the helix bridge — east india dock -...

1
The Helix Bridge relies on the segments at each end of the deck being able to wind around the quayside hub to retract the spans. Each segment comprises a large steel torsion box oset to the edge of the steel deck. Between segments, the boxes are connected by a pair of large steel hinges along the outer vertical edge. These hinges comprise a series of interlinking at plates with low friction bearing surfaces and steel pin. Structural continuity of the torsion box between adjacent units is provided by the torsional stiness of the hinges when acting as a pair. At the free edge of the deck, continuity is provided by interlocking nger plates which transfer shear between units providing a loadpath to the oset torsion box and to the hub support. At midspan, the closing joint comprises nger plates and a pair of pin locks to secure the bridge in its closed position. THE HELIX BRIDGE — East India Dock Team 19. IABSE Future of Design Conference 2015 1. Construct sheet pile caisson in the river channel, install bored concrete piles to bedrock at pier and quayside base, construct concrete pier and quayside base. 2. Form approaches to structure at 1:20 gradient, install end support internal frame. 3. Rotate hub frame to the ‘bridge open’ position and erect steel bridge hub onto support frame. 4. Individually hang 2.2m long steel bridge segments onto hub, making the hinged connection between adjacent segments, commence with segment 1 and proceed to segment 9. 5. Install guided roller bearings to pier top and erect central deck section 10, secure onto guided roller bearings at pier and make connection to segment 9 (erected in stage 4). 6. Install steel ballast plates into section 10, complete deck and parapet nishes, install lighting and rotate hub into bridge closed position. (Only 1 half shown here for clarity). Elevation AA Open Position Elevation AA Closed Position Plan Deck Plan and Elevation (Parapet omitted for clarity) 1 2 3 4 5 6 7 8 9 10 Oset torsion box 1.4m high parapet posts at 100mm clear gap 3500mm clear 35m x 9.39m clearance above MHWS (13.3mAoD) 35m x 2.59m clearance above MHWS (6.50mAoD) Parapet Detail/ Finishes Construction Sequence Segmental Mechanism Geometry The Helix Bridge is in part inspired by Thomas Heatherwick’s Rolling Bridge at Paddington Basin, London. Unlike the Rolling Bridge, this structure retracts by winding around a vertical axis on both banks. The segmented steel box units, the rst of which is permanently xed to the cylindrical steel hub, are drawn away from the span as the hub and its walking surface rotate anticlockwise. As each segment separates from the adjacent unit and contacts with the hub, a large pin on the rear face of the unit locks into the hub making a secure connection. The winding of the segmental units forms a helix around the hub and withdraws the central span over the pier providing the required navigation clearance. The parapet comprises a series of vertical 1.4m high, 50mm wide posts, positioned with a 100mm clear gap. With a gradient over the bridge of less than 1:20, a handrail has not been included in the parapet detail. The parapet post features a timber facing on the inner aspect, the pattern of which continues onto the torsion box. The deck is surfaced in a matching hardwood timber with the individual deck boards aligned longitudinally along the span. Lighting to the bridge is provided by units located at deck level positioned between the parapet posts. On either bank, around the perimeter of the rotating hub, the existing quayside has been proled at 1:20 to meet the structure. The proled approach features a retractable barrier which, when raised during opening operations, will safely segregate the public from the bridge. N Oset torsion box 1.4m high parapet posts at 100mm clear gap Ballast plates in section 10 to quayside of pier Ballast plates in section 10 to quayside of pier Segmental units 37.5m C/L Pier — C/L Pier 1 2 3 4 5 6 A B C Each retracting half of the bridge deck is mirrored around the central joint and comprises a large 750mm wide, 1.4m high torsion box and steel box deck. Along the length of the bridge, the torsion box retains its 1.4m height and transitions into a pedestrian parapet, tapering from 750mm at the hub to 100mm wide at the opposite end of the deck (see A>B>C above right). The torsion box and parapet’s inner faces splay outwards giving a 3.5m clear gap at deck level increasing to 3.7m at 1.4m. Units 1 to 9 and the quayside hub are constructed from painted steel, to minimise weight in the cantilever tip, unit 10 is constructed using a bre reinforced polymer with additional steel ballast plates positioned in unit 10 to balance the cantilever. Across the structure, key moving components are manufactured using stainless steel. Colours for illustrative purposes only Bridge Open Bridge Closed Footbridge Concept

Upload: lehuong

Post on 24-Apr-2018

222 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: THE HELIX BRIDGE — East India Dock - IABSEiabse.org.uk/wp-content/uploads/2015/09/Team_19_Helix-Bridge.pdf · The Helix Bridge relies on the segments at each end ... the boxes are

