the gimbal and telescope assembly for nasa's next ... · presentation “sgslr site ... final...

27
13 October 2016 1 The Gimbal and Telescope Assembly for NASA's Next Generation Space Geodesy SLR Systems 20 th International Laser Ranging Workshop Potsdam, Germany October 9 – 14, 2016 H. Donovan 1 , D. Patterson 1 , S. Wetzel 1 , J. Marzouk 2 , J. Mcgarry, J 3 . Degnan 2 , A. Nelson 1 , F. Hall 1 , J. Horvath 1 , J. Cheek 2 , M. Shappirio 3 , E. Hoffman 3 1 Honeywell Technology Solutions Inc., Lanham, MD | 2 Sigma Space Corp., Greenbelt, MD | 3 NASA Goddard Space Flight Center, Greenbelt, MD

Upload: others

Post on 17-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 1

The Gimbal and Telescope Assembly for NASA's Next Generation Space Geodesy SLR Systems

20th International Laser Ranging Workshop

Potsdam, Germany October 9 – 14, 2016

H. Donovan1, D. Patterson1, S. Wetzel1, J. Marzouk2, J. Mcgarry, J3. Degnan2,

A. Nelson1, F. Hall1, J. Horvath1, J. Cheek2, M. Shappirio3, E. Hoffman3

1Honeywell Technology Solutions Inc., Lanham, MD | 2Sigma Space Corp., Greenbelt, MD | 3NASA Goddard Space Flight Center, Greenbelt, MD

Page 2: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 2

Outline

Introduction

SGSLR Gimbal and Telescope Assembly (GTA) Locations

Specification Development

– Invariant Point

– Precision Pointing

Vendor Selection

Design Status

– Gimbal Design

– Optical Design

– GTA Imaging properties required by sensor array

Summary

Page 3: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 3

INTRODUCTION

Page 4: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 4

Introduction

The Gimbal and Telescope Assembly (GTA) – One of the most important components of an SLR system – The component with the longest lead time item

Specification and Procurement – The SGSLR GTA team developed very stringent specifications in 2015 – The NASA Space Geodesy Project (SGP) is in the process of procuring three

highly precise and very stable GTA systems

Design and fabrication efforts include complex modeling which ensures – Precise telescope pointing – A very stable invariant point through a wide range of temperatures

• Required due to the variations in the climate at the expected NASA SGP network sites

SGSLR GTA will need to take advantage of the pixelated receiver subsystem which provides range and angular information needed for automated tracking operations – See John Degnan’s paper “PROGRESS ON THE MULTIFUNCTIONAL RANGE

RECEIVER FOR SGSLR”

Page 5: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 5

GTA LOCATIONS

Page 6: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 6

SGSLR Locations

GTA #1 delivered to GSFC in Greenbelt, MD: Field Acceptance Testing then shipped to Ny-Alesund, Norway Norwegian Mapping Agency (NMA)

GTA #2 delivered to GSFC in Greenbelt, MD: Field Acceptance Testing, then to Haleakala, HI

GTA #3 delivered directly to MLRS in Ft. Davis, TX: Filed Acceptance Testing

Please see Scott Wetzel’s

presentation “SGSLR Site

Preparation and Deployment Plans for the First Set of SGSLR Systems”

Page 7: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 7

Features of the Ny-Ålesund Site

Colder than any site currently in operation for NASA SLR Network

– Reaches -20⁰C, average minimum for coldest month is -15⁰C

– Average high 5⁰C with a max of 11⁰C

– GTA will be able to handle these temperatures

Star calibrations must be done in daylight

– Mount stability is expected to hold mount model for months

– Technique developed where two offset images are taken then one is subtracted from the other to remove background

