the korea shipbuilders’ association shipbuilders’ experience & feedback on iacs c ommon s...
TRANSCRIPT
The Korea Shipbuilders’ AssociationThe Korea Shipbuilders’ Association
Shipbuilders’ Experience & Feedback on IACS Common Structural Rules
1.1. IntroductionIntroduction
2.2. Technical Issues for Oil TankersTechnical Issues for Oil Tankers
3.3. Technical Issues for Bulk CarriersTechnical Issues for Bulk Carriers
4.4. Performance of IACS FeedbackPerformance of IACS Feedback
5.5. SoftwareSoftware
6.6. Concluding RemarkConcluding Remark
ContentsContents
1/31
1. Introduction1. Introduction
Common Structural Rules (CSR)Common Structural Rules (CSR)
- Adopted at the End of 2005
- Effective since April 1, 2006
- Oil Tankers, Length ≥150m
Bulk Carriers, Length ≥ 90m
2/31
1. Introduction1. Introduction
Design Experience (Oil Tankers)
MR Aframax 1 Aframax 2 Suezmax VLCC
LBP 173.9 234 239 264 324
B 32.2 42 44 50 60
D 19.1 21.2 21 23.2 29.6
Ts 13.15 15 14.9 17.15 22
DWT 50 K 105 K 115 K 165 K 317 K
Classification LR KR/ABS DNV/ABS DNV KR/ABS
3/31
1. Introduction1. Introduction
Design Experience (Bulk Carriers)
Supramax Capesize
LBP 183.3 283
B 32.26 45
D 18.5 24.7
Ts 13 18.2
DWT 58 K 180 K
Classification KR/LR LR/BV
4/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.1 Weight Increase / Corrosion Addition
2.2 Minimum / Maximum Draughts of Abreast Full / Empty Conditions
2.3 D/B Floor Thickness Requirement (Bottom Slamming)
2.4 Shear Force Correction in way of Bulkhead Stringers
2.5 Prescriptive Requirement for Primary Support Member (PSM)
2.6 Effect of Toe Grinding on Fatigue Strength
5/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.1 Weight Increase / Corrosion Addition [Unit : ton]
MR Aframax 1 Aframax 2 Suezmax VLCC
Weight
Increase
+415
(7.5%)
+1,000
(9.4%)
+940
(8.4%)
+1,200
(7.4%)
+2,000
(6.0%)
Note : Cargo Block Only
6/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
Note: Design Corrosion Addition
of CSR <Pre-CSR(ABS)>
Received a letter from an Received a letter from an engineering company ;engineering company ;
“… preparing a bid for an FPSO to be converted from a 1996 DH VLCC … In our search for candidate tankers we looked closely at your hull (1997)your hull (1997) and found it in excellent condition. Ballast tank coatings, cargo tank under deck coatings, and tank bottom coatings are still in excellent excellent conditioncondition so there is virtually no corrosionvirtually no corrosion. We looked at another shipyard’sanother shipyard’s tanker tanker (1996)(1996) which was built with no coating under deck in the cargo tanks, and found general wastage around 2mm2mm on the deck on the deck plateplate; there was little or no wastagelittle or no wastage on uncoated structure (longs, transverse webs) lower in the cargo tanks.”
3mm<1mm>
3mm<2mm>
3.5mm<1.5mm>
4mm<1mm>
4mm<1.5mm>
3mm<2mm>
4.5mm<1.5mm>
3.5mm<1.5mm>
3.5mm<1.5mm>
2.5mm<1mm>
2.5mm<1mm>
2.5mm<1mm>
3mm<1mm>
7/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.2 Minimum / Maximum Draughts of Abreast Full / Empty Conditions
L. BHD Type Center L.BHDCenter L.BHD Two(2) L.BHDTwo(2) L.BHD
Rule reference
ConditionAbreast
Full Abreast Empty
Abreast Full
Abreast Empty
Prescriptive 0.6 Tsc 0.9 Tsc 0.6 Tsc 0.9 Tsc Table 8.1.6
FEA
Sea 0.6 Tsc 0.9 Tsc 0.8 Tsc 0.55 Tsc Table B.2.3/
B.2.4Harbor 1/3 Tsc Tsc 0.7 Tsc 0.65 Tsc
Note : Tsc = Scantling Draught
8/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
Condition Draught
Abreast
Full Condition
Tmin ( l( lhh / L ) / L ) x Tsc
But not lesser than heavy ballast arrival condition
Abreast Empty Condition
Tmax ( L / l( L / lhh ) ) x Tsc
But not greater than Tsc
Min./Max. Draught Requirements (Proposed by KOSHIPA)
9/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.3 D/B Floor Thick. Requirement (Bottom Slamming)
42mm (HT32 )42mm (HT32 )By Prescriptive Req. 42mm(HT32)42mm(HT32)
ttmeanmean = = 65 65 MpaMpa<<164 164 MpaMpa(Criteria)(Criteria) 40%40% ONLYONLY
10/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
- Coefficient ffdistdist must be
lesserlesser, since floor length is short.
