Testing& Software Metrics

CM602 Effective Systems Development

Page 2: Testing & Software Metrics CM602 Effective Systems Development

Objectives

In this lecture we will consider Validation, verification and testing in

UML Objectives of Software Metrics Planning a Metrics Programme

What are metricsGQM and other techniques“Dos and Don’ts”

Page 3: Testing & Software Metrics CM602 Effective Systems Development

Validation and Verification

Validation refers to a set of activities that ensure that the software that has been built is traceable to customer requirements “Are we building the right product ?”

Verification refers to the set of activities that ensure that software correctly implements a specific function. “Are we building the product right ?”

(Pressman, 2000)

Page 4: Testing & Software Metrics CM602 Effective Systems Development

Validation in UMLUse the design walkthrough technique to check: classes (including interface objects) and class

diagrams interaction sequence diagrams collaboration diagrams state diagrams data dictionary (possibly)

Check for consistency between models

Check for completeness and redundancy

Check for correctness of all OO models

Page 5: Testing & Software Metrics CM602 Effective Systems Development

Difficulties in ValidationIt is difficult to know exactly what is being looked for in validation

Looking for anything that might make the final system less useful for the customer / user than the system should be.

To do validation effectively need to involve the customer

Page 6: Testing & Software Metrics CM602 Effective Systems Development

Software ValidationDemonstrate conformity with requirements.Check for: all functional requirements satisfied all behavioural characteristics are achieved all performance requirements are attained documentation is correct

Two possible conditions after testing conformance to requirements non-conformance: create a defect list

Page 7: Testing & Software Metrics CM602 Effective Systems Development

Verification in UMLTesting of one explicit thing (the product) against another (the specification)Verify that the use cases described in the UML model satisfy the requirements described in the requirements specificationVerify that the classes are capable of providing the use casesVerify that the code corresponds to the classes in the design

Page 8: Testing & Software Metrics CM602 Effective Systems Development

OO testing strategiesUnit testing – Class (or Component) Level Focuses on the operations and the state

behaviour of the class.

Integration testing – Subsystem Level Test that combinations of components work as

expected

Validation testing – System testing focus on user interactions and user visible actions

of the system

Page 9: Testing & Software Metrics CM602 Effective Systems Development

Unit Test CasesTest cases should focus on the class (or component).

Test cases primarily derived from sequence and class diagrams.

Need to consider the implications of inheritance in test cases

White box test cases – written with knowledge of the internal workings of the test item.

Page 10: Testing & Software Metrics CM602 Effective Systems Development

System Testing – Done by Developers

Exercise the whole system using use cases as the basis for many of the test scripts.Also includes: Recovery testing Security testing

Stress testing quantity, frequency, volume, growth

Performance testing run time of software, response times

Page 11: Testing & Software Metrics CM602 Effective Systems Development

Acceptance Testing – Done by Users

Exercise the whole system using use cases as the basis for many of the test scripts.Also includes: Recovery testing Security testing

Stress testing quantity, frequency, volume, growth

Performance testing run time of software, response times

Page 12: Testing & Software Metrics CM602 Effective Systems Development

Metrics: Your starter for ten.

Two programmers are working for the same company, though not on the same project. In one week of work, Fred produces half as much again as Jim, measured in lines of source code.What do you conclude from this?

Page 13: Testing & Software Metrics CM602 Effective Systems Development

Software Metrics

Measurement is defined as a process by which numbers or symbols are assigned to attributes of entities in the real world in such a way as to describe them according to clearly defined rules. (Fenton N 1994)

Page 14: Testing & Software Metrics CM602 Effective Systems Development

Direct and Indirect

We measure by direct (most accurate) and indirect measurements.Many quality factors are measured indirectly.

Direct or indirect?

Speed = Distance*time

Page 15: Testing & Software Metrics CM602 Effective Systems Development

Internal/External Attributes

Typical internal attributes:- Time, effort, and number of events of a

particular type which occurred during the process, eg number of defect reports raised

Others include size, modularity

Typical external attributes Cost, controllability and stability,

reliability of the code, readability of the documents

Page 16: Testing & Software Metrics CM602 Effective Systems Development

Problems with Measurement

Costs incurred The result of any business activity

should be related to the business needs (ie reduce cost). No point measuring for the sake of measuring.

Disruptions caused Developing and using the right method

(consistency in results & repeatability).

Page 17: Testing & Software Metrics CM602 Effective Systems Development

Basics

We need to assert whether we are measuring to predict or to assess.All metrics must be validated

Next question:-When do we measure what?

Page 18: Testing & Software Metrics CM602 Effective Systems Development

Requirement Definition

Structural Design

Detailed Design Coding Unit Testing

Integration testing

Document metrics

Size of product

System structure

Defect detection and removal effort

Effectiveness of defect correction process

Requirements faults and changes

Structural design faults and changes

Detailed design faults and changes

Changes in number of modules

Configuration management system

Test planning

Test effectiveness

Effectiveness of test planningLife-cycle stages and metricsManns T & Coleman M (1996)

Page 19: Testing & Software Metrics CM602 Effective Systems Development

Software Metrics Considerations

Cost Oriented labour cost (normal time) £/hour labour cost (overtime) £/hour

Size Oriented lines of source code 000s project elapsed time months number of project staff people project effort person hours system documentation pages

Function Oriented number of tasks number task complexity scale number of system interfaces number

Productivity Oriented output LOC/person-month documentation produce pages/person-month

