the case for longer duration of pumping testsand … case for longer duration of pumping testsand...

24
The case for longer duration of pumping tests and confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA Annual Conference March 2, 2016

Upload: vuthuy

Post on 04-May-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

The case for longer duration of pumping tests and  confined aquifer well deep well seals

Presented by:

Doug Geller, M.Sc.,P.Geo.

BCGWA Annual Conference March 2, 2016

Page 2: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

2

Presentation Topics

Pumping test durationo Perspectives

o What the experts say

o Time of year - significance

o Pumping test examples

o Why “volume” tests are not pumping tests

Effective casing seals in confined aquifer wells Where and when

Regulatory examples from other areas

Page 3: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

3

Pumping tests: how long is long enough?

Client’s perspective – keep costs low

Hydrogeologists’s perspective – need data to support conclusions

Purpose / use of the well and the test

Yield of well versus yield requirement

Possible interference or “boundary” effects

Concerns of neighbouring well owners

Specific regulatory requirements

Page 4: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

4

When in doubt, consult the bible

Page 5: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

5

‘GROUNDWATER AND WELLS’ (Driscoll 1986)

Pumping test duration: Confined aquifer: 24 hours

Unconfined aquifer: 72 hours

…in B.C. the unpredictable nature of fractured bedrock aquifers suggests durations of 48 to 72 hours

“In no event should pumping tests be terminated prematurely, because the limited data collected may not reveal the true nature of the aquifer” p. 554 Driscoll 2nd

ed.

Page 6: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

6

BC’s own CPCN Guidelines and “Guide to Conducting Well Pumping Tests”

Pretty much the same as Driscoll:

Unconfined aquifer: 48-72 hours

Confined aquifer: 24 hours

Bedrock: 72 hours(note: new GW Protection Reg. Div. 4,

#32 does not specify duration)

Page 7: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

7

Time of year

Test analysis assumes ‘no recharge’

Therefore, in coastal settings best to test in late summer/early fall

Interior settings, fall to mid winter

Given the above, with appropriate analysis, tests can be done throughout the year

Important to have pre-test and recovery data

Page 8: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

8

Pumping Test Examples

To illustrate how often a brief four-hour test is nowhere near long enough

Sometimes, 24 hours is not sufficient

Even longer tests lasting > 1 week can reveal surprises

Page 9: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

When is 4 hours long enough?Figure 2: Semilogarithmic Plot of Drawdown

Pumping Test Pumping Rate - 1 Igpm, Nov, 2006

0

20

40

60

80

100

120

140

160

180

2000.1 1 10 100 1000 10000

Elapsed Time (min)

Dra

wdo

wn

(m)

48hour

24 hour

Pump intake

Four hours

9

Page 10: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

Look what happens after 4 hours….Semi Log Plot of Pumping Test 1.0 Igpm

August 2007

0

100

200

300

400

500

600

0.1 1 10 100 1000 10000Time (minutes)

Dra

wdo

wn

(feet

)

Pump Depth 697'

Four hours

10

Page 11: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

So is 12 hours long enough?Semi-logarithmic Graph of Drawdown vs Time

Subdivision well test near Vernon BC1 I GPM December 2007

0

50

100

150

200

250

3001 10 100 1000 10000

Elapsed Time (minutes)

Dra

wdo

wn

(ft)

Pump Intake 228ft

70% available draw dow n = 159.6ft

Four hours

11

“stabilization”

Page 12: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

How about 24 hours?Semi-log plot of constant rate pumping testConstant Rate Test May, 2009 (1.2 US GPM)

0.0

50.0

100.0

150.0

200.0

250.0

300.0

350.0

400.0

450.0

500.01 10 100 1000 10000 100000 1000000

Time (minutes)

Dep

th to

Wat

er (f

eet)

100 days1 day

Note: All depths from Top of Casing, 1 ft above ground surface

Total depth 500 ft; Pump set at 450 ftAssume max pump set = 480 ft

12

Page 13: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

How about 20 days? 

13

Constant rate 650 US gpmFive distinct drawdown slopesMultiple boundary conditions

Page 14: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

600 ft bedrock well, 0.6 US gpm fracked then tested at 1.7 US gpm

14

Page 15: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

Need another one? 

15

Page 16: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

“Volume tests”  are not pumping tests Example #1

• Pump at high rate to maximize drawdown

• Reduce flow rate

• Achieve a stabilized water level

• “Stabilized” level – is reflecting recovery due to flow rate reductions

• It is not stabilization

0

10

20

30

40

50

60

70

80

90

100

30 60 90 120 150 240

16

10 gpm

3 gpm

Time (min)

Dra

wdo

wn

(m)

Page 17: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

“Volume tests”  are not pumping tests Example #2

• Pump enough to equal a daily volume requirement 

• (e.g. “2300 L/day” for some regional districts)

• Record  the drawdown

• Measure well recovery

• If well recovers to some arbitrary level, it “passes” 

17

Page 18: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

Part 2 –The case for deep(er) well seals in confined aquifer wells•Why?

• Drilling and casing advancement do not ensure a tight seal between formation and well casing

• Prevent loss of confining pressure in lower aquifer

• Prevent co‐mingling of waters between two aquifers

• More safely contains potential artesian flow• ….and it is standard practice in many areas with complex hydrogeology

18

Page 19: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

Deep well seals in confined aquifer wells

•When and where• Upper unconfined aquifer and lower confined, with an 

aquitard in between

• Expected different water levels and water chemistry between upper and lower aquifer(s)

• Anywhere with known or possible flowing conditions (see Golder’s presentation on Coldstream well)

• Contaminated upper aquifer or contamination threatens shallow zone (e.g. GUDI, nitrates, etc)

19

Page 20: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

Examples of “full” annular seal regulations

20

• Ontario Water Resources Act, RRO 1990 Reg 903

• Washington Code (WAC 173‐160‐241)

• Alberta Water Regulation (Section 48, AR 205/98)

And many other locations

Page 21: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

The well casing in the next slide was fully sealed into a confining unit prior 

to drilling into the aquifer

21

Page 22: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

2,000+ gpm of artesian flow from 500 ft 

22

Page 23: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

Why should our industry promote these standards?  

• Keeping to minimum pumping test durations would• Marginally increase costs of 

testing

• Fewer unexpected poor yielding wells 

• Reduce opportunity to “cut corners “

• Promotes better science and more reliable results for well owners

• Lower cost in the long run

23

• If full annular seals are required in BC this would• Increase well drilling costs 

especially in deeper confined wells

• Prevent cross‐connection of multiple aquifers

• Protect gw quality

• Reduce chances of uncontrolled flowing wells (if casings are sealed in place before drilling through aquitards)

• …..and lower cost in the long run! 

Page 24: The case for longer duration of pumping testsand … case for longer duration of pumping testsand confined aquifer well deep well seals Presented by: Doug Geller, M.Sc.,P.Geo. BCGWA

24

Thank You!