Page 8: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 8

Features of the Texas & Hawaii Site

Texas - No extreme weather conditions

– Average low is -17⁰C but has reached -20⁰C

– Average high 37⁰C but has reached 45⁰C

– GTA will be able to handle these temperatures

Hawaii - No extreme weather conditions

– Average low is 8⁰C but has reached -9⁰C

– Average high 17⁰C but has reached 23⁰C

– GTA will be able to handle these temperatures

Page 9: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 9

SPECIFICATION DEVELOPMENT

Page 10: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 10

GTA Requirements

Tracking requirements:

– Satellite altitudes

• 300 km to 22,000 km (LEO to GNSS), day & night

• 42,000 km geosynchronous and geostationary, night only

– Tight divergence, low laser energy, small receiver FOV

• Requires precision pointing to place and maintain the low laser energy on the satellite and the receiver in the FOV

• Support varying velocities, high accelerations, and high inertial loads while providing smooth trajectory to maintain link to the satellite

• Gimbal pointing must synchronously intersect the satellite trajectory coincident with the laser 2 kHz transmit rate

Page 11: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 11

GTA Requirements

Invariant Point (System Origin) – Motion of the intersection of the GTA axes must be known with

respect to external reference points and measured by survey

– Affected by temperature, bearing wobble, bearing runout, axis orthogonality, and axis intersection

– Knowledge reduces range measurement uncertainty

– Knowledge increases the accuracy of the GTA position location

Range includes motion induced

by mechanical movement and

optical alignment

Conceptual range of

motion for invariant

point

Elevation

Axis

Azim

uth

Axis

Invariant

Point

Survey Reference

Point (x2)

Elevation

Axis

Azim

uth

Axis

Page 12: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 12

Invariant Point

Origin of SGSLR system is the theoretical point used by the Science Community to define the location of the SLR system – Location where theoretical azimuth and elevation axes meet

Theoretical start and stop of the range time measurement is the time of the laser pulse as it crosses the invariant point

The distance to the satellite is measured from the invariant point As azimuth and elevation angles move and the temperature

changes, actual origin of the GTA can move around To achieve accurate to the millimeter level ranging measurements,

the invariant point of the system must be known at all times to within 1 millimeter

Vector Tie System (VTS) will monitor external points on the gimbal and determine movement

Movement of the invariant point with respect to these external points is important so the Science Community can fully determine the system’s origin at all times

Page 13: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 13

Gimbal Stability and Stiffness

– Invariant point knowledge to meet range measurement uncertainty requirement

– Tight pointing capability to meet target tracking requirements

– Day/night operations required over large temperature swings

– Operational range -40°C to +50°C

– Survival Temperature: -50°C to 55°C

– Solar and wind loading managed using a open slit dome

High Reliability

– 24/7 continuous operations with minimum downtime

– Gimbal design must be very robust and require little maintenance to achieve automation

GTA Requirements

Page 14: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 14

VENDOR SELECTION

Page 15: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 15

Vendor Selected

COBHAM

– Selected as the Vendor for the SGSLR Gimbal Telescope Assembly

Used with permission from Cobham, LLC

Page 16: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 16

Procurement Status

NASA tasked Honeywell to

– Develop a procurement strategy and RFP with a team of subject matter experts (NASA, Honeywell, Sigma Space) to procure 3 GTA’s

Key Dates

– RFP Released May 2015

– Cobham Selected as SGSLR GTA Vendor – November 2015

– Cobham Preliminary Design Review – March 2016

– Cobham Critical Design Review – August 2016

First GTA delivery expected July 2017

Final GTA delivery expected November 2017

Page 17: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 17

DESIGN STATUS GIMBAL

Page 18: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 18

Gimbal Design

Steel and ductile iron casting construction (with corrosion protection) for thermal stability

Slotless, brushless, frameless torque motors

Angular contact bearing in a kingpost arrangement

Modularized inductosyn and resolver encoder package

Enclosed coudé path

Over travel shock absorbers, elevation

Manual brakes in azimuth and elevation

Used with permission from Cobham, LLC

Page 19: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 19

Gimbal Primary Specifications

Specification Allocation

Jitter: 1 arcsec RMS

Absolute open loop pointing: ≤ 3 arcsec RMS

Invariant Point: 1mm in 3D space

Tracking Az Velocity: Tracking Az Acceleration:

