the decision box represents key management decisions and serve as the gates which delineate phases....

1
The decision box represents key management decisions and serve as the GATES which delineate phases. The decision can be to proceed, exit, or recycle. More complex projects may need additional intermediate decision reviews in a phase. Stop, Hold, Recycle The decision makers are individuals responsible for the framing of the opportunity and having the authority to approve the work plan. Stop, Hold, Recycle Stop, Hold, Recycle Stop, Hold, Recycle New Opportunities PHASE 1 ASSESS PHASE 2 SELECT PHASE 3 DEVELOP PHASE 4 EXECUTE PHASE 5 OPERATE&EVALUATE DECISION EXECUTIVE …………… ………………………. ………………………. DECISION EXECUTIVE …………… ………………………. ………………………. DECISION EXECUTIVE …………… ………………………. ………………………. DECISION EXECUTIVE …………… ………………………. ………………………. DECISION EXECUTIVE …………… ………………………. ………………………. Opportunity Commit resources to progress opportunity Commit To Execution FID Asset Acceptance Proceed or bail out Commit to Development Plan Screen Opportun ity Identify Feasible Concept(s ) Interim Review(s) Generate Value/ Revenue Decision Makers Deliverables at Major Reviews Work Team Focus Items TO PHASE 1 The primary activities completed by the work team in each phase The multifunctional work team carries out the work under the guidance of the project manager or team leader. Expectations of the decision team are met through frequent communication & alignment of goals. TEAM LEADER……………… ……….………………. ……………………….. The process does not end here! Secondary opportunities and projects will loop back into the appropriate phase. Documentation facilitates continuity of effort, captures lessons learned for future projects and evaluates the work done in that phase. CLEARLY FRAME GOAL TEST FOR STRATEGIC FIT PRELIMINARY OVERALL PLAN PRELIMINARY ASSESSMENT (eg Technical, market, etc.) REGULATORY APPROVAL PLAN FOR PHASE 2 (incl. Funding approval and resource requirements) REASSESS EFC, INCL. FUNDING FOR EACH SUCCESSIVE OPREP PHASE & REPORT ON COST & OTHER PERFORMANCE FOR CURRENT PHASE OTHER FOCUS ITEMS ... GENERATE ALTERNATIVES PRELIMINARY DEVELOPMENT OF ALTERNATIVES DEVELOP EXPECTED VALUE IDENTIFY PREFERRED ALTERNATIVE(S) REGULATORY APPROVAL PLAN FOR PHASE 3 (incl. Funding approval and resource requirements) REASSESS EFC, INCL. FUNDING FOR EACH SUCCESSIVE OPREP PHASE & REPORT ON COST & OTHER PERFORMANCE FOR CURRENT PHASE OTHER FOCUS ITEMS... FULLY DEFINE SCOPE REFINE ESTIMATE DEVELOP FINAL EXPECTED VALUE REGULATORY APPROVAL SUBMIT FUNDING FOR APPROVAL DEVELOP DETAILED EXECUTION PLAN FOR PHASE 4 OTHER FOCUS ITEMS BUSINESS PLAN FOR PHASE 5 (DRAFT) IMPLEMENT EXECUTION PLAN FINALISE OPERATIONS PLAN BUSINESS PLAN FOR PHASE 5 PROJECT REVIEW REGULATORY APPROVAL OTHER FOCUS ITEMS OPERATE ASSET MONITOR AND EVALUATE PERFORMANCE IDENTIFY NEW OPPORTUNITIES REGULATORY APPROVAL OTHER FOCUS ITEMS Focus items provide a checklist of key activities, ensuring the quality of the work is commensurate with the next milestone decision being made. Identifies the required deliverable(s) that will enable the decision D o c u m e n t D o c u m e n t D o c u m e n t D o c u m e n t TEAM LEADER……………… ……….………………. ……………………….. PROJECT MANAGER ………… ……….………………. ……………………….. PROJECT MANAGER ………… ……….………………. ……………………….. ASSET MANAGER ………… ……….………………. ……………………….. Primary Activity Value Improving Practices Assurance Checks VIP’s are available to help progression through a particular phase. They assist the teams to maximise value of an opportunity. Assurance Checks support the milestone decision to move to the next phase. They provide decision makers (both technical & commercial) assurance that the recommendations are sound and will deliver maximum value. Refine Selected Alternative (s) Selection Report Feasible Concept(s) Business Proposal Package Functional Asset(s) Performance Assessment Valuatio n Report Value Enhancing Opportunity POST INVESTMENT REVIEW FINAL: BENCHMARKING REVIEW FINAL INVESTMENT DECISION REVIEW BENCHMARKING REVIEW (FEL) COMMERCIAL ASSURANCE REVIEW OPPORTUNITY FRAMING TECHNOLOGY MANAGEMENT PROJECT EXECUTION PLANNING RISK MANAGEMENT CONSTRUCTABILITY STANDARDS CONTRACTING STRATEGY COST ENGINEERING PEER ASSISTS SUBSURFACE UNCERTAINTY MANAGEMENT OPPORTUNITY FRAMING TECHNOLOGY MANAGEMENT PROJECT EXECUTION PLANNING RISK MANAGEMENT CONTRACTING STRATEGY COST ENGINEERING ASSURANCE PLANNING PEER ASSISTS SUBSURFACE UNCERTAINTY MANAGEMENT PROJECT INITIATION REVIEW COMMERCIAL ASSURANCE REVIEW SUBSURFACE UNCERTAINTY MANAGEMENT FEASIBILITY REVIEW DEVELOPMENT PLAN(CONCEPT SELECTION ) REVIEW BENCHMARKING REVIEW (FEL) COMMERCIAL ASSURANCE REVIEW PRE START UP REVIEW Commit To Concept Alternative (s) Final Development Plan Recommendation Finalis e Busines s Proposa l TECHNOLOGY MANAGEMENT PROJECT EXECUTION PLANNING CONSTRUCTABILITY STANDARDS RISK MANAGEMENT CONTRACTING STRATEGY COST ENGINEERING PEER ASSISTS SUBSURFACE UNCERTAINTY MANAGEMENT PROJECT EXECUTION PLANNING(FINAL) CONSTRUCTABILITY RISK MANAGEMENT COST ENGINEERING SUBSURFACE UNCERTAINTY MANAGEMENT OPPORTUNITY & PROJECT REALISATION PROCESS Execute Interim Review(s) Refine Developmen t Plan Option Guidelines Guidelines or “how to” manuals/handbooks are available to support key activities in each phase. 22-2-2000 FDP BOD ARP

