the expanded very large array...5.13118 4.02882 cage1 2.125 cage2 2.775 3 4 2.450 cage5 sw1 1 2 3...
TRANSCRIPT
National Research CouncilCanada
Conseil national de recherchesCanada
The EVLA CorrelatorP. Dewdney
Herzberg Institute of AstrophysicsNational Research Council Canada
P. Dewdney EVLA Review - May 2006 2National Research CouncilCanada
Conseil national de recherchesCanada
Outline
1. Correlator Performance Goals2. Hardware Progress3. Software Progress4. System Progress5. Prototype Testing6. Installation Estimates7. Funding, Budget & Schedule8. Risk Issues
P. Dewdney EVLA Review - May 2006 3National Research CouncilCanada
Conseil national de recherchesCanada
Key EVLA Processing Capabilities8 GHz Bandwidth (dual polarization).Full polarization processing.Wide-field imaging.
Deep ImagingPolarization
16,000 channels at max. bandwidth (BW).>106 channels at narrow BWs.Spectral resolution to match any linewidth.Spectral polarization (Zeeman Splitting).
Narrow spectral linesWideband searches
8 tunable 2 GHz wide bands.Each band - 16 tunable sub-bands.Sub-band – independent spectral resolution.Simultaneous line and continuum.
Flexibility Many resources
1000 pulsar “phase bins”.“Single-dish” data output to user instruments.Very fast time sampling (<20 µs).
High time resolution
EVLA Correlator System Diagram
Significant Events Since Dec. 2004
• Correlator Chip CDR – Jan/05• Software Review – Jan/05.• Correlator Preliminary Design Review – July/05.• PCB fabricator contract signed – Jan/06.• Prototype Correlator chip wafers fab’d – Feb/06.• Software Review – Mar/06.• Prototype chip delivery – early Jun/06.• Baseline Board prototype delivery – Jun/06.• Station Board prototype delivery – est. Aug/06.
P. Dewdney EVLA Review - May 2006 6National Research CouncilCanada
Conseil national de recherchesCanada
Hardware Progress• FPGA’s
– All FPGA’s are designed, including the Filter Chip.• Station board
– Layout is close to completion, including Design-for-Manufacture approval.– Presently undergoing signal integrity simulation.– Prototype fabrication order expected in June.
• Baseline Board– Prototype fabrication under way.
• Phasing board– Draft specification (RFS) released.– Deferred in time but not reduced in priority.
• Other boards– Prototypes for all other boards already fabricated.– Fan-out board needs redesign for better signal margins.
• System– Racks designed and prototyped; thermal analysis done.– Power system RFP draft written.– Reliability analysis system in place – first draft of analysis complete.
Station Board Layout
• “Daughter” Board - brown.
• Power Supplies – pink.
• FPGA’s – Green
• Connectors – light brown and white.
• ~5000 parts.
• 140 required for EVLA.
Size: ~510 x ~410 mm
Baseline Board Layout
• Green chips – front side.
• Blue chips – back side.
• 8 x 8 array of correlator chips.
• LTA chips on the back side.
• Recirculation Controller.
• ~12000 parts
• ~177 required for EVLA.
