the case for integrated gasification combined cycle … · recovery unit sulfur air separation unit...
TRANSCRIPT
1
The Case for Integrated Gasification Combined Cycle
Technology
Presentation to Michigan Public Service CommissionLansing, MI
August 22, 2006
Dale E. HeydlauffVice President-New Generation
2
AEP: An introduction
Coal NG Nuclear Hydro Wind
75% 15% 6% 2% 2%
AEP Facts at a Glance
Largest U.S. Electricity Generator and coal user
• 11 States (7-East & 4-West)• 36,000 MW Generation• 78 MM tons of coal per year• 39,000 Miles Transmission
210,000 Miles Distribution • 5 Million Customers• 20,000 Employees• US$ 14.5 Billion Revenue• US$ 36.7 Billion in Assets
3
Now is the Time to Upgrade our Nation’s Electricity Infrastructure
• 70% load growth in past 25 years– Little new baseload capacity added– Little new transmission added
• Nuclear generation capacity reaching output limit– 1990 66% capacity factor – 2004 91% capacity factor
• Coal generation capacity becoming fully utilized– 1990 59% capacity factor– 2004 74% capacity factor
• Demand expected to grow another 20% over next 10 years– Long lead time for baseload generation capacity
4
Electric Power’s Future
• Population growth and increased electrification requires about 250-300 GW of baseload generating capacity over next 25 years
• No silver bullet … Need a portfolio• Future demand probably met largely by coal:
– Gas supply issues and price volatility in North America
– LNG imports will exacerbate U.S. trade imbalance
– Nuclear could be revived, but probably decades away from a major resurgence
– Renewables (particularly wind) promising, but infrastructure/intermittency limits penetration
5
U.S. Forecasts Largest Coal Generation Capacity Installation in 40 Years
Source: U.S. Department of Energy NETL & Annual Energy Outlook 2005.
Cap
acity
Add
ed (G
Ws) Capacity Addition
Levels Not Seen in 40 Years
Industry Growth Trend Not Seen in
50 Years
20 YearMarket Trough
U.S. Coal Capacity Additions, 1940 U.S. Coal Capacity Additions, 1940 –– 20252025
0123456789
1011121314151617181920
1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020 2025
6Source: Energy Information Administration, March 2005.
8.1¢ 30%
6.1¢65%
5.8¢94%
5.6¢10%
5.7¢64%
5.0¢96%
7.0¢74%
6.1¢7%
6.5¢74%
7.2¢88%
8.6¢50%
11.3¢1%
5.8¢95%
6.6¢48%
7.8¢42%
6.5¢82%
6.3¢65%
6.6¢56%
6.1¢86%
6.9¢49%
7.6¢38%
6.9¢70%
5.8¢51%
7.1¢ 35%
7.0¢59%
5.6¢98%
6.8¢87%
9.4¢1%
12.0¢16%
7.0¢42%
6.1¢56%
6.7¢65%
6.2¢ 41%
4.6¢ 92%
6.5¢45%
8.1¢55%
5.1¢99%
7.0¢62%
6.1¢ 60%
5.0¢0%
10.8¢8%
15.6¢15%
NH 11.4¢ 17%VT 11.1¢ 0% MA 10.8¢ 22% RI 10.8¢ 0%CT 10.4¢ 13%NJ 10.2¢ 19%DE 7.3¢ 65%MD 7.2¢ 52%
¢ = average retail price per kilowatt hour for 2004
% = percent of total generation from coal for 2004 < 6.0¢
≥ 6.0¢ - < 7.0¢≥ 7.0¢ - < 8.5¢≥ 8.5¢ Hydro
Retail Cost Per kWh & Percent of Coal GenerationRetail Cost Per kWh & Percent of Coal Generation
Low-Cost Electricity from Coal:Coal Fuels 50%+ of U.S. Electricity
7
Emissions from CoalEmissions from Coal--Fueled Generating PlantsFueled Generating Plants
* EstimateSource: EPA’s Clean Air Markets database; EIA 2004 Annual Energy Outlook; GE Energy; SFA Pacific.
