tf joint operations review commissioning plan c neumeyer 2/10/05 test shots instrumentation...
DESCRIPTION
In-Plane Moments Corresponding to Bt Levels in Shot List Mech Failure 2004 Run Worst Case 2004 Run Worst Case Liftoff 4.5kG Applied EM Load (Worst Case) Applied EM Load (Worst Case) Moment at Joint Based on Analysis (Best Case) Moment at Joint Based on Analysis (Best Case)TRANSCRIPT
![Page 1: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/1.jpg)
TF Joint Operations ReviewCommissioning Plan
C Neumeyer2/10/05
Test ShotsInstrumentationBenchmarking
![Page 2: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/2.jpg)
Shot List (Initial Phase to 4.5kG)Bt
(kG)TF_dT (degC)
TF_Tflat (sec) PF Event
Time (sec)
ITF (kA)
IOH (kA)
IPF1A (kA)
IPF1B (kA)
IPF2 (kA)
IPF3 (kA)
IPF4 (kA)
IPF5 (kA)
1 2.25 11 1 0% TF_SOFT 0.0 26.7 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 1.0 26.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0
2 3.18 22 1 0% TF_SOFT 0.0 37.8 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 1.0 37.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0
3 3.90 35 1 0% TF_SOFT 0.0 46.2 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 1.0 46.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0
4 4.50 48 1 0% TF_SOFT 0.0 53.4 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 1.0 53.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0
4a 4.50 48 1 OH Only -/+12
4b PF1a Only-7.5/ +2.5
4c PF1b Only -54d PF2 Only -5
4e PF3 Only-2.5/ +7.5
4f PF5 Only +105 2.25 11 1 50% TF_SOFT 0.0 26.7 -12.0 2.5 0.0 0.0 -2.5 0.0 0.0
50% OHSS 0.5 26.7 12.0 -7.5 -5.0 -5.0 7.5 0.0 10.0 50% TF_EOFT 1.0 26.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0
6 4.50 48 1 100% TF_SOFT 0.0 53.4 -24.0 5.0 0.0 0.0 -5.0 0.0 0.0 100% OHSS 0.5 53.4 24.0 -15.0 -10.0 -10.0 15.0 0.0 20.0 100% TF_EOFT 1.0 53.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0
7 5.03 41 0.5 0% TF_SOFT 0.0 59.7 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 0.5 59.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0
8 5.51 53 0.5 0% TF_SOFT 0.0 65.4 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 0.5 65.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0
9 6.00 71 0.5 0% TF_SOFT 0.0 71.2 0.0 0.0 0.0 0.0 0.0 0.0 0.00% TF_EOFT 0.5 71.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0
10 6.00 71 0.5 50% TF_SOFT 0.0 71.2 -12.0 2.5 0.0 0.0 -2.5 0.0 0.0
50%OHSS & TF_EOFT 0.5 71.2 12.0 -7.5 -5.0 -5.0 7.5 0.0 10.0
11 6.00 71 0.5 100% TF_SOFT 0.0 71.2 -24.0 5.0 0.0 0.0 -5.0 0.0 0.0
100%OHSS & TF_EOFT 0.5 71.2 24.0 -15.0 -10.0 -10.0 15.0 0.0 20.0
![Page 3: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/3.jpg)
In-Plane Moments Corresponding to Bt Levels in Shot List
Commissioning Shot In-Plane Moments
0
10000
20000
30000
40000
50000
60000
70000
80000
2.0 3.0 4.0 5.0 6.0Bt (kG)
M_IP (in-lbf)
M_lP_EMM_IP
Mech Failure
2004 Run Worst Case
Liftoff
4.5kGApplied EM Load(Worst Case)
Moment at JointBased on Analysis(Best Case)
![Page 4: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/4.jpg)
Commissioning Shot In-Plane Pressures
05000
100001500020000250003000035000400004500050000
2.0 3.0 4.0 5.0 6.0
Bt (kG)
Peak Pressure (psi)
P_IP_EMP_IP
In-Plane Pressures Corresponding to Bt Levels in Shot List
Peak Pressure at JointWith No Support(Worst Case)
Peak Pressure at JointBased on Analysis(Best Case)
4.5kG
![Page 5: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/5.jpg)
Voltage Probes
• Same as last run except 8 channels have A&B monitoring
• Allows monitoring of out-of-plane loading
• Web page developed to archive probe vs. channel assignments (instead of reliance on notebook records)
![Page 6: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/6.jpg)
Fiber Optic Temperature, Strain, and Displacement• Flags (inner, outer/top, bottom)
4 flags x 3 strain/flag = 12 strain4 flags x 1 temp/flag = 4 temp
• Hub and Flag twist angle (top, bottom)2 displacement
• Flag end ∆Z & ∆ motion (top, bottom)4 displacement
• Hub (top only)1 displacement
FISO Technologies, Inc.
Total 23 transducers 8 conditioner channels
New
![Page 7: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/7.jpg)
FISO
Joint Res Meas
System
CAMAC
FISOTF Joint Inst Rack
Top Voltage Probe CableTray + 8 f/o extension cables
Bottom Voltage Probe CableTray + 8 f/o extensioncables
Max 8 signalsat a time from Top or bottom
![Page 8: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/8.jpg)
Fiber Optic Displacement Mounting
• Monitor Flag End Motion Same As Last Time
![Page 9: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/9.jpg)
Fiber Optic Displacement Mounting• Relocate Hub/Spline Twist on to Hub
Top Hub Plate Connections
![Page 10: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/10.jpg)
Fiber Optic Displacement Mounting
• Modify for ∆Z & ∆ motion on a single flag • Extend over new insulating boots
![Page 11: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/11.jpg)
Benchmarking Measurements#1 #2 #3 #4 #5 #6SOFT EOFT SOFT EOFT SOFT EOFT SOFT EOFT SOFT OHSS EOFT SOFT OHSS EOFT
Outer Flag delta T (degC) ANSYSFlag Strain A ( μS) ANSYSFlag Strain B (μS) ANSYSShoe Strain B (μS) NASTRANFlag End Toroidal Motion (μils) NASTRANFlag End Poloidal Motion (μils) NASTRANFlag End Toroidal Twist (degrees) NASTRANApparent Resistance (nohμ) ANSYS
Inner Flag delta T (degC) ANSYSFlag Strain A (μS) ANSYSFlag Strain B (μS) ANSYSShoe Strain B (μS) NASTRANFlag End Toroidal Motion (μils) NASTRANFlag End Poloidal Motion (μils) NASTRANFlag End Toroidal Twist (degrees) NASTRAN
Bundle twist angle (degrees) NASTRANHub twist angle (degrees) NASTRAN
Info to be extracted from analysis
• In addition, IP and OOP moments will be backed-out from voltage probe data for one-PF-at-a-time shots to benchmark against influence matrix generated from NASTRAN
![Page 12: TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking](https://reader036.vdocuments.us/reader036/viewer/2022062523/5a4d1ae97f8b9ab059979f23/html5/thumbnails/12.jpg)
Procedure
• Initial phase will commission up to 4.5kG
• Test shots will be conducted and data compared to predictions after each shot
• Performance of system vs. predictions will be judged
• Modeling coefficients and protection limits will be iterated including additional NASTRAN runs as necessary
• Operating envelope will be adjusted accordingly
• Later phase of commissioning toward 6kG will be performed at future date pending results at 4.5kG and when needed for NSTX research program