Upload: magdalen-ray

Post on 16-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The decision box represents key management decisions and serve as the GATES which delineate phases. The decision can be to proceed, exit, or recycle. More

The decision box represents key management decisions and serve as the GATES which delineate phases. The decision can be to proceed, exit, or recycle.

More complex projects may need additionalintermediate decision reviews in a phase.

Stop, Hold, RecycleThe decision makers are individuals responsible for the framing of the opportunity and having the authority to

approve the work plan.

Stop, Hold, Recycle Stop, Hold, Recycle Stop, Hold, Recycle New Opportunities

PHASE 1ASSESS

PHASE 2SELECT

PHASE 3DEVELOP

PHASE 4EXECUTE

PHASE 5 OPERATE&EVALUATE

DECISION EXECUTIVE ……………

……………………….……………………….

DECISION EXECUTIVE ……………

……………………….……………………….

DECISION EXECUTIVE ……………

……………………….……………………….

DECISION EXECUTIVE ……………

……………………….……………………….

DECISION EXECUTIVE ……………

……………………….……………………….

Opportunity

Commitresources to

progress opportunity

Commit To Execution

FID

Asset Acceptance

Proceed or bail out

Commit to Development

Plan

Screen Opportunity

Identify Feasible

Concept(s)

Interim Review(s)

Generate Value/

Revenue

Decision Makers

Deliverables at Major Reviews

Work Team

Focus Items

TO PHASE 1

The primary activities completed by the work teamin each phase

The multifunctional work team carries out the work under the guidance of the project manager or team leader. Expectations of the decision team are met through frequent communication &

alignment of goals.

TEAM LEADER……………………….……………….………………………..

The process does not end here!Secondary opportunities andprojects will loop back into the

appropriate phase.

Documentation facilitatescontinuity of effort, captureslessons learned for futureprojects and evaluates the work done in that

phase.

CLEARLY FRAME GOAL

TEST FOR STRATEGIC FIT

PRELIMINARY OVERALL PLAN

PRELIMINARY ASSESSMENT(eg Technical, market, etc.)

REGULATORY APPROVAL

PLAN FOR PHASE 2 (incl. Funding approval and resource requirements)

REASSESS EFC, INCL. FUNDING FOR EACH SUCCESSIVE OPREP PHASE & REPORT ON COST & OTHER PERFORMANCE FOR CURRENT PHASE

OTHER FOCUS ITEMS ...

