the city assembly house bringing the building up to fire ... · consarc conservation presentation...

36
CONSARC CONSERVATION Presentation Bringing the Building up to Fire safety Requirements October 2018 The City Assembly House

Upload: others

Post on 08-Oct-2019

4 views

Category:

Documents


0 download

TRANSCRIPT

CONSARC CONSERVATION

Presentat ion

Br ing i n g t he Bu i l d i n g up t o F i r e sa f e t y Requ i r em e n t s

O c t o b e r 2 0 1 8

Th

e C

ity A

ss

em

bly

Ho

us

e

CITY ASSEMBLY HOUSE

The Society of Artists

2

CITY ASSEMBLY HOUSE

City Assembly House History

3

James Malton, Powerscourt House, Dublin 1795

SWS, engraved by James Ford c. 1810 (NGI)

John Rocque’s map 1756 OSi map 1843(surveyed 1838)

CITY ASSEMBLY HOUSE

Existing Building – Phases of Development

4

CITY ASSEMBLY HOUSE

Timeline

5

CITY ASSEMBLY HOUSE

Phase 1 Works

Date: 2012-2013

Contract Sum = €0.4m

Scope of Works:

Material alterations to upgrade the front section of the building to comply with fire;

Repair and redecoration works.

• 60 minute fire separation between basement and rest of the building; upper basement below the exhibition room & lower basement

• All doors leading to the central staircase were upgraded to 30 minutes

• Aspirating system installed

• An AOV installed in the roof light above the Staircase

• Emergency lighting & exit signage installed

6

CITY ASSEMBLY HOUSE

Phase 1 Works

7

First Floor before works commenced

CITY ASSEMBLY HOUSE

Phase 1 Works

8

Basement Ceiling before works commenced

CITY ASSEMBLY HOUSE

Phase 1 Works

9

CITY ASSEMBLY HOUSE

Phase 1 Works

10

CITY ASSEMBLY HOUSE

Phase 1 Works

11

Aspiration system and emergency lighting in ceiling of staircase

CITY ASSEMBLY HOUSE

Phase 1 Works - Completion

12

CITY ASSEMBLY HOUSE

Phase 1 Works - Conclusion

Fire upgrade works were relatively straightforward

• Occupancy levels were low (34)

• Travel distances were short

• No living accommodation to deal with

13

Works were carried out with minimal intervention to historic fabric

• M&E consultants and contractors embraced the process to think creatively about how to distribute services around the building without creating additional openings, chasing walls or notching joists

• This also reduced the amount of fire stopping required

CITY ASSEMBLY HOUSE

Phase 2 Works

Date: March 2017 – June 2018

Contract Sum: €1m

Scope of Works:

Upgrade the Assembly Room as an art gallery (and performance space) with the vision of recreating the original art exhibition of the 18th Century

Three main issues:

• Provision of an alternative means of escape from the Assembly Room

• Provide universal access to the building

• Provide Climate control to meet international lending criteria

14

CITY ASSEMBLY HOUSE 15

An early option exploring an alternative means of escape from the exhibition room

Phase 2 Works - Fire

CITY ASSEMBLY HOUSE 16

Phase 2 Works - Fire

CITY ASSEMBLY HOUSE 17

Phase 2 Works - Fire

CITY ASSEMBLY HOUSE 18

Phase 2 Works - Fire

CITY ASSEMBLY HOUSE 19

The location of the proposed staircase

Phase 2 Works - Fire

CITY ASSEMBLY HOUSE

Phase 2 Works - Fire

20

CITY ASSEMBLY HOUSE

Phase 2 Works - Access

21

CITY ASSEMBLY HOUSE 22

Phase 2 Works - Access

CITY ASSEMBLY HOUSE 23

Phase 2 Works - Access

CITY ASSEMBLY HOUSE

Phase 2 Works - Access

24

CITY ASSEMBLY HOUSE

Phase 2 Works - Fire & Access

25

CITY ASSEMBLY HOUSE

Phase 2 Works – Access, Lift insertion

26

CITY ASSEMBLY HOUSE

Phase 2 works - Exhibition Room

27

Location of the Air Handling Unit within the basement of the building. It takes up a lot of space.

CITY ASSEMBLY HOUSE

Phase 2 works - Exhibition Room

28

CITY ASSEMBLY HOUSE

Phase 2 Works - Exhibition Room

29

CITY ASSEMBLY HOUSE

Phase 2 Works - Climate ControL, Smart Glass & AOVs

30

CITY ASSEMBLY HOUSE

Phase 2 Works - Exhibition Room

31

CITY ASSEMBLY HOUSE

Phase 2 Works - Exhibition Room

32

CITY ASSEMBLY HOUSE

Phase 2 Works - Conclusion

Challenging Project

• Invasive work with the installation of the new lift, staircase & new exit

• Building is now fit for public use & is a cultural hub in the city centre

33

BCaR

• Resulted in a higher level of inspection on site.

• It caused delays and stress on site (partly due to unknows in existing buildings. Everything cannot be pre-designed)

• Future programmes should reflect this

• Better and safer building as a result

CITY ASSEMBLY HOUSE 34

CITY ASSEMBLY HOUSE

Team

Consultants

• Architects: Consarc Conservation (Grainne Keogh, assistant architect)

• Structural Engineer: Lisa Edden

• QS: Daughton + Associates

• M&E: Hayes Higgins

• Fire: Joe Gannon & MSA

35

Contractor & Specialist Craftsmen:

• Main Contractor: JV Ledwith

• Façade: Shane Nolan

• Shopfront: CDS Metalwork

• Plasterwork: Smith & Henderson: George O’Malley

• Rooflights: Lambstongue

• Windows: McLyn Joinery

• Stone Floor: McConnells

CONSARC CONSERVATION

Thank You

Th

e C

ity A

ss

em

bly

Ho

us

e