the american recovery and reinvestment act of 2009 (arra) federal highway administration wisconsin...

29
The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

Upload: collin-mcbride

Post on 20-Jan-2016

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

The American Recovery and Reinvestment Act of 2009 (ARRA)

Federal Highway Administration

Wisconsin Division

January, 2010

Jason P. Spilak, PE, ARRA Engineer

Page 2: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

2

Agenda

Introduction Wisconsin statistics Federal Highway’s expectations 2010 areas for improvement Conclusion

Page 3: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

3

Introduction

Congratulations on 2009 success– Transparency (Reporting)– Delivery was successful

Challenges for 2010– All funds committed by March 2nd

– No ARRA funding changes after September 30th

– Notice to Proceed & Expenditures soon after award

Page 4: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

Statistic from 2009

There are 72 counties in Wisconsin and our FHWA ARRA engineer made it to 68 of them.

Page 5: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

5

2009 Wisconsin statistics

  Wisconsin 2009 ARRA Projects    

     

Region Total Inspections Resurfacing Bridges

NW 25 24 11 14

NC 38 30 20 13

NE 26 26 7 13

SW 32 22 10 19

SE 15 9 4 3

Total  136 111    

Page 6: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

6

FHWA Expectations

Proper contracting procedures to be followed– Advertising & Awarding– NTP following award & work commencing

All parties to abide by and enforce the contract; both the letter and spirit thereof.

“Not Business as Usual” for ARRA means:– Stop poor practices– Enforce contract provisions

Page 7: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

7

FHWA Expectations (continued)

The WisDOT is accountable for the local program.

All parties that work on ARRA projects must:follow all requirements prior to meeting local

desires, or risk losing federal funds

Federal reporting requirements must be adhered to without exception.

Page 8: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

8

Areas for Improvement in 2010

Examples from 2009– Safety– Pavements– Environmental– Bridges– DBE and contract compliance

Page 9: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

9

Safety

General– Fall protection– Trench safety– Protective clothes– Confined space entry

Page 10: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

10

Fall Protection

Walkway without railings or tie off system

Page 11: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

11

Trench Safety

Pipe installation 20+ feet in the ground without trench box

Page 12: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

12

Personal Protective Devices

No shirt No hardhat No reflective clothes

Page 13: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

13

Safety (continued)

Work Zone– Eliminate unsafe traffic barriers– Use only safe end terminals– Crash tested systems installed correctly– Beam guard installed same day as removed– Drop off criteria identified and protected

Page 14: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

14

Safe Barriers

Ensure barrier is in acceptable condition when delivered to the project

Page 15: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

15

Safe End Terminals

Use in correct situations

Place in safe location

Page 16: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

16

Ensure Correct Installation

Safety systems do not work if they are not installed correctly

Page 17: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

17

Unsafe conditions

There needs to be an effort to replace rail systems the same day they are removed, or make necessary accommodations as the specifications dictate.

Page 18: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

18

Drop Off Conditions

Grade for safety or protect public from hazard.

Page 19: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

19

Pavements

No paving in the rain. No water curing asphalt. Concrete pavement cured per specification.

Page 20: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

20

Paving in the rain

Not a good practice.

Page 21: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

21

Moisture curing asphalt

Also not a good practice, warranty or no warranty.

Page 22: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

22

Concrete curing

Make sure curing compound application timeframes specified are followed.

Page 23: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

23

Environmental

Permits need to be on site.

Erosion and Sediment control is important.

Page 24: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

24

Bridges

Understand and follow “Buy America” provisions for steel and cast iron products.

– Certification for all manufacturing procedures.

Reinforcing steel needs to be laid out and poured per design and plan details.

Do not proceed with “critical” items of work without proper inspection.

Ensure inspectors are “comfortable” to inspect the project they are assigned to.

Page 25: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

25

Reinforcing Steel

Poor practice. Chair misaligned. Steel not tied correctly.

Page 26: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

26

DBE & Contract Compliancy

Emergency phone numbers posted. DBE waiver in project files on site. Project Board location is important.

Page 27: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

27

Emergency Contact Information

This information needs to be current and posted on project where the public can see it during “off-hours”.

Page 28: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

28

Project Compliancy Board

Location and employee accessibility is important.

Page 29: The American Recovery and Reinvestment Act of 2009 (ARRA) Federal Highway Administration Wisconsin Division January, 2010 Jason P. Spilak, PE, ARRA Engineer

29

Conclusion

2009 was very successful Most projects went well Some project had “challenges” 2010 can be even better than 2009 Be Safe!