TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

1 Anderson 121653.00 I-75 ITS Instrumentation at SR-61 (Andersonville Hwy., Exit 122) Interchange (IA)

0.6 PE 0.0 0.0 PE

3 Bedford 124118.00 SR-437 EXT

Shelbyville Bypass From US-41A (SR-16) To US-231 (SR-10) (IA)

6.2 Right-of-Way 0.0 0.0 ROW

4 Benton 124119.00 I-40 From Decatur-Benton County Line to SR-191 (Birdsong Rd.) (IA)

7.0 Environmental Studies

ENV. 0.0 PE

4 Benton 124123.00 I-40 Benton County Rest Area Renovation (IA) 1.1 PE 0.0 0.0 PE

4 Benton 105768.00 SR-1 US-70

From Camden ByPass to Tennessee River (IA) 4.1 Construction CN 0.0 0.0

1 Blount, Knox 124131.00 I-140 ITS Expansion From I-140 MM 2 to SR-115 (US-129, Alcoa Hwy., Exit 11) (IA)

9.2 PE PE 0.0 CN

1 Blount 124754.00 SR-115 US-129

(US-129 Bypass) From SR-73 (Lamar Alexander Pkwy) to SR-35 (IA)

2.9 Right-of-Way 0.0 ROW 0.0

2

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

1 Blount 100241.01 SR-115 US-129

(Alcoa Highway); Pellissippi Parkway to South of Topside Road (IA)

2.4 Construction 0.0 0.0 CN

1 Blount 101651.02 SR-115 US-129

(Relocated Alcoa Highway), From Proposed Interchange at Tyson Boulevard to SR-162 (Pellissippi Parkway) (IA)

2.4 Construction 0.0 CN 0.0

1 Blount 101423.00 SR-162 EXT

(Pellissippi Pkwy) From SR-33 to SR-73 (US-321) (Re-Budgeted-ROW&Stage Const) (IA)

4.4 Right-of-Way 0.0 ROW 0.0

1 Blount 101725.02 SR-336 (Montvale Rd.), From Montvale Station Road to SR-73 (Lamar Alexander Pkwy) (IA)

0.6 Right-of-Way ROW 0.0 0.0

2 Bradley 124013.00 I-75 From Near Interchange 33 (SR-308) to Near Bradley-McMinn County Line (IA)

2.1 Construction 0.0 0.0 CN

2 Bradley 124018.00 SR-2 US-11

(N. Lee Hwy.) from near Anatole Lane to SR-308 in Charleston (IA)

4.4 Right-of-Way 0.0 ROW 0.0

2 Bradley 101430.01 SR-60 (Georgetown Rd. NW) From 4-Lane North of I-75 (Westlake Drive) to Near SR-306 (IA)

3.2 Construction CN 0.0 0.0

3

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

2 Bradley-Hamilton-Meigs

101430.02 SR-60 (Georgetown Rd. NW) From Near SR-306 in Bradley County to Near SR-58 in Hamilton County (IA)

6.3 Right-of-Way 0.0 0.0 ROW

1 Campbell 124150.00 I-75 ITS Expansion on I-75 at SR-63 (Howard Baker Rd., Exit 141) Interchange (IA)

0.3 PE 0.0 PE 0.0

1 Campbell 124153.00 I-75 ITS Implement a fog and severe weather detection system on I-75 over Jellico Mountain (IA)

25.0 PE PE 0.0 CN

1 Campbell 124156.00 I-75 ITS Expansion at SR-9/SR-116 (US-25W, Exit 134) Interchange (IA)

0.1 PE 0.0 PE 0.0

1 Campbell 101407.01 SR-63 (General Carl W. Stiner Hwy.) From LaFollette Urban Boundary to Frontier Road/Woodson Lane (Re-Budgeted CONST) (IA) APD

4.8 Construction CN 0.0 0.0

1 Campbell 101407.02 SR-63 (General Carl W. Stiner Hwy.) From Near Frontier Road/Woodson Lane to Near Claiborne County Line (Re-Budgeted-ROW&CONST) (IA)

5.2 Right-of-Way ROW 0.0 CN

4 Carroll-Gibson

100326.01 SR-76 US-79

(E. Main St.) From West of Cades-Atwood Road to East of SR-77 (IA)

4.0 Construction 0.0 CN 0.0

4

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

1 Carter 043975.01 SR-91 EXT

(W. Elk Ave.), From SR-67 (US-321) to SR-37 (US-19E) (Re-Budgeted ROW)

5.0 Construction CN 0.0 0.0

1 Claiborne 118734.00 SR-32 US-25E

(Dixie Hwy) Interchange at SR-345 (IA) 0.1 Right-of-Way ROW CN 0.0

1 Claiborne 101409.00 SR-63 From Near Campbell Co. Line to Near Hall Lane (Re-Budgeted ROW&Const.) (IA)

5.2 Right-of-Way ROW 0.0 CN

1 Claiborne 105763.00 SR-63 From West of Old Town Creek to Near SR-32 (US-25E) (***) (IA)

6.2 Construction CN 0.0 0.0

1 Cocke 124292.00 I-40 ITS Rural Deployment on I-40 to State Line (IA) 21.9 PE 0.0 PE 0.0

2 Coffee 123817.00 SR-2 US-41

(Hillsboro Hwy.) From Joe Hickerson Rd. to AEDC Rd. (IA)

