unlike the sandstone, this has suffered  little transportation. Angular to sub‐angular 

grains and rock fragments of quartz, microcline and altered oligoclase occur in a fine‐grained 

matrix of quartz and clay material which has been silicified in part. This matrix may be well‐

developed or almost non‐existent. Heavy mineral separations on this type of silcrete showed 

grains of magnetite, ilmenite, mica, pyrite, zircon, tourmaline, chlorite, monazite and barite. 

In  the  Bahi  depression,  thirty miles  to  the  south  of  the  sheet,  75 metre  of  lake  beds 

provisionally  referred  to  Plio‐Pleistocene,  overlie  the  Kilimatinde  "Cement"  which might 

therefore extend down to early Pliocene or Miocene. 

2.4.2  Structure. 

The main morphological  features of  the country are defined by  faulting. Some of  the 

faults are Plio‐Pleistocene (Rift) in age and others are older, but there has almost certainly 

been subsequent movement along some of the older faults during the Plio‐Pleistocene rifting. 

Page 13: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

12 | P a g e     o f   E I S   a n d   E M & S P    

 

The  southern  boundary  of  the  Kwa Mtoro  block  is  determined  by  the  northwesterly‐

trending Sanzawa fault which has itself apparently followed a Precambrian structural zone. 

The  trace of  this  fault  is  to  a  large  extent  concealed beneath  superficial deposits. The 

block  is  broken  into  segments  by  numerous  north‐easterly‐striking  fractures which were 

probably initiated at the same time as the Sanzawa fault. Associated with the fractures are 

parallel‐striking dolerite dykes which are particularly well‐developed  in  the Toncolo area, 

one  olivine‐dolerite  striking  for  eleven  miles.  The  north‐easterly‐striking  structures 

control  the drainage of  the Kwa Mtoro block; all  the primary  tributaries of  the Bubu 

and Mpondi rivers follow these lines. In the north‐west, the block is terminated by a fault 

zone which runs to the east of, and parallel to, the Mpondi rift‐fault. It is considered that 

these  faults were  also  initiated  at  the  same  time  as  the  Sanzawa  fault and  that  further 

movement occurred along this zone during the rifting when these faults probably acted as 

antithetic fractures to the Mpondi rift‐fault. Two of the helium‐bearing hot spring localities 

are situated on this line. 

The Kwa Mtoro block extends to the east, beyond the area, into the Chenene Hills. The 

northern termination of the block is an erosion feature marking the well‐defined shear zones 

which  occur  in  the  granite  to  the  north  and west  of  Kwa Mtoro.  The  wide  valley  now 

occupied by the Basua stream to the north of this erosion feature is thought to have been 

formed by the Mpondi River prior to the deflection of  its course southwards as a result of 

block‐tilting during the Plio‐Pleistocene rift‐faulting. The Mpondi River may originally have 

flowed to the south‐east as a tributary of the Bubu‐Kinyasungwe drainage system. 

The  Mpondi  and  Bubu  Plio‐Pleistocene  rift‐faults  strike  approximately  parallel  in  a 

north‐easterly direction in the south of the area. The Bubu Fault continues to the north‐

east following the old fracture direction of the Kwa Mtoro block. To the east of Kilinga Hill, 

the Mpondi Fault assumes a north‐north‐westerly direction, apparently  following  the  line of 

the  shear  zone  at  the  junction of  the  granite  and  the banded migmatites.  Further  to  the 

north,  cross‐fractures  in  the  fault‐system  follow  the  old  north‐easterly‐striking  structural 

pattern. 

2.4.3  Economic Geology. 

The mica‐bearing  pegmatites  at Maganzase were  investigated  by  the  Geological  Survey 

Division, but were  found  to be of  a  low  grade with only  few pockets  of  good‐quality mica. 

Kimberlites so far recorded do not apparently carry diamonds; other pipes may occur beneath 

the Kilimatinde "Cement". 

The hot springs at Minyere (Manyeghi) have recently been  investigated as a source of 

helium by  the Geological  Survey Division, but  it would not  appear  that  the  flow of helium 

Page 14: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

13 | P a g e     o f   E I S   a n d   E M & S P    

 

could  be  increased  to make  an  economic  proposition. Other  similar  helium‐bearing  springs 

occur at Takwa, Sambaru and Conga. 

2.5. Project Life Span 

Based  on  preliminary  exploration  results  in  the  licence  area,  it  is  expected  that  a medium scale mine capable of processing a maximum of 250 tonnes per day of gold bearing ore will be initially installed. Basing on this and the requirement of the law, the licence will be sought for an initial period of 10 years. This is based on the proposed mining operations and equipment that will be employed.  

The  size  of  the  licence will  be  approximately  1.5  square  kilometres; well  below  the maximum permissible size of ten (10) square kilometres. 

2.6. Proposed Mining Equipment  

The company has started preparations  to acquire mining equipment  in anticipation of granting of the applied mining licences. 

Table 2.2: Equipments and Machinery to be Procured 

No.  Item   Quantity 

1.  Backhoe  1 

2.  Excavator   1 

3.  Bulldozer   1 

4.  Compressors   2 

5.  Dumpers 20t  2 

6.  Drilling machines 2 

7.  Wheel Loaders  2 

8.  Water Pumps  2 

9.  4 Wheel drive P/ ups  2 

10.  Generators  2 

11.  Workshop Equipments  Various 

12.  Welding machine  1 

13.  Drilling rods   Various 

14.  Mineral Processing Plant Unit 

2.7. Mining Methods 

The mining method used to extract a particular mineral deposit depends on the type of deposit and the economics  involved with extraction. When the deposit occurs  in veins or beds  that extend deep  into  the Earth's crust or when  the overburden  (overlying soil and 

Page 15: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

14 | P a g e     o f   E I S   a n d   E M & S P    

 

rocks)  is very thick, underground mining methods are required. When the deposit  is near the surface, surface mining methods such as open pit or quarrying may be most efficient. 

Surface mining methods are commonly used for mineral resources that are close to the surface, low in quality, and large in quantity. Even though the mineral resource is near the surface, however,  the overburden must be  removed before  the mineral  resource can be extracted. Bulldozers and power shovels are used to remove the overburden and to mine the  mineral  resource.  Some  mineral  resources  that  are  mined  using  surface  methods include  coal,  gold,  iron,  gypsum,  and  copper.  Special  surface mining methods  used  for specific conditions include open pit mining and strip mining, which involve the same basic methods  and  equipment.  While  quarrying  and  placer  mining  are  also  surface  mining methods, they use significantly different methods and equipment as discussed below. 

For this project as outlines earlier, the deposit occurs as both alluvial and primary veins. Initially, therefore the project proponents intend to use open‐pit mining method down to a depth of about 30 to 50 metres for both the alluvial and primary oxidised veins. Thereafter, evaluation will  be made  to  assess  the  existing  reserves  and  evaluate  alternative mining methods.  

2.7.1 Mining operation 

Bulldozer will be used  to  strip  the  top  soil  to clear  the ground  to  remove  shrubs and bushes. Thereafter, the top soil (humus layer) will be carefully stripped and stockpiled at a designated  place  for  later  usage  in  rehabilitation.  The  rest  of  the  overburden  will  be excavated using excavator up to a depth of between4‐6 m and will be stockpiled separately. 

 

 

 

 

 

Plate 2.5: Typical Bulldozer    Plate 2.6: Typical Excavator 

Once the overburden has been stripped, the gold bearing ore will be blasted and then mined by excavator and then loaded into 20 tonne dump trucks which will haul it to the ore stockpile area near the processing plant. 

Only one shift (8 hrs) will be used, and for that one day shift, about 250 tonnes of ore will be mined. 

 

Page 16: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

15 | P a g e     o f   E I S   a n d   E M & S P    

 

2.7.2 Processing operation 

Processing  of  mineral  ore  is  the  most  important  and  crucial  aspect  of  mineral exploitation. Knowing the characteristic of the mineral ore, how the valuable minerals are interlocked  in  the mineral matrix,  its  grindability  to  free  up  the  valuables  among  other things  is  important  to  enable one make  a better  choice  to use  in  the processing of  that particular  ore.  Often  the  ore  characteristics  changes  with  depth,  and  hence  processing methods should be able to compensate for such changes. 

Depending on the characteristic of the ore; the process might follow one or more of the steps shown on figure 2.1 below. 

 

Figure 2.1: Different Ways of Doing Gold Concentration 

For this project, the stockpiled ore will be fed into a primary crusher to reduce its size to a feed  that will  be  acceptable  to  the  ball mill.  If  required  the  ore will  be  feed  to  a  semi‐autogenous grinding (SAG) mill which will be  in closed circuit with secondary crusher prior to  reporting  to  the  ball  mill.  The  ground  ore  will  then  be  sent  to  cyclone  where  the underflow will  be  returned  to  the  ball mill  and  the  overflow will  report  to  roughers  via screens to remove any trash. Typical example of the process is as depicted on figure 2.2. 

Page 17: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

16 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Figure 2.2: Schematic Drawing of gold Process Plant 

 

Page 18: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

17 | P a g e     o f   E I S   a n d   E M & S P    

 

3. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 

3.1. Overview 

This  chapter  is  necessary  and  mandatory  as  it  ensures  that  necessary  steps  and adequate precautions are well thought out and  instituted  in the project design to prevent environmental damage,  injury  to persons, other  living  resources, and pollution caused by effects  of  mining  operation  activities  in  line  with  the  policies,  laws,  regulations  and guidelines.  

The National Environment Policy, 1997 and the National Mineral Policy 1997 emphasize the  need  for  an  investor  to  undertake  an  environmental  impact  assessment  where applicable. The chapter  is prepared  in  line with  the Environmental  Impact Statement and Audit Regulations, Section 18(2) of 2005 and conforms to the requirements of Section 81 of the Environmental Management Act, 2004 

3.2. National Policies 

Relevant  policies with  relevance  to  this project  are  examined.  Polices  in  this  chapter include  the Mineral Policy,  the National Environment Policy,  the Land Policy,  the National Water Policy, etc. These policies are sectoral in nature guiding each sector on activities and are examined because they influence directly this project.  

3.2.1. National Environment Policy of 1997 

The  integrated  approach  of  the  proposal  is  in  harmony with  the  plan,  schedule  and operation of the project. The project ensures that its operation is consistent with the overall objectives of  the National Environment Policy. The policy provides a  framework  for multi‐sector  participation  and  cooperation  to  achieve  sustainable  development;  and  seeks  to ensure sustainable and equitable use of  resources  for meeting  the basic needs of present and  future  generations,  without  degrading  the  environmental  resource  base  or  risking health and safety.  

The policy among other  issues emphasizes  the need  to protect water, vegetation and air; to conserve and enhance natural and manmade heritage; including biological diversity; to  improve  condition  and  productivity  of  rural  and  urban  settlements.  Furthermore,  the policy emphasizes on the importance of observing procedures for proper use of chemicals in order to minimize pollution of water sources. 

 

Page 19: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

18 | P a g e     o f   E I S   a n d   E M & S P    

 

3.2.2. Mineral Sector Policy of 1997  

The Mineral Policy stresses private sector led mineral development, which ensures that mining is conducted in an environmentally sustainable manner. The major roles of the government are regulating, promoting and facilitating.  

Some of the mineral policy objectives, which are directly related to the project, are:  

• to stimulate exploration and mining activities;  

• to ensure that wealth generated from mining support sustainable economic and social development;  

• to minimise  or  eliminate  adverse  social  and  environmental  impact  of mining activities; 

It  is from these objectives that the government  instituted environmental management regulations under the mining law. 