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
Poun
ds P
er M
illio
n B
tu
Sulfur DioxideNitrogen Oxide
U.S.Average
2004*
Clean AirInterstate
Rule2010
New Midwest
Mine-mouth
Clean AirInterstate
Rule2015
0.10
0.340.39
0.16
0.26
0.120.182
0.07 0.06
0.94
New PRB Plant
Near-Zero
FutureGenGoals
0.030.06
New IGCCProjection
ExistingIGCC
(PermitLevel)
0.17
0.08
The Path Toward Near-Zero Emissionsfrom Coal-Fueled Generating Plants
8
Ultra-Supercritical Pulverized Coal
• For technical or financial reasons, IGCC technology may not be available for new coal generation
• To achieve maximum efficiency, AEP plans to build ultra-supercritical pulverized coal plants were IGCC is not feasible
• Ultra-supercritical PC plants have main boiler steam temperatures >1100oF and pressures >3600 PSI
• The technology costs 1-3% more than supercritical PC plantsTechnology PC PC PCSteam Cycle USC Supercritical SubcriticalThrottle Pressure, psig 3500 3500 2400Steam Temperature, F 1110/1125 1000/1000 1000/1000Fuel Lignite Lignite LigniteFuel HHV, Btu/lb 6360 6360 6360FGD Technology Wet FGD Wet FGD Wet FGDGross Turbine Heat Rate, Btu/kwh 7247 7526 7733Aux Power, % 0.09 0.09 0.09Boiler Efficiency, % 0.825 0.825 0.825Net Unit Heat Rate (Full Load), Btu/kwh 9653 10025 10300CO2 Emissions (Full Load), lb/MMBtu 218 218 218CO2 Emissions (Full Load), Tons/MWH 1.05 1.09 1.12
9
Sulfur
CO2Low Temp Gas Cooling
Shift Rx(option)
HgRemoval
ParticulateScrubber
GE"Quench"Gasifier
Slag/Frit
Coal
H2O
+
Air Separation Unit (ASU)
O2
Slurry
Acid Gas Removal
CO/H2
Fines/Char
Flexibility for CO2 Sequestration
(Concentrated Stream)
Sulfur RecoveryClaus/Scot
PRE-COMBUSTIONTreatment of Pollutants
•High pressure•Low Volume•Concentrated stream(easier to treat)
Air
Sulfur RecoveryClaus/Scot
Combustion Turbine
Compressed Air to ASU
HRSG
Steam Turbine
Electricity
Electricity
90+%Removal
98+%Removal
Courtesy Eastman Gasification Services
IGCC Overview
10
IGCC: Feedstock & by-product flexibility
Syngas
CoalBiomass
Refinery By-products• Petroleum Coke• Oil tars
Marketable By-products, e.g.:
SulfurSulfuric AcidSlag / Frits
Hydrogen Liquid Chemicals• Methanol• Diesel FuelsElectricity
Nitrogen From ASU
Lock Hopper
Coal Slurry Tank
Coal Slurry Mill
Slurry Pump
Water
Coal
Gasifier
Oxygen
Air from Combustion Turbine
Nitrogen to Combustion Turbine
Water
Steam to HP Steam Drum
HRSG
Slag
COS Hydrolyzer
Mercury Removal
Bed Acid Gas Removal/Sulfur Recovery Unit
Sulfur
Air Separation Unit (ASU)
Scrubbed Syngas
Clean Syngas
Combustion Turbine
From Power Block
Raw Syngas
Boiler Feed Pump
Compressed Air to ASU
Heat Recovery Steam GeneratorExhaust
Gas
Air
Steam Turbine
Syngas Scrubber
Steam from Radiant Syngas Cooler
Flare
CO2
Shift Reaction (Future)
Recycle to Process
Water to Radiant Syngas Cooler
Radiant Syngas Cooler (RSC)
Ambient Air
Future
Nitrogen From ASU
Lock Hopper
Coal Slurry Tank
Coal Slurry Mill
Slurry Pump
Water
Coal
Gasifier
Oxygen
Air from Combustion Turbine
Nitrogen to Combustion Turbine
Water
Steam to HP Steam Drum
HRSG
Slag
COS Hydrolyzer
Mercury Removal
Bed Acid Gas Removal/Sulfur Recovery Unit
Sulfur
Air Separation Unit (ASU)
Scrubbed Syngas
Clean Syngas
Combustion Turbine
From Power Block
Raw Syngas
