the integration of social concerns into electricity power planning - fretz josue

63
The Integration of Social Concerns into Electricity Power Planning: A combined Delphi and AHP Approach By : Fretz Josue 23210104

Upload: fretz-josue-s

Post on 08-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 1/66

The Integration of Social Concerns into

Electricity Power Planning:A combined Delphi and AHP Approach

By : Fretz Josue

23210104

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 2/66

Abstract

The increasing acceptance of the principle of sustainable development has been a majordriving force towards new approaches to

energy planning

Energy planning is a complex process involving

multiple and conflicting objectives such asenvironment, social and economic issues, thisis not an easy task

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 3/66

Abstract

This study explores the issue of the social

impact, as a fundamental aspect of the

electricity planning process, aiming to give

measurable interpretation of the expected

social impact of future electricity scenario

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 4/66

Abstract

A structured methodology, based on a

combination of the Analytic Hierarchy Process

and Delphi process

The metodology is applied for the social

evaluation of future electricity scenarios in

Portugal

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 5/66

Introduction

Sustainable long-range electricity planning

involves tradeoffs between multiple goals, such

as multiple attributes of each competing and

acceptable electricity generation technology

Integrated resource planning should seek to

identify the mix of resources that can best meetthe future electricity needs of consumers, the

economy, the environment and the society

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 6/66

Introduction

Environmental impacts of electricity generationactivities becomes increasingly critical

Cost minimisation is also perceived asfundamental to ensure the competitiveness of the economy.

Long-term electricity planning frequently relieson complex optimisation models drawn tominimise cost, restricted by technical andenvironmental conditions

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 7/66

Introduction

The complexcity of the problem increased furtherdue to the desirable inclusion of a  number of unquantifiable or subjectively valued objectives,

thus making energy planning decisions prone tosome degree of controversy.

For example, renewable energy project, and inparticular wind power plants, frequently have to

face local opposition, and the spread of theserenewable technologies may be slowed down bylow social acceptability

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 8/66

Introduction

The electricity planning process needs to rely ona formal approach for the assessment of theoverall social outcome of each particular

generation mix.This work addresses this matter and deal with thecomplexcity of the social issues surroundingelectricity planning, providing guidance on how

to integrate the social dimension into thedevelopment of sustainable electricity plans forthe future

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 9/66

Energy and Sustainable Development

Energy use and availability are central issues in

sustainable development. Energy is essential

for economic development and for improving

societys living standards.

Until recently, sustainable development was

perceived as an essential environmental issue,

concerning the integration of environmental

concerns into economic decision-making.

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 10/66

For example, for the particular case of the role

of renewable energy sources (RES) to

sustainable development, support the view

that much emphasis is being put on the

environmental benefits, while socioeconomic

impacts have not receive a comparable

attention

Energy and Sustainable Development

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 11/66

G8 Renewable Energy Task Force (2001) recognises:

Economies can only grow if they are notthreatened by environmental catastrophe orsocial unrest. Environmental quality can only beprotected if basic economic needs are fulfilledand individuals take responsibility for publicgoods. Finally, social development rest oneconomic growth as well as a healthyenvironment

Energy and Sustainable Development

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 12/66

The economic, social and environmentalperspectives are all included in the keyelements of a sustainable energy system listed

by Jefferson (2006):Sufficient growth of energy supplies to meethuman needs, energy efficiency andconservation measures, addressing publichealth and safety issues and protection of thebiosphere.

Energy and Sustainable Development

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 13/66

The sustainable development and sustainable

energy planning are based on three

dimensions: economic, environmental and

social.

Energy and Sustainable Development

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 14/66

Achieving the goal of sustainable development

implies recognising and including the social and

environmental impacts of the energy sector in

the decision making process.

Under conditions of sustainable energy planning,

the profitability of energy companies and thefinancial viability of energy project become highly

dependent on non-financial factors.

Energy and Sustainable Development

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 15/66

Energy and Sustainable Development

The simultaneuos assesment of economic, strategic,social, environmental and technical aspects isfundamental for making professionally correctinvestment in any sector.