3.2.3. National Land Policy of 1995 

The project proposal is consistent with the National Land Policy of 1995 which provides among  other  considerations,  incentives  for  promoters  to maintain  and  develop  the  site accordingly,  reduce  land use  conflicts and  increase value added on products. The project implementation will abide to all requirements of the policy. 

3.2.4. National Water Policy of 2002 

The  planning,  sitting,  designing  and  construction/operations  of  the  project  is  also consistent with  the  National Water  Policy  of  2002 which  provides  for  a  comprehensive sustainable  and  equitable  development  and  use  of  water  resources  for  sustainable development. The policy among other  things, seeks  to ensure more efficient utilization of existing  water  resources  and  improved  monitoring  to  control  water  quality  and  arrest contamination  from  industrial  sewerage and excessive use of  chemicals. These objectives require  on  integrated  and  holistic  planning  and management  in  areas  of water  use  and disposal of effluents.  

The planned project objectives are consistent with the objectives of the water policy on cleaner production practices, effective and efficient utilization of water, water conservation, and  application  of  environmentally  friendly  chemicals  to  minimize  pollution  of  water sources, to mention a few.  

3.2.5. National Human Settlement Development Policy of 2000 

The  planning  of  the  proposed mining  project  is  in  harmony with  this  policy.  Among others, one of the objectives of National Human Settlement Development Policy of 2000 is 

Page 20: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

19 | P a g e     o f   E I S   a n d   E M & S P    

 

to protect human  settlements,  the environment and embedded ecosystems  thereof  from environmental pollution, environmental degradation and destruction or loss of biodiversity in order to attain sustainable development. The project is in line with this policy. The project operation  will  as much  as  possible  be  confined  to  areas  far  from  concentrated  village settlements. 

3.2.6. National Health Policy of 1990 

The policy objectives  related  to  the mining project  are  the provision of neighbouring village community needs such as water supplies, waste disposal services and promotion of other related health programmes such as food and hygiene. The project proponent will at all time seek to help the surrounding community in the provision of water, health services, waste disposal services and environmental education.  

3.3. Legal Framework 

The project will be implemented in the overall context of legal frameworks that govern mining  activities.  Some  of  the  few  legal  frameworks  that  are  to  be  observed  by  the proponents pertaining to mining activities include: 

3.3.1. Environmental Management Act of 2004 

The Act provides a  legal and  institutional  framework  for  the sustainable management of  the  environment.  It  outlines  the  principles  for  management,  impact  and  risk assessments, the prevention and control of pollution, waste management, environmental quality standards, public participation, compliance and enforcement.  It provides the basis for the implementation of international instruments on the environment and the National Environmental Policy. The mining operations for this project will be in consistence with the Act. 

3.3.2. Mining Act of 1998 

It  is  perhaps  under  the  newly  enacted Mining  Act,  1998  that  a much more  serious attempt has been made to incorporate EIA requirements into planning and decision‐making processes. This legislation makes extensive provisions for environmental matters in relation to mining  activities,  introducing  ‐  for  the  first  time  ‐ mandatory  EIA  requirements  as  a condition for granting various categories of mining licenses.  

Under section 38(4)(c), every application for a mining  license must be accompanied by the  applicant's  environmental management  plan  (EMP),  including  his  proposals  for  the prevention  of  pollution, waste  treatment,  protection  and  reclamation  of  land  and water resources and  for eliminating or minimizing adverse effects on the environment of mining 

Page 21: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

20 | P a g e     o f   E I S   a n d   E M & S P    

 

operations. This  requirement  is also applicable  in cases of application  for  renewals of  the mining license. 

In  addition,  the  Act  requires  every  applicant  for  a mining  license  to  liaise  with  the commission and produce  to  the Minister  responsible  for mining an environmental  impact assessment on proposed mining operations from  independent consultants of  international standing short‐listed by the applicant and approved by the Government. 

The project is applying for Mining Licence, which is valid for 10 years and renewable for a similar  term. The  requirement under  the mining  law  for an EIA  is also applicable  to  this type of licence. It is under these conditions that this report has been prepared. 

3.3.3. Explosives Act of 1963 

Under  this Act, a permit  is  required  for  the acquisition, possession,  storage or use of 

explosives. The project is going to use explosives during mining of primary reefs. The project 

developer will adhere to the provisions under the Explosives Act during blasting operations 

in the project. 

3.3.4. Land Act and Village Land Act of 1999 

The Acts seek to control land use and clarify issues pertaining to ownership of land and land‐based resources, transactions on  land and land administration. The Land Acts identify three categories of  land; village, public and/ general and protected or restricted  land (e.g. national parks,  forest  reserves, etc). The planned mining activities  is consistent with both legislations will strictly consider the existing land use systems.  

3.3.5. Water Act of 1974 

The proposed mining activities are also  in conformity with Water Acts. As mentioned before,  the Water Act principally  seeks  to ensure  that water  is utilized without  sectoral conflicts, and without causing pollution. This  is  the  spirit of both Act of 1974 and Act of 1981. They were enacted to control and protect water resources. The Act places a regime of water rights  to govern access  to water use. Pollution control norms and standards are embodied in the water rights and the mining activities operations will be bound to strictly observe the requirement of the Act. 

Apart from  incorporating pollution control and having prevention conditionality  in the water  rights,  the  Act  goes  a  step  further  by  putting  in  place  a  regime  in  consent with discharge of effluent. Under Section 15 A (1) of the Act, no person may discharge effluent from any commercial, industrial or other trade waste systems into receiving waters without a consent duly granted by a Water Officer. The Act also contains two schedules which set standards for receiving waters and effluent. 

Page 22: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

21 | P a g e     o f   E I S   a n d   E M & S P    

 

The project will use water for various stages of mineral exploitation. As such retaining and  settling  ponds will  be  used  to  enable water  recycling  and  clearing/cleaning  before returning the same to the river system. Furthermore, the project will recycle wastewater as much as possible  in a closed water system hence, reducing the need to return water  into the river system. 

3.3.6. Local Government (District and Urban Authorities) Act of 1982 

This  Act  provides  for  detailed  responsibility  for  Urban  and  District  councils  in  the administration of their day‐to‐day activities. Waste management  is pointed out as one of the  activities  to  be  managed  by  both  District  and  Urban  Authorities.  Accordingly,  the proposed mining activities will seek to liaise with District Authorities. 

3.4. Administrative Framework 

3.4.1. The Vice President’s Office 

The  Vice  President’s  Office  has  the  overall  responsibility  of  environmental  issues  in Tanzania.  There  is  a  National  Environmental  Advisory  Committee  which  serves  as  an advisory  body  to  the  Minister  responsible  for  environment,  or  sector  Ministry,  on environmental  matters  referred  to  it.  There  is  a  Director  of  Environment  heading  the Division of Environment. The Director for Environment is responsible for matters pertaining to the management of the environment. 

3.4.2. Ministry of Energy and Minerals 

The  Ministry  for  Energy  and  Minerals  (MEM)  is  responsible  for  monitoring  the development  and  proper  function  of  the mining  sector  of  Tanzania. MEM  is  the  Lead Ministry  in  the proposed undertaking by  the project. MEM  is  responsible  for  the periodic inspection and monitoring of mining activities. The nearest office to the project is in Singida Town.  

3.4.3. The National Environment Management Council 

The National Environment Management Council (NEMC) is a corporate body mandated by the Environmental Management Act to undertake enforcement, compliance, and review and monitoring of environmental  impact assessment and  facilitates public participation  in environmental  decision‐making,  among  other  responsibilities.  NEMC  advices  Ministerial sectors  to  ensure  compliance with  the  requirements  of  the  Environmental Management Act. 

3.4.4. The Local Government Authority  

Page 23: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

22 | P a g e     o f   E I S   a n d   E M & S P    

 

The  local government authority  in  the project area  is  responsible  for  such day  to day activities  that have direct  impact on  the  local  community, namely health,  education  and related issues. The proponents will collaborate with the local authorities on these and other matters. 

3.4.5. Nongovernmental Organisations 

The  role  of  the  NGOs  and  CBOs  is  to  act  as  watchdog  to  ensure  that  the  project developers adhere  to agreed environmental management and  social monitoring plans.  In addition, they will act as awareness and outreach agents for the community. 

 

Page 24: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

23 | P a g e     o f   E I S   a n d   E M & S P    

 

4. BASELINE OR EXISTING CONDITIONS 

4.1. Physical Environment 

4.1.1. Topography and Drainage  

Singida  region occupies  the northern part  of  the  central plateau.  Topographically,  its 

landscape drops east‐ward to the rift valley and west‐ward to the Wembere depression. A 

large plateau of an average elevation of 1000 metres extends from the centre towards the 

south  and  south‐west of  Singida  Township, while  in  the north  ‐ west of  the  region,  the 

Iramba plateau rises to an elevation of about 1,500 metres above sea level. 

A large part of Singida region is arid, and the rainfall amount decreases from north to 

south of the region. 

The  region  has  a  series  of  valleys,  depressions  and  river  catchments which  form  the 

basis of its land drainage system and soil types. Geologically, the region consists of granite 

batholiths  rocks, peneplains, and volcanic plateaus  comprising  fertile  clay  loamy  soils on 

top and sandy clay  loams  to sandy pebbly surface materials down  the catena. There are 

five rivers in the region namely Ndurumo, Wamba, Msuguluda, Heka and Mponda. Except 

for Ndurumo River, the rest are seasonal.  

There are also  three major distinguished  river catchments, namely: Ndurumo catchment 

discharging  into  Lake  Kitangiri  towards  the  north‐west, Wamba/Msugulunda  catchment 

discharging  into  the Wembere  Swamps  which  are  in  the West  of  Singida  region,  and 

Maduma/Msemembo catchment discharging into the Bahi Swamps in the south east. 

4.1.2. Climate 

The average annual rainfall ranges between 500 ‐ 800 millimetres. The highest and more 

reliable rainfall  is recorded  in the northern part of  the region where rainfall exceeds 750 

millimetres in most seasons. The  lowest rainfall is usually recorded  in the western part of 

Manyoni district. Rainfall  in  this area  is as  low as 500 millimetres. The highest  rainfall  is 

usually recorded in Iramba Plateau and the north‐eastern part of Iramba where it reaches 

800 millimetres. In normal circumstances, rainfall usually takes place from mid‐November 

ending in April or early May every year. 

Temperature  in  the  region  ranges  between  15°C  and 30°C  depending on  season  and 

altitude. The coldest period in the year is in July while the hottest period is in October and 

November. On the other hand, relative humidity (Rh) at noon rises from 36 percent in the 

driest month  to  58  percent  during  the wet  season.  Evaporation  is  almost  similar  in  the 

Page 25: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

24 | P a g e     o f   E I S   a n d   E M & S P    

 

region  and  averages  close  to  2000 millimetres  annually,  being  a  bit  higher  in  Singida 

district.  It  is  lowest  in  April.  During  this  month  it  goes  down  to  1400  millimetres. 

Evaporation  is highest  in October reaching about 2200 millimetres. Wind speed  is usually 

highest  in Singida and gets particularly high during the dry season which  is between May 

and October. 

4.2. Flora and Fauna 

About 1,775,000 hectares or about 36 percent of  the  total  land area  in  the  region  is 

covered with different tree species, thickets and miombo woodlands. A large part of the 

region offers a natural habitat for wildlife with a wide range of game. 

No major  fauna encountered within the area except  for a  few Monkeys, Snakes, Rats, 

lizards, and some frogs and toads. 