0.0000.118
19.68719.569
9.8435
0.413
0.000
.2185
19.4685
19.687
3.5205
1.27914
3.3265
10.913
11.77914
13.8265
6 x .106" DIA
J3_1
J3
17.418
15.839
14.260
12.681
11.102
9.523
7.944
6.365
5.61295
4.580
8.3377
7.5503
5.9713
6.7587
9.1293
9.9167
10.7083
11.4957
12.2873
13.0747
13.8663
14.6537
15.4453
16.2327
17.0243
17.8117
5.13118
4.02882
CAGE1
CAGE22.125
2.775 CAGE3
CAGE4
2.450 CAGE5
SW1123
SW2
3
2
1
U100
U425 U109 U113 U427 U110 U428
U1_7
U2_7
U1_6
U2_6
U1_5
U2_5
U1_4
U2_4
U1_3
U2_3
U1_2
U2_2
U1_1
U2_1
U1
U2
U1_63
U2_63U3_63
U1_62
U2_62
U1_61
U2_61
U1_60
U2_60
U1_59
U2_59
U1_58
U2_58
U1_57
U2_57
U1_56
U2_56
U1_55
U2_55U3_55
U1_54
U2_54
U1_53
U2_53
U1_52
U2_52
U1_51
U2_51
U1_50
U2_50
U1_49
U2_49
U1_48
U2_48
U1_47
U2_47U3_47
U1_46
U2_46
U1_45
U2_45
U1_44
U2_44
U1_43
U2_43
U1_42
U2_42
U1_41
U2_41
U1_40
U2_40
U1_39
U2_39U3_39
U1_38
U2_38
U1_37
U2_37
U1_36
U2_36
U1_35
U2_35
U1_34
U2_34
U1_33
U2_33
U1_32
U2_32
U1_31
U2_31U3_31
U1_30
U2_30
U1_29
U2_29
U1_28
U2_28
U1_27
U2_27
U1_26
U2_26
U1_25
U2_25
U1_24
U2_24
U1_23
U2_23U3_23
U1_22
U2_22
U1_21
U2_21
U1_20
U2_20
U1_19
U2_19
U1_18
U2_18
U1_17
U2_17
U1_16
U2_16
U1_15
U2_15U3_15
U1_14
U2_14
U1_13
U2_13
U1_12
U2_12
U1_11
U2_11
U1_10
U2_10
U1_9
U2_9
U1_8
U2_8
J15
J12
J11
1.216
5.006
18.520
19.035
16.6285
15.0495
17.9298
16.3508
17.3647
16.8597
15.2807
15.7857
D3
D2
D1
D17
D4
D35
D36
D37
D5
D6
D10
D12
D13
D14
D15
D16
13.7017
12.6277
12.1227
U105
U107
U429
U111
U108
U115
3.150
14.2067
10.5437
9.4697
8.9647
11.0487
7.3857
6.3117
5.8067
7.8907
.320
U4_7
U5_29
U5_30
U5_31
U5_28
U4_6
U5_25
U5_26
U5_27
U5_24
U4_5
U5_21
U5_22
U5_23
U5_20
U4_4
U5_17
U5_18
U5_19
U5_16
U4_3
U5_13
U5_14
U5_15
U5_12
U4_2
U5_9
U5_10
U5_11
U5_8
U4_1
U5_5
U5_6
U5_7
U5_4
U4
U5_1
U5_2
U5_3
U5
6.993196.87681
6.274
6.027
18.04619
U3_7 U3_6
U3_62
U3_54
U3_46
U3_38
U3_30
U3_22
U3_14
U3_5
U3_61
U3_53
U3_45
U3_37
U3_29
U3_21
U3_13
U3_4
U3_60
U3_52
U3_44
U3_36
U3_28
U3_20
U3_12
U3_3
U3_59
U3_51
U3_43
U3_35
U3_27
U3_19
U3_11
U3_2
U3_58
U3_50
U3_42
U3_34
U3_26
U3_18
U3_10
U3_1
U3_57
U3_49
U3_41
U3_33
U3_25
U3_17
U3_9
U3_56
U3_48
U3_40
U3_32
U3_24
U3_16
U3_8
P. Dewdney EVLA Review - May 2006 9National Research CouncilCanada
Conseil national de recherchesCanada
Software Progress• GUI-based prototype testing software
– Complete enough to be useful already.– All FPGA’s covered except Phasing Board.– Provides “engineer’s view of correlator system.
• Permanent maintenance value.– Top-level GUI’s now under development.
• Virtual Correlator Interface– Well defined except for correlator output area.– Communications protocol well defined except for transport layer.
• Master Correlator Control Computer (MCCC)– Work deferred for GUI development.– Architecture/scope well defined.
• Real-time control software– “CMIB” processor on each board.– Operating system has been working for a long time.– XML-based communication with “outside world”.– Drivers for FPGA’s are well under way.