However, it is particularly important for the energysector, traditionally associated with large-scale projectswith strong and conflicting social impacts: on the onehand, these project are absolutely indispensable forthe social welfare of the population, but on the otherhand, they are frequently associated withenvironmental problems and have to deal with socialopposition

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 16/66

The evaluation of technologies and future

scenarios needs to expand beyond financial

cost alone and the appraisal process must be

based on a framework recognising full social

cost

Energy and Sustainable Development

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 17/66

Electricity power planning is, using the

definition of Hobbs (1995) :

the selection of power generation and energyefficency resources to meet customer

demands of electricity over a multi-decade

time horizon

Sustainable Energy Planning

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 18/66

There are three reason for the increased

complexity of the energy planning process:

The increasing number options� The great uncertainnty in load growth,

fuel market, technological development

and government regulation

� The inclusion of new objectives other than

cost

Sustainable Energy Planning

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 19/66

The increassing use of RES in electricity systemsadds additional considerations to the traditionalplanning models, in particular the need to take

into account:1. Their frequent priority access to the grid

system

2. The impact that technologies of variable

output such as wind energy can have on theoverall operation of the electricity system

3. Public attitude towards these technologies

Sustainable Energy Planning

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 20/66

The central electricity planning process basedon a single decision maker is no longeracceptable, and the importance of examining

tradeoffs amongt objectives is now wellrecognised.

Considering the three dimensions of sustainable development has graduallyincreased the importance of the social aspectin the decision process

Sustainable Energy Planning

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 21/66

Importance of the Social Dimension

The thinking about social sustainability is not yetas advanced as for the other two pillars (worldbank 2003).

However, the Brundtland Report (WorldCommision on Environment and Development1987) made clear the need to expand thesustainable development concept beyondecological concerns and fully recognise and

integrate the social dimensions of sustainability,reflecting the need to ensure equitable socialprogress and overall social welfare

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 22/66

The question of public acceptance is now

generally viewed as a fundamental aspect to

be included in the social dimension of 

sustainable energy planning process,

frequently addressed by participatory

methods.

Importance of the Social Dimension

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 23/66

The consultation of relevant experts andcompetent authorities is an essential element inthe decision process, and multi criteria

applications frequently involve a large andinterdisciplinary group of stakeholders

The assessment of a project sustainability should

focus not only on the impact of the proposal, butalso on how this impact is perceived by the localpopulation.

Importance of the Social Dimension

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 24/66

The acceptance or rejection of a renewable

energy project by the local population can

make its implementation and its contribution

to local sustainability either a succes or a

failure

Importance of the Social Dimension

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 25/66

The creation of clear energy strategiesmerging cost effectiveness with environmentaland social issues is the main challenge for

energy planners. Cost oriented approaches,where the monetary assessment is the onlybasis for the decision making, are no longer anoption, and information on the ecological and

social impacts of possible energy plans needto be combined with traditional economicmonetary indicators.

Importance of the Social Dimension

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 26/66

Sustainable energy planning should now be

seen as a multidisciplinary process, where the

economic, environmental and social impacts

must be taken into consideration, at local and

global level, and where the participatory

approaches can bring considerable benefits.

Importance of the Social Dimension

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 27/66

The social dimension of sustainable

development is much more elusive and

recognizably difficult to analyse quantitatively.

The social analysis cannot be addressed with

the same analytic toolbox as the environment

and economic.

Importance of the Social Dimension

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 28/66

Methodology

The core elements of the proposed methodologyare Delphi and the AHP analysis.

By subdividing the problem into its constituent parts

(Analytic Hierarchy), the problem is simplified andallows information on each separate issue to beexamined.

The relative strength or priority of each objective

can be established (Delphi process) and the resultssynthesised to drive a single overall priority for allactivities.

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 29/66

The user chooses weights by comparing

attributes two at a time, assesing the ratios for

their importance. These ratios are used not

only to compute the weights of individual

attributes, but also to measure the

consistency of the users assesment.