Boiler Feed Pump
Compressed Air to ASU
Heat Recovery Steam GeneratorExhaust
Gas
Air
Steam Turbine
Syngas Scrubber
Steam from Radiant Syngas Cooler
Flare
CO2
Shift Reaction (Future)
Recycle to Process
Water to Radiant Syngas Cooler
Radiant Syngas Cooler (RSC)
Ambient Air
Future
11
+53%+38%+63%Cost of Electricity
-20 to 25%-18% to 22%-30% to 35%Efficiency
+85% to 90%+30% to 40%+65% to 75%Capital Cost
NGCCIGCCPulverized Coal
Impact of Adding CO2 Capture
CO2 Capture – Eastern Bituminous Coal
Carbon capture (“scrubbing”) is a difficult and expensive process:– CO2 is a very stable
molecule– CO2 concentration is very
low in flue gases– Amine processes (MEA) are
the only currently proven approach - high capital cost
– A large amount of steam is required to regenerate the amine (strip the CO2 from the “carbon getter”) – large efficiency penalty
0
500
1000
1500
2000
2500
PC w/o CO2 PC w/CO2 IGCC w/oCO2 IGCC w/CO2
Capital Cost$/kW Heat Rate x10 (BTU/kWh)
Source: AEP , EPRI, and US DOE
3000
1212
Investing in IGCC
IGCC technology is strategic to keeping coal in the money IGCC technology is strategic to keeping coal in the money
13
Integrated Gasification Combined Cycle’s Promise
• Lowest capital cost (when mature) coal-based technology
• Feedstock & product flexibility (with added cost)– Coal, petcoke, or biomass feedstocks– Electricity, steam, syngas, liquid fuels, or chemical products
• Most efficient coal-based technology (when mature)• Best emission characteristics among coal-based
technologies• Most carbon-friendly coal technology• The technology of choice to KEEP COAL IN THE
MIX– Strategically important to the energy security and economies
of many states and the U.S.
14
AEP’s IGCC Investment• 600 MW Plant built by 2010; Another 600 MW by 2013
– Front-End Engineering & Design and environmental permitting underway on both plants
– Transmission studies requested of PJM
• Sites being considered include: – Meigs County, OH– Mason County, WV (adjacent to Mountaineer Plant)
• Regulatory cost recovery– Filed cost recovery plan with PUCO in 2005; Phase I approved– Filed Certificate of Convenience and Necessity in WV in 2006
• R&D Activities– Mountaineer Sequestration Project– FutureGen participation
15
Public policy tools to support IGCC:(Ohio example)
1. Public Utilities Commission suggested IGCC plant be built
3. AEP Ohio filed plan (March 2005) for recovering costs for 600 MW plant in operation mid-2010– Phase 1 (2006): $23.7 million for site engineering and plant
design approved on April 10, 2006. – Phase 2 (2007-2010): $237.4 million to recover financing
costs. Case to be filed in November 2006.– Phase 3: Recover $1.033 billion estimated plant cost over
its 40-year operating life with a regulated return on the investment. Case to be filed at conclusion of construction.
2. Need pre-construction assurance investment is recoverable
16
Leadership
• Choosing IGCC is not just a technology decision; it’s a leadership decision– If not AEP, then who?– If not coal, then what?
• Being a leader has its perils and risks– Partnerships and cooperation are necessary for
success• Federal and State Governments have a
critical role– Provide incentives and remove roadblocks