  Testing requirements for CSCCertification of  Heavy Load Platform Test 1: stacking Platform is to be placed on 4 pads, one under each corner casting. Each corner casting is to be loaded with a load of  942kN (all 4 simultaneously).  Alternatively,  a test were 2 corners at the endframe are tested is also allowed (see left figure below) The force is to be applied by other corner castings (or similar shaped objects) which are shifted longitudinally 38mm and 25.4mm in lateral direction. Test 2: Lifting from top corner fittings Platform is to be lifted by its four topcorners.  The force applied is to be in strict vertical  direction. Platform is to be loaded with a mass of  2*RT=5.1t  Platform needs to be suspended during 5 minutes before it’s lowered onto the ground Test 3: Lifting from bottom corner fittings Platform is to be lifted from its 4 bottom corners.  longitudinal  angles between cables and vertical are to be 45° Platform is to be loaded with 5.1t (=2*RT) 

Upload: tvpcontech

Post on 16-Mar-2016

3 views

Category:

Documents


0 download

DESCRIPTION

testing container CSC requirements ISO containers, flatracks, high cube, TEU, FEU, 8'6", securing, shipping, regulations,

TRANSCRIPT

7/21/2019 Testing Requirements for CSC

http://slidepdf.com/reader/full/testing-requirements-for-csc 1/2

 Testing requirements for CSC‐Certification of  Heavy Load Platform 

Test 1: stacking 

‐Platform is to be placed on 4 pads, one under each corner casting. 

‐Each corner casting is to be loaded with a load of  942kN (all 4 simultaneously). Alternatively, a test 

were 2 corners

 at

 the

 endframe

 are

 tested

 is

 also

 allowed

 (see

 left

 figure

 below)

 

‐The force is to be applied by other corner castings (or similar shaped objects) which are shifted 

longitudinally 38mm and 25.4mm in lateral direction. 

Test 2:

 Lifting

 from

 top

 corner

 fittings

 

‐Platform is to be lifted by its four topcorners. The force applied is to be in strict vertical direction. 

‐Platform is to be loaded with a mass of  2*R‐T=5.1t 

‐Platform needs to be suspended during 5 minutes before it’s lowered onto the ground 

Test 3: Lifting from bottom corner fittings 

‐Platform is to be lifted from its 4 bottom corners. 

‐longitudinal angles between cables and vertical are to be 45° 

‐Platform is to be loaded with 5.1t (=2*R‐T) 

7/21/2019 Testing Requirements for CSC

http://slidepdf.com/reader/full/testing-requirements-for-csc 2/2

Test 4: Longitudinal Restraint 

‐Platform is to be secured at one end against longitudinal sliding(side indicated with blue arrows) 

‐Platform is unloaded 

‐Each corner of  the other end is loaded with 5.1t (total is 10.2t). 

‐Test

 is

 performed

 one

 time

 with

 the

 loads

 towards

 the

 securing

 points(platform

 in

 compression)

 and

 

one time with loads away from the securing points(platform in tension) 

Test 8: Floor strength 

‐Test to be done with vehicle that drives around on the platform. 

‐Load per wheel is 2.73t 

‐distance between wheels centers about 760mm 

‐Contact surface max 142cm² per wheel 

Test 9: Transverse rigidity 

‐Platform

 is

 to

 be

 unloaded

 

‐Platform is to be secured on 1 point against transversal sliding(see blue arrow), other points 

probably will need vertical and lateral support. 

‐1 topcorner is to loaded with 150kN 

‐Only 1 end needs to be tested 

Test 10: Longitudinal rigidity 

‐Same

 as

 transversal

 rigidity

 but

 in

 longitudinal

 direction.

 

‐Load is only 75kN instead of  150kN