4.3.  Social and Economic Environment  

4.3.1. General Description  

The economy of Singida region is predominantly rural with well over 95 per cent of its 

population engaging in subsistence land based production. The main productive sectors in 

the  region are agriculture,  livestock, natural  resources, mining,  industry and  trade.  Like 

many regions in the country, agriculture is a major occupation of a large number of people 

in  the  region and accounts  for about 60 percent of  the  region's  total  income. The main 

food  crops  are  maize,  millet  and  finger  millet,  sorghum,  paddy,  cassava  and  sweat 

potatoes; while sunflower, cotton,  tobacco, wheat, beans, groundnuts, peas and onions 

are the major cash crops. 

Livestock  is  the  second  most  important  resource  for  the  region's  economy.  Most 

people  own  livestock  and  depend  on  them  for  their  livelihood.  The  region  is  a major 

exporter of beef  cattle  to other parts of  the country. Other  sectors contributing  to  the 

economy  of  the  region  are;  natural  resources  (mainly  through  agro‐forestry,  wildlife, 

beekeeping and fishing), mining, industry and commence.  

Industrial  production  and  commercial  activities  in  the  region  are  still minimal  and 

contribute very  little to the region's GDP. However studies made for the sector  indicate 

that  the  region  has  great  potential  for  business  and  establishment  of  small  scale 

industries, especially rural industries which can utilize local materials and easily acquired 

or existing local skills to meet the local demand for goods and services of the community 

in the region and for export.  

Page 26: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

25 | P a g e     o f   E I S   a n d   E M & S P    

 

4.3.1.1  Socio‐Economic Conditions 

Singida region is performing well in a number of socio‐economic aspects. For example, the 

region is doing fairly well in health provision, where in some cases, it even excels national 

standards. However  the  region  is poor with  regard  to primary arid secondary education 

given its high illiteracy rate.  

4.3.1.2  Natural Resources 

The region is endowed with a vast natural resource base. About 36 percent of the region is 

forest consisting mainly of Miombo woodlands which provide excellent tropical hardwood. 

The  forest  land  also  provides  a  favourable  habitat  for wildlife with  tourist  attractions. 

These forests have high potential for beeswax and honey production, besides contributing 

to soil and water conservation.  

4.3.1.3  Industry 

The  level of  industrial activities  in Singida region  is very  low contributing very little to the 

regions income. Industrial activities are mainly small scale processing industries, operated 

mainly by private entrepreneurs. The region is well endowed with a wide range of natural 

wood  for  timber,  hence  it  has  great  potential  for  both  non‐farm  and  agro‐forestry 

industrial activities. Potential industrial activities in the region  include oil seed processing, 

saw‐milling, logging and carpentry. 

4.3.1.4  Mining 

Mineral  reserves  in  the  region  include  gold,  diamonds,  silicon  salt,  gypsum  and  green 

tourmaline. Others are emerald, soda‐ash, limestone, garnets, ruby, rhodolite, amethyst, 

and aquamarine. Extraction of  these minerals  is done on a very  small  scale, mostly by 

local small miners who are ill‐equipped, lack capital, and are poorly organized. Thus, the 

contribution of the mining sector to the economy of the region is minimal. In short, there 

is a big potential for development of the sector for both small and large scale miners. 

4.3.1.5  Employment 

The major category of employment  in Singida consists of people earning  their  livelihood 

from  income  ‐  generating  activities  undertaken  by  them. Apart  from  this  self‐employed 

category, there is also another group of people employed in both public and private sector. 

The informal sector is also emerging in all urban areas in the region. 

Page 27: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

26 | P a g e     o f   E I S   a n d   E M & S P    

 

4.3.1.6  Industrial Development 

Singida  region  is one of  the regions with poor  industrial development. Certainly,  this has 

been  caused  by  various  factors  which  are  cultural,  economic  and  social  in  nature. 

Currently, the region has established small scale  industries which are mainly operated by 

private individuals, partnership companies, co‐operatives and few by public institutions. 

4.3.1.7  Industrial Potential 

Singida region  is endowed with a wide range of natural resources that could  lead to the 

establishment of  resource based  industries  like  gypsum mining, milling,  lime  and  chalk 

making,  tomato  sauce production, brewing of whisky  from honey,  salt extraction, ghee 

extraction,  carpet  weaving,  pottery  and  handcraft  production.  The  region  has  a  wide 

scope of establishing demand‐based  industries since most of these products are brought 

to Singida from other regions. Because of excessive transport cost it would be economical 

to produce some of these locally, so as to satisfy local demand.  

4.3.2. Infrastructure  

The  road  network  is  not well  developed  in  Singida  region  despite  the  fact  that,  it  is 

surrounded by six regions. Trunk, regional, district and feeder roads account for 18, 26, 26, 

and 30 per cent of the total road network respectively. The Regional road network can be 

categorized according to the surface of the roads. According to this criterion, Singida region 

has three types of road surface namely: tarmac, gravel and earth.  

Generally, Singida region has the least tarmac road network. On the other hand, the 

general condition of road network is poor, due to irregular maintenance. The condition of 

rural  roads  is worse  despite  the  importance  attached  to  these  roads  as  links  between 

producing  areas  and marketing  centres. Available data  shows  that,  about  86 percent of 

Singida rural roads are in poor condition and always impassable during rainy season.  

4.3.2.1  Railways 

The  central  railway  line crosses  the  region  in  the Southern part of Manyoni District. 

This  line  is  very  crucial  economically  to  Singida  region  since  it  serves  directly  several 

villages  of  Kintinku, Makutopora,  Saranda  and  the  towns  of Manyoni  and  Itigi.  Other 

villages  served  are  Aghondi,  Kitaraka  and  Kalangasi.  This  line  serves  transportation  of 

passengers, goods and  livestock. There  is also a Manyoni‐Singida  railway extension  line 

that provides services to villages along its line and Singida Town.  

Page 28: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

27 | P a g e     o f   E I S   a n d   E M & S P    

 

4.3.2.2  Air Transport 

There  is  no  airport  in  the  region;  hence  there  are  no  regular  commercial  flights. 

However,  there  are  several  private  airstrips  which  cater  for  light  air  craft mainly  for 

emergency cases such as flying doctors. One private airstrip is located a few metres to the 

north of the mining licence application in question. 

4.3.3. Social Service Infrastructure  

4.3.4.1  Education 

Education  in  any  society  is  fundamental  and  a  pre‐requisite  for  socio‐economic 

development.  The  region  has  several  primary  and  secondary  school.  Some  of  these  are 

owned by Government and others are owned by private sector  including various religious 

bodies. 

4.3.4.2  Health Services 

The health sector policy in Singida region, as elsewhere in the country, is geared toward 

promoting primary health care and  the general health status of all people  in  the  region. 

The region has a fairly satisfactory health infrastructure including several Hospitals. Health 

Centres and a good number of Dispensaries. However hospitals and most of  rural health 

centres  and  dispensaries  need  rehabilitation  and  provision  of  essential  tools  and 

equipments in order to work effectively.  

The distribution of health  service  is uneven, although given  the  statistics on health  in 

relation to served population, the region fares close to the national targets. Nevertheless, 

not all of  the population  is covered satisfactorily. There  is also a shortage of  trained and 

qualified personnel, mainly specialists, Medical Officers and Grade A nurses. 

In general, health performance  in  the  region  is adversely affected by  limited  funding, 

that has resulted into inadequate supply of drugs and Materials, poor incentives for health 

workers,  little efforts on primary health  care,  inadequate  transport  facilities when need 

arises,  and poor working environment due  to  lack of maintenance and  rehabilitation of 

existing  facilities.  In  spite of  this,  the performance of  the health  sector  in  the  region  is 

encouraging. 

4.3.4.3  Water Supply 

Singida  region  like other  regions  in  central Tanzania has  very  limited water  sources. 

Rivers which  are  the  only  reliable  source  of water  are  seasonal  and  dry  up  in  the  dry 

Page 29: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

28 | P a g e     o f   E I S   a n d   E M & S P    

 

season. Although there are several  lakes and dams  in the region their water are virtually 

unfit  for domestic consumption because of high  salinity and contamination. There are a 

number of rivers and natural water springs scattered  in the region, but they do not yield 

adequate water to meet the high water demand in the region. 

The region will, for foreseeable future, depend mainly on ground water as a reliable safe 

water source for domestic use and few surface water sources.  

In  rural areas  it  is estimated  that  about 56 percent of  the  region's water  is obtained 

from  traditional  unimproved  dug‐wells,  ponds  and  open  holes.  Natural  water  springs, 

shallow‐wells,  tube‐wells  and bore‐holes  constitute  a minority 44 percent,  although  they 

represent a dependable and safe rural water supply source in the region, while small dams 

and  swamps constitute  the main  source of water  for  livestock. Rain water harvest  is also 

one  possible  source  of  rural  water  supply  that  has  not  been  exploited  although  a  few 

catchment  systems  are being  tried by  some  institutions within  the  region  to  supplement 

other sources. 

The  current  policy  on water  supply  in  both  rural  and  urban  areas,  in  the  country,  is 

geared  towards  providing  adequate water  supply,  efficient Management  and  supportive 

systems,  while  promoting  community  and  private  participation  at  all  levels  of  water 

development programmes, The policy aims at  creating an appropriate organisational and 

support  systems  that  involve  all water beneficiaries  from plan  formulation,  construction, 

operations and maintenance of water projects. So far the participation of non‐governmental 

organizations  (NGOs),  community  based  organisations  (CBO),  and  the  general  public  in 

support of the government efforts in rural water supply in Singida region is very high. 

The technology used for supply of safe water  in Singida region  is quite varied, ranging 

from  gravity,  shallow‐wells  fitted with  hand‐pumps,  diesel  and  electric  or motor  driven 

engine‐pumps, drawing water from surface source and boreholes, wind‐mills, dams charcos 

and rain water harvest. 

Gravity schemes are not prevalent  in Singida because of severe dry climatic conditions 

where many  rivers do not  survive  even  a  single  season. Diesel pumped‐piped water  and 

electric‐driven‐pumps, or motor driven technology is extremely expensive, and is only used 

in  areas where no other option  is  feasible.  Shallow‐wells  fitted with hand‐pumps on  the 

other hand, are preferable to motor pumped schemes, and is a prevalent technology in the 

region because they are less expensive, easier to maintain, sustainable and can serve a large 

number of people.  

Rain water harvest is also a lesser expensive technology which is starting to take root in 

the region. Although not yet adequately exploited, and still nascent in the region, a number 

Page 30: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

29 | P a g e     o f   E I S   a n d   E M & S P    

 

of  rain  water  catchment  systems  have  successful  been  developed  especially  by  private 

institutions, mainly  Christian Missions.  In  these  institutions  rain  water  is  being  used  to 

supplement other water sources. The technology is generally unpopular in the region, but it 

can effectively reduce the problem of clean water shortage  in Singida region  if efforts and 

resources are directed to exploit its abundant potentials. 

4.3.4.4  Energy Sources 

Singida region is connected to the national grid which also serves Mwanza and Musoma 

regions.  This  line  serves  a  few  areas  leaving  the  district  headquarters  of Manyoni  and 

Iramba without electricity. This means the region has limited industrial development, due to 

lack of power supply. 

The  entire  population  residing  in  the  rural  areas  depend  heavily  on  firewood  as  the 

main  source  of  energy.  The  demand  for  fuel  wood  has  a  detrimental  effect  on  the 

environment as  it accelerates soil erosion and soil  infertility, which together,  lead to poor 

crop production.  In order  to restore the ecosystems  in the region, there  is a need  to  find 

another source of energy. 