Page 20: Testing & Software Metrics CM602 Effective Systems Development

Function Point Analysis

algorithmic modelling techniqueproposed by Albrechtproductivity measurement based on function pointsmethod based on functionality rather than sizeuseful analogies: building a house: each type of house has a configuration of windows, rooms, fittings ... etc. all with a norm for construction upon which the surveyor bases his cost estimates. FPA uses the software design as a blueprint and the design components as its configuration

standard costs in Accounting: everything in a business has a cost

Page 21: Testing & Software Metrics CM602 Effective Systems Development

Function Point Analysis

Function points are computed by counting the software characteristics:

number of user inputs number of user outputs number of user inquiries number of files number of external interfaces

a complexity value is associated with each of the countsa Function Point Count is computed using the formula:

FP = count-total x [0.65 + 0.01 x SUM(Fii)]

once calculated function points are used in a way analogous to LOC

Page 22: Testing & Software Metrics CM602 Effective Systems Development

GQM

1. Set goals specific to needs in terms of purpose, perspective and environment.

2. Refine the goals into quantifiable questions that are tractable.

3. Deduce the metrics and data to be collected (and the means for collecting them) to answer the questions

Page 23: Testing & Software Metrics CM602 Effective Systems Development
Page 24: Testing & Software Metrics CM602 Effective Systems Development

GQM phases

Interpretation

Data Collection

Definition

Measurement resultsAnswers to Questions

Evaluation of goal attainment

Collected Data

Goals, questions, metrics, hypotheses

PlanningProject selected

Project plan

Page 25: Testing & Software Metrics CM602 Effective Systems Development

Example

Goal – Reduce helpdesk maximum turnaround time for basic queries below 48hrs.Questions: What proportion of queries take longer than

48hrs? What types of queries take longer than 48

hrs? What throughput of queries per person leads

to unacceptable turnaround time?

Page 26: Testing & Software Metrics CM602 Effective Systems Development

Example metrics

Metrics Average turnaround time for the last year. Number of queries dealt with. Number of queries taking > 48 hrs. Correlation of staff on duty with turnaround

time. Correlation of query type with turnaround

time. Etc.

Page 27: Testing & Software Metrics CM602 Effective Systems Development

What can goals relate to?

Products which are output from processes Artefacts, deliverables or documents which

arise from the processes

Processes Are any software related activities which take

place over time

Resources which are inputs to processes E.g. person-hours, processing time, office

space.

Page 28: Testing & Software Metrics CM602 Effective Systems Development

Checklist for using GQM

Define human resources are in placeAll necessary resources are availableGoals are identifiedProject team support the goalsProject plans are availableCommunication strategy is in place

Metrics are defined and are consistent with goals and questionsGQM/Measurement/ Analysis plan are available and agreedManagement are fully involvedTrial measurement period is held

Page 29: Testing & Software Metrics CM602 Effective Systems Development

Making the Decision to use metrics

Triggers: General quality concerns Concerns about customer complaints Customers’ requirements for increased information Knowledge of competitors activities in the metrics area Process improvement programmes Cost Cutting Management pressure for information A consultancy recommendation New awareness of possibility of measurement, perhaps

as a result of someone attending a conference Forrester Research Inc. (Barnett et al., 2005)

Page 30: Testing & Software Metrics CM602 Effective Systems Development

Developing a Measurement Culture

Plan your measurement activities Before you start the work

Fear of data being used negatively Confidentiality of the data

Educate the team Provide appropriate training, explain

why

Share the data within the team

Page 31: Testing & Software Metrics CM602 Effective Systems Development

Developing the habit

Measurements do not have to be time consuming Use commercial toolsTracking forms/Spreadsheets/ChartsStart small/explain why/share resultsUse the information extracted to improve development work

Page 32: Testing & Software Metrics CM602 Effective Systems Development

Starting points (1)

Individual developers Work Effort distribution Estimation vs task durations and

efforts Code covered by unit testing No of defects found per unit testing Code and design complexity

Page 33: Testing & Software Metrics CM602 Effective Systems Development

Starting points (2)

Project Teams Product size Work effort distribution Requirements stats, (how many,

implemented, verified) Estimation vs actual Defect counts found when integrating

systems Defect counts found by inspections Requirement stability Number of tasks planned and completed

Page 34: Testing & Software Metrics CM602 Effective Systems Development

What to avoid

Lack of management commitmentMeasuring too much, too soonMeasuring too little, too lateMeasuring the wrong thingsImprecise metrics definitions

Page 35: Testing & Software Metrics CM602 Effective Systems Development

What to avoid

Using metrics data to evaluate individualsUsing metrics to motivateCollecting data that is not usedLack of communication & trainingMisinterpreting metrics data

Page 36: Testing & Software Metrics CM602 Effective Systems Development

Summary

Overview of V&V, testing.What software metrics are concerned with, and what we can measure.Approaches, especially GQM.Good and bad practice in using metrics.

Page 37: Testing & Software Metrics CM602 Effective Systems Development

ReadingPressman (2000)

Chapter 4 on project and process metrics; sections on estimating & function points in chapter 5.

(Also some good material on testing.) Equivalents in other editions will do.

Good article on GQM: “Software Acquisition GOLD PRACTICETM Goal-

Question-Metric (GQM) Approach” at http://www.goldpractices.com/practices/gqm/index.php

Bennett, McRobb & Farmer (2005), Chapter 19, on implementation (testing) Or equivalent in earlier versions

Page 38: Testing & Software Metrics CM602 Effective Systems Development

References

Bennett, S., McRobb, S. & Farmer, R. (2005), Object-Oriented Analysis and Design using UML, 3rd edn. McGraw-Hill.Pressman, R.S. (2000), Software Engineering, A Practitioner’s Approach, 5th edn (European), McGraw-Hill.Barnett, L., Visitacion, M., Gilpin, M. & Symons, C. (2005), “Metrics For Application Development: Selecting A Balanced Set Is No Easy Task” available at http://www.forrester.com/Research/ [viewed 1/12/05].