the gimbal and telescope assembly for nasa's next ... · presentation “sgslr site ... final...
TRANSCRIPT
![Page 1: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/1.jpg)
13 October 2016 1
The Gimbal and Telescope Assembly for NASA's Next Generation Space Geodesy SLR Systems
20th International Laser Ranging Workshop
Potsdam, Germany October 9 – 14, 2016
H. Donovan1, D. Patterson1, S. Wetzel1, J. Marzouk2, J. Mcgarry, J3. Degnan2,
A. Nelson1, F. Hall1, J. Horvath1, J. Cheek2, M. Shappirio3, E. Hoffman3
1Honeywell Technology Solutions Inc., Lanham, MD | 2Sigma Space Corp., Greenbelt, MD | 3NASA Goddard Space Flight Center, Greenbelt, MD
![Page 2: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/2.jpg)
13 October 2016 2
Outline
Introduction
SGSLR Gimbal and Telescope Assembly (GTA) Locations
Specification Development
– Invariant Point
– Precision Pointing
Vendor Selection
Design Status
– Gimbal Design
– Optical Design
– GTA Imaging properties required by sensor array
Summary
![Page 3: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/3.jpg)
13 October 2016 3
INTRODUCTION
![Page 4: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/4.jpg)
13 October 2016 4
Introduction
The Gimbal and Telescope Assembly (GTA) – One of the most important components of an SLR system – The component with the longest lead time item
Specification and Procurement – The SGSLR GTA team developed very stringent specifications in 2015 – The NASA Space Geodesy Project (SGP) is in the process of procuring three
highly precise and very stable GTA systems
Design and fabrication efforts include complex modeling which ensures – Precise telescope pointing – A very stable invariant point through a wide range of temperatures
• Required due to the variations in the climate at the expected NASA SGP network sites
SGSLR GTA will need to take advantage of the pixelated receiver subsystem which provides range and angular information needed for automated tracking operations – See John Degnan’s paper “PROGRESS ON THE MULTIFUNCTIONAL RANGE
RECEIVER FOR SGSLR”
![Page 5: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/5.jpg)
13 October 2016 5
GTA LOCATIONS
![Page 6: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/6.jpg)
13 October 2016 6
SGSLR Locations
GTA #1 delivered to GSFC in Greenbelt, MD: Field Acceptance Testing then shipped to Ny-Alesund, Norway Norwegian Mapping Agency (NMA)
GTA #2 delivered to GSFC in Greenbelt, MD: Field Acceptance Testing, then to Haleakala, HI
GTA #3 delivered directly to MLRS in Ft. Davis, TX: Filed Acceptance Testing
Please see Scott Wetzel’s
presentation “SGSLR Site
Preparation and Deployment Plans for the First Set of SGSLR Systems”
![Page 7: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/7.jpg)
13 October 2016 7
Features of the Ny-Ålesund Site
Colder than any site currently in operation for NASA SLR Network
– Reaches -20⁰C, average minimum for coldest month is -15⁰C
– Average high 5⁰C with a max of 11⁰C
– GTA will be able to handle these temperatures
Star calibrations must be done in daylight
– Mount stability is expected to hold mount model for months
– Technique developed where two offset images are taken then one is subtracted from the other to remove background
![Page 8: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/8.jpg)
13 October 2016 8
Features of the Texas & Hawaii Site
Texas - No extreme weather conditions
– Average low is -17⁰C but has reached -20⁰C
– Average high 37⁰C but has reached 45⁰C
– GTA will be able to handle these temperatures
Hawaii - No extreme weather conditions
– Average low is 8⁰C but has reached -9⁰C
– Average high 17⁰C but has reached 23⁰C
– GTA will be able to handle these temperatures
![Page 9: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/9.jpg)
13 October 2016 9
SPECIFICATION DEVELOPMENT
![Page 10: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/10.jpg)
13 October 2016 10
GTA Requirements
Tracking requirements:
– Satellite altitudes
• 300 km to 22,000 km (LEO to GNSS), day & night
• 42,000 km geosynchronous and geostationary, night only
– Tight divergence, low laser energy, small receiver FOV
• Requires precision pointing to place and maintain the low laser energy on the satellite and the receiver in the FOV