Methodology

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 30/66

In this case we deal with the complecxity of 

the social issues surrounding electricity

planning. A methodology is proposed

establishing a possible way of allocating

weights to the major social impacts and

resulting in a final scoring of the electricity

generation options

Methodology

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 31/66

The process involved the following steps:

1. The identification of difficult to quantifyattributes and options to analyse. This step

corresponds to the definition of the socialcriteria to select the best electricity generationoptions.

2. The establishment of hierarchical structure. The

top of the hierarcy is the main goalcorresponding to the social index and the lowerlevels describe the criteria.

Methodology

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 32/66

3. Selection of a group of experts and establishment of 

the pairwise comparison of the elements of the

hierarchical structure.

4. Testing the consistency of data collected from theexperts.

5. Aggregation of the scores collected from the expert.

6. Combine the relative weights of the elements of each level of the hierarchical structure

Methodology

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 33/66

The analytical hierarchy process wasdeveloped by Saaty (1980) and is based on theformulation of the decision problem in a

hierarchical structure.Typically, the overall objectives or goal of thedecision-making process is represented at thetop level, criterion or attribute elementsaffecting the decision at the intermediate leveland the decision options at the lower level.

Suitability of the AHP Approach

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 34/66

AHP Process

The Process involves the following main steps:1. Subdividing the problem into a hierarcy, with the

main objective placed in the top, the criteria andsub-criteria placed in the intermediaate levels

and the alternatives placed on the bottom levelFigure represent an exampleof a simple hierarcy tree,where X.1, and X.2 are two

criteria, X1.1, X1.2 and X1.3are sub-criteria associatedwith X1 and A1, and A2 arethe alternatives

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 35/66

2. Pairwise comparison of the elements in each

level with respect to their importance to

each of the higher-level elements to which

they re linked. For example elements, X1.1,

X1.2 and X1.3 are pairwise compared

concerning their importance with regards to

X1 criterion and the proces will be repeatedat each level until reaching the top of 

hierarchy.

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 36/66

3. Estimation of the global contribution of each

alternative to the main objective, by the

aggregation of the comparison levels

identified in step (2)

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 37/66

The values used for the pairwise comparison

are usually based on saaty scale of preferences

score Pairwise evaluation

9 A absolutely more important than B

7A is very strongly more important than B

5 A is strongly more important than B

3 A is moderately more important than B

1 A is equally important to B

1/9, 1/7, 1/5,1/3, 1 Reciprocal values

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 38/66

For this paricular research, the aim was to address the

negative social impact of each generating technology. For

the comparison a scale based on Saaty (1980) proposal

was used, detailed in following Table

Range Category

Superior Absolutely superior

Very strongly superior

Strongly superior

Moderately superior

Equal Equal

Inferior Absolutely inferior

Very strongly inferior

Strongly inferior

Moderately inferior

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 39/66

Coal Gas Wind

Coal 1 1 1/3

Gas 1 1 1/5

Wind 3 5 1

Table represent a pairwise comparison matrix, with the elements

representing the quantified judgment on a pair of solutions. The

matrix was drawn from the result obtained for the pairwise of the

three possible generation technologies againts noise impact,

provided by one of the experts. The matrix show the noise impactof coal solution is equal to the noise impact of gas solution. The

noise impact of the wind solution is strongly superior to the noise

impact of the gas solution and moderately superior to the coal

solution

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 40/66

Computation of the weights AHP using theeigenvector analysis. After decision maker makingpairwise comparison between alternatives(A1,A2,....An) these may be represented as in thefollowing matrix :

A1 A2 ... An

A1 a11 a12 ... a1n

A = A2 a21 a22 ... a2n.. ... ... ... ...