GENERATE ALTERNATIVES

PRELIMINARY DEVELOPMENT OFALTERNATIVES

DEVELOP EXPECTED VALUE

IDENTIFY PREFERRED ALTERNATIVE(S)

REGULATORY APPROVAL

PLAN FOR PHASE 3 (incl. Funding approvaland resource requirements)

REASSESS EFC, INCL. FUNDING FOR EACH SUCCESSIVE OPREP PHASE & REPORT ON COST & OTHER PERFORMANCE FOR CURRENT PHASE

OTHER FOCUS ITEMS...

FULLY DEFINE SCOPE

REFINE ESTIMATE

DEVELOP FINAL EXPECTED VALUE

REGULATORY APPROVAL

SUBMIT FUNDING FOR APPROVAL DEVELOP DETAILED EXECUTION PLAN FOR PHASE 4

OTHER FOCUS ITEMS• BUSINESS PLAN FOR PHASE 5 (DRAFT)•

IMPLEMENT EXECUTION PLAN

FINALISE OPERATIONS PLAN

BUSINESS PLAN FOR PHASE 5

PROJECT REVIEW

REGULATORY APPROVAL

OTHER FOCUS ITEMS• •

OPERATE ASSET

MONITOR AND EVALUATE PERFORMANCE

IDENTIFY NEW OPPORTUNITIES

REGULATORY APPROVAL

OTHER FOCUS ITEMS

Focus items provide a checklist of key activities, ensuring the quality of the work is commensurate with the next milestone

decision being made.

Identifies the required deliverable(s) that will enable the decision

Do cu m

e nt

Do cu m

e nt

Do cu m

e nt

Do cu m

e nt

TEAM LEADER……………………….……………….………………………..

PROJECT MANAGER ………………….……………….………………………..

PROJECT MANAGER ………………….……………….………………………..

ASSET MANAGER ………………….……………….………………………..

Primary Activity

Value ImprovingPractices

Assurance Checks

VIP’s are available to help progression through a particular phase. They assist the teams to maximise value of an opportunity.

Assurance Checks support the milestonedecision to move to the next phase. They provide decision makers (both technical & commercial) assurance that the recommendations are sound and will deliver maximum value.

Refine Selected

Alternative(s)

Selection Report Feasible

Concept(s)

Business Proposal Package Functional

Asset(s)

Performance

Assessment

ValuationReport

Value Enhancing Opportunity

• POST INVESTMENT REVIEW• FINAL: BENCHMARKING REVIEW

• FINAL INVESTMENT DECISION REVIEW• BENCHMARKING REVIEW (FEL)• COMMERCIAL ASSURANCE REVIEW•

•OPPORTUNITY FRAMING•TECHNOLOGY MANAGEMENT•PROJECT EXECUTION PLANNING•RISK MANAGEMENT•CONSTRUCTABILITY•STANDARDS•

•CONTRACTING STRATEGY•COST ENGINEERING•PEER ASSISTS•SUBSURFACE UNCERTAINTY

MANAGEMENT

•OPPORTUNITY FRAMING•TECHNOLOGY MANAGEMENT•PROJECT EXECUTION PLANNING•RISK MANAGEMENT

•CONTRACTING STRATEGY•COST ENGINEERING•ASSURANCE PLANNING•PEER ASSISTS•SUBSURFACE UNCERTAINTY

MANAGEMENT

• PROJECT INITIATION REVIEW• COMMERCIAL ASSURANCE REVIEW

• SUBSURFACE UNCERTAINTY MANAGEMENT

• FEASIBILITY REVIEW• DEVELOPMENT PLAN(CONCEPT

SELECTION ) REVIEW• BENCHMARKING REVIEW (FEL)• COMMERCIAL ASSURANCE REVIEW

• PRE START UP REVIEW•

CommitTo Concept Alternative(s)

FinalDevelopment Plan Recommendation

Finalise Business Proposal

•TECHNOLOGY MANAGEMENT•PROJECT EXECUTION PLANNING•CONSTRUCTABILITY•STANDARDS•RISK MANAGEMENT• •

•CONTRACTING STRATEGY•COST ENGINEERING•PEER ASSISTS•SUBSURFACE UNCERTAINTY

MANAGEMENT•

•PROJECT EXECUTION PLANNING(FINAL)•CONSTRUCTABILITY•RISK MANAGEMENT•

•COST ENGINEERING•SUBSURFACE UNCERTAINTY

MANAGEMENT•

OPPORTUNITY & PROJECT REALISATION PROCESS

Execute

Interim Review(s)

Refine Development Plan Option

GuidelinesGuidelines or “how to” manuals/handbooks are available to support key activities in each phase.

22-2-2000

FDPBODARP