• Support varying velocities, high accelerations, and high inertial loads while providing smooth trajectory to maintain link to the satellite
• Gimbal pointing must synchronously intersect the satellite trajectory coincident with the laser 2 kHz transmit rate
![Page 11: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/11.jpg)
13 October 2016 11
GTA Requirements
Invariant Point (System Origin) – Motion of the intersection of the GTA axes must be known with
respect to external reference points and measured by survey
– Affected by temperature, bearing wobble, bearing runout, axis orthogonality, and axis intersection
– Knowledge reduces range measurement uncertainty
– Knowledge increases the accuracy of the GTA position location
Range includes motion induced
by mechanical movement and
optical alignment
Conceptual range of
motion for invariant
point
Elevation
Axis
Azim
uth
Axis
Invariant
Point
Survey Reference
Point (x2)
Elevation
Axis
Azim
uth
Axis
![Page 12: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/12.jpg)
13 October 2016 12
Invariant Point
Origin of SGSLR system is the theoretical point used by the Science Community to define the location of the SLR system – Location where theoretical azimuth and elevation axes meet
Theoretical start and stop of the range time measurement is the time of the laser pulse as it crosses the invariant point
The distance to the satellite is measured from the invariant point As azimuth and elevation angles move and the temperature
changes, actual origin of the GTA can move around To achieve accurate to the millimeter level ranging measurements,
the invariant point of the system must be known at all times to within 1 millimeter
Vector Tie System (VTS) will monitor external points on the gimbal and determine movement
Movement of the invariant point with respect to these external points is important so the Science Community can fully determine the system’s origin at all times
![Page 13: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/13.jpg)
13 October 2016 13
Gimbal Stability and Stiffness
– Invariant point knowledge to meet range measurement uncertainty requirement
– Tight pointing capability to meet target tracking requirements
– Day/night operations required over large temperature swings
– Operational range -40°C to +50°C
– Survival Temperature: -50°C to 55°C
– Solar and wind loading managed using a open slit dome
High Reliability
– 24/7 continuous operations with minimum downtime
– Gimbal design must be very robust and require little maintenance to achieve automation
GTA Requirements
![Page 14: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/14.jpg)
13 October 2016 14
VENDOR SELECTION
![Page 15: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/15.jpg)
13 October 2016 15
Vendor Selected
COBHAM
– Selected as the Vendor for the SGSLR Gimbal Telescope Assembly
Used with permission from Cobham, LLC
![Page 16: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/16.jpg)
13 October 2016 16
Procurement Status
NASA tasked Honeywell to
– Develop a procurement strategy and RFP with a team of subject matter experts (NASA, Honeywell, Sigma Space) to procure 3 GTA’s
Key Dates
– RFP Released May 2015
– Cobham Selected as SGSLR GTA Vendor – November 2015
– Cobham Preliminary Design Review – March 2016
– Cobham Critical Design Review – August 2016
First GTA delivery expected July 2017
Final GTA delivery expected November 2017
![Page 17: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/17.jpg)
13 October 2016 17
DESIGN STATUS GIMBAL
![Page 18: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/18.jpg)
13 October 2016 18
Gimbal Design
Steel and ductile iron casting construction (with corrosion protection) for thermal stability
Slotless, brushless, frameless torque motors
Angular contact bearing in a kingpost arrangement
Modularized inductosyn and resolver encoder package
Enclosed coudé path
Over travel shock absorbers, elevation
Manual brakes in azimuth and elevation
Used with permission from Cobham, LLC
![Page 19: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/19.jpg)
13 October 2016 19
Gimbal Primary Specifications