Correlator Software System Context
Archive
Model Server
Backend
Observation Layer
Log Server
Station Board Baseline Board
MCCC(1+1)
CPCC(1+1)
Monitor & Control Data
Astronomical (observed) Data
EVLA Monitor & Control
Correlator System GUI WIDAR Correlator - Top level system view (40 stations configuration)
Main
Rack 006 Rack 010
Rack 001 Rack 004Rack 003Rack 002 Rack 005
Rack 008 Rack 009
Rack 105 Rack 109
Rack 100 Rack 103Rack 102Rack 101
Rack 106
Rack 104
Rack 107 Rack 008
Rack 115
Rack 110 Rack 113Rack 112Rack 111 Rack 114
Rack 007
MCCC 1Active
MCCC 2Standby
CPCC 2Active
CPCC 1Standby
BootServerLog Server
2007-123-09:30:00.000 In progress2007-123:10:35:30.0002007-123-09:45:34.0002007-124:11:05:00.0002007-122:23:30:00.0002007-123:10:15:00.0002007-123:09:30:00.000
In progressRejectedIn progressAcceptedIn progress
Status
Test21V01V23V01V22V014Q01V021A90V013Q23V013Q22
Observation Start Time
Accepted
PowerSystems
Heatingand
Cooling
Details
01 4020304050506
44222
001-0-0001-0-4001-1-0001-1-4002-0-0002-0-2002-0-4
001-0-1001-0-5001-1-1001-1-5002-0-1002-0-3002-0-5
Board2Board1#Boards
EVLA07EVLA06EVLA05EVLA04EVLA03EVLA02EVLA01
Antenna Quad
4
Backend101-1-7 110-1-7Running
2007-123-09:45:34.010 2007-123-09:45:34.010
TGM 1
Time 2Time 1Time 0StatusBoard
TGM 0
Running
Details
Individual RackWIDAR Correlator - Rack
Main
31 2
Crate 0
0 4 5 76
31 2
Crate 1
0 4 5 76
Rack 001
---1514 ---
OK 123.23.1.60------------------
TGMTGM123.23.1.60
131211109877 OK
OK 123.23.1.1OKOK
InitializingOK------
123.23.1.17123.23.1.25123.23.1.34
STBSTBSTBSTBBLB
TypeIP
6543210
Board Status
123.23.1.9
2007-90-11:15 Replaced STB12007-89-13:45 Initial installation
Operator Log
Station Board Top Level
Station Board Rack: 1 Crate: 0 Slot : 5 Filter 0_12
Screen Hardware
Register: Read:Write:
Read Write Write/Read
Read/Write Registers
Test Port TP0 TP1 TP2 TP3
33 5 17 255
Configuration
Refresh
Sec: Once
General
/evla/widar/stb/filter/cfg_01.xmlConfiguration File
FPGA Bit File /evla/widar/stb/filter/bit/abc Browse
Design/Revision/Version: running01 71 State:
Browse
Input delay calibration:
Status
Input delay adjust:
Delay Module Input:System clock:
Read/Write:
Reset status indicators
CRC
View Error Counts
Reset Error Counts
Input: B
InOut
AOutput Enable:
Input Delay: 37 112Daisy Delay:
Time Interval :
Delay Model: External
Delay: 123456 Delay Rate: 0
Demux Factor:
Delay0Data Input Rate: 15
Phase Factor: 0x4000
/evla/widar/stb/filter/s1prd/abcProduct File: Browse
Invalid Stretch Length :
Scale Factor : 1
Filter Delay :
Data Output Rate:
Number of Taps :
Stage 1
16
XBAR
32
/evla/widar/stb/filter/s2cof/abcCoefficient file Browse
Invalid Stretch Length :
Scale Factor : 1
Filter Delay :
Output Rate:
16
Calculation Rate:
32
Stage 2
Number of Taps
/evla/widar/stb/filter/s3cof/abcCoefficient file Browse
Invalid Stretch Length :
Scale Factor : 1
Filter Delay :
Output Rate:
16
Calculation Rate:
32
Stage 3
Number of Taps
/evla/widar/stb/filter/s4cof/abcCoefficient file Browse
Invalid Stretch Length :
Scale Factor : 1
Filter Delay :
Output Rate:
16
Calculation Rate:
32
Stage 4
Number of Taps
Format
Valids
on
313
Power off 12345
Quantizer Clip Count
Quantizer State Count
Quantizer Power
RFI Detections
TEX Valids
TEX Sums
Quantized State:
RFI Detect Level:
RFI Detect Length:
Auto -3
Select Data:
Quantizer Scaling:
Quantizer # Bits:
TEX Trig File
TEX Phase Model
TEX Phase:
TEX Phase Rate:
/evla/widar/stb/filter/fm/tex/trig/abc
External
0xFEDCBA9
0x12345678
Browse
0x17534
0x1234
4
256
Select Clip:
cos sin
on off
Output File: /evla/widar/stb/filter/fm/out/abc Browse
Clip Count
Sideband Flipper On
Histogram
VCI
Input # bands:
Output band width (MHZ):
Output band center (MHz):
Input # bits:
Input band width (MHz):
Mix:
Output # bits:
192.0000000
Input band:
Setup
/evla/widar/stb/filter/fm/out/abcResults file: Browse
Fbit:
Accumulation (interrupts): 100
Flip:
LSB:
Mixer Phase Model:
Phase Rate: 0xFEDCBA9
Phase:
Use mixer
0x00000000
/evla/widar/stb/filter/s2mix/abcMixer Trig File Browse
Mixer
External
Filter Control GUI
P. Dewdney EVLA Review - May 2006 15National Research CouncilCanada
Conseil national de recherchesCanada
Correlator Software People• Sonja Vrcic (Penticton)
– Coordinates overall design and specification.– Virtual Correlator Interface (VCI) definition.– Master Correlator Control Computer (MCCC) S/W.
