The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Upload: shavonne-bryan

Post on 22-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

The countdown to 2016:Your action list to be ready

Daniel WalshSenior BIM Author

@DanWalsh82

Page 2: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Countdown to Level 2 BIMB/555 Roadmap

Level 2 BIM TimelineAction List

Your checklist to be ready

Today’sAgenda

Page 3: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Government Construction Strategy - May 2011

History of

Mandate

2011

2016

2012

2013

2014

2015

Page 4: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Government Construction Strategy - May 2011Now = March 2015

History of

Mandate

2011

2016

2012

2013

2014

2015

You are Here

Page 5: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Government Construction Strategy - May 2011Now = March 2015Level 2 BIM by early 2016

History of

Mandate

2011

2016

2012

2013

2014

2015

You are Here

Page 6: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

B/555Roadmap

Page 7: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

B/555Roadmap

Page 8: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

B/555Roadmap

Page 9: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Level 2 BIMTimeline

2011

2016

2012

2013

2014

2015

Government Construction Strategy

Now

Page 10: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

1192Standards

2011

2016

2012

2013

2014

2015

BS 1192:2007Collaborative production of architectural,

engineering and construction information. Code of practice

Now

Page 11: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

2011

2016

2012

2013

2014

2015

PAS 1192-2:2013Specification for information management

for the capital/delivery phase of construction projects using building

information modelling

1192Standards

Now

Page 12: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

2011

2016

2012

2013

2014

2015

PAS 1192-3:2014Specification for information management

for the operational phase of assets using building information modelling

1192Standards

Now

Page 13: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

2011

2016

2012

2013

2014

2015

BS 1192-4:2014Fulfilling employers information exchange

requirements using COBieCode of practice

1192Standards

Now

Page 14: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

2011

2016

2012

2013

2014

2015

PAS 1192-5:DraftSpecification for security-minded building

information modelling, digital built environments and smart asset management.

PAS 1192-5

DRAFT

1192Standards

PAS 1192-5

DRAFTNow

Page 15: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BS 8541-1:2012Library objects for architecture, engineering and

construction - Identification and classification.

8541Standards

Now

Page 16: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BS 8541-2:2011Library objects for architecture, engineering and

construction – Recommended 2D symbols of building elements for use in Building Information

Modelling.

8541Standards

Now

Page 17: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BS 8541-3:2012Library objects for architecture, engineering and

construction – Shape and measurement

8541Standards

Now

Page 18: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BS 8541-4:2012Library objects for architecture, engineering and construction – Attributes for specification and

assessment

8541Standards

Now

Page 19: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

BS 8541-5

TBD

2011

2016

2012

2013

2014

2015

BS 8541-5:TBDLibrary objects for architecture, engineering and

construction – Assemblies

8541Standards

PAS 1192-5

TBDNow

Page 20: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BS 8541-6:TBDLibrary objects for architecture, engineering and

construction – Product Declarations

8541StandardsBS 8541-6

TBD

PAS 1192-5

TBD

PAS 1192-6

TBDNow

Page 21: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BS 7000-4:2013Design Management Systems:

Guide to managing design in construction

7000Standards

PAS 1192-5

TBD

PAS 1192-6

TBDNow

Page 22: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

BIP 2207Building Information Management – A standard

framework and guide to BS 1192

BIP 2207Guide

PAS 1192-5

TBD

PAS 1192-6

TBDNow

Page 23: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

Uniclass 1 & 1.4 & 2 & TBDClassification system for structuring

construction information.

UniclassClassification

PAS 1192-5

TBD

PAS 1192-6

TBD

1

2 TBDUniclass

TBDNow

Page 24: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

NRM 1Order of Cost Estimating and Cost Planning for

Capital Building Works

Method of

Measurement

PAS 1192-5

TBD

PAS 1192-6

TBD

1

2 TBDUniclass

TBDNow

Page 25: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

NRM 2Detailed Measurement for Building Works

Method of

Measurement

PAS 1192-5

TBD

PAS 1192-6

TBD

1

2 TBDUniclass

TBDNow

Page 26: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

NRM 3Order of cost estimating and cost planning for

building maintenance works

Method of

Measurement

PAS 1192-5

TBD

PAS 1192-6

TBD

1

2 TBDUniclass

TBDNow

Page 27: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

CESMM4Civil Engineering Standard Method of

Measurement 4th edition

Method of

Measurement

PAS 1192-5

TBD

PAS 1192-6

TBD

1

2 TBDUniclass

TBDNow

Page 28: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 1192-5

DRAFT

2011

2016

2012

2013

2014

2015

DPoWDigital Plan of Work

Delivery

PAS 1192-5

TBD

PAS 1192-6

TBD

1

2 TBDUniclass

TBDNow

Page 29: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Pre-Qualification Questionnaire

Be able to respond to the 4 BIM questions that form table 8 of PAS 91.

PAS 91

ActionList

Page 30: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Employer’s Information Requirements

Be able to prepare, contribute to or respond to EIRs.

EIR

ActionList

Page 31: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

BIM Execution Plan

Be able to prepare or contribute to pre and post contract BEPs.

BEP

ActionList

Page 32: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

CIC BIM Protocol

Aware of implications of, and have willingness and ability to append BIM Protocol to contracts and PI insurances.

BIM Protocol

ActionList

Page 33: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Common Data Environment

Able to work within a CDE that is capable of achieving the processes outlined within 1192 suite of documents.

CDE

ActionList

Page 34: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Able to produce graphical and / or information BIM data in the format required by all project participants, including IFC and COBie.

Producing BIM Data

ActionList

Page 35: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Able to interrogate the BIM data produced by all project participants, using findings to inform decisions.

Interrogating BIM Data

ActionList

Page 36: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Able to produce or contribute to BIM uses required for project: Clash resolution; programme analysis; cost analysis; etc

BIM Uses

ActionList

Page 37: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

Digital Plan of Works

Use the Digital Plan of Works to be able to define, manage and interact with the management processes and Levels of Development required for the project.

DPoW

ActionList

Page 38: The countdown to 2016: Your action list to be ready Daniel Walsh Senior BIM Author @DanWalsh82

PAS 91EIRBEPBIM ProtocolCDE

Producing BIM Data Interrogating BIM DataBIM UsesDPoW

ActionList