The Construction of a New Roskilde Fjord Link
Information Meeting October 30th 2014 13.00 - 16.00
Park Inn Hotel, Copenhagen S
![Page 2: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/2.jpg)
Agenda
• Welcome Jens Jørgen Holmboe, Construction & Maintenance Director
• Background and Overview Niels Korsgaard, Senior Project Manager
• Tender details – as seen now by DRD Erik Stoklund Larsen, Construction Director
• Technical Dialogue Bo Tarp and Torkil Schrøder-Hansen, Procurement & Contracts
• Outline of Project and Technical Challenges Gráinne Wolfe, Technical Advisor
• Closure Erik Stoklund Larsen, Construction Director
![Page 3: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/3.jpg)
The Danish Road Directorate
We work in these main areas: Planning We conduct studies and plan in order to determine
where new roads are to be built and where there is a
need for increased traffic safety or capacity on the
national road network
Construction We construct new roads and bridges and develop the
existing network
Operation
We operate and maintain the road and the
surrounding areas – new asphalt, mow the grass and
clear the roads of snow
Traffic administration and management
We guide road users through the traffic in event of
accidents or roadworks via signposting, electronic
information boards etc. Motorway
Motorway (Sund & Bælt)
Expressway
Other trunk roads
![Page 4: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/4.jpg)
The Present Situation
• Many on-going projects
• New expressways
• New railways
• Improvements of capacity of existing expressways and railways
• Improvements and rehabilitation of the network
• A growing Danish market if seen in perspective of infrastructural
investments the coming years
• Broad experience with different contract forms such as BoQ-
based, D&B, PPP
• Long tradition of dialog with the market (contractors, consultants,
suppliers, etc.)
![Page 5: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/5.jpg)
This Information Meeting
• To give general information of the Roskilde Fjord Link Project
• As per DRD general policy
• Dealing with a design & build project
• Contract conditions will be based on Danish law and tradition
• Line out the announced technical dialog
• Technical dialog that shall inspire DRD in its work with the tender
documents
• Participation in technical dialogue has no influence on participation
in the later pre-qualification as contractors
• The technical dialog meetings will be confidential
![Page 6: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/6.jpg)
Questions
• Questions can be asked by the end of each theme to ensure the
flow in the slide show
• Questions and answers will be noted by DRD
• Questions asked during this meeting can be sent via e-mail to
[email protected] and [email protected]
• Further questions can be asked by the end of the presentation
![Page 7: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/7.jpg)
Background and Overview Niels Korsgaard, Senior Project Manager
![Page 8: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/8.jpg)
Roskilde Fjord Link
N
![Page 9: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/9.jpg)
The Existing Bridge Kronprins Frederiks Bro
![Page 10: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/10.jpg)
The Existing Bridge Kronprins Frederiks Bro
![Page 11: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/11.jpg)
Roskilde Fjord Link Summary of EIA study in 2010
![Page 12: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/12.jpg)
Roskilde Fjord Link Expressway / 2x2 Lanes / 90 km/h – Length 9.5 km
![Page 13: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/13.jpg)
Roskilde Fjord Link Natura 2000 Areas
![Page 14: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/14.jpg)
Roskilde Fjord Link Tender Packages
Contract 3 (D&B)
Contract 2 (D&B)
Contract 1
![Page 15: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/15.jpg)
Contract 1 Typical Cross Section - East
![Page 16: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/16.jpg)
Contract 2 Typical Cross Section – High Bridge
![Page 17: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/17.jpg)
Contract 2 (cont.) High Bridge – Length 1360 m
![Page 18: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/18.jpg)
Contract 2 (cont.) Water Depths in the fjord
![Page 19: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/19.jpg)
Contract 2 (cont.)
Land area Land Development Plan for Tørslev Hage – Summerhouse Area
![Page 20: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/20.jpg)
Contract 2 (cont.)
Tørslev Hage – Summerhouse Area
![Page 21: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/21.jpg)
Contract 2 (cont.)
Tørslev Hage – Summerhouse Area
![Page 22: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/22.jpg)
Contract 2 (cont.)
