terminating a construction contract: getting it right

15
Terminating a contract: getting it right 3 June 2014 Ben Worthington, Senior Associate [email protected] | + 44 20 7067 3541

Upload: francis-ho

Post on 20-Jan-2017

72 views

Category:

Real Estate


0 download

TRANSCRIPT

Page 1: Terminating a Construction Contract: Getting it Right

Terminating a contract: getting it right 3 June 2014

Ben Worthington, Senior [email protected] | + 44 20 7067 3541

Page 2: Terminating a Construction Contract: Getting it Right

2

Introduction

• types of termination

• termination under the JCT SBC 2011

• wrongful termination

• “termination at will” clauses

• good faith / co-operation clauses and termination

• the power to omit work

• practical tips

www.constructiveblog.com

Page 3: Terminating a Construction Contract: Getting it Right

3

Types of termination

• when can a party terminate a contract?

• common law termination

• termination under standard form building contracts

• contractor performance

• contractor insolvency

• employer non-payment

• force majeure

www.constructiveblog.com

Page 4: Terminating a Construction Contract: Getting it Right

4

An example…the JCT SBC 2011

• Detailed provisions setting out:

• the grounds for termination

• The relevant procedure (i.e. notices)

• terminating party must not act unreasonably or vexatiously (see Reinwood Limited v L.Brown and Sons [2008]

www.constructiveblog.com

Page 5: Terminating a Construction Contract: Getting it Right

5

The grounds for termination

• The Employer can terminate the contract if the contractor:

• wholly or substantially suspends the Work;

• fails to proceed regularly and diligently with the Work;

• refuses or neglects to comply with an instruction from the CA requiring him to remove work, materials or goods which are not compliant AND by such refusal the works are materially affected

• sub-contracts the works without consent

• assigns the contract without consent

• fails to comply with certain CDM regulations

• Contractor insolvency

www.constructiveblog.com

Page 6: Terminating a Construction Contract: Getting it Right

6

Recognising a failure to proceed regularly and diligently

www.constructiveblog.com

West Faulkner Associates v London Borough of Newham (1994) 71 BLR 1 – the contractor must proceed:

“continuously, industriously and efficiently with appropriate physical resources so as to progress the work steadily towards completion substantially in accordance with the contractual requirements as to time, sequence and quality of work”.

Page 7: Terminating a Construction Contract: Getting it Right

7

The procedure

• two stage procedure for terminating the contract. The CA must serve:

• a notice specifying the nature of the default;

• a termination notice terminating the contractor's employment under the contract.

• Note the strict time periods:

• termination notice can only be served where the contractor continues with a specified default for 14 days from the default notice.

• right must be exercised within 21 days of the expiry of the 14 day default period

www.constructiveblog.com

Page 8: Terminating a Construction Contract: Getting it Right

8

Wrongful termination

• wrongful termination = repudiatory breach of contract

• innocent party entitled to damages

• no right to "reinstate" the contract

• Losses might include

• demobilisation costs

• supply chain costs

• finance and hire charges

• redundancy payments

• loss of profits

www.constructiveblog.com

Page 9: Terminating a Construction Contract: Getting it Right

www.olswang.com9

Termination at will clauses• what is a termination at will clause ?

• are they lawful?

• drafting tips:

• % complete condition precedent

• rights for both parties

• compensation for terminated party

Page 10: Terminating a Construction Contract: Getting it Right

www.olswang.com10

Good faith clauses and termination

• TSG Building Services Plc v South Anglia Housing Limited: either party, for no, good or bad reason could terminate at any time before the contract term was completed.

• Mid Essex NHS Trust v Compass: the Trust was entitled to exercise absolute right to terminate regardless of good faith clause.

Page 11: Terminating a Construction Contract: Getting it Right

www.olswang.com11

Can I omit work?

• What is the purpose of the omission?

• Abbey Developments Ltd v PP Brickwork Limited (2003) – “It is implicit in most contracts that an owner who exercises a power to omit work must genuinely require the work not to be done at all, and cannot exercise such a power with a view to having the work carried out by someone else.”

• Clear words required to over turn this assumption

Page 12: Terminating a Construction Contract: Getting it Right

www.olswang.com12

Key considerations

• What's your strategy?

• Is there a reputational impact?

• Who will finish the work?

• What are the costs?

• Are there other (better) remedies available?

Page 13: Terminating a Construction Contract: Getting it Right

www.olswang.com13

Practical tips

• Check the contractual grounds

• Get your documents in order

• Follow the contractual procedures rigorously. Check:

• notice periods

• Who to serve / address for service

• grounds are set out properly

• Be consistent in correspondence

• Mitigate loss

• Do not delay

Page 14: Terminating a Construction Contract: Getting it Right

www.olswang.com14

If you receive a notice…

• Keep a tight reign on communications

• consider starting a formal dispute resolution procedure

• consider scope for commercial settlement

• respond firmly

• emphasise breaches by the terminating party

Page 15: Terminating a Construction Contract: Getting it Right

Any questions?