An an1 an2 ... ann

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 41/66

The values assigned to aij are usually in accordancewith Saaty scale. A is then a consistent matrix of judgment and Saatys method computes K (vector of weights) as the principal right eigenvector of thematrix A:

a11 a12 ... a1n W1 W1

a21 a22 ... a2n W2 = W2 or AK = K

... ... ... ... ... ...

an1 an2 ... ann Wn Wn

(A-max Z)K = 0

Where max is the largest possible value of an eigenvalue () of matrix A and Z is the identity matrix and K is the eigenvector

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 42/66

If the pairwise matrix is perfectly consisten then will be equal to the number of alternatives underconsideration (n). The consistency index (CI) andthe random consistency index/consistency ratio

(CR) may be computed by:

CI = max- n CR = CI / RI

n - 1

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 43/66

The consistency ration is measure of how a

given matrix compares to a purely random

matrix in terms of their consistency indices.

The value of the random index (RI) may be

obtained from published tables for each of the

matrix, n. In practice if CR 0.10, the

consistency of this matrix is acceptable.

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 44/66

For the computation of the weights and the

consistency ranking, the software package

Super Decision was used. This software was

available in the internet

(http://www.superdecisions.com)

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 45/66

For the particular example of matrix A, Saatys

method may be applied to derive the vector of 

weights  along with the consistency ratio:

1  1  1/3         Wcoal Wcoal

1  1  1/5 Wgas = Wgas

3  5      1 Wwind Wwind

Vector of weights of the alternatives with respect to the noise impact

Noise Impact

Gas 0.156

Coal 0.185

Wind 0.659

CR 0.0280

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 46/66

As  result gas is the most desirable solution,

followed by coal generation plants with wind

generation being the least desirable.

AHP Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 47/66

Suitability of the Delphi Approach

The main objective of the Delphi technique is to

describe a variety of alternatives and to provide a

constructive forum in which consensus may

occur (Rayens and Hahn, 2000).

The three basic conditions of the process are:

1. anonymity of the respondents

2. statistical treatment of the responses3. controlled feedback in subsequent rounds.

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 48/66

Delphi Process

Choice of thesubject

Choice of the

topic

Selection of 

the expert

Writing of the

questionnaire

First round

Statistical analysisof the result

Re-writing of the

questionnaire

New round

Statistical analysis

of the result

Consensus or

stability

No Consensus or

stability

Consensus orstability

Conclusion

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 49/66

The first phase is characterised by the

description of the subject to study and the

objectives of the research. Based on this , the

expert are chosen.

The selection of the expert is crucial phase

because the quality of the result depends

heavily on the knowledge and commitment of the participant.

Delphi Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 50/66

The reseach team explaining the experts aboutthe basis of the Delphi technique, the objective of the research and their role in the process.

The responses of this first round are collectedand the research team process to the statisticalanalysis.

The new questionnaire presents the results of thefirst round; it frequently includes comments

received during the first round, new questionmay be added and some other questions may beeliminated

Delphi Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 51/66

The approach to measuring consensus variesfrom study to study. Rayens and Hahn (2000)present some examples of measure used in

past studies such as:The frequency distributions. The criterion of atleast 51% reesponding to a certain categorymay be used to determine consensus, or least

67% in a yes-no study, as presented in thefollowing example for two possible questions.

Delphi Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 52/66

Question A                                                

Response % of responses Response % of responses

Strongly agree 20% Agree 80%Agree 58% Disagree                  20%

Neither agree or

Disagree 4%

Disagree 15%

Strongly disagree 3%

Consensus Achieved Consensus Achieved

Delphi Process

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 53/66

Hierarchical structure formulation

� Options or alternatives

The process started with the identification of the

options to be analysed. There three electricity

generation options were included: coal, gas andwind.

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 54/66

� Criteria

The next step was the identification of the criteria

to be included in the evaluation process.

Negative impact of wind power: the impact on

wild life, the noise pollution, negative

visulaimpact on the landscape.

Negative impact of coal and gas power dealmainly with the cost and environmental

emissiona

Hierarchical structure formulation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 55/66

� Criteria ( Semi-structured interview with experts)

Following literatur  analysis, semi-structured

interview were conducted with experts from the

academic field, energy consultant, member of 

environmental associations and reseachers.