Tørslev Hage Typical Cross Section
![Page 23: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/23.jpg)
Contract 3 Typical Cross Section - West
![Page 24: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/24.jpg)
Tolling – Free Flow System Independent tender
Gantries
![Page 25: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/25.jpg)
Questions
![Page 26: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/26.jpg)
Tender Schedule and strategy Erik Stoklund Larsen, Construction Director
![Page 27: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/27.jpg)
Company behind the project
• The first DRD bridge with a tolling system
• Politically decided to establish a SOV (Independent governmental
company) to be the owner of the new bridge
• Fjordforbindelsen Frederikssund
• DRD as the daily manager
• Operations and maintanance
• Tolling
• DRD manages the tenders and the contracts on behalf of the SOV
![Page 28: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/28.jpg)
Tender strategy
• General DRD strategy
• Transparency – our templates are publicly available on
• http://vejdirektoratet.dk/en/roadsector/supplierportal/pages/default.aspx#.VAtTR_l_u4J
• http://vejregler.lovportaler.dk/
• Dialogue with the contractors and consultants etc. by regular meetings
• Consensus strategy
• Information meetings relating specific projects
• Open process
• Published in TED and performed as per EU Procurement directive
• Two envelope system
![Page 29: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/29.jpg)
Tender strategy (cont.)
• Tender strategy in the Roskilde Fjord Link project
• Openness towards the market
• Technical dialogue to ensure the best tender material
• Design and build contract
• Four contracts due to the differences in the stages
• PQ criteria for the bridge
• Financial strong contractors/JV/consortiums (5 nos.)
• References and capacity (technical similar projects)
• Award criteria
• Most economically advantageous tender based upon price and technical
proposal
![Page 30: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/30.jpg)
Expected Tender time schedule
Contract 1
2015
• Tender formulation
• Tender Process for the new expressway on the eastern side
of the fjord
2016
• Contracts and start of works
2016 - 2017
• Construction of the new expressway on the eastern side of
the fjord
![Page 31: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/31.jpg)
Expected Tender time schedule
Contract 2
2015
• Technical dialogue and tender project formulation
• Tender Process for the new bridge
2016
• Contracts and start of works, establishment of construction /
production site, etc.
2016/17- 2019
• Construction of the new bridge
![Page 32: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/32.jpg)
Expected Tender time schedule
Contract 3
2016
• Tender formulation
• Tender Process for the new bridge
2017
• Contracts and start of works
2016/17- 2019
• Construction of the new expressway on the western side of
the fjord
![Page 33: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/33.jpg)
Expected Tender time schedule
Contract 4 – Tolling system
2018
• Tender project formulation
• Tender process for the tolling system
• Contracts and start of works
2019
• Construction of the tolling system
![Page 34: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/34.jpg)
Time schedule Political decision and process
2014
• October 8th – Submission of 1st treatment of the
Construction Law
• October 23rd - 1st treatment of the Construction Law
• Political process
• Expected adoption of the Construction Law Medio
December
2015
• Establishment of the SOV (Independent governmental
company) Ultimo January
![Page 35: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/35.jpg)
Questions
![Page 36: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/36.jpg)
Tender Details Erik Stoklund Larsen, Construction Director
![Page 37: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/37.jpg)
Contract and award criteria
• The contracts are made in accordance with Danish law
• Design and build contract – ABT93
• English version: http://www.danskbyggeri.dk/Servicebutik/Vis%20vare?docid=23590
• Agreed document between contractors and employers
• Project specific conditions - “SB” based on
• http://www.vejdirektoratet.dk/DA/vejsektor/leverandoerportal/Retningslinjerogpara
digmer/Inkoeb/Udbud-kontrahering/udbudsh%C3%A5ndbog/Sider/SB-
TE.aspx#.VAo6e_l_u4I
• Award criteria
• Most economically advantageous tender (MEAT)
• based upon price and technical proposal
![Page 38: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/38.jpg)
Contract Language
• The language of the contract is Danish
• The tender material will be in Danish as well as a service
translation in English
• The Danish version is the contractually legal binding version
• It is possible to submit bids in both Danish and English
• However juridical documents (to be defined) shall be submitted in
Danish and technical documents (to be defined) can be accepted
in English only
• Disputes are settled in Danish Courts or Danish Arbitration
Courts
![Page 39: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/39.jpg)
Expect demands on social clauses
• ILO-convention no. 94
• No social dumping
• Equal wages
• Clauses about apprentices/interns/trainees
• A clause that obligates the contractor to have a number of apprentices
measured in Full-Time-Equivalent (FTE) of 1924 hours/year