The Helix Bridge relies on the segments at each end of the deck being able to wind around the quayside hub to retract the spans. Each segment comprises a large steel torsion box offset to the edge of the steel deck. Between segments, the boxes are connected by a pair of large steel hinges along the outer vertical edge. These hinges comprise a series of interlinking flat plates with low friction bearing surfaces and steel pin. Structural continuity of the torsion box between adjacent units is provided by the torsional stiffness of the hinges when acting as a pair. At the free edge of the deck, continuity is provided by interlocking finger plates which transfer shear between units providing a loadpath to the offset torsion box and to the hub support. At midspan, the closing joint comprises finger plates and a pair of pin locks to secure the bridge in its closed position.

THE HELIX BRIDGE — East India Dock Team 19. IABSE Future of Design Conference 2015 

1. Construct sheet pile caisson in the river channel, install bored concrete piles to bedrock at pier and quayside base, construct concrete pier and quayside base. 2. Form approaches to structure at 1:20 gradient, install end support internal frame. 3. Rotate hub frame to the ‘bridge open’ position and erect steel bridge hub onto support frame. 4. Individually hang 2.2m long steel bridge segments onto hub, making the hinged connection between adjacent segments, commence with segment 1 and proceed to segment 9. 5. Install guided roller bearings to pier top and erect central deck section 10, secure onto guided roller bearings at pier and make connection to segment 9 (erected in stage 4). 6. Install steel ballast plates into section 10, complete deck and parapet finishes, install lighting and rotate hub into bridge closed position. (Only 1 half shown here for clarity).

Elevation A‐A Open Position

Elevation A‐A Closed Position

Plan

Deck Plan and Elevation (Parapet omitted for clarity)

1 2 3 4 5 6 7 8 9 10

Offset torsion box 1.4m high parapet posts at 100mm clear gap

3500mm clear

35m x 9.39m clearance above MHWS (13.3mAoD)

35m x 2.59m clearance above MHWS (6.50mAoD)

Parapet Detail/ Finishes

Construction Sequence

Segmental Mechanism

Geometry

The Helix Bridge is in part inspired by Thomas Heatherwick’s Rolling Bridge at Paddington Basin, London. Unlike the Rolling Bridge, this structure retracts by winding around a vertical axis on both banks. The segmented steel box units, the first of which is permanently fixed to the cylindrical steel hub, are drawn away from the span as the hub and its walking surface rotate anti‐clockwise. As each segment separates from the adjacent unit and contacts with the hub, a large pin on the rear face of the unit locks into the hub making a secure connection. The winding of the segmental units forms a helix around the hub and withdraws the central span over the pier providing the required navigation clearance. The parapet comprises a series of vertical 1.4m high, 50mm wide posts, positioned with a 100mm clear gap. With a gradient over the bridge of less than 1:20, a handrail has not been included in the parapet detail. The parapet post features a timber facing on the inner aspect, the pattern of which continues onto the torsion box. The deck is surfaced in a matching hardwood timber with the individual deck boards aligned longitudinally along the span. Lighting to the bridge is provided by units located at deck level positioned between the parapet posts. On either bank, around the perimeter of the rotating hub, the existing quayside has been profiled at 1:20 to meet the structure. The profiled approach features a retractable barrier which, when raised during opening operations, will safely segregate the public from the bridge.

N

Offset torsion box 1.4m high parapet posts at 100mm clear gap

Ballast plates in section 10 to quayside of pier

Ballast plates in section 10 to quayside of pier

Segmental units

37.5m C/L Pier — C/L Pier

1 2 3

4 5 6

A

B

C

Each retracting half of the bridge deck is mirrored around the central joint and comprises a large 750mm wide, 1.4m high torsion box and steel box deck. Along the length of the bridge, the torsion box retains its 1.4m height and transitions into a pedestrian parapet, tapering from 750mm at the hub to 100mm wide at the opposite end of the deck (see A‐>B‐>C above right). The torsion box and parapet’s inner faces splay outwards giving a 3.5m clear gap at deck level increasing to 3.7m at 1.4m. Units 1 to 9 and the quayside hub are constructed from painted steel, to minimise weight in the cantilever tip, unit 10 is constructed using a fibre reinforced polymer with additional steel ballast plates positioned in unit 10 to balance the cantilever. Across the structure, key moving components are manufactured using stainless steel.

Colours for illustrative purposes only

Bridge Open

Bridge Closed

Footbridge Concept