the following clarifications are issued with this...

11
INVITATION FOR BIDS (IFB) NO. 160001 KMHS/BHA - Cottages at Forest Park for the Housing Authority of the City of Bremerton (BHA) ADDENDUM NO. 5 Solicitation Issued: Questions Due: Adden #5 Issued: Submittals Due: 8/22/16 MON 9/14/16 WED by 2:00 PM 9/7/2016 WED 9/28/16 WED by 2:00 PM The following clarifications are issued with this Addendum #5: CHANGES TO ELECTRICAL SPECIFICATIONS SE5.1 SECTION 28 1300 – ACCESS CONTROL SYSTEM ADD the following “1.2 BID ALTERNATE #1 A. Access Control System.” SE5.2 SECTION 28 1300 – ACCESS CONTROL SYSTEM 2.2, CHANGE - from “APPROVED MANUFACTURER’S CERTIFIED VENDOR AND INSTALLERS” to “APPROVED MANUFACTURER’S CERTIFIED INSTALLERS.” SE5.3 SECTION 28 1300 – ACCESS CONTROL SYSTEM 2.2.D, CHANGE - from “Only pre-approved vendors are acceptable prior to final bid.” to “Only pre-approved manufactures are acceptable prior to final bid.” SE5.4 SECTION 28 2300 – VIDEO SURVEILLANCE SYSTEM ADD the following “1.2 BID ALTERNATE #2 A. Video Surveillance System.” SE5.5 SECTION 28 2300 – VIDEO SURVEILLANCE SYSTEM 2.2, CHANGE - from “APPROVED MANUFACTURER’S CERTIFIED VENDOR AND INSTALLERS” to “APPROVED MANUFACTURER’S CERTIFIED INSTALLERS.” SE5.6 SECTION 28 2300 – VIDEO SURVEILLANCE SYSTEM 2.2.D, CHANGE - from “Only pre-approved vendors are acceptable prior to final bid.” to “Only pre-approved manufactures are acceptable prior to final bid.” SE5.7 SECTION 28 3100 – FIRE DETECTOR AND ALARM SYSTEM 2.2.D, CHANGE - from “APPROVED MANUFACTURER’S CERTIFIED VENDOR AND INSTALLERS” to “APPROVED MANUFACTURER’S CERTIFIED INSTALLERS.”

Upload: others

Post on 04-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan

INVITATION FOR BIDS (IFB) NO. 160001 KMHS/BHA - Cottages at Forest Park

for the Housing Authority of the City of Bremerton (BHA)

ADDENDUM NO. 5

Solicitation Issued: Questions Due: Adden #5 Issued: Submittals Due:

8/22/16 MON 9/14/16 WED by 2:00 PM 9/7/2016 WED 9/28/16 WED by 2:00 PM

The following clarifications are issued with this Addendum #5:

CHANGES TO ELECTRICAL SPECIFICATIONS SE5.1 SECTION 28 1300 – ACCESS CONTROL SYSTEM ADD the following “1.2 BID ALTERNATE #1 A. Access Control System.” SE5.2 SECTION 28 1300 – ACCESS CONTROL SYSTEM

2.2, CHANGE - from “APPROVED MANUFACTURER’S CERTIFIED VENDOR AND INSTALLERS” to “APPROVED MANUFACTURER’S CERTIFIED INSTALLERS.”

SE5.3 SECTION 28 1300 – ACCESS CONTROL SYSTEM

2.2.D, CHANGE - from “Only pre-approved vendors are acceptable prior to final bid.” to “Only pre-approved manufactures are acceptable prior to final bid.”

SE5.4 SECTION 28 2300 – VIDEO SURVEILLANCE SYSTEM ADD the following “1.2 BID ALTERNATE #2 A. Video Surveillance System.” SE5.5 SECTION 28 2300 – VIDEO SURVEILLANCE SYSTEM

2.2, CHANGE - from “APPROVED MANUFACTURER’S CERTIFIED VENDOR AND INSTALLERS” to “APPROVED MANUFACTURER’S CERTIFIED INSTALLERS.”

SE5.6 SECTION 28 2300 – VIDEO SURVEILLANCE SYSTEM

2.2.D, CHANGE - from “Only pre-approved vendors are acceptable prior to final bid.” to “Only pre-approved manufactures are acceptable prior to final bid.”

SE5.7 SECTION 28 3100 – FIRE DETECTOR AND ALARM SYSTEM

2.2.D, CHANGE - from “APPROVED MANUFACTURER’S CERTIFIED VENDOR AND INSTALLERS” to “APPROVED MANUFACTURER’S CERTIFIED INSTALLERS.”

Page 2: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan

Addendum #5 – IFB #160001 Page 2 of 4 9/7/2016

CHANGES TO THE ELECTRICAL DRAWINGS DE5.1 SHEET E0.1

A. Added Bid Alternate 1 Access Control System. Refer to replaced electrical sheet. B. Added Bid Alternate 2 Video Surveillance System. Refer to replace electrical sheet.