• http://eng.uvm.dk/Education/Upper-Secondary-Education/Vocational-
Education-and-Training-(vet)?allowCookies=off&remember=on
• Registration of foreign workers working in Denmark
• RUT register – Register of Foreign Services Providers
• https://indberet.virk.dk/myndigheder/stat/ERST/Register_of_Foreign_Service_Provider
s_RUT
• Danish regulations to health and safety
![Page 40: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/40.jpg)
Two Envelope System
• The award criteria is Most economically advantageous tender
(MEAT) based upon price and technical proposal
• The bid shall be submitted in two parts in two sealed packages
• Part 1 – Price
• Part 2 – Technical proposal
• DRD will open Part 2 – Technical Proposal and assess the
qualitative sub-criteria. The grades based on the evaluation will
be notified to the bidders before Part 1 - Price are opened
• Afterwards Part 1 - Price will be opened and the sub-criteria Price
is assessed
• Notification of awarding of the contract will be issued
• All conditional tenders except the winner will receive a reasonable fee for
their bid
![Page 41: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/41.jpg)
Consortia, JV, Subcontractors
• Consortia or JV
• Where a consortium or other amalgamation is awarded the
contract, the participants must assume joint and individual liability
• Subcontractors
• If the bidder relies on other entities, including subcontractors
technical and/or financial capacity the bidder must provide
evidence to the DRD that it will have the necessary resources from
these entities at its disposal
![Page 42: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/42.jpg)
Performance Bond
• As per ABT93
• ABT93 § 6 subs. 2
• Until the handing-over of the work, the bond provided must correspond
to 15 % of the contract sum.
• After handing-over the bond must correspond to 10 % of the contract
sum.
• ABT93 § 6 subs. 3
• One year after handing-over the bond is reduced to 2 % unless prior
claim
• ABT93 § 6 subs. 4
• 5 years after handing-over the bond will cease unless prior claim
• Performance bond must be made by a third party
• No possibility for Parent Company Guarantee (PCG)
![Page 43: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/43.jpg)
Questions
![Page 44: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/44.jpg)
Technical dialogue Bo Tarp and Torkil Schrøder-Hansen, Procurement & Contracts
![Page 45: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/45.jpg)
Purpose
• The expectations for the technical dialogue
• Making sure our restrictions in the project are the right and
proportional
• To make DRD more knowledgeable about different technical
solutions
• To ensure we allow new techniques and solutions
• Creating room for innovation
• Ensure a better tender material
• Making DRD a better buyer
• A tool for a better tender process
![Page 46: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/46.jpg)
Basis
• Prior to the tender process
• Not prequalification
• Does not affect the prequalification process
• In accordance with the EU Public Procurement rules
• The Public Procurement Directive preamble no. 8
• Will be based on DRD’s experiences with technical dialogue from
other tenders e.g. the Storstrøm Bridge project
• The participants will not receive any compensation due to cost
incurred during the technical dialogue
• Maximum 6 participating companies
• Expected to be contractors
• Consulting companies are not excluded
![Page 47: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/47.jpg)
Time Schedule
• Friday the 21st of November 2014 at 13.00
- Deadline for submitting the application
• The application must be sent electronically via e-mail to [email protected] and
• 2nd of December 2014 announcement of participants on DRD
website and by e-mail to the applicants
• Maximum 6 participating companies
• Week 3-6
• First round of bilateral meetings
• Week 7-10
• A possible second round of bilateral meetings
![Page 48: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/48.jpg)
Application (max 20 A4-pages) Language of application can be Danish or English
• Motivated application (max 5 A4 pages)
• The applicant's qualifications
• Relevant references to bridge construction
• The applicant's technical capabilities
• A list of dates the applicant prefer to participate in the bilateral
meetings.
• Both the first and the possible second round.
• Names of the participating persons in the dialogue
![Page 49: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/49.jpg)
Motivated Application (Max 5 A4 Pages)
• What is a motivated application for the technical dialogue?
• A statement from the applicant where the applicant justifies why
DRD should have technical dialogue with the applicant
• Could contain:
– Reasons why your company can contribute to better technical
solutions
– Which specific subjects you can contribute e.g. working in Natura
2000 areas, dredging, foundation, superstructures
– Previous bridge projects
– Relevant experiences with foundation, superstructures or other
relevant parts of a bridge project
• No formal requirements
![Page 50: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/50.jpg)
Selection
• The purpose of the selection is to ensure the best technical
dialogue possible.
• In the assessing of "the best technical dialogue" the applicant's
size may also be included.
