tennessee valley authority · tennessee valley authority chattanooga. tinnrssee 37401 s400 chestnat...

3
TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TINNrSSEE 37401 S400 Chestnat Street Toer II m It, 1983 U1MD-50-390/83-53 SUD-50-39113-50 U.S. nolear Iegulatory Comissio eiaona In Atta: IL*. Jaes P. 0*Reilly, Regional Administrator 101 INrietta Street, 1W, Suite 2900 Atlanta, Georgia 30303 Dear Mr. O'Reilly: UWATS BAU NUCLEAR PLANT UNITS 1 AI 2 - MDIIPB NOT ADEQUATELY SIOM 0O DESIGI TTPICAL DBAINGS - BRD-50-390/83-53, uBRD-50-391/83-50 - FINBL POMT The subject deficiency as initially reported to RC-OIE Inspector Linda Iatson on August 24, 1983 in aoordance with 10' CFR 50.55(e) as ICR 1B5 5036. Our first interi report as submitted on September 21, 1983. Enolosed is our final report. If you have any questions, please get in touch with R. 8. Shell at MS 858-2688. Very truly yours, TEllESSEE VALLEY AUTHIORIT L. M. Mills, Manager Nuclear Licensing Enclosure oo: Mr. Richard C. Deloung, Director (Enclosure) Office of Inspection and Enforcement U.S. Nuclear Regulatory Comission Washington, D.C. 20555 Records Center (Enolosure) Institute of Nuclear Power Operations 1100 Cirole 75 Parkway, Suite 1500 Atlanta, Georgia 30339 8312130204 831205 LCO PDR ADOCK 05000390 S PDR 1983-TVA 50TH ANNIVERSARY An Equal Opportunity Employer

Upload: others

Post on 01-Nov-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TENNESSEE VALLEY AUTHORITY · TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TINNrSSEE 37401 S400 Chestnat Street Toer II m It, 1983 U1MD-50-390/83-53 SUD-50-39113-50 U.S. nolear Iegulatory

TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TINNrSSEE 37401

S400 Chestnat Street Toer II

m It, 1983

U1MD-50-390/83-53 SUD-50-39113-50

U.S. nolear Iegulatory Comissio eiaona In Atta: IL*. Jaes P. 0*Reilly, Regional Administrator 101 INrietta Street, 1W, Suite 2900 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

UWATS BAU NUCLEAR PLANT UNITS 1 AI 2 - MDIIPB NOT ADEQUATELY SIOM 0O DESIGI TTPICAL DBAINGS - BRD-50-390/83-53, uBRD-50-391/83-50 - FINBL POMT

The subject deficiency as initially reported to RC-OIE Inspector Linda Iatson on August 24, 1983 in aoordance with 10' CFR 50.55(e) as ICR 1B5 5036. Our first interi report as submitted on September 21, 1983. Enolosed is our final report.

If you have any questions, please get in touch with R. 8. Shell at MS 858-2688.

Very truly yours,

TEllESSEE VALLEY AUTHIORIT

L. M. Mills, Manager Nuclear Licensing

Enclosure oo: Mr. Richard C. Deloung, Director (Enclosure)

Office of Inspection and Enforcement U.S. Nuclear Regulatory Comission Washington, D.C. 20555

Records Center (Enolosure) Institute of Nuclear Power Operations 1100 Cirole 75 Parkway, Suite 1500 Atlanta, Georgia 30339

8312130204 831205 LCO

PDR ADOCK 05000390 S PDR

1983-TVA 50TH ANNIVERSARY An Equal Opportunity Employer

Page 2: TENNESSEE VALLEY AUTHORITY · TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TINNrSSEE 37401 S400 Chestnat Street Toer II m It, 1983 U1MD-50-390/83-53 SUD-50-39113-50 U.S. nolear Iegulatory

* ~U " TTS MA U OCLAl PLAU ONITS 1AMD 2 DIMlfES 1NOT ADIQOATLT SO 0 DUSIC TYPICAL DUAVIS

cM M5036 o10 M 50.55(e)

fINAL WORT

Description of Deficiency

TWAos typical installation drawings for fire dampers do not reflect the minimm space requimremnts needed for expansion between the fire dampers and the embedded sLwev. There ar. no installation drawings for backdraft dampers, and the installation drawings for flow control dampers are not adequate.

