the aurora mine, - · pdf filethe aurora mine, alberta, canada. discover more on week 1...
TRANSCRIPT
From the depths oF the earth: bringing up 10,000 tons in less than Four weeks.the aurora mine, alberta, Canada
Discover more on www.mammoet.com
week 1
week 4
surge bin being moved Job Completed suCCessFully and saFely
how a unique JaCking system saved at least $5,000,000.
week 4
spF on 168 axle lines oF spmtweek 3
tailor-made JaCking system
a Z
The Aurora mine is one of the
largest combined oil sands
mining and refinery facilities in
the world. Mammoet was asked
to relocate two of its process
trains, which meant moving the
complete trains from the bottom
of an open mine to their new
location at the top. The operation
involved transporting loads in
excess of 3,000 tons over two and
a half kilometers up a 6.4% grade
hill. Through the application of a
range of tailor-made equipment
and techniques, Mammoet
completed the dangerous
relocation without incident and
five days ahead of schedule.
From the moment the power to the
process train was turned off, the
mine’s output dropped and the
clock began to tick. There were
three active process trains in the
mine, which meant Mammoet had
to work amid the constant traffic of
heavy haulers feeding raw oil sand
into the other two trains.
The heaviest component was the
Slurry Prep Facility (SPF), estimated
to weigh in at around 3,300 tons.
In total, Mammoet had to move
approximately 20,000 tons of
equipment up to the top of the mine
via a steep and treacherous road in
two phases of less than four weeks
each.
As the mine was built on moving oil
sand deposits, Mammoet tested
ground compaction along the entire
way before transporting any
modules. Besides terrain stability,
one of the main challenges was
how to safely jack the SPF and
support it while the SPMTs were
rolled under it. The concerns were
not so much about weight as about
structural integrity. Mammoet
designed a unique jacking system
that allowed the incremental jacking
and support of the construction
whilst maintaining a balanced
weight distribution during each
stage of the lift. The system jacked
the 3,300-ton building four feet in
the air and supported it for two
days while 168 axle lines of SPMT
were positioned underneath.
Each process train was moved in
approximately four weeks without a
single incident. Thanks to the
success of the SPF jacking system
and by moving multiple loads
simultaneously, Mammoet short-
ened the overall schedule by five
days. These time savings allowed
re-commissioning works at the new
location to start earlier than
expected. The client estimated that
each workday eliminated from the
schedule represented a per day
savings of 1 million to 1.5 million
dollars.
ResouRces
cRanes 2 crawler cranes7 hydraulic cranes
TRanspoRT 202 axle lines of SPMT32 axle lines of conventional trailers3 prime movers
special equipmenT 10,000Te Hydraulic Jacking System
cRew 62 Mammoet professionals