Despite having  a  good number of  livestock, biogas  technology  is not  known  to many 

people. It has been estimated that only 7 cattle are needed to produce energy sufficient for 

cooking and lighting for a family of ten people. It is, therefore, being suggested that, efforts 

should be directed towards the use of biogas technology as an alternative source of energy, 

particularly for the rural people, 

Page 31: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

30 | P a g e     o f   E I S   a n d   E M & S P    

 

5. ASSESSMENT OF IMPACTS AND IDENTIFICATION OF ALTERNATIVES 

5.1. Impact Identification  

Mining  operations  involve  different  activities  which  may  have  both  positive  and negative  impacts  both  during  exploration,  construction,  operation  and  mine  closure activities.  As  such  it  is  imperative  that  planning  of  all  mining  activities  should  include measures that are geared to minimize negative  impacts taking  into consideration that the area has already been subjected to artisanal mining activities. 

The  most  common  environmental  impacts  associated  with  mining  activities  include impact to soil, erosion, alteration to natural topography of the area and its associated visual impacts as well as nuisance impacts, such as noise and dust. In addition, there are potential social‐economic  impacts  resulting  from  the mining  activities  as outline below. A detailed account  of  the  potential  impacts  is  included  in  tabular  forms  giving  a  rating  on  each potential impact. 

5.2. Physical Impacts 

These are impacts related to the actual operations at the licence area. The impacts are the outcome of mining operations, (i.e. stripping the topsoil, removing the overburden and gem paying gravel, and  transportation of  these materials); processing or washing of gem gravel and lastly during rehabilitation. The impacts will extent into the decommissioning and closure phase as well. 

5.2.1. Construction Phase 

The  abandoned mine  pits  are  the most  conspicuous  environmental  impact  so  far  of small scale miners who have caused environmental degradation. The pits were dug without using any acceptable techniques.  

Additional  but  minor  impacts  are  expected  from  construction  of  supportive infrastructures e.g. Mineral recovery plant, Power  lines, water storage  facilities, workshop facilities, housing accommodation for workers etc, which can result into loss of biodiversity, aesthetic  impacts  (the  visibility  of  the  accommodation  and  other  buildings),  improper sewage treatment and waste disposal, as well as littering.  

Anticipated  impacts  during  the  construction  phase  include  air  pollution,  increased sediment load, interference with natural drainage and restricted access through the project area.  

Page 32: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

31 | P a g e     o f   E I S   a n d   E M & S P    

 

5.2.2. Mineral extraction/Operation phase 

During mining operations  that will  initially  involve mining of alluvial and/or oxide ore and  stripping  of  overburden  to  reach  the  ore  body, will  result  into movement  of  large quantities of soil for stockpiling and treatment. Later on, mining of primary reefs will involve drilling,  limited blasting and  loading of  the blasted material and  its  transportation  to  the processing plant. 

Expected  impacts  will  be  air  and  water  pollution,  destruction  of  property  due  to vibrations and health and safety hazards on workers. The potential impacts could arise from the following: 

• Wind  and  water  erosion  that may  increase  sediment  loads  and  decrease  water quality in streams, reduce the productivity of the soil and create a dust nuisance;  

• Contamination of  surface or ground water by  sediment,  release of  toxic elements from overburden,  tailings or wastes, or  spills of oil or  fuel as  surface  runoff or as underground seepage;  

• Changes to surface and ground water flows and levels;  

• Damage  to  soils  including  acidification  (from  use  of  ammonia  nitrate  explosives), pollution and compaction or loss of soil structure;  

• Dust/smoke and a reduction of visibility caused by the following: 

Table 5.1: Source of Fugitive Dust and Smoke 

Source  Cause of Emission

Mining Areas 

• Excavation and digging by machines 

• Wind erosion of the mined & exposed surfaces. 

• Movement of machines and vehicles within the mining area. 

Processing Plant 

• Movement of haul trucks. 

• Dumping and tipping of ore 

• Processing of dry solids. 

Soil and Ore Stockpiles • Creation of stockpiles. 

• Wind erosion of stockpiled materials. 

• Physical rehabilitation actions 

Roads • Movement of heavy machines and vehicles 

• Wind erosion of surfaces. 

 

Page 33: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

32 | P a g e     o f   E I S   a n d   E M & S P    

 

• Noise nuisance, the likely sources of which would include the following: 

o The  diesel  driven  generators  used  for  the  provision  of  power  for  both  the washing plant and staff quarters; 

o Vehicle noise; particularly from heavy earthmoving machinery; 

o Noise associated with crushing and grinding of ore in the process plant, and 

o Noise associated with staff quarters. 

• Generation  of  tailings  and  other  wastes  that may  release  toxic  elements  or  be mobilised by erosive forces;  

• Possible sudden  failure of engineered containment structures such as  tailings dam embankments, settling and holding ponds, resulting in release of sediments into the water system;  

• Acid mine  drainage  from  tailings,  ore  and  waste  dumps  that  can  generate  acid through bacterial oxidation when exposed to moisture and oxygen ‐ this acid  leach may then mobilise heavy metals that can be released into the environment; 

• Loss of flora including direct  losses through clearing and indirect effects due to the spread of plant pathogens and weeds;  

• Loss  of  fauna  including  direct  losses  through  vegetation  clearing  and  the  indirect effects  on  species  through  the  reduction  and  fragmentation  of  habitat  and  the introduction of feral animals;  

• Damage to heritage sites; and  

• Destruction  of  adjacent  habitats  arising  from  the  development  of  camps,  mine villages/towns and services stimulated by the mining project  

5.2.3. Decommissioning Phase 

Activities  during  decommissioning  and  mine  closure  after  the  resources  have  been exhausted  could  result  into  negative  environmental  impacts  such  as  pollution  of  water (surface and underground) and accidents due to uncovered mine workings.  

5.3. Social‐Economic Impacts 

While mining projects,  undeniably, may  cause  severe  localised  effects,  some positive aspects are always experienced such as bringing in of massive investment capital into those localised  areas,  the  creation  of  local  jobs,  getting  involved  in  the  building  of  new 

Page 34: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

33 | P a g e     o f   E I S   a n d   E M & S P    

 

infrastructure, and generating substantive profits  that help  improve  the condition of  local people, including those who have been displaced or relocated.  

However,  it  is  not  easy  to  judge  if  these  benefits  outweigh  any  local  loss  of  land regardless of any compensation to landowners. Displacement involves not only the physical eviction  from  a  dwelling,  but  also  the  expropriation  of  productive  farm‐lands  and  other assets. 

 Always  there  are  people  who  are  negatively  impacted  and  stand  to  lose,  as  a consequence of  the project, all or part of their physical and non‐physical assets,  including homes; communities; productive lands; resources such as forests, rangelands, or important cultural sites; commercial properties; tenancy; income‐earning opportunities; and social and cultural networks and activities. This being the case, addressing the issue of “Rehabilitation” matters  pertaining  to  restoring  the  incomes,  livelihoods,  and  social  systems  of  those impacted upon by the project should be included and assurance given to at least return to the level of their pre‐project status.  

Health  risks  associated with mining  ventures  include  impact  on  the  already marginal health  status  of  local  areas  and  are  worsened  by  the  stress  and  trauma  of  moving (displaced)  and  increased  population.  Recurring  problems  are  reported  with  resettled populations not gaining access to safe potable water and safe sewage;‐ increased diarrhoea, dysentery and epidemic  infections often  result. As might be expected,  the health  impacts fall disproportionately on infants, children, expecting mothers and the elderly. 

Other  comparable  risks  and  impacts  include  the  loss  of  access  to  public  services, increased food insecurity, the loss of access to common property, social disarticulation, and the loss of civil and human rights. 

The  obvious  impact  will  be  the  influx  of  a  large  than  usual  number  of  temporary workers, of which a significant number might become permanent residents in or around the licence  area.  The  increase  in  the  population  in  the  area will  impact  on  the  local  natural ecosystem  (due  to  increased  pressure  and  resource  exploitation)  like water  abstraction, wood fuel and food availability, and the local physical and social infrastructure like schools and hospital services. This trend in population growth ultimately will also result in endemic of disease, especially those related to STDs such as HIV/AIDs; and also malaria in the area. 

It is clear that family and community cohesion will be disrupted by new personal, social and commercial relationships brought about by this project. Changes to long‐standing terms of trade will be effected owing to increased competition (demand). This might bring about price escalation  that will negatively  impact  the  locals, particularly  those not employed or earning sufficient  income.   Natural and human production systems come under stress due to increased population with effect that local demand for food and other consumables will increase. 

Page 35: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

34 | P a g e     o f   E I S   a n d   E M & S P    

 

During  consultation  with  various  stakeholders,  a  number  of  issues  were  raised  and comment,  contributions  and  concerns  noted.  These  have  been  incorporated  in  this statement.  The project  is being welcomed by  the  local  community  as  it  is  anticipated  to contribute  a  great  deal  towards  the  development  of  the  local  area.  Some  of  the expectations and anticipation include the contribution towards the development of services provided  to  the  community  such  as  education,  health  and  infrastructures;  and  also  job creation. 

It was quite rightly pointed out that physical  impacts brought about on most areas by small scale mining exists and gives a bad reputation to the mining industry. It is hoped and expected that this project will have less or no major physical environmental impact on the area.  It  is expected that the proponent has  taken  trouble  to  fairly compensate those who have given up or lost their land to the project. 

Community involvement was another issue that was raised by stakeholders. Comments and  suggestions were  given  that  the  project  proponent  should  involve  the  surrounding community  and  engage  them  in  a  dialogue  that  will  lead  to  a  long‐lasting,  fruitful relationship or partnership that would be beneficial to both parties. Availability of safe and clean water  is also one of  the outcries of  the  locals.  It  is anticipated  that this new project would be able to contribute on countering this problem.  

The proponent is urged to get involved in local community affairs such as tree planting exercise in the area. Trees are planted in order to provide for shading, fruits and firewood to the  local community.  In addition,  it was suggested  that  the proponent give preference  to locals on employment rather that employing migrant workers for unskilled labour. 

During decommissioning and mine closure, potential impacts may include:  

• loss  of  employment  and  possible  market  for  local  supplies.  The  proponent  will consult the community in designing mine closure plan to identify alternative sources of employment. 

• inadequate re‐settlement package to the few locals could result into disputes. 

• Conflicts due  to  land use  issues; e.g. Mining  could destroy  farm‐land, which even after restoration is not suitable for farming activities. 

5.4. Evaluation of Alternatives 

The  choices  of  various  alternatives  are  however  limited  due  to  the  nature  of  the undertaking. The exploitation of mineral resources dictate that ores or deposits are mined as  they are  found and  the processing  to  recover valuable mineral depends on  the nature and composition of  the ore. The  type of deposit and processing method also dictates  the 

Page 36: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

35 | P a g e     o f   E I S   a n d   E M & S P    

 

type  of waste  streams  to  be  generated,  thus  the  choice  of  disposing methods  of  these wastes. The mineral deposit in the area is a combination of both alluvial and primary ore.  

5.4.1. Mining Method 

The planned production capacity and the size of operation, and the choice of machinery also  reflect  the  way  stripping  will  be  carried  out.  In  the  primary  veins,  which  reach  a thickness of 2‐4 metres, there is not much flexibility in mining the reefs. Initially, mining will be open‐cast to about 20‐30 metres deep. Thereafter, if economics allows, the reefs will be mined using underground method. However, after mining, care will be taken to fill‐back the open pits where possible. 