• Bruce Rowen (Socorro)– Correlator hardware control S/W (CMIB).
• Kevin Ryan (Socorro)– GUI development and hardware control S/W.
• Martin Pokorny (Socorro)– Correlator Backend software.
• Michael Rupen, John Romney, Bryan Butler, Ken Sowinski, Barry Clark, Bill Sahr (Socorro)
– Advisory capacity.
P. Dewdney EVLA Review - May 2006 16National Research CouncilCanada
Conseil national de recherchesCanada
Correlator-related Software Issues
• Correlator output: ALMA Science Data Model (ASDM) must be qualified for EVLA use.– On the surface ASDM looks all right in the sense that additions can be
made to meet EVLA requirements.– Is ALMA effort required and is it available?– This issue is to be addressed later in the series of presentations.
• Preliminary plans to add “blocks” in the Correlator Back End (CBE).– Additional Ethernet Switch and output Fast Data Formatter
computer(s).– Formatting to ASDM spec’s will probably take place in the Fast Data
Formatter.– Details to be worked out.
• Virtual Correlator Interface (VCI) Transport protocol is to be defined.
• Potential unknown throughput issues could arise.
System Progress
• NRAO work on correlator room is progressing rapidly.• Design of overall room layout is complete.• Environmental specifications have been developed.
– Air flow & temperature: ~1700 cfm per rack, 15 oC.– ElectroStatic Discharge (ESD)
• 90 nm devices used extensively (<1/1000 thickness of human hair)• Humidity specs.• Strict handling and servicing procedures.
– Air quality• ISO 14644-1 class 8 + MERV 13 filter.
• Racks– “Thermal prototypes” have been built and tested.– “Mechanical prototypes” ditto.– Preliminary fabrication plan is being developed.
• Preliminary installation plan is being developed.• Power plant specifications/RFP draft written for
acquisition this fiscal year (ends Mar 31/07).
Correlator Rack Layout1 GbpsEthernet
to Backend
100/1000 MbpsEthernet M&C
M&CEthernetswitch
-48 VDCbreakerpanel
Up to 40, 4-wafer,1.024 Gbpscables from
station racks toFanout Boards.
-48 VDC,48VRET frompower plant
Up to 256, 4-wafer,
1.024 Gbpscables: Fanout-
to-BaselineBoards
FRONT
Raised floor
Rack pedestal
airflow
airflow
Correlator Room Layout48'-0"
Prim
Bay
47'-0
"
2-cable 48VDC connects from each DCPDU breaker output to each rack
seperately.(24 cable pairs in a 32-Station correlator)
115VAC
Fiber Fiber
HV
AC C
W U
NIT
HV
AC C
W U
NIT
SPARE - reservedHVAC 5th CW UNIT
(if req’d)
40-Station Expansionadds 2 Station racks
B
B
B
B
B
B
S40
S40
Station Racks(8)
BaselineRacks(16)
AC input for HVAC andlighting.
AC input, 50 kW, 56 kVA for backendcomputers, MCCC, CPCC, testoutlets
480 VAC, 3-phasedelta, 190 kW (211kVA) for 48 VDC plant
Sec
Bay
Battery String 1
Battery String 2
BE1
BE2
BE3
BE4
BE5
BE6
HVAC DXCOMPR UNIT
HVAC DXCOMPR UNIT
-48VDC Power Plant
Battery Strings
Backend Computers
B
B
B
B
B
B
B
B
S
S
S
S
B
B
S
S
S
S
SwitchRack
MCCC/CPCCRack
ElectroStatic Discharge (ESD)
RESTRICTED ACCESS
Overriding door interlock will soundALARM
ESD Protected Areawear ESD coats and shoes
P. Dewdney EVLA Review - May 2006 21National Research CouncilCanada
Conseil national de recherchesCanada
Correlator Testing
• Production correlator chip tests– Functional acceptance test by supplier using DRAO-
supplied equipment.• At speed, but not over temperature range.