• Objective criteria in accordance with the EU Public Procurement
rules
• maximum 6 participants is based on an assessment of
• the applicant’s motivated application,
• the applicant's qualifications, including references relevant to the
bridge,
• and the technical capability
![Page 51: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/51.jpg)
Questionnaire as basis
• The questionnaire will be made publically available after the
information meeting
• The questionnaire will secure
• Transparency of the process
• Equality of treatment for the participants
• Parties not involved in the bilateral meetings will know the
framework
• Will give parties not involved in the bilateral meetings the
opportunity to comment or ask questions to the questionnaire
– These comments or questions will be made publically available in
a Q/A
![Page 52: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/52.jpg)
Questionnaire as basis (cont.)
• DRD reserves the right to update the questionnaire until the start
of the technical dialogue and again before the start of a possible
second round of bilateral meetings
• DRD will stay within the framework of the questionnaire
• If not any questions asked by DRD is exceeding the framework will
separately be made public on the Supplier Portal
• All other written questions, comments and answers to the
questionnaire will be made public on the Supplier Portal in
anonymous form in a Q/A
![Page 53: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/53.jpg)
Bilateral Technical Dialogue
Meetings
• The bilateral technical dialogue meetings are confidential
• The meetings will be held in accordance to the questionnaire
• The questionnaire might be update before:
• The first meeting
• The start of the meetings in the possible second round
• DRD will stay within the framework of the questionnaire
• The bilateral meetings will not exceed time allocated to it
• DRD are responsible for the time management
![Page 54: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/54.jpg)
Bilateral Technical Dialogue
Meetings (Cont.)
• It is not mandatory for the participants to discuss all of the themes
in the questionnaire
• The bilateral technical dialogue meetings will be held in
confidentiality
• The main participants from DRD in the bilateral meetings will be
the same to ensure equal treatment of the participants
![Page 55: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/55.jpg)
Practical Information
• The meetings will be held at The Danish Road Directorate,
Niels Juels Gade 13, 1022 Copenhagen K from 13:00 to 17:00
• Dates for the meetings in the 1st round: • Week 3: Tuesday the 13th and Wednesday the 14th of January 2015 from 13:00 to 17:00.
• Week 4: Tuesday the 20th and Wednesday the 21st of January 2015 from 13:00 to 17:00.
• Week 5: Tuesday the 27th and Wednesday the 28th of January 2015 from 13:00 to 17:00.
• Week 6: Tuesday the 3rd and Wednesday the 4th of February 2015 from 13:00 to 17:00.
• Eight meetings have been scheduled to ensure the flexibility in planning
the logistics of the meetings
• If less than 6 requests for participation the timetable will be moved
proportionally
• If convergence between the dates for the respective applicants this will
be settled by a draw made by DRD
• The dates for the meetings with respective applicants will be announced
Tuesday the 2nd of December 2014 at DRD website and by e-mail
![Page 56: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/56.jpg)
Second Round of Meetings
• DRD will announce whether a possible second round of bilateral
meetings will be held with the same participating companies
• Latest by Thursday 5th of February 2015
• The dates will be announced together with the announcement of
the dates for the first round – Tuesday the 2nd of December 2014
• The participating companies can choose to withdraw after the first
round of bilateral meetings
![Page 57: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/57.jpg)
Second Round of Meetings (Cont.)