5.4.2. Processing of Mineral Ore 

There are few alternatives in sitting the plant, namely i) erecting the processing plant in one central ML, and hauling  the ore  from the various  locations  for processing;  ii) erecting the plant near the primary reefs, and hauling alluvial gravels from the other licences;  

Each alternative has some limitations and advantages over the others. Erecting the plant at  the  centre  of  the  licence will  involve  selecting  an  area  close  to water  sources,  hence reducing water pumping over long distances. This however, will lead to designing long haul routes  that will need  to  be wetted  to  reduce  dust.  This will  also  involve  construction  of roads hence increasing the likelihood of soil erosion to occur. 

The second alternative of locating the processing plant close to the primary reef has the advantage  of  reducing  hauling  distance  for  the  high  probability  of  getting  quick  returns. However, this alternative will increase the chances of burying and rendering some ore. This is compensated if the reefs have more gem materials than the alluvial gravel. The converse is unfortunately more costly, with more negative impacts. 

Finally,  a  combination  of  the  various  alternatives  could  be  most  feasible  with appropriate optimization. 

5.4.3. Energy Source 

Diesel  will  be  the  main  source  of  energy  for  the  processing  plant,  earth  moving equipment,  generators  and  vehicles.  The  use  of  diesel  contributes  significantly  on  local impacts and has various potential impacts such as being a source of water and air pollution. On  average,  daily  fuel  consumption  is  estimated  at  between  1000  and  1800  litres,  in addition  to oils and  lubricants. These will add  to  transportation and  storage  logistic costs and potential impacts. 

Alternative  to  using  diesel  is  the  use  of  power  from  the  nation  grid  supplied  by  the Utility Company‐TANESCO.  

Page 37: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

36 | P a g e     o f   E I S   a n d   E M & S P    

 

5.4.4. No Project alternative 

The  no  alternative  scenario  entails  the  proponent  to  abandon  developing  mining operations  in  the  license area. This alternative  is not attractive  in  that,  the  former mining activities  by  artisan  miners  resulted  in  rapid  physical  degradation  of  the  area  with  no contribution to the surrounding community in whatsoever form. The project will somehow restore these areas. 

Another reason is the economic benefits associated with going ahead with the project. The gold deposits so  far discovered and exploited by the artisan miners have  far reaching economic benefits if properly managed. It is the proponent’s anticipation that there will be more  economic  benefits  to  the  nation  to  continue  with  the  project  development  than otherwise. 

The current proposal has many advantages compared  to  the no project alternative  in that  it  will  contribute  significantly  to  the  socio‐economic  well‐being  of  the  surrounding community  in  provision  of  such  services  as  health,  education  and  provide  employment opportunities to many local people. According to the anticipated mining plan, the areas that have  already  been  degraded  will  be  rehabilitated  and  brought  to  a  condition  that  is acceptable for planned land use which is farming. 

5.5. Detailed Potential Environmental and Socio‐Economic Impacts 

The  following  tables  summarise  in detail  the various potential  impacts and  their weights, and alternatives. 

Table 5.2: Potential Impacts of the Project 

Phase  Activities  Issues  Potential Impact 

Construction  

Construction & 

maintenance of haul roads. 

Oil and fuel spillage  Soil, surface and groundwater pollution 

Running of machinery & vehicles  

• Air pollution due to exhaust fumes • Noise pollution causing nuisance and health 

hazards 

Movement of vehicles & machinery 

• Dust pollution causing visual impact and health hazard. 

• Loss of soil structure due to compaction • Visual impact 

Loading/unloading of construction soils 

• Dust pollution causing visual impact and health hazard. 

• Noise pollution causing nuisance and health hazards 

Water usage  Wastage & depletion of water resources 

Ablation of top soil 

• Loss & degradation of biota within soil structure. 

• Accelerate erosion due to surface exposure. • Loss of aesthetics. 

Page 38: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

37 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Phase  Activities  Issues  Potential Impact 

Mineral Excavation 

Clearance of topsoil, overburden removal and excavation of gold ore 

Striping of topsoil 

• Air pollution resulting from dust, noise and noxious gases. 

• Loss and/or degradation of biota within soil structure. 

• Accelerated erosion • Visual impact due to presence 

of workings and dust generation. 

Oil and fuel spillage 

Soil, surface and groundwater pollution 

Running of machinery, equipment & vehicles  

• Air pollution due to exhaust fumes 

• Noise pollution causing nuisance and health hazards 

Digging and excavating gem‐paying gravel using heavy machinery & equipment 

• Dust pollution causing visual impact and health hazard. 

• Increase in safety risks due to presence of workings. 

• Visual impact 

Loading and haulage of topsoil, overburden and gold ore 

Loading of materials 

• Air  pollution  resulting  from dust, noise and noxious gases. 

• Loss  and/or  degradation  of biota within soil structure. 

• Increased  safety  risks  to workers. 

• Visual  impact  due  to  loading works  and  dust  generated (impairing vision). 

Oil and fuel spillage 

Soil, surface and groundwater pollution 

Transportation of materials  

• Air  pollution  due  to  exhaust fumes 

• Noise  pollution  causing nuisance and health hazards 

• Compaction of soils. • Dust  pollution  causing  visual 

impact and health hazard. • Visual impact. 

 

Page 39: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

38 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Phase  Activities  Issues  Potential Impact 

Stockpiling of topsoil & Gem‐paying gravel 

Stockpiling of topsoil.  Stockpiling action & presence of topsoil. 

• Loss  and/or  degradation  of biota within soil structure. 

• Increased  safety  risks  to workers. 

• Visual  impact due  to  stockpiled topsoil (increase in elevation). 

• Dust and noise pollution. • Destruction  of  biota within  the 

area identified for stockpiling. 

Stockpiling of gold bearing ore 

Stockpiling & presence of stockpiled material 

• Increased  safety  risks  to workers. 

• Visual  impact due  to  stockpiled ore (increase in elevation). 

• Dust and noise pollution. • Destruction  of  biota within  the 

area identified for stockpiling. 

Running of machinery & equipment. 

Working of machines & spillage of oil and fuel. 

• Air  pollution  (noise,  dust  & gases). 

• Compaction  of  soils.  Soil, surface  and  groundwater pollution 

• Visual  impact  due  to  presence of machines. 

Mineral Extraction. 

Crushing and grinding of ore  

Loading, hauling & tipping of ore. 

• Air  pollution  (noise,  dust  & gases). 

• Increased  safety  risks  to workers. 

• Visual  impact  due  to  presence of machines. 

• Soil,  surface  and  groundwater pollution. 

Water usage • Potential  for  wastage  and 

misuse. • Potential for contamination. 

Running of machinery & equipment. 

Working of machines & spillage of oil and fuel within the washing plant premises. 

• Air pollution (noise, dust & gases). 

• Compaction of soils. • Visual impact due to presence 

of machines. • Soil, surface and groundwater 

pollution.

Operation & maintenance of other project components. 

Excavation of clear water pond 

Creation of pond 

• Loss and disruption of biotic life within the soils of the area. 

• Increase  in  fine  sediments  and mud. 

Presence  of stagnant water 

• Creation of temporary breeding habitat for mosquito vectors of disease. 

• Creation of habitat for other organisms. 

• Disturbance to natural flow regime within the area. 

• Loss and change of biota. 

Page 40: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

39 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Phase  Activities  Issues  Potential Impact 

Operation & maintenance of other project components. 

Excavation of sludge pond 

Creation  of  sludge pond 

• Loss and disruption of biotic life within the soils of the area. 

• Increase in fine sediments and mud. 

• Disturbance to natural flow regime within the area. 

Power generation 

Running  the generators 

• Air pollution (noise & noxious gases). 

• Increased running costs to project 

Fuel and oil spillages • Soil, surface and groundwater 

pollution 

Workshop  Maintenance & repair • Soil,  surface  &  groundwater 

pollution. • Air pollution due to noise 

Use of site accommodation 

Littering • Potential health hazard • Aesthetic & visual impact. 

Sewage management  • Contamination  of  surface  and 

groundwater. • Nuisance due to odour 

Domestic waste • Nuisance due to odour. • Pollution of water bodies. • Attraction of vermin and pests. 

Rehabilitation 

Use of washed out gravel 

Backfilling  mined  out areas 

• Reduction  in  amount  of  & space  for  storage  of  washed out gravel. 

• Reduction in visual impact. • Decreased  health  and  safety 

risks • Formation  of  proper  base 

foundation for reclamation. 

Use of stockpiled topsoil  

Backfilling  mined  out areas 

• Reclamation and  restoration of mined  out  areas  to  a  state similar to original state. 

• Replenishment  of  biota  within the area. 

• Recovery  of  soil  structure integrity. 

• Reduction of soil erosion due to wind  and  water  after regeneration of biota. 

• Reduction in visual impacts 

Decommissioning & Mine closure  

Decommissioning Demolition  of infrastructure 

• Loss  of  amenity  due  to  waste generation. 

• Reduction in visual impact. • Decreased  health  and  safety 

risks • Air pollution. 

Page 41: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

40 | P a g e     o f   E I S   a n d   E M & S P    

 

Phase  Activities  Issues  Potential Impact 

Decommissioning & Mine closure 

Decommissioning Abandoned Infrastructure 

• Visual impact. • Reduced land for other 

economic activities. • May be put to positive uses, 

e.g. schools etc. 

Mine closure 

Employment 

• Loss of jobs. • Reduction in income to locals in 

the area. • Increased  social  stress  and 

unrest. • Decreased  employment 

opportunities and competition. 

Social –Economic 

• Loss to business that depended on the mine. 

• Decline to provision of services to the community. 

• Loss  to  revenue  for  the  locals, district  council  and government. 

• Reclaimed  and  rehabilitated land  used  for  other  income generating  activities,  e.g. farming, and grazing. 

Socio‐economic aspects 

Employment 

Lack  of  local  qualified personnel  and employing  outside local area. 

• Influx  of  workers  from elsewhere 

• Increase  pressure  on  local resources 

• Needs  for  areas  to accommodate newcomers. 

Use  of  Local  workers and staff 

• Reduction  in  accommodation needs 

• Normal  pressure  on  local resources 

• Increased  local  economic power 

• Increased competition  for  local human resources 

Social responsibility 

Influx  of  people  as temporary workers 

• Introduction of new diseases. • Risk  of  contracting  STDs  and 

related diseases. Like HIV/AIDS. • Decreased  health  and  safety 

risks • Increased  impact  on  available 

resources & demand. 

Interaction  of  people (locals  &  migrant workers) 

• Disruption  of  family  ties  and cohesion 

• Introduction of new ways of life (good & bad). 

Healthy,  Education, and Social services 

• Increased pressure  for demand of these services. 

• Disruption  of  formal educational activities. 

• Loss  of  access  to  basic  public services. 

Page 42: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

41 | P a g e     o f   E I S   a n d   E M & S P    

 

5.6. Environmental Impact Ratings for the Project 

The  following  table  shows how each  identified  source of  impact  can have a direct or indirect influence and its likelihood of happening. In addition, the anticipated severity of the impact before and after mitigation is indicated. 

Table 5.3: Impact Rating of the Project Potential 

Environmental Impact 

Source of Impact Direct or 

indirect Likelihood  Severity  Extent 

Rating Before 

Mitigation Pollution by litter  Improper management 

of domestic waste  Indirect  Possible  High  Local  High 

Contamination or Pollution to Water 

Improper management of hazardous waste  Indirect  Possible  High  Local  High 

Accidental spillage of hazardous substance  Indirect  Possible  High  Local  High 

Sewage Indirect  Possible  Low 

Immediate area 

Medium 

Impact to Flora  Disturbance during mining  Direct  Possible  High  Local  High 

Impact to Fauna  Disturbance during mining  Both  Possible  Medium  Local  Medium 

Disturbance to Soils/Erosion 

During mining and movement of machines  Direct  Probable  High  Local  High 

Noise  Diesel driven generators, vehicle noise, sorting of ore in the washing plant, staff quarters 

Direct  Definite  Low Immediate 

area Low 

Dust  Vehicles and earthmoving equipment; ore handling 

Direct  Definite  Medium  Local  Medium 

Visual Impact  Equipment, Plant Structures, Stockpiles, Trenches, Pits etc. 