– DRAO lab tests: special jig to be fabricated.• HALT/HASS tests being investigated (advanced version of
“burn-in”).• Unit PCB hardware tests during production:
– Fast functional tests performed at factory in DRAO-supplied equipment.
• Unit hardware tests after acceptance– HALT/HASS tests of circuit boards (or equivalent).– Extended functional tests.
P. Dewdney EVLA Review - May 2006 22National Research CouncilCanada
Conseil national de recherchesCanada
Correlator Testing (cont’d)
• System Tests– Prototype Stage
• Extended testing/debug cycle in lab – all functions.• Many self-tests, simulated observations.• Should confer a high degree of reliability for On-the-Sky tests.
– On-the-sky Tests• Final demonstration of prototype tests – designed to be quasi-
independent of EVLA S/W.• Begin System Integration with EVLA software (continuing
process).• Hardware left at VLA site.
– Software Tests after On-the-Sky correlator delivered.• Continued testing with hardware that will remain at the VLA.• Understand interference (RFI) and the “clues” that the WIDAR
system provides.
Test Configuration – Software View
On-the-Sky Test Setup
Fan Tray
-48 VDC Power Supply
Ethernet Switch
12Ucrate
Sta
tion
Boar
d
Base
line
Boar
d
Sta
tion
Boar
d
Sta
tion
Boar
d
Sta
tion
Boar
d Tim
ecod
e B
oard
4' 5"
27"
Host ComputerBackendComputer
To NRAO network
1 phase: 170-264 VAC (30 A)
Host ComputerHostComputer
“External Timecode” (fiber)
128 MHz CW, 0dBm
110 VAC, 15 A
From NRAOArray TimingReference
-48 VDC Breaker Panel
P. Dewdney EVLA Review - May 2006 25National Research CouncilCanada
Conseil national de recherchesCanada
Installation Procedure(Note: Dates from Apr/06 Long Term Schedule)
• 06-07: Install –48V DC power system.• 06-07: Install underfloor cables.• 08: Manufacture racks in Penticton.• 08: Install overhead power distribution.• 08: Install control computers, Ethernet switches,
backend computers and other COTS equipment.• 08-09: Install boards into racks in an order that
maximizes scientific benefit.
P. Dewdney EVLA Review - May 2006 26National Research CouncilCanada
Conseil national de recherchesCanada
Preliminary Installation Estimates(Note: Dates from Apr/06 Long Term Schedule)
• Q4-06/Q1-07 – power supply (-48 V DC) .– Procurement, installation, training.– 40 person-days of NRAO effort.
• Q3/Q4-07 – signal cabling.– Installation of inter-rack high-speed cabling.– 512 pre-fab cables, 3 different lengths; 24 pre-fab power monitor &
control cables.– 52 person-days of NRAO effort.
• Q4-07/Q1-08 – Racks– 24 racks, pre-fabricated, tested in Penticton.– 24 person days of NRAO effort.
• Q1-08 – power cabling.– Two cable runs: To distribution panel; distribution panel-to-racks.– 20 person-days of NRAO effort.
P. Dewdney EVLA Review - May 2006 27National Research CouncilCanada
Conseil national de recherchesCanada
Preliminary Installation Estimates (cont’d)
• Q2-08 – control computers, M&C Ethernet– MCCC, CPCC, Ethernet switches, etc.– 120 VAC power required.– 8 person-days of NRAO effort.
• Q3-08 – Back-end computers and equipment.– Gbit Ethernet system.– 20 person-days of NRAO effort.
• Q3-08/Q3-09 – Board installation and test.– Occasional NRAO effort.
• Total Est. NRAO installation effort:– ≥ 8.2 Person-Months.
EVLA Correlator Group
DRAO-based.
NRAO-based.
P. Dewdney EVLA Review - May 2006 29National Research CouncilCanada
Conseil national de recherchesCanada
Funding in Canada – No ChangeAug/03 – Canadian Treasury Board approval of
submitted budget ($C 20M over 5 years).
• Most spending in $US.• But see risk factors.
