Page 1: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

The ABC’s of the Development Review Process:

Navigating the Bureaucratic Maze

2007 GPA Fall Conference

Page 2: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Presented by:

Dale Hall, RLA, ASLA, AICPDirector of Municipal ServicesWilliams & Associates, [email protected]

Teresa [email protected]

Page 3: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Developer (Public Sector) Anxiety

Page 4: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Perception of Government?

Page 5: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Reality …Neither can exist without the other

Page 6: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Basic Steps to Development

1. Planning2. Rezoning3. Design4. Permitting5. Construction6. Occupancy

Page 7: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

1. Planning

Developer considering what to do …

Utilizing Services of a Professional Consultant

Page 8: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

2. Rezoning

Conceptual Approval from Governmental Jurisdiction

Based on Preliminary Design

Page 9: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

3. Design

Consultant prepares drawings to Owners specifications

Developers Push the Envelope!

Page 10: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

4. Permitting

Site (Civil) Plan Reviews

Building (Architectural) Plan Reviews

Page 11: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

5. Construction

Rubber Hits the Road – When Permits are issued

Building the Project

Making the Plans a reality

Page 12: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

6. Occupancy

Building is Complete!

If all construction meets requirements

Issuance of a Certificate of Occupancy

Page 13: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Basic Types of Development

ResidentialCommercialIndustrialMixed-UseGovernmental/Institutional

Page 14: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Why so many sets of plans?

Page 15: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

Site Plan Review

… a left turn through the mazePermits

Ribbon Cuttings

Certificates

Page 16: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Typical Site Plan Reviews

1. Planning2. Erosion & Sediment Control3. Utilities4. Roadway

Page 17: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

1. Planning

Each Jurisdiction has different rules …

• Zoning• Parking• Internal Circulation• Landscaping

Page 18: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

A. Zoning

Conformance to conditions of zoning

Standards Set by OrdinanceAny Overlay Issues

Historic Districts Watershed Districts Floodplain Wetland Buffers

Page 19: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

B. ParkingMinimum Sizes in OrdinanceMinimum Numbers Set by use

Page 20: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

C. Internal Circulation

Movement of goods, people, vehicles

Typically minimum standards Parking Space length and width Minimum travel aisle width

Page 21: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

D. Landscaping

BuffersPlanting StripsTree Preservation PlansMinimum landscape area?Landscape Architect’s

seal/signature required?

Page 22: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

2. Erosion & Sediment Control

Who is the Issuing Authority?

Stormwater Policy Handbook (Green Book) Guidelines on principles

of stormwater management

Not for Design (Blue Book)

Page 23: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

3. Utilities

A. WaterB. SewerC. Stormwater Management

Page 24: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

A. Water

Is there a Well? EPD Regulated

Development on Jurisdictional Water

Local Authority has Standard Requirements/Details

Page 25: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

B. Sewer

Is this on Septic? Health Department Approvals Each County has specific

Requirements

Development on Jurisdictional Sewer Local Authority has Standard

Requirements/Details

Page 26: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

C. Stormwater Management

Technical Handbook (Blue Book) Sets Guidelines for

review of stormwater runoff

Not for construction (Green Book)

Addresses water quality and quantity issues

Page 27: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

4. Roadway

Who has jurisdiction?Site Access/Curb CutsSite Distance Certification

Requires Engineer Seal/Signature

Page 28: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Review ProcessPaperwork

Checklists Notes Code issues

Redlines Show exact issue

Either can lead to more comments

Page 29: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

What about the Fees?

City Employee SalariesConsultant Review Fees

Plus minimal % - administrative

State Erosion FeesCosts Directly Related to reviews

Page 30: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

What’s not included?

Bonds Construction Soil & Erosion Landscape

Sign Permits

Page 31: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

Building Plan Review

… a right turn through the mazePermits

Ribbon Cuttings

Certificates

Page 32: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Commercial Construction Codes

Georgia State Minimum Standard Building Code

2006 International Building Code (IBC)

Includes GA Amendments

Page 33: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Amendments:

NFPA 101Commonly known as “Life Safety

Code”Pertains to:

Occupancy classifications Means of egress Interior Finishes Sprinkler Systems

Page 34: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Where’s Your Permit?

Page 35: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Prior to issuance of Building Permit

1. State Fire Marshall Approvals2. Site (Civil) Plans3. Building Plan Issues4. Life Safety Issues

Page 36: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

1. State Fire MarshallCriteria Typically Required for Fire

Marshall Approval:

Building height and size Building purpose or designated function Number of rooms, floors, and square

footage depending on uses State, public or institutional uses Occupancy loads per type Food or alcohol service Licensure for operation

Page 37: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

State Fire Marshall cont.

Complete Code at:

http://www.lexis-nexis.com/hottopics/gacode

Contact Local Fire Marshall or Atlanta 404-655-2056

Page 38: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Once you get Set of Approved Fire Marshall Plans

Your building permit may be just around the corner!

Page 39: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

2. Site (Civil) Plans

Wall Heights Any wall over four

feet (4’) requires Engineer’s Stamp Design by others?

Temporary Sanitary Facilities Notations required

Page 40: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

3. Specific Notes for Building Plans

Elevation Drawings Confirm Height Materials must conform to Local codes

Floor Plans Check Dimensions How different are they from the Site

Plan?

Page 41: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Specific Notes cont.

Uses Should be listed Seating Occupancy? Conform to zoning?

Code Summary Summarizes building basics

Code to which Building was designed Occupancies (uses) Building Square Footages Parking Requirements

Page 42: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

4. Life-Safety Issues

Means of egress Headroom

Minimum Standards NFPA 101, 7.1.5

Travel Length for Exiting Varies depending on occupancy type

Panic Hardware on Doors Is this noted NFPA 101, 7.2.1.7

Page 43: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Certificate of Occupancy

Sprinkler Plans Due before issuance of CO

Special Inspection Reports Insures various construction

requirements are met Due before issuance of CO

Page 44: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Finally … Emerging Unscathed

Page 45: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Why do we do all this?

Protect Health, Safety, and Welfare

Sets expected development level

Page 46: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07 Williams & Associates - Deitz Consulting

Key to Success

Communication!Discuss expectationsHave Clear Standards

& Procedures

Spoon Feed Each other

Page 47: The ABC ’ s of the Development Review Process :   Navigating the Bureaucratic Maze

09/21/07

Questions?The ABC’s of the Development Review Process:

Navigating the Bureaucratic Maze

Dale Hall, RLA, ASLA, AICPDirector of Municipal ServicesWilliams & Associates, [email protected]

Teresa [email protected]