Page 1: TGC Big wheel  Sector assembly plan

TGC Big wheel Sector assembly plan

12.23.2004 Tatsuo Kawamoto

ATLAS workshop 2005

Page 2: TGC Big wheel  Sector assembly plan
Page 3: TGC Big wheel  Sector assembly plan

Some history

• 2003 Autumn : 1/24 full size frame in b188 trial of cable installation finalize cable length

• Feb 2004 : Idea of sector assembly tooling • March 2004 : Chamber mounting tool test operation at CERN

• Summer 2004: Realistic installation of cables on the 1/1 model. documentation

Trial of T7, etc handling at CERN(need further study• Oct. 2004: Signal cable preparation at CERN

Page 4: TGC Big wheel  Sector assembly plan

Taking into account considerations and constraints due to - availability of space as a function of time - delivery of major components (planned, possible) - installation at the pit - assumed assembly speed of 1 sector/2 weeks/site

neglecting for the moment worries like

- we don’t know yet the detail of TGC2/3 services assembly (we have better idea about TGC1: full size mock-up)

and assuming we still have reasonable time to learn

- with TGC-1A

Page 5: TGC Big wheel  Sector assembly plan

2004 2005 2006

Part of 180 Full 180

1-C

BW side C? BW side A?

The schedule might look like

1-A 2-C 3-C 2-A 3-A1-A

Beam

pip

e c

losu

re

tilt table

H-table

1 65

6 6 6 66

66 6 6 6

Wedge test?

spokesrim

transv.bar

A-frame, V-standstorage

Bracket 1-C/A

site-1

site-2

Page 6: TGC Big wheel  Sector assembly plan

b180

2nd site(somewhere) 1st site

Assembly + storage

Surface assembly site

Page 7: TGC Big wheel  Sector assembly plan

Horizontal+ tilt

Vertical

storage

Page 8: TGC Big wheel  Sector assembly plan

In order that it somehow works

• Space of the 1st site available (EC cal must move a bit) • Major components are/will-be there in January 2005• Tooling should arrive as planned Status : 1 tilt table mid. January H-table mid. Feb or later A-frame, V-stand early March (to decide how many) 2nd tilt table early March • TGC mounting tool (adapter for all chamber types): will come• Cables, PS-pack, tubes, DCS equipments• Test equipments: gas, electronics

• Man power : many things to do from January for the detector group, be ready in particular in February/March to establish many things.

The 1st sector TGC1-A

Page 9: TGC Big wheel  Sector assembly plan
Page 10: TGC Big wheel  Sector assembly plan

In order that it somehow works

• Space for the 2nd site from April• Components have to be delivered in time Status : complicated, but it should work• Bracket : Need 1/2 of 1-C by mid March, 1/2 of 1-C by mid April, the rest (1-A + tooling) by end June Status : price inquiery launched. Need conscious effort.

• Storage: space and tooling Status : storage tooling 3-d desgin made, gave go-ahead • 10 more PS packs, and then 20 more PS packs by April• DCS sensors, cables

TGC1-C + 1-A series production

Page 11: TGC Big wheel  Sector assembly plan

In order that it somehow works

• Components have to be delivered in time Status : Design not completely finished Strategy for contract

• Services Status : Design not finished

TGC2/3 series production

Ideally, better start assembly as soon as 1-C are finished June/July 2005.But, unlikely to have all above be ready by then.Therefore 1-A is inserted after 1-C assembly.Nevertheless, fall 2005 is not very far !!

Page 12: TGC Big wheel  Sector assembly plan

A few things which are not very clear. would like to learn with the 1st sector. need preparation/consideration by then.

• Assembly procedure in general• Access to height: what kind of tools are needed• Test procedure Gas : perhaps, fairly clear? Readout : starting to play with 5-10 PS-packs

be prepared to 2 independent test set-ups ? (2 sites working in parallel)

Page 13: TGC Big wheel  Sector assembly plan

Chamber installation

• max height to reach is ~7m (TGC-1, bracket T9)• max height difference to access at a time is ~2 m (T9)• max horizontal distance to access at a time is ~2.5m (T3/T6)• height varies as a function of horizontal position

Not obvious what kind of lifting device is optimum

Scaffold, scissors lift, cherry picker just one, or combination of two?

Page 14: TGC Big wheel  Sector assembly plan
Page 15: TGC Big wheel  Sector assembly plan
Page 16: TGC Big wheel  Sector assembly plan
Page 17: TGC Big wheel  Sector assembly plan

stabilizer bar

wallWall of concrete blocks

5.1m

4.3m

1m

The Storage tooling

Random access is not foreseen : order of assembly is important

Page 18: TGC Big wheel  Sector assembly plan

75cm

100cm

With this pitch,the total width of storagefor 6 sectors is ~ 12 m

We will need access to Install PS packs

Scaffold, scissors lift ?

4.3m

5.1m

Height of PS-pack is~5.7m

Space is 75-100cm(depending on installation)

Page 19: TGC Big wheel  Sector assembly plan

• Preparation of TGC-1 surface assembly is in progress• To watch TGC-2/3• very little or no margin in space-time

Schedule of near Future

• mid Jan: TV conf with Israel (Meir, Erez, Ishino, TK, ….)• End Jan: Chamber handling week (+Ochi, Tanaka, Ishino,…)• End Jan.-beg.Feb : b180 preparation week (Meir, Erez, MI, TK, ..• Mid Feb.: 3 technicians from Israel at CERN (+ Meir for a few week

Man power

4 technicians ( payed by Japan) + 4 technicians ( payed by TCn)+ physicists (to plan)

Page 20: TGC Big wheel  Sector assembly plan

Future is not that far