• DRD will decide whether a second round of bilateral meetings are
needed on the following criteria:
• Whether the time allocated in the first round was adequate
• If the questionnaire in bilateral meetings has not been fully
answered
• If the answers or comments to the questionnaire has raised further
questions to the participants
• If it is DRD’s assessment that a second round will clarify the
process further
![Page 58: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/58.jpg)
Publicly Available Documents
• This slideshow
• Prior information notice about the information meeting for the new
Roskilde Fjord Link
• The questionnaire for the bilateral technical dialogue meetings
• Technical description of the Bridge Project including sample
drawings
• List of participants of the information meeting
• EIA Report
• The green flyer including a CD containing all EIA documents
• http://www.vejdirektoratet.dk/DA/vejprojekter/fjordforbindelsen/Dokumenter/Sider/defa
ult.aspx#.VD52Svl_u4I
• Other documents
• http://www.vejdirektoratet.dk/DA/vejprojekter/fjordforbindelsen/Dokumenter/Sider/defa
ult.aspx#.VD52Svl_u4I
• http://www.ft.dk/samling/20141/lovforslag/L21/index.htm#dok
![Page 59: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/59.jpg)
Supplier Portal
• DRD homepage for tenders - ”Supplier portal”
• http://vejdirektoratet.dk/en/roadsector/supplierportal/pages/default.aspx#.V
AuVDPl_u4L
• All DRD tenders are available here
• Forthcoming tenders
• Ongoing tenders
• Awarded Contracts
• Road standards
• English translations coming up
![Page 60: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/60.jpg)
Supplier Portal
![Page 61: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/61.jpg)
Supplier Portal
![Page 62: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/62.jpg)
Supplier Portal
![Page 63: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/63.jpg)
Supplier Portal
![Page 64: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/64.jpg)
Questions
![Page 65: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/65.jpg)
Technical Presentation Of The Bridge Project Gráinne Wolfe, Technical Advisor
![Page 66: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/66.jpg)
Oversight plan
![Page 67: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/67.jpg)
Aesthetic View
![Page 68: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/68.jpg)
High Bridge Crossing Location
Total length 1360 m Span arrangement
End spans: 2 x 55.25 m Middle spans: 17 x 73.50 m
Total width 19.7 m Maximum vertical clearance 22.2 m Superstructure: Post Tensioned Box
![Page 69: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/69.jpg)
Post tensioned box Cross section
![Page 70: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/70.jpg)
PT box superstructure with circular piers
Pier Design
![Page 71: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/71.jpg)
Pier Design
PT box superstructure with rectangular V- shaped piers
![Page 72: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/72.jpg)
Pier options
![Page 73: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/73.jpg)
Pier options
![Page 74: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/74.jpg)
Geotechnical conditions
![Page 75: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/75.jpg)
Geotechnical conditions
• Main geotechnical units
• Limestone (pre-quaternary)
• Glacial layers (cohesionless or cohesive)
• Post- and late-glacial layers
• Main considerations
• Limestone found between -15 and -45m DVR90
• The shallow post-glacial deposits include gyttja and shell
material
• Presence of soft soil at shallow depths of up to 12m
thickness
• Pile driveability in the glacial layers
• Potential for the presence of a fault where the limestone
formation is deepest
![Page 76: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/76.jpg)
Bathymetry
![Page 77: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/77.jpg)
Navigational Channel
![Page 78: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/78.jpg)
Navigational Channel
![Page 79: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/79.jpg)
Compound areas
Construction site
Working port
Possible
compound area
Possible
Compound Area
![Page 80: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/80.jpg)
Environmental Constraints
EU protected areas
Natura 2000 Area – Construction Windows
• Dredging should be done Oct. – Dec.
• Most noisy works, e.g. pile driving, should be done March – Dec.
![Page 81: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/81.jpg)
Questions
![Page 82: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/82.jpg)
Closure Erik Stoklund Larsen, Construction Director
![Page 83: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/83.jpg)
Today
• To give general information of the Roskilde Fjord Link Project
• As per DRD general policy
• Dealing with a design & build project
• Contract conditions will be based on Danish law and tradition
• Line out the announced technical dialog
• Technical dialog that shall inspire DRD in its work with the tender
documents
• Participation in technical dialogue has no influence on participation
in the later pre-qualification as contractors
• The technical dialog meetings will be confidential
![Page 84: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/84.jpg)
Calling For Technical Dialogue
• Friday the 21st of November 2014 at 13.00
- Deadline for submitting the application
• The application must be sent electronically via e-mail to [email protected] and
• 2nd of December 2014 announcement of participants on DRD
website and by e-mail to the applicants
• Maximum 6 participating companies
• Week 3-6
• First round of bilateral meetings
• Week 7-10
• A possible second round of bilateral meetings
![Page 85: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/85.jpg)
Application (max 20 A4-pages)
• Language of application can be Danish or English
• Should contain:
• Motivated application (max 5 A4 pages)
– Why your company should be chosen e.g. because of specials skills for working
in Natura 2000 areas, dredging, foundation, superstructures etc.
• The applicant's qualifications
• Relevant references to bridge construction
• The applicant's technical capabilities
• A list of dates the applicant prefer to participate in the bilateral
meetings for both the first and the possible second round.
• Names of the participating persons in the dialogue
![Page 86: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/86.jpg)
Questions
![Page 87: The Construction of a New Roskilde Fjord Linkleverandorportal.vejdirektoratet.dk/Udbuds... · The Present Situation • Many on-going projects • New expressways • New railways](https://reader034.vdocuments.us/reader034/viewer/2022042419/5f35d4b47be1c64e9b373499/html5/thumbnails/87.jpg)