- Effect on stiffness of stiffness of bottombottom longitudinalslongitudinals is necessary.
fdist
ffbtm-lgbtm-lg
Prescriptive Requirement
??
11/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.4 Shear Force Correction i.w.o. Bulkhead Stringers
POSITIONMax.
StressStress Criteria
Deviation
Below No.1 STR.
160 Mpa 188 Mpa - 15 %- 15 %
Below No.2 STR.
161 Mpa 188 Mpa - 14 %- 14 %
Below No.3 STR.
220 Mpa 252 Mpa - 13 %- 13 %
26mm (HT32 )26mm (HT32 )By Prescriptive Req.
28mm (mold )28mm (mold )By Prescriptive Req.
28mm (mild )28mm (mild )By Prescriptive Req.
O.T
.BH
D
No.1STR.
No.2STR.
No.3STR.
12/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil TankersPrescriptive Requirement FE Analysis
?? ??
??
13/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.5 Prescriptive Requirement for Primary Support Member (PSM)
CSR specifies as follows;
“The section modulus and/or shear area of a primary support member and/or the cross sectional area of a primary support member and a cross tie may be reduced to 85% of the prescriptive requirementsprescriptive requirements provided that the reduced scantlings comply with the FE cargo tank structural analysisFE cargo tank structural analysis”
14/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
LOAD CASE 10 LOAD CASE 20
Subject requirement is based on simple formula with simple formula with unclear assumptionsunclear assumptions, which can be dealt with by FEA properly and transparently.
Prescriptive Requirement
D = 0.2 D = 0.2 llbdg-dtbdg-dt D = 0.13D = 0.13 l lbdg-dtbdg-dt
Z =Z =1000 M1000 MC C σσyieldyield
LOAD CASE 30 LOAD CASE 40
LOAD CASE 50 LOAD CASE 60 LOAD CASE 70 LOAD CASE 80
LOAD CASE 90 LOAD CASE 10 LOAD CASE 11 LOAD CASE 12
LOAD CASE 13 LOAD CASE 14 LOAD CASE 15 LOAD CASE 16
LOAD CASE 17 LOAD CASE 18 LOAD CASE 19 LOAD CASE 20
FE Analysis15/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
LOAD CASE 10LOAD CASE 20
Subject requirement is based on simple formula with simple formula with unclear assumptionsunclear assumptions, which can be dealt with by FEA properly and transparently.
Prescriptive Requirement
D = 0.2 D = 0.2 llbdg-dtbdg-dt D = 0.13D = 0.13 l lbdg-dtbdg-dt
Z =Z =1000 M1000 MC C σσyieldyield
LOAD CASE 30LOAD CASE 40LOAD CASE 50LOAD CASE 60LOAD CASE 70LOAD CASE 80LOAD CASE 90LOAD CASE 10LOAD CASE 11LOAD CASE 12LOAD CASE 13LOAD CASE 14LOAD CASE 15LOAD CASE 16LOAD CASE 17LOAD CASE 18LOAD CASE 19LOAD CASE 20
FE Analysis16/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
2.6 Effect of Toe Grinding on Fatigue Strength
CSR specifies as follows;
“The benefits of weld toe grinding should not be taken should not be taken into consideration at the design stageinto consideration at the design stage. However, an exception may be made for the weld connection between the hopper plate and inner bottom if the required design fatigue life can not be satisfied by means of practical design options such as increasing local thickness, extending weld leg length and modifying local geometry. The calculated fatigue life is to be greater than 17 years excluding grinding is to be greater than 17 years excluding grinding effectseffects.”
17/31
2. Technical Issues for Oil Tankers2. Technical Issues for Oil Tankers
KOSHIPA carried out fatigue experiment &
analysis with a lot of test specimens.