Tracking El Velocity: Tracking El Acceleration

0°– 10°/sec

0°– 1°/sec2

0°– 2°/sec 0°– 0.5°/sec2

Slew Az Velocity: Slew Az Acceleration:

Slew El Velocity: Slew El Acceleration:

≥20°/sec

≥5°/sec2

≥20°/sec

≥5°/sec2

Page 20: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 20

DESIGN STATUS OPTICAL

Page 21: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 21

Telescope Design

Theoretical performance analyzed by the NASA/Honeywell/Sigma Space team optical subject matter experts

Diffraction limited performance over the full field and temperature range

A-focal design

Carbon fiber tube

Sealed System Used with permission

from Cobham, LLC

Page 22: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 22

Telescope Primary Specifications

Specification Allocation

Type: A-focal, Monostatic

Diameter: 0.5 meters

Wavelength: 532nm, 1064nm, 1550nm, Broadband

Throughput: <2% loss per surface

Stray Light Rejection: 106

9.5° to 85° acceptance angle

System FOV: Acquisition Tracking Star Calibration

60 arcsec 14 arcsec 2.5 arcmin

Telescope and Relay Path: Sealed

Wavefront Quality: 80% encircled energy for 0.8 arcsec diameter

full field circle @ 532nm

Page 23: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 23

Classic Coudé feed

Rotational axes and mechanical axes are co-aligned

Transmit and receive path are coupled using an insertion fold mirror

A beam illumination path to perform boresight using GSE equipment

Simplified Optical System Layout

Star Camera leg

Transmit Leg

Back Illumination Channel

Receive leg

Beam Reducer

Telescope Assembly

Coude Feed

Invariant Point (System Origin)

Page 24: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 24

Telescope FOV to Receiver

CLOSED LOOP TRACKING

· Signal Identification (esp. for weak GNSS returns)

· Decrease acquisition time

· Once acquired => signal identification

· Automatically maximize return signal

· Peak up on the signal with knowledge of pointing

A Proposed Multifunctional Multichannel Receiver for

SGSLR (3020) J. Degnan 2014

Presented at the 19th International Laser Ranging Workshop,

Annapolis, MD (2014)

Detector Array

(14 arcsec. FOV)

Mirror

Acquistion camera(Wide FOV) 1 2 3 4 5 6 7

1

2

3

4

5

6

7

Detector Anode

Array

Limit of Field of

View

Perimeter pixel

used for CLT

Corner pixels not

used

Noise Satellite Returns

(collected over a frame)

Closed loop tracking

– Signal Identification (esp. for weak GNSS returns)

– Automatically maximize return signal

– Decrease acquisition time

Receiver

FOV Device

Wide FOV for Acquisition

Receiver

FOV Device

Narrow FOV for Tracking Please see John Degnan’s presentation “Progress on the multifunctional range receiver for SGSLR”

Page 25: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 25

SUMMARY

Page 26: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 26

Summary

GTA is one of the most important components of the SLR system

GTA will be robust to support 24/7 tracking operations SGP project level requirements for data quantity and quality

require a precise gimbal and telescope assembly GTA performance is key to the data volume

– Tracking performance (extremely good tracking RMS up to relatively high velocities and accelerations, slewing speed, and stability throughout large temperature variations) will increase the amount of data collected/data volume and and will also increase the data collection rate, improving the NPT precision

Knowledge of invariant point is key to getting to the 1 mm ranging level – Expect to achieve knowledge of the invariant point to 1 mm

First Cobham GTA delivery expected July 2017 with the final GTA delivery expected November 2017

Page 27: The Gimbal and Telescope Assembly for NASA's Next ... · presentation “SGSLR Site ... Final GTA delivery expected November 2017 . 13 October 2016 17 DESIGN STATUS GIMBAL . 13 October

13 October 2016 27

Thank You!

Used with permission from Cobham, LLC