DE5.2 SHEET E3.1

A. Added Bid Alternate 1 Access Control System. Refer to replaced electrical sheet. B. Added Bid Alternate 2 Video Surveillance System. Refer to replace electrical sheet.

DE5.3 SHEET E3.2

A. Added Bid Alternate 1 Access Control System. Refer to replaced electrical sheet. B. Added Bid Alternate 2 Video Surveillance System. Refer to replace electrical sheet.

DE5.4 SHEET E3.3

A. Added Bid Alternate 1 Access Control System. Refer to replaced electrical sheet. B. Added Bid Alternate 2 Video Surveillance System. Refer to replace electrical sheet.

DE5.5 SHEET E3.10

A. Added Bid Alternate 1 Access Control System. Refer to replaced electrical sheet. B. Added Bid Alternate 2 Video Surveillance System. Refer to replace electrical sheet.

CHANGES TO THE MECHANICAL DRAWINGS DM5.1 SHEET M0.02

A. Gas Fired Water Heater Schedule; Revise Note #2 as follows: “Unit shall replace existing in place.”

DM5.2 SHEET M0.03

A. Electric Wall Heater Schedule; Remove EWH-215, EWH-216 & EWH-314 from schedule.

DM 5.3 SHEET M2.01

A. Plan Note #1; Remove “Contractor shall re-use existing mixing valve assembly” from paragraph. Mixing valve not required,

DM5.4 SHEET M2.02

A. Plan Note #1; Remove “Contractor shall re-use existing mixing valve assembly” from paragraph. Mixing valve not required.

Page 3: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan

Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016

DM5.5 SHEET M2.03

A. Plan Note #1; Remove “Contractor shall re-use existing mixing valve assembly” from paragraph. Mixing valve not required.

DM5.6 SHEET M3.02

A. Remove EWH-215 from Storage 215. B. Remove EWH-216 from Storage 216.

DM5.7 SHEET M3.03

A. Remove EWH-314 from Storage 314. APPROVED MANUFACTURERS The following have been approved as manufacturers only, and not for specified products. Approval does not relieve listed manufacturers from specification requirements.

SECTION # DESCRIPTION MANUFACTURER

1 26 5000 Interior and Exterior Lighting Request from Zuli Lighting Approved types fixtures are the following: F1 & F1E – LED 19” round (19” & 4000K) - Lightway F3 – LED Strip Light 2”x4” (22SL=2200 Lumens & 4000K) - Metalux F32 – LED Strip Light 2”x2” (4000K) - Metalux W1 – Exterior LED Wall Pack (4000K) – Mc Graw-Ed X – LED Exit – All Pro Em

The list of attendees at the pre-bid job walk on August 31 is attached. Questions Received: 1. Have the buildings been tested for lead and asbestos?

Lead and asbestos were tested for. The report is available in the specs.

2. How do we get specification substitution requests to the architect? Is it only by mail? Generally, there is a fax number or an email address to send to.

A revised substitution form is attached.

Page 4: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan

Addendum #5 – IFB #160001 Page 4 of 4 9/7/2016

3. When will substitution requests be approved? A final addendum will be issued on September 15th with approved substitutions.

4. I am looking at bidding the card access and the video. Do I bid that to bidding general contractors or directly to the BHA? If I am bidding directly, does my7 bid include the electric lock on the doors for the card access? You will need to provide your bid to bidding general contractors. You will find a list of those contractors who attended the job walk and are eligible to bid attached to this addendum.

END OF ADDENDUM

Page 5: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan
Page 6: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan

Bremerton Housing Authority SUBSTITUION REQUIREMENTS KMHS/BHA Cottages at Forest Park 01 2500 Rice Fergus Miller Project No. 201411.00

Bid Set August 1, 2016 Attachment A - 1

SUBSTITUTION REQUEST FORM

To: Architect: Rice Fergus Miller Architecture & Planning, Inc. 275 5th Street, Suite 100 Bremerton, Washington 98337 Kristen Linn [email protected] Project Name: KMHS / BHA Cottages at Forest Park Contractor: We hereby submit for consideration the following product instead of specified item for above project: Section Paragraph Specified Item Proposed Substitution: Attachments: (If not applicable, write N/A left of item number.) No. 1: Complete product data. No. 2: Drawings showing dimensional changes and other change to drawings. No. 3: Complete description of all changes to specifications. No. 4: Description of effect on other trades, other contracts, and contract completion date. No. 5: List of differences between proposed and specified items. No. 6: List of names and addresses of three similar projects on which product was used, date of in-

stallation, and Architect’s name and address. No. 7: Cost impact. Undersigned attests function and quality equivalent or superior to specified item. Submitted by: (Person and Firm) Date Phone Signature Acceptance by Architect: By: Accepted Date: Accepted as Noted Remarks: Not Accepted

END OF SECTION

Page 7: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan
Page 8: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan
Page 9: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan
Page 10: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan
Page 11: The following clarifications are issued with this …bremertonhousing.org/images/Contracts/Cottages_IFB/...Addendum #5 – IFB #160001 Page 3 of 4 9/7/2016 DM5.5 SHEET M2.03 A. Plan