18/31
3. Technical Issues for Bulk carriers3. Technical Issues for Bulk carriers
3.1 Weight Increase / Corrosion Addition
3.2 Hot Spot Stress for Fatigue Strength Assessment
3.3 Effect of Toe Grinding on Fatigue Strength
19/31
3. Technical Issues for Bulk carriers3. Technical Issues for Bulk carriers
3.1 Weight Increase / Corrosion Addition [Unit : ton]
Supramax Capesize
Weight
Increase+460(8.2%)
+2,200(12.6%)
Note : Cargo Block Only
20/31
3. Technical Issues for Bulk carriers3. Technical Issues for Bulk carriers
Note : Design Corrosion Addition of CSR <Pre-CSR(ABS)>
5.5mm<2.0mm>
6.5mm<1.0mm>
6.5mm<1.0mm>
5.5mm<2.0mm>
4.0mm<1.0mm>
3.5mm<1.5mm>
4.5mm<3.5mm>
4.5mm<1.5mm>
5.0mm<1.5mm>
3.5mm<1.0mm>4.0mm<2.0mm>
3.5
mm
<1
.5m
m>
3.0mm<1.0mm>
3.0mm<1.5or2.0mm>
4.0mm<1.5mm>4.0mm<1.5mm>
21/31
3.2 Hot Spot Stress for Fatigue Strength Assessment
3. Technical Issues for Bulk carriers3. Technical Issues for Bulk carriers
Hotspot Stress = ll x Extrapolated Stress
22/31
3. Technical Issues for Bulk carriers3. Technical Issues for Bulk carriers
0.5t
1.5t
1.0
s
0.8
s
: ExtrapolatedStress
Hotspot Hotspot Stress ?Stress ?
t
Hotspot Hotspot Stress ?Stress ?
23/31
3.3 Effect of Toe Grinding on Fatigue Strength
3. Technical Issues for Bulk carriers3. Technical Issues for Bulk carriers
NOT MentionedNOT Mentioned
24/31
4. Performance of IACS feedback4. Performance of IACS feedback
IACS CSR Maintenance Structure
??
25/31
4. Performance of IACS feedback4. Performance of IACS feedback
4.1 Time Required for Reply by IACS Hull Panel
Subject Ship TypeIssued to
IACS
Received Reply by Shipyard
Duration
Effect of Toe Grinding on Fatigue Strength
Oil Tankers
07.5.14 Not YetNot Yet > 4 months> 4 months
Bottom Forward DraughtOil Tankers
06.12.24 07.1.23 4 weeks4 weeks
Usage Factor for CrosstieOil Tankers
06.12.1 (SAJ)
07.3. (KOSHIPA) Not YetNot Yet > 5 months> 5 months
T.B Spacing on Enlarged LongL.(PMA)
Oil Tankers
07.6.19 Not YetNot Yet > 3 months> 3 months
Stress Increase Factor for Longls i.w.o BHD. for Fatigue
Oil Tankers
07.7 Not YetNot Yet > 2 months> 2 months
26/31
4.2 Interpretation from Each Classification
Classification Item
Ship Type A B C D
Is hull girder strength check necessary for flooding case for IACS UR S25 ?
Bulk Carriers YESYES ?? YESYES NONO
Is a certain portion of dynamic load necessary for non-floodable empty holds in port ?
Bulk Carriers NONO NONO YESYES NONO
4. Performance of IACS feedback4. Performance of IACS feedback
27/31
5. Software5. Software
- Computational Softwares are incompleteincomplete yet.
- There is inconsistencyinconsistency between results of respective Classification Societies so far.
The result of any other Class’ software
(IACS) must be accepted for drawing
approval in due timein due time.
28/31
6. Concluding Remark6. Concluding Remark
CSR is welcomed in principlewelcomed in principle because ;
- It utilizes high technologyhigh technology such as computerized calculation, introduction of dynamic loading and ultimate strength.
- Shipbuilders need to concentrate only only one (1)one (1) set rule.
29/31
6. Concluding Remark6. Concluding Remark
However, However,
- CSR contains several technical subjects, which are NOTNOT transparent / rationaltransparent / rational.
Hence, those should be reinvestigated and corrected as necessary with urgencywith urgency.
30/31
6. Concluding Remark6. Concluding Remark
RobustnessRobustness means
not necessarilynot necessarily the “Fat Boy”.“Fat Boy”.
??31/31
Thank YouQ & AQ & A