Direct  Definite  High  Local  High 

Occupational Impacts 

Noise and Dust Direct  Definite  Medium 

Immediate area 

Medium 

Rehabilitation (Decommissioning & Mine Closure) 

Excavated trenches, pits, waste dump, etc.  Direct  Definite  High 

Immediate area 

High 

Plant Structure, Camp structures  Direct  Definite  High 

Immediate area 

High 

Waste Direct  Definite  Medium 

Immediate area 

Medium 

Roads and Tracks  Direct  Definite  High  Local  High 

 

 

Page 43: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

42 | P a g e     o f   E I S   a n d   E M & S P    

 

6. MITIGATION OF IMPACTS 

Having identified potential impacts in the previous chapter, in this chapter a summary is provided  of  measures  to  mitigate  the  identified  potential  adverse  impacts  which  are considered to be of moderate to high significance.  

6.1 Mitigation of Physical Environmental Impacts  

Most of  the physical environmental  impacts  identified earlier  involve  impacts  that are direct and physical  in nature. These  include physical pollution  (littering), contamination or pollution of water, noise and dust pollution, soil degradation and aesthetic  impacts. These result  from  the  choices  of  physical  mine  location  and  construction  of  operations  (site selection); carrying out the operations (mining and processing) and decommissioning. 

6.1.1 Site Specific Impacts 

Most of the impacts associated with specific site selection for various activities such as location of accommodation and office blocks, plants and workshops on the licence area can be eliminated through proper management controls that include: 

• Locating those sites close to existing tracks, preferably on already disturbed ground, and utilising existing infrastructure. 

• Providing ablution facilities such as chemical toilets, French drains or pit system and ensuring that they are maintained in a hygienic and good working order. 

• Ensuring  that  on  site  waste management  facilities  (such  as  waste  containers  or skips) are provided. No waste  is to be buried on site and all waste generated must be transported to the nearest designated waste disposal site. 

• Only  uncontaminated,  non‐hazardous  combustible  substances  (e.g.  wood, cardboards, paper and food scraps) if not needed for recycling, they may be burned on site. 

• Ensuring  that  all  surroundings within  the  licence  area  are  kept  in  clean  and  neat conditions at all times and that windblown litter is cleared on a daily basis. 

• Ensuring  that  fire  extinguishers,  first  aid  kits  and  any  other  relevant  safety equipment are available. 

 

Page 44: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

43 | P a g e     o f   E I S   a n d   E M & S P    

 

6.1.2 Loss/Disturbance of Biodiversity and Land Degradation 

To minimize loss of biodiversity and land degradation, the proponent will undertake the following measures:‐  

• Ensure minimal  vegetation clearance;  • Stock pile top soil for future use and restoration of soil;  • Carry out detailed soil analysis;  • Restore disturbed areas;  • Monitor movement of equipment; and • Rehabilitate waste dumps and plant vegetation on all the slopes.  

6.1.3 Sediment Load 

To reduce sediment load, the following will be undertaken: 

• Backfilling of all excavations;  • Planting of trees and grass; • Construction of run‐off prevention; and  • Progressive rehabilitation of mined‐out areas. 

6.1.4 Surface / Underground Water Pollution  

To  prevent  accidental  spillage  from  occurring  causing  water  pollution  and contamination, the following measures are recommended: 

• Provision of and maintenance of adequate bounding (i.e. impervious concrete slabs, or  plastic  linings,  drip  trays,  traps,  sumps,  etc.)  where  hazardous  materials  are stored and handled (e.g. at diesel generators and refuelling depots). Bounds will be adequately sized and capable of containing all the substances they are intended for. Bound walls will be constructed, for example around the bulk fuel tanks. 

• Always bounded areas will be used when re‐fuelling or doing maintenance work on vehicles, machinery or  equipment or when  transferring hazardous materials  from one container to another.  

• Hazardous substances  (hydrocarbons, etc.) will be stored  in a well‐ventilated area, and behind lock and key. 

• There will be installed sufficient fire fighting equipment at the campsites. 

• Ensuring  that all  staff are adequately protected and educated about  the  safe and proper handling and disposal of hazardous substances. 

Page 45: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

44 | P a g e     o f   E I S   a n d   E M & S P    

 

• Used  fuels, oils, hydraulic  fluids, paints and  solvents, and grease will be  stored  in drums or other suitable containers. It is essential that this waste type is segregated from general or domestic waste stream. These wastes shall be labelled, sealed and removed from the site to an appropriate disposal site or recycling facility. 

• In  the  event  of  a  hazardous  spill,  whether  accidental,  deliberate  or  through negligence; on site or during transportation of these substances to/from the site: 

o Immediately implementing actions to stop or reduce and contain the spill, 

o Reporting the spill to the site manager, 

o Collecting  contaminated  soil, water  and  other material  and  dispose  of  at  an appropriate site. 

6.1.5 Air Pollution 

Air pollution impacts may be effectively minimised through: 

• Periodic wetting of the road surfaces, particularly in areas where a significant safety risk exists. 

• Restriction of vehicle speeds on site. 

• Effective dust extraction, particularly at ore transfer points on the washing plants. 

• Limiting disturbance to soils by remaining on existing tracks within the licence area, thereby maintaining the integrity of the soil surface, and 

• Provision of personal protective equipment (PPE) to all those employees potentially exposed to silica in dust through the provision of adequate face masks. 

• Conducting regular maintenance of equipment to reduce emissions; 

• Identifying and using fuels that have minimum emissions;  

• Conducting  blasting  on  specific  days  and  time,  limited  blasting  practices  will  be applied;  

6.1.6 Waste Dumps and Other Infrastructure 

Sites  will  be  selected  for  the  location  of  waste  dumps,  haul  roads  and  other infrastructure such that those operations do not interfere with the natural drainage system. Waste dumps slopes will be stabilized and vegetations planted on them in order to prevent sediment runoff. 

Page 46: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

45 | P a g e     o f   E I S   a n d   E M & S P    

 

6.1.7 Noise and Vibrations 

It is noted that noise levels generated by a source should not add more than 7 dB(A) to the ambient noise levels in an area. A distance of approximately 1 km is required during the day  before  the  noise  generated  for  instance  by  heavy moving  equipment  is  dissipated sufficiently  to meet  the 7 dB(A)  requirement. During  the evening, however, a distance of approximately  4  to  6  km  is  required  to  achieve  the  same  result.  As  such  the  following measures will be used in mitigating noise impacts: 

• Installation of mufflers  in all generators and ensuring that generators that operate the plant, are run during day time only. Smaller generators will be run for supplying lights for security and accommodation quarter during the night; 

• Operating heavy earth moving machinery and carrying out mining operation during day time only; 

• Operating the washing plant during day time. 

• Requesting workers to keep noise levels in their quarters low at all times. 

Destruction  of  property  from  vibrations  e.g.  due  to  blasting,  will  be  mitigated  by deploying  limited blasting techniques and awareness to the community in the surrounding the area. Geophones will be used to monitor blasting intensity so as to ensure that blasting vibrations and noise levels are kept to acceptable thresholds. 

6.1.8 Health and Safety Hazards 

These  can  be  avoided  by  providing  personal  protecting  equipment,  training  and maintaining appropriate sign posts conspicuously. 

6.2 Mitigation of Socio‐Economic Impacts 

Socio‐economic impacts are complex, far reaching and full of or laden with perceptions. Due  to  this,  effective  communication  between  the  proponent  and  the  surrounding communities is the key if satisfactory mitigation measures are to be realistically achieved. It should  be  note  however  that,  because  of  varying  expectations  of  each  stakeholder balancing these expectations is not an easy task.  

Demographic differences  and  personal beliefs may  be  based  on  a  range  of  culturally determined  influences such as religious beliefs,  ideology,  lifestyle, expectations and so on. Similarly,  preferred  solutions  to  problems  are  also  influenced  by  cultural  beliefs  and altruistic values. 

Page 47: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

46 | P a g e     o f   E I S   a n d   E M & S P    

 

From  initial  consultation with  the  stakeholders,  the  community had  a  view  that  their long term social problems, like lack of school, health facility and infrastructure will be eased by the project. The local government reflected the views of the community that the project will assist  in solving some  local problems. Conversely,  the  leaders at  the district  level had expectations that the project will bring more harm than good to the community.  

The  proponents  are  propagating  that  the  project  will  assist  and  provide  the  local community with the basic social services they expect. With more knowledge and continued and  constant  consultations,  it  is  believed  that  all  stakeholders’  expectations  will  be achieved. 

6.3 Measures to Mitigate Environmental and Socio‐Economic Impacts 

The  following  table  summarises  in  detail  the  measures  to  mitigate  potential environmental and socio‐economic impacts due to the mining project. 

Table 6.1: Mitigation Measures 

Potential Impact  Mitigation measures Rating of Impact After Mitigation 

Litter 

Provision of on‐site waste management  facilities  (such as waste containers) 

Low 

Strict control and periodic independent audits 

Not  tolerating  illegal  dumping  and  littering  by  staff within and outside licence area 

Ensuring  that  the  staff  quarters,  mine  site  and  the surroundings  are  kept  clean  and  neat  at  all  times  and that windblown litter is cleared on a daily basis. 

Water Pollution (Management of 

Hazardous Material) 

Hazardous substances (hydrocarbons etc.) will be stored in a well‐ventilated area, and behind lock and key. 

Low 

Used oils, fuel, hydraulic fluids, paints and solvents, and grease  will  be  stored  in  drums  or  other  suitable containers.  The  drums  will  be  labelled,  sealed  and removed from the site to an appropriate disposal site or re‐cycling facility. 

Oil contaminated  soils  (e.g. From  spillages etc.) will be collected,  stored  and  removed  for  disposal  at  an appropriate waste storage facility. 

Providing  and  maintaining adequate  bounding  where hazardous materials  are  stored  and  handled  (iso  9002 compliant) 

Ensuring  that  all  staff  are  adequately  protected  and trained  in the safe and proper handling and disposal of hazardous substances. 

Page 48: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

47 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Potential Impact  Mitigation measures Rating of Impact After Mitigation 

 (Accidental Spillages) 

Prohibiting smoking  near  refuelling  depots  or  near  any flammable substances. 

Medium Installing sufficient fire fighting equipment available at the campsite. 

Water Pollution (Sewage) 

Providing  ablution  facilities  such  as  chemical  toilets,  French drains  or  pit  system.  These  facilities will  be maintained  in  a hygienic and good working order. 

Low 

Impact to Flora 

Avoiding destroying vegetation as much as possible. 

Medium 

Ensuring  staff  awareness  so  as  to  prevent  the  unwanted destruction of vegetation. 

Prohibiting  the use of  vehicles off established and well used tracks within the licence area. 

Ensuring  topsoil and overburden  is conserved and  stockpiled separately for later rehabilitation of disturbed areas 

Impact to Fauna 

Applying  strict disciplinary measures  to  staff  caught  trapping or attempting to trap wildlife. 

Low 

Adherence  to  rules  with  respect  to  littering  in  order  to avoid/prevent attracting pest animals. 

Enforcement of  speed  restriction on all mining haul  roads  to prevent accidents with animals. 