Hierarchical structure formulation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 56/66

�Criteria ( Semi-structured interview with experts)The interview addreesd the following issues:

The general public reaction towards wind power, coaland natural gas power lants and the opinion of localpopulations.

The major complains expressed by the population inwhat concerns wind, coal, and natural gas power plant.

The major benefits that new power plants may bring tolocal populations

The most important aspect to be taken into accountfor the electricity planning in Portugal

What the expert felt would be the desirable andexpected future scenarios for electricity power sectorin Portugal

Hierarchical structure formulation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 57/66

� Criteria ( Selection of the criteria)

Base on the literature and on the interview, the

following non quantitative criteria were chosen

for the social evaluation process: Noise impact

Impact on birds and wildlife

Visual Impact The social acceptance

Hierarchical structure formulation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 58/66

Combining the options and the criteria , thehierarchical structure of the problem may be

represented :

Hierarchical structure formulation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 59/66

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 60/66

� First questionaireThe questionnaire asks the experts to assume the need to increase theavailable power by about 1000MW. This may be done by increasing thenumber of coal, natural gas or wind power plants, described as follows:

Coal solution

Description 2 new coal power plants, one with installed capacity equal

to7

00M

W and another one with installed capacity equal to450MW.

Placement Close to large electricity consumption centres.

Characteristics In each power station there will be one chimney 225 mhigh and one cooling tower. Each power plant may occupyan area of about 1.5 ha (0.015 km2) and burns imported

coal.Examples Presently two power stations operate in Portugal: one in

Sines and another one in Pego.

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 61/66

Gas solution

Description 2 new combined cycle natural gas power plants, one with

installed capacity equal to 660MW and another one with

installed capacity equal to 400MW.

Placement Close to large electricity consumption centres.

Characteristics The 660MW power station will have two chimneys. The 400MW power station will have 1 chimney. All the chimneys will

be 80 m high. Each power station will have a cooling

tower. Each power station may occupy an area of 

about 1.5 ha (0.015 km2). It burns imported natural gas.

Examples Presently two CCGT operate in Portugal: one in Ribatejo(Carregado) and another one inTapada do Outerio

(Gondomar).

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 62/66

Wind solution

Description 250 new wind farms, with total installed capacity equal to

3800MW.

Placement Spread across the country, but with higher concentration in

the inland North hills.Characteristics Each wind farm will have between 10 and 15 turbine, about

65 m high and may occupy an area of about 100 ha (1 km2).

Examples Presently there are about 1000 turbines operating in the

mainland, some examples may be seen inMarão, Açor,

Barroso among many others.

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 63/66

A brief definition of these social criteria was also included in the questionnaire, as follows:

DefinitionVisual impact This criterion is difficult to quantify and depends heavily on individual

perception. It is associated with the aesthetic aspect, and it will be necessaryto assess if the

project will bring significant changes to the landscape and if these changes will

reduce the visual quality of the region.

Noise level This criterion is usually associated with sleeping disorders, interference with

learning activities and general annoyance, caused by undesirable noise. It willbe necessary to assess if the project will change the noise levels in the region.

Impact on This criterion is associated with problems like bird electrocution, collision

birds and mortality, reduction of available habitat, disturbance of nesting, alteration of 

Wildlife migration habits and general habitat disturbances due the increase of humanactivity.

Social This criterion is associated with the way the project will be seen and accepted

Acceptance bythe population in general. It may generate some resistance or on the otherhand may be considered desirable.

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 64/66

Determination of weights for the electricity

generation options

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 65/66

Determination of weights for the electricity

generation options

Delphi Implementation

8/7/2019 The Integration of Social Concerns into Electricity Power Planning - Fretz Josue

http://slidepdf.com/reader/full/the-integration-of-social-concerns-into-electricity-power-planning-fretz 66/66

Incorporating the social index into the

electricity planning model

Integrated Electricity PlanningModel (IEPM)

non-linear electricity planning model (NLEPM)