Detailed Installation drawings for backdraft sad flow control dampers were not providod by TWA because the vendor drawings for installation MAre thought to be adequate. A review of the vendor drawings indicates that some clarifications and consolidations of design requrenmmts mere needed, inasmauch as there wmere four different contracts covering a period of moe than seven years which -esulted in som variation of design requireents. TIA purchased all insert-type dampers as 'undersied to manufacturer's standard size' while specifying the actual opening size and the nominal damper size to provide for clearance betwen the damper frame and the concrete opening. TWA designers incorrectly assumed that the vendor would supply undersized dampers to met the clearance requirements since the actual all opening sizes were given. In addition, the construction tolerances of the concrete openings were not considered when sizing the fire dampers. Some tire dampers were therefore installed without sufficient clearance and, in sow oases the sleeve was rewmoved by COIST personnel to facilitate the fitting of the dampers in the openings.

TVA has determined that none of the deficiencies described above exist

at Drowns Ferry, Sequoyah, or Bellefonte Nuclear Plants.

Safety aImlicoations

Some curtain-type dampers were installed in accordance with the typical drawings which did not reflect the minimum space requirements. In the event of a fire, the fire might not be contained and isolated in the area Inasmoh as the dampers my partially reopen due to trame distortion caused by inadequate clearance. This could subsequently lead to the fire spreading throughout the HYAC system. Also, the backdraft and flow control dampers might becom detached from the duotwork which could result in the lack of proper ventilation or cooling air supply to safety-related equipment due to failure of the dampers to function properly. The lack of adequate cooling for safety-related electrical equipment could result in their failure. Thus, the safe operation of the plant could possibly be adversely affected.

Page 3: TENNESSEE VALLEY AUTHORITY · TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TINNrSSEE 37401 S400 Chestnat Street Toer II m It, 1983 U1MD-50-390/83-53 SUD-50-39113-50 U.S. nolear Iegulatory

Corrective Action - C01100 to Both units

TWA has completed a 100 percent inspection of all fire daeo r s to

nsure that they met the requiremnts in the area of compartmentation

and fire protection. Replacement dampers have been ordered from

Rudin Copany for all dampers which do not met minimm clearanee

reuirwMts or were installed without sleeves.

TVA requested Underwriter's Laboratory (L) to test fire dampers

installed with no clearance, and fire dampers shic tare Installed

using methods that differed from the vendor's recommlded method.

Preliminary test results have been received from OL which has given

TWA a good indication of what fire dampers mst be replaced and which

ones are acceptable %s-installed.0 Evaluation of the inspection

reports and the final results of the additional UL testing will enable

TVA to determine the number of fire dampers that are acceptable "as

installed.6

TVA is revising construction drawings under Engineering Change Notice

(EC) 4297 to reflect damper installation requirements including the

vendor's recommendations. All fire dampers requiring replacement will

be installed in accordance with UL and vendor specifications. All TVA

drawings will be issued by January 3, 1981, to enable CONST to

eomplete fire damper replacement by February 26, 198.

TVA had concluded after a review of baekdraft and flow control damper

installations that these dampers are adequately installed to meet

design requirements. Therefore, no replaoement is necessary. The

drawings associated with the backdraft and flow control damper

installations will be Issued by January 3, 1984.

EN DES's Mechanical Engineering Support Branch will issue Design Guide

DO H 18.2.15 "Fire Damper Application Selection and Installation* by

February 1, 1984, to ensure that future fire dampers are purchased

with the proper type and size and necessary installation details are

specified on construction drawings.