Avoiding any damage to a 10m buffer zone from the edge of river banks. 

Disturbance to Soils/Erosion 

Prohibiting  the use of  vehicles off established and well used tracks within the licence area. 

Medium 

Finalisation of a detailed mining plan, showing areas to be mined and all proposed haulage routes, including possible new routes. 

Enforcement of the mining plan and an audit of compliance to the finalised mining plan to reduce impact to soils to an absolute minimum. 

Noise Ensuring adequate and regular maintenance of machinery and equipment. 

Low 

Dust 

Restriction of vehicle speeds on site to less than 30 km/h 

Low 

Periodic  wetting  of  the  road  surface,  particularly  in  areas where a significant safety risks exists.. 

Effective dust extraction, particularly at ore transfer points on the washing plants. 

Limiting  disturbance  to  soils  by  remaining  on  existing  tracks within  the  licence  area,  thereby maintaining  the  integrity  of the soil surface. 

Page 49: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

48 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Potential Impact  Mitigation measures Rating of Impact After Mitigation 

Visual Impact 

Ensuring  adequate  control  of  dust  generated  within  the mining areas, including the haul roads and washing plant. 

Medium 

Adequate disposal methods for all waste types, including domestic waste, scrap metal, etc. 

Reducing the visibility of structures, including water tanks, bulk fuel tanks, etc. by adequate sitting and painting with a non‐reflective paint that blends in with the surroundings. 

Reducing  the  visibility  of  open  trenches,  pits  and  stockpiles through ongoing rehabilitation. 

Sitting of plants and other structures out of the line of sight. 

Promotion of a  culture of awareness amongst  all employees involved  with  mining  on  the  visual  impacts  resulting  from mining operations. 

Occupational Impacts Provision of personal protective equipment  (ppe) such as ear plugs and dust masks to limit employee exposure to dust and noise. 

Medium 

Rehabilitation (Excavations) 

Ensuring  that  used  pits  and  trenches  are  backfilled  on  a continuous basis. Waste materials will be backfilled into active trenches  to ensure  the  surface area of excavated  trenches  is minimised. 

Medium 

Where topsoil is available, it will be spread evenly over areas requiring rehabilitation. Overburden and mud will be pre‐backfilled first. 

Waste dumps if applicable will be contoured to fit in with the lie of the natural topography as much as possible. 

Backfilled material will be  compacted marginally  (to prevent slumping) and contoured to follow the natural contours of the land. 

Rehabilitation  Closure and 

Decommissioning (Plant Structure) 

Removing  all  construction  equipment,  surplus  material  and temporary structures, fence and works of every kind. 

Low 

Salvaging and  removing all structures,  including all scrap and other plant structures and equipment. 

Breaking‐up bounds and all other concrete slabs and removing these, together with all waste concrete, to a recognised waste dump. 

Demolishing  buildings  that  will  no  longer  be  used  by  the community, if applicable. 

Page 50: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

49 | P a g e     o f   E I S   a n d   E M & S P    

 

 

Potential Impact  Mitigation measures Rating of Impact After Mitigation 

Rehabilitation  (Wastes) 

Ensuing oil spills are cleaned up immediately. 

Low Ensuring contaminated soils are disposed of at an approved disposal site. 

Ensuring all construction rubble (i.e. waste concrete) are removed from site. 

Rehabilitation  Closure and 

Decommissioning (Roads & Tracks) 

Ensuring the surface of used roads and tracks that are not  in use anymore are broken up (scarified) to alleviate compaction and promote natural re‐vegetation. 

Medium  

Employment Employ  locals  as many  as possible  to  reduce workers  influx. Provide  training  to workers  and  locals  so  as  to  get qualified personnel. 

Medium 

Social Responsibility Involve  the  surrounding community prior  to undertaking any social  service project and any other works  to  reduce conflict and make them part of the partnership to that development 

Low 

 

Page 51: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

50 | P a g e     o f   E I S   a n d   E M & S P    

 

7 ENVIRONMENT AND SOCIAL MANAGEMENT PLAN  

7.1 Monitoring Activities 

It  is necessary to put  in place a plan which shall ensure that all mining activities  in the  licence  areas  are  sustainable. A mini‐laboratory will  be  constructed  at  the  site  for water quality analysis on issues such as turbidity; total dissolved and suspended solids and coli forms and acidity or alkalinity levels.  Dust monitoring stations will be established near the  pit  and  at  the  processing  plant  to  analyse  the  air  quality  and monitor  particulate matter at the level PM10 .  

Furthermore, monitoring of activities will include to: 

• Monitor storage and transportation procedures and equipment; 

• Monitor employees and contractors training to ensure that they are familiar with safe material handling  and appropriate fist aid measures; 

• Monitor  risk of  leakage  fuel by  checking  the  corrosion of  tanks  and other facilities; 

• Monitor the possibility of acid rock drainage on waste dump; 

• Monitoring  the  measures  taken  to  protect  plants  and  aquatic  biological resources; and 

• On  the  socio‐economic  activities  will  be  to monitor  agriculture,  livestock development and other economic activities  in the area and their  impact to the project. 

• monitoring of complaints of any compensation issues and method used., 

• monitor  health  and  safety  of  the  workers  (incident  of  diseases  including HIV/AIDS and water access and use). 

7.2 Resource Evaluation/ Cost Benefit Analysis 

The cost benefit analysis should have contained  financial analysis, economic analysis of  the mining  activities  and  extended  cost  benefit  analysis  for  the  proposed  project. However,  lack  of  information  from  aspects  such  as  the  feasibility  study  and  quantity survey,  list  of  units  and  costs  of  various  materials  that  will  be  used  in  the  mining construction and costs of other process activities, prices per head and overall operating costs, made it difficult to prepare a detailed cost benefit analysis in this statement. These 

Page 52: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

51 | P a g e     o f   E I S   a n d   E M & S P    

 

aspects of  resource evaluation and  financial analysis will be contained  in  the Feasibility Study Report. 

7.2.1 Benefits Related to the Project 

Several  benefits will  be  attributed  to  the  proposed  development  both  at  local  and national  levels  in  terms  of  revenue  generation  and  stimulating  local  economic  growth through employment and  local purchase of  goods  and  services. The project  is  going  to give priority of employment to the local people for skilled and unskilled work. 

At  the  national  level,  benefits  will  be  accrued  from  increased  government  tax revenues  from sales proceedings,  increased balance of payments  from  foreign exchange earnings and employment generated from value‐added activities. 

7.2.2 Costs Related to the Project 

The costs  related  to  the project  include  those of selection of equipment and spares based  on  the  chosen  technology  and  also  considering  the  technology  needs  for  future projects  or  further developments  like  underground mining  and  production  selection  of technologies will  involve  to  a  large  extent  possible  use  of  local materials,  service  and labour  force.  Just  as  it  is  apparent  that  a  project  will  have  a  poor  economic  base  if inefficient  technology  is  selected,  on  the  other  hand  a  project  cannot  be  successful without cost consideration and adequate financing. 

Other  inherent  costs  due  to  the  destruction  of  environment  and  opportunity  costs from loss of farmland will be adequately compensated by the benefits from the revenues generated.  In  addition,  the  project  will  restore  all  land  hence;  farmland  will  only  be temporarily lost. 

7.3 Decommissioning 

The company already has a  rehabilitation plan which  is a component of  the closure plan.  The  rehabilitation  plan  identifies  the  activities  and  research  required  to  address ongoing rehabilitation for exploration works. 

Upon  final  implementation  of  the  project,  decommissioning  of  the  project  closure activities will be undertaken to ensure that the site is properly decommissioned and does not  pose  any  ongoing  risk  to  the  environment  and  humans.  All  buildings/tents will  be dismantled. Holes that were dug during exploration will be filled to form stable ground. All remains of plastic cables and wires will be collected and safely disposed at selected areas. 

All water ponds will either be backfilled to required standards as provided for  in the Mining  (Environmental  Management)  and  Mining  (Occupational  Health  and  Safety) Regulations,  1999  or  left  for  used  by  the  surrounding  community.  The  proponent will 

Page 53: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

52 | P a g e     o f   E I S   a n d   E M & S P    

 

prepare  a  Mining  Closure  Plan  involving  consultation  with  all  stakeholders  aimed  at providing better alternative livelihood to the local community following closure. 

7.4 Detailed Summary of the Environmental Management Plan 

The  following  table  summarises  in detail  the proposed environmental management plan  for  the  possible  impacts  identified  from  the  proposed  project.  The  total  annual package of management measures is estimated to cost over TZS 198 million. 

Table 7.1: Environmental Management Plan (EMP) General  

Management Issue 

Specific Management 

Issue 

Management Strategies, Actions & Measures 

Responsibility & Implementation 

Estimated Cost TZS/year 

Solid

 Waste M

anagem

ent 

Waste Rock/Gravel 

Provision of on‐site waste rock management facilities  

Site Foreman  6,000,000 

Send waste rock to backfilling areas that have been mined out, and ensure the sites are graded prior to introduction of topsoil. 

Mine & Environmental foremen 

4,000,000 

Bund stockpiled waste rock to avoid displacement 

Site Foreman 7,000,000 

Non‐Hazardous Wastes 

Not tolerating illegal dumping and littering by staff within and outside licence area  

Mine Manager & Site Supervisor  1,300,000 

Only uncontaminated, non‐hazardous combustible substances may be burned on site. 

Site Supervisor 1,700,000 

Ensuring that the staff quarters, mine site and the surroundings are kept clean and neat condition at all times and that windblown litter is cleared on a daily basis. 

Site Supervisor  

4,000,000 

Provision of on‐site waste management facilities (Such as waste containers) 

Site Foreman 1,000,000 

Strict control and periodic independent audits 

Mine Manager 5,000,000 

Water and

 Sew

age Man

agem

ent 

Water intake facility 

Constructing water intake facility on properly selected sites; 

Mine Manager & Site Supervisor  8,000,000 

Conduct regular consultation with other users within the vicinity of the licence area and relative bodies. 

Mine Manager & Site Supervisor  2,000,000 

Institute and implement water management plan and water quantity monitoring programme. 

Mine Manager 1,000,000 

Water Pollution (spillages) 

Institute and implement water quality monitoring programme  

Site Foreman 2,000,000 

Ensure regular and proper maintenance of equipment and machinery. 

Mine Manager 3,000,000 

Instigate proper bounding procedure for all facilities containing and used for storage of hydrocarbons and other chemicals. 

Construction, Mine & Environmental Foremen 

5,000,000 

Water Pollution 

Conduct hydrological study within areas earmarked for establishment of sewerage. 

Mine Manager 4,000,000 

Page 54: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

53 | P a g e     o f   E I S   a n d   E M & S P    

 

General  Management 

Issue 

Specific Management 

Issue 

Management Strategies, Actions & Measures 

Responsibility & Implementation 

Estimated Cost TZS/year 

(Sewage)  Institute and implement monitoring programme and ensure toilet facilities are kept in a hygienic order. 

Site Foreman 

1,500,000 

Water pollution (general) 

Assess current storm water drainage patterns and construct drainages that will isolate storm water from other water source. 

Mine Manager 

5,500,000 

Prepare reports and disseminate information on water status (quantity & quality) to all stakeholders on a regular basis. 

Mine Manager 

1,500,000 

Topsoil M

anagem

ent 

Topsoil removal 

Remove topsoil only on areas earmarked for stripping in the mining programme. 

Site Supervisor or Manager  8,500,000 

Use lightweight equipment in topsoil removal to minimise destruction of soil structure and biota. 