Specification Allocation
Jitter: 1 arcsec RMS
Absolute open loop pointing: ≤ 3 arcsec RMS
Invariant Point: 1mm in 3D space
Tracking Az Velocity: Tracking Az Acceleration:
Tracking El Velocity: Tracking El Acceleration
0°– 10°/sec
0°– 1°/sec2
0°– 2°/sec 0°– 0.5°/sec2
Slew Az Velocity: Slew Az Acceleration:
Slew El Velocity: Slew El Acceleration:
≥20°/sec
≥5°/sec2
≥20°/sec
≥5°/sec2
![Page 20: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/20.jpg)
13 October 2016 20
DESIGN STATUS OPTICAL
![Page 21: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/21.jpg)
13 October 2016 21
Telescope Design
Theoretical performance analyzed by the NASA/Honeywell/Sigma Space team optical subject matter experts
Diffraction limited performance over the full field and temperature range
A-focal design
Carbon fiber tube
Sealed System Used with permission
from Cobham, LLC
![Page 22: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/22.jpg)
13 October 2016 22
Telescope Primary Specifications
Specification Allocation
Type: A-focal, Monostatic
Diameter: 0.5 meters
Wavelength: 532nm, 1064nm, 1550nm, Broadband
Throughput: <2% loss per surface
Stray Light Rejection: 106
9.5° to 85° acceptance angle
System FOV: Acquisition Tracking Star Calibration
60 arcsec 14 arcsec 2.5 arcmin
Telescope and Relay Path: Sealed
Wavefront Quality: 80% encircled energy for 0.8 arcsec diameter
full field circle @ 532nm
![Page 23: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/23.jpg)
13 October 2016 23
Classic Coudé feed
Rotational axes and mechanical axes are co-aligned
Transmit and receive path are coupled using an insertion fold mirror
A beam illumination path to perform boresight using GSE equipment
Simplified Optical System Layout
Star Camera leg
Transmit Leg
Back Illumination Channel
Receive leg
Beam Reducer
Telescope Assembly
Coude Feed
Invariant Point (System Origin)
![Page 24: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/24.jpg)
13 October 2016 24
Telescope FOV to Receiver
CLOSED LOOP TRACKING
· Signal Identification (esp. for weak GNSS returns)
· Decrease acquisition time
· Once acquired => signal identification
· Automatically maximize return signal
· Peak up on the signal with knowledge of pointing
A Proposed Multifunctional Multichannel Receiver for
SGSLR (3020) J. Degnan 2014
Presented at the 19th International Laser Ranging Workshop,
Annapolis, MD (2014)
Detector Array
(14 arcsec. FOV)
Mirror
Acquistion camera(Wide FOV) 1 2 3 4 5 6 7
1
2
3
4
5
6
7
Detector Anode
Array
Limit of Field of
View
Perimeter pixel
used for CLT
Corner pixels not
used
Noise Satellite Returns
(collected over a frame)
Closed loop tracking
– Signal Identification (esp. for weak GNSS returns)
– Automatically maximize return signal
– Decrease acquisition time
Receiver
FOV Device
Wide FOV for Acquisition
Receiver
FOV Device
Narrow FOV for Tracking Please see John Degnan’s presentation “Progress on the multifunctional range receiver for SGSLR”
![Page 25: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/25.jpg)
13 October 2016 25
SUMMARY
![Page 26: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/26.jpg)
13 October 2016 26
Summary
GTA is one of the most important components of the SLR system
GTA will be robust to support 24/7 tracking operations SGP project level requirements for data quantity and quality
require a precise gimbal and telescope assembly GTA performance is key to the data volume
– Tracking performance (extremely good tracking RMS up to relatively high velocities and accelerations, slewing speed, and stability throughout large temperature variations) will increase the amount of data collected/data volume and and will also increase the data collection rate, improving the NPT precision
Knowledge of invariant point is key to getting to the 1 mm ranging level – Expect to achieve knowledge of the invariant point to 1 mm
First Cobham GTA delivery expected July 2017 with the final GTA delivery expected November 2017
![Page 27: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October](https://reader035.vdocuments.us/reader035/viewer/2022071002/5fbf06076cba2627ff3e53f3/html5/thumbnails/27.jpg)
13 October 2016 27
Thank You!
Used with permission from Cobham, LLC