Correlator Projected Spending Profile
EVLA Spending Profile
$-
$1,000,000.00
$2,000,000.00
$3,000,000.00
$4,000,000.00
$5,000,000.00
$6,000,000.00
1999
/0020
00/01
2001
/0220
02/03
2003
/0420
04/05
2005
/0620
06/07
2007
/0820
08/09
2009
/10
Fiscal Year
$C
Labour
Fabrication
Contracts
Equipment
Softw are
Miscellaneous
Travel
EVLA Spending Profile
$-
$1,000,000.00
$2,000,000.00
$3,000,000.00
$4,000,000.00
$5,000,000.00
$6,000,000.00
$7,000,000.00
1999
/0020
00/01
2001
/0220
02/03
2003
/0420
04/05
2005
/0620
06/07
2007
/0820
08/09
2009
/10
Fiscal Year
$C
Labour
Fabrication
Contracts
Equipment
Softw are
Miscellaneous
Travel
Correlator Summary ScheduleVery Uncertain Time Scale
Milestone Progress
P. Dewdney EVLA Review - May 2006 33National Research CouncilCanada
Conseil national de recherchesCanada
Project Management
• Schedule– Detailed schedule periodically updated.– Near-term (target) schedule updated weekly.– Long-term schedule discussed monthly, and
cross-checked against detailed schedule.• Budget
– Projections updated with schedule.• Bills of Materials (BOM’s)
– 1000’s of components.– Maintenance required.
P. Dewdney EVLA Review - May 2006 34National Research CouncilCanada
Conseil national de recherchesCanada
Correlator Documentation
• Master Document Tracking Spreadsheet Maintained at DRAO.
• 115 documents written so far, including “Memos”.
• Additional 23 documents with designations and titles are anticipated.
P. Dewdney EVLA Review - May 2006 35National Research CouncilCanada
Conseil national de recherchesCanada
Principal Design Reviews
• Three Design Reviews:– Conceptual (CoDR – Nov, 2001)
• Review architecture and overall design.
– Preliminary (PDR – July, 2005)• Review detailed designs before prototypes.
– Critical (CDR)• Review system before “limited production” stage.• Scheduled for Q2/Q3, 2007.
P. Dewdney EVLA Review - May 2006 36National Research CouncilCanada
Conseil national de recherchesCanada
Non-Technical Program Risks• Funding
– Original allotment of funds was over five years.– NRC management was made aware in Aug/03 that this does not fit the project spending profile – they
decided that internal cash management could deal with the problem.– Will have to apply for an extension, which in the present climate presents a risk.– Worst case is that project could hypothetically be halted in April 2008.– Active cash management at HIA, NRC level.
• Schedule slippage?– Due to a slow start (already happened at the beginning).– Concerns over procurement processes.
• This risk is retired. Major procurement contracts are in place except for power supply.
– Technical progress slower than the deliberately aggressive initial schedule.– “Re-spins” will present additional schedule risk.
• Inadequate contingency?– The contingency fractions are much smaller than most high-tech projects.– Cost risk will be reduced quickly once prototypes are tested. – Exchange-rate changes have been favourable to date.
• Inflation not being recognized in funding profile?– Inflation is a corrosive influence.
P. Dewdney EVLA Review - May 2006 37National Research CouncilCanada
Conseil national de recherchesCanada
Technical Program Risks• Technical risk is currently at a maximum
– Much design effort and prototype expenditure has taken place.– Prototype hardware is being fabricated (or about to be fab’d), but not
received/tested.• But …
– Considerable design effort expended to reduce technical risk.• Finely divided testing schemes for circuit boards – every path can be checked
independently.• Correlator chip underwent an independent test and verification process, including a
major simulation campaign after the “place-and-route” stage.• A separate Design for Manufacturability (DFM) analysis done for circuit boards –
results in a major reduction in risk.
• Formal system reliability analysis has been done, and will be updated.• Funds and design effort has been expended to minimize technical risk.
– We are optimistic and confident that technical risk is reasonably low.
P. Dewdney EVLA Review - May 2006 38National Research CouncilCanada
Conseil national de recherchesCanada
Descoping
• The correlator is difficult to split, once designed, and saving is inefficient.
• Have not reconsidered descoping options since the budget is currently “under control”.
• If the previously-mentioned non-technical risks become imminent concerns, then de-scoping options will have to be revisited.
P. Dewdney EVLA Review - May 2006 39National Research CouncilCanada
Conseil national de recherchesCanada
Project Summary• Are we meeting the required schedule?
– We are sticking with the original delivery date, although there is now some squeezing of activities towards the end.
• Are we over budget at this stage?– Budget is slimly allocated, but we are not over budget.
• Are we planning to deliver on what we said we would do?– Yes, with minor improvements.
• What are the major risks at this stage?– Hypothetical funding difficulty in 2008.– Technical risks should be reduced this year as prototypes are
tested.
End