Site Supervisor or Manager  ‐ 

Avoid and minimise mixing topsoil with barren overburden 

Site Foreman ‐ 

Topsoil stockpiling 

Stockpile topsoil to heights not exceeding one metre to conserve the biota within. 

Site Foreman 3,000,000 

Avoid stockpiling topsoil on slopes in order to minimise soil erosion. 

Mine Manager  

.Avoid compaction of stockpiled topsoil during and after stockpiling. 

Site Supervisor  

Topsoil backfilling 

Ensure topsoil stockpiled first is sent back to backfilling  

Mine & Environmental Foremen 

5,000,000 During backfilling, lightweight vehicles/equipment should be used to minimise compaction of the topsoil. 

Mine & Environmental Foremen 

Air Qua

lity Co

ntrol 

Dust  Ensure all roads are wetted on a frequent basis and vehicle speed is below 40 km/hr. 

Site Supervisor  6,000,000 

Instigate effective dust extraction methods, particularly at ore transfer points on the processing plants. 

Site Supervisor  

2,000,000 

Limit disturbance to soils by remaining on existing tracks within the licence area. 

Mine & Environmental Foremen (M&EF) 

2,000,000 

Implement dust monitoring programme for the site areas. 

M&EF 2,000,000 

Vegetating exposed and cleared surfaces/areas. 

M&EF3,000,000 

Implement regular employee health medical checkups, including pre‐ and post checks assessment for nose, throat and lungs. 

Health Officer 

2,000,000 

Implementing good housekeeping practice in order to minimise accumulation of loose dust piles. 

Site Supervisor 

2,000,000 

Emissions  Ensure regular equipment maintenance to minimise emission. 

Site Foreman 3,000,000 

Page 55: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

54 | P a g e     o f   E I S   a n d   E M & S P    

 

General  Management 

Issue 

Specific Management 

Issue 

Management Strategies, Actions & Measures 

Responsibility & Implementation 

Estimated Cost TZS/year 

Ensure all equipment needing stacking is properly stacked. 

Site Supervisor 2,000,000 

Instigate and implement emission controls and monitoring programme. 

M&EF 3,000,000 

Provide PPEs to employees and conduct training on their use. 

Safety Officer 1,000,000 

Implement regular employee health medical checkups, including pre‐ and post checks assessment for nose, throat and lungs. 

Health Officer 

2,000,000 

Conduct mining and washing operations during daytime only. 

Site Foreman 1,000,000 

Noise Gen

eration Co

ntrol 

Noise  Ensure regular equipment service to minimise noise generation. 

Chief Mechanic 2,000,000 

Provide PPEs to employees and conduct training on their use. 

Safety Officer 1,000,000 

Instigate and implement employee’s regular health medical checkups for hearing; including hearing checkups assessment prior to and after employment. 

Health Officer 

1,000,000 

Implement noise monitoring programme for site areas. 

Safety Officer & Environmental Foreman 

400,000 

Limiting hours of operation. (Operations during daytime only). 

Site Supervisor 800,000 

Adequate distances between mining and residential areas. 

Mine Manager 1,600,000 

Locating haul roads a sufficient distance from residences and in such a way that there is as much screening from residences as possible. 

Site Foreman 

1,500,000 

Locating plants a sufficient distance from residences. 

Manager 1,500,000 

Lining noise‐generating components and equipment with resilient material to dampen vibrating surfaces. 

Chief Mechanic 

3,000,000 

Fitting effective mufflers to all items of equipment. 

Chief Mechanic 2,000,000 

Maintaining all roads in good condition to reduce vehicle noise. 

Mine Manager  2,000,000 

Use of tree cover to muffle noise from site activities to reduce noise disturbances to areas outside the site. Planting trees on licence perimeter. 

Mine & Environmental Foremen  1,000,000 

Hazardo

us 

Material 

Man

agem

ent  Storage and 

Handling Implement proper storage and handling of hazardous materials, including requirements regarding the segregation of incompatible materials. 

Site Supervisor r 

5,000,000 

Page 56: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

55 | P a g e     o f   E I S   a n d   E M & S P    

 

General  Management 

Issue 

Specific Management 

Issue 

Management Strategies, Actions & Measures 

Responsibility & Implementation 

Estimated Cost TZS/year 

Instigate and implement employee training programme, including the use of Material Safety Data Sheets (MSDS). 

Site Supervisor  & Safety Officer  2,000,000 

Used oils, fuel, hydraulic fluids, paints and solvents, and grease should be stored in drums or other suitable containers and labelled, sealed and removed from the site to an appropriate disposal site or re‐cycling facility. 

Chief Mechanic 

3,000,000 

Oil contaminated soils (e.g. from spillages etc.) must be collected, stored and removed for disposal at an appropriate waste storage facility 

Mine & Environmental Foremen 

2,500,000 

Constructing storage facilities that will contain the materials in all foreseen circumstances. 

Construction Supervisor  5,000,000 

Implement physical controls and procedural measures to ensure that no materials escape during normal and abnormal operations. 

Safety Officer 

1,500,000 

Instigate emergency response plans in place to ensure immediate action should an accidental release occur. 

Safety Officer 

2,000,000 

Instigate and keep adequate records and review them regularly so future environmental problems are anticipated and avoided. 

Mine & Environmental Foremen 

500,000 

Uses  Ensure regular service of equipment using hydrocarbons to eliminate spills. 

Site Foreman 2,500,000 

Minimise the use and/or generation of hazardous materials wastes. 

Mine Manager 1,000,000 

Promote re‐use and recycling of materials whenever possible. 

Mine Manager 400,000 

Visua

l Impa

ct M

anagem

ent 

Visual Impacts (Workers) 

Minimise or eliminate dust generation to promote better vision for workers. 

Site Supervisor or Manager 

500,000 

Reduce the visibility of structures by adequately sitting and painting with appropriate paints that are non‐reflective. 

Site Supervisor or Manager 

800,000 

Implement physical controls and procedural measures to ensure that no unsightly situation is visible. 

Construction & Environmental Foremen 

500,000 

Visual Impacts (Surrounding Community) 

Use of tree cover to obscure the mining activities, structures and processing plants by planting trees around the perimeter of the MLA. 

Site Foreman 

500,000 

Reduce the visibility of structures by adequately sitting and painting with appropriate paints that are non‐reflective. 

Mine Manager 

500,000 

Decom

mission

ing

 and

 Closure  Dismantling 

of Site structures 

Consultation with local community on alternative use of the site. 

Mine Manager & Public Relation Officer 

2,000,000 

Page 57: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

56 | P a g e     o f   E I S   a n d   E M & S P    

 

General  Management 

Issue 

Specific Management 

Issue 

Management Strategies, Actions & Measures 

Responsibility & Implementation 

Estimated Cost TZS/year 

Dismantling and removal of all plants and structures that the community will no longer need. 

Construction Supervisor  12,000,000 

Removal of all earthmoving equipment Site Foreman  13,000,000 

Site Clean‐up  Filling of excavated sites and restoring of site to conform to the natural topography. 

Environmental & mine Foremen  10,000,000 

Planting of indigenous trees to prevent soil erosion and re‐seeding of natural grasses. 

Environmental & mine Foremen  5,000,000 

      Subtotal 198,500,000  

  

 

Page 58: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

57 | P a g e     o f   E I S   a n d   E M & S P    

 

7.5 Detailed Social Monitoring Plan (SMP) 

The table below outlines a detailed plan to monitor measures to mitigate social impacts. It is estimated that the social monitoring plan will cost around TZS 57 million per annum to maintain. 

Table 7.2: Social monitoring Plan (SMP) General Monitoring Issue 

Specific monitoring Issue  

Strategies, Actions & Measures  Responsibility & Implementation 

Estimated Cost TZS/year 

Surrou

nding Co

mmun

ity Interaction 

Displacement and security 

Consults with the surrounding community and local authorities on any pending compensation and settlement issues. 

Mine Manager & Public Relation Officer (PRO) 

1,000,000 

Review and monitor regularly the status of migration of people around the licence area. 

Mine Manager & Public Relation Officer 

2,000,000 

Improve and support existing security status within the area in conjunction with the local community and authorities. 

Mine Manager & Public Relation Officer 

5,000,000 

Pressure on resources 

Consult, organise and conduct campaigns aimed at imparting knowledge as to the importance of conservation, effective and efficient use of resources. 

Environmental & Public Relation Officer  5,000,000 

Business opportunities 

Establish community outreach programmes in consultation with the recipient and local authorities. 

Mine Manager & Public Relation Officer 

5,000,000 

Provide assistance to surrounding local communities on way to start and keep up business ventures that are sustainable and non dependent to the mining activities in the area. 

Mine Manager & Public Relation Officer  3,000,000 

Employment  Give priority of employment to local people where appropriate. 

Mine Manager & PRO  4,000,000 

Give and support on job training in order to improve workers ability. 

Mine Manager & Site Supervisor  2,000,000 

Access to Services 

Provide and assist in the provisions of health and education. 

Mine Manager, Health Officer & PRO 

20,000,000 

Assist in providing the community access to safe and clean water. 

Mine Manager, Health Officer & PRO 

10,000,000 

      Subtotal  46,000,000 

 

 

Page 59: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

58 | P a g e     o f   E I S   a n d   E M & S P    

 

8 CONCLUSION AND RECOMMENDATIONS 

8.1 Conclusion 

The  company  plans  to  engage  villagers who will  volunteer  to  be  trained  on  how  to monitor water quality as well as  in tree planting campaigns.  Indigenous tree nurseries will be established and trees will be offered to villages to plant  in their areas as a part of tree planting campaigns.  

The proponents aspire to contribute towards several socio – economic facilities that will be established  in the surrounding area  including health centre; school building and others that might be mooted by the surrounding community. 

8.2 Recommendations 

In order to ensure that mitigation measures are successful and  impacts are minimized, the focus will be on ensuring operations follow the established procedures. Conduct training to  all  employees  in  environmental management,  conservation  norms  and  responsibilities and  ensure  that  joint  efforts  are  run  collaboratively  so  that  all  personnel  receive  basic environmental awareness  training and contingency plans are  in place  to deal  swiftly with any potential negatively impacting incidents and incidences.  

Should  there  be  any  operational  changes  likely  to  cause  a  significant  shift  to  the assessment of  impacts, this will be  incorporated within the operational addendum. At this stage  it  is thought most  likely that potential changes will be minor and that these will not significantly alter the impact assessment.  

The Environmental Management Plan will be  reviewed periodically and  in accordance with the laws to ensure that all changes in the environment as a result of mining operations are adequately addressed. 

Page 60: THE MANG’ONYI GOLD MINING PROJECT SINGIDA ... Gold...Mr. Idd Mhina & Mr. Frank Nnongi 5 | Page of EIS and EM&SP During the course of initial mining operation, the proponent discovered

Mr. Idd Mhina & Mr. Frank Nnongi  

59 | P a g e     o f   E I S   a n d   E M & S P    

 

BIBLIOGRAPHY 

Agricultural and Livestock Policy, 1987 

Beekeeping Act, 2002 

Environmental Management Act, 2004 

Explosives Act, 1963 

Land Act, 1999 

Local Government (District and Urban Authorities) Act, 1982 

Mineral Policy, 1996 

Mining Act, 1998 

National Beekeeping Policy, 1998 

National Environmental Policy, 1997 

National Forestry Policy, 1998 

National Health Policy, 1990 

National Human Settlement Development Policy, 2000 

National lands Policy, 1995 

National Tourism Policy, 1999 

National Water Policy, 2002 

Occupational Safety and Health Authority (OSHA) Act, 2005 

Village Land Act, 1999 

Water Act, 1981