2.1 Environmental Studies

ENV. PE 0.0

2 Coffee 101589.01 SR-55 (Wilson Ave.) From Near First Ave. in Tullahoma to Near SR-16 (US-41A) N. of Jackson St. (IA)

0.6 Construction CN 0.0 0.0

5

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

2 Cumberland-Putnam

124054.00 I-40 ITS (Cumberland Plateau) from near Spring Street in Cookeville (Exit 290) to near SR-299 (Exit 338) (Expansion at Rockwood Mountain (IA))

48.2 Construction 0.0 CN 0.0

2 Cumberland 100260.01 SR-28 US-127

From North of I-40 to Near Potato Farm Road (IA)

4.9 Construction CN 0.0 0.0

2 Fentress-Cumberland

100260.05 SR-28 US-127

(S. York Hwy.) From near Lowe Road in Cumberland County to Near Little Road in Clarkrange (IA)

3.2 Construction 0.0 CN 0.0

3 Davidson 123055.00 I-24 Interchange modification at Hickory Hollow Parkway (IA)

0.6 Construction CN 0.0 0.0

3 Davidson 124165.00 I-24 Ramp Improvements Exits 35, 40, 57, 59, and 60 (IA)

0.5 Environmental Studies

ENV. PE

3 Davidson 124173.00 I-24 Downtown loop I-24, including south of Fern to Trinity Lane (IA)

0.8 Environmental Studies

ENV. PE 0.0

3 Davidson-Rutherford

124260.03 I-24 ITS SMART Corridor, From I-440 (Exit 53) to SR-10 (Exit 81 / US-231) in Murfreesboro and SR-1 from I-24 to SR-10 in Murfreesboro and Various Connector Routes. (IA) (Phase 1)

94.1 Construction CN 0.0 0.0

6

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

3 Davidson-Rutherford

124260.04 I-24 ITS SMART Corridor, From I-440 (Exit 53) to SR-10 (Exit 81 / US-231) in Murfreesboro and SR-1 from I-24 to SR-10 in Murfreesboro and Various Connector Routes. (IA) (Phase 2)

94.1 Construction 0.0 0.0 CN

3 Davidson 116896.00 I-40 SR-255 (Donelson Pike) Relocation From Taxiway Bridges Over Existing Donelson Pike to I-40 (IA)

0.8 Right-of-Way ROW 0.0 CN

3 Davidson-Dickson-Cheatham-Williamson-Wilson

124255.00 I-40 ITS From Near US-70S (Exit 196) to Near I-840 and from Near SR-255 (Donelson Pike, Exit 216) to Near US-70 (Exit 239) (IA)

46.4 Construction 0.0 CN 0.0

3 Davidson-Sumner

124263.01 I-65 From Near Rivergate Pkwy. to Near SR-41 (US-31W) (Design Build) (IA)

3.1 Construction CN CN 0.0

3 Sumner-Robertson

124263.02 I-65 From near SR-41 (US-31W) to near SR-257 (Exit 104) (IA) (Design Build)

5.8 Construction 0.0 0.0 CN

3 Robertson 124263.03 I-65 From near SR-257 (Exit 104) to near SR-25 (Exit 112) (IA)

8.7 Environmental Studies

ENV. PE

3 Robertson 124263.04 I-65 From near SR-25 (Exit 112) to near SR-109 (IA) 8.8 Environmental Studies

ENV. PE 0.0

7

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

3 Davidson 125325.00 I-440 From I-40 to I-24 (Design Build) 7.7 Construction CN

3 Davidson 105766.02 SR-11 US-31A

(Nolensville Pike) From North of Mill Creek to Near SR-254 (Old Hickory Boulevard) (IA)

2.5 Construction 0.0 CN 0.0

3 Davidson 124781.00 SR-11 US-31A

(Dickerson Pike) From Fannin Dr. to Old Stone Bridge Rd. to include the CSX Railroad Overpass Structure (IA)

0.2 Environmental Studies

ENV. 0.0 PE

3 Davidson 123814.00 SR-24 US-70

(Charlotte Pike) From American Rd. to White Bridge Rd. (IA)

0.9 Environmental Studies

ENV. PE 0.0

3 Davidson 123815.00 SR-24 US-70

(Charlotte Pike) From I-40 to American Rd. (IA) 1.8 Environmental Studies

ENV. 0.0 PE

4 Dyer 124207.00 I-155 Dyersburg Welcome Center Renovation (IA) 0.6 Environmental Studies

ENV. 0.0 PE

4 Dyer-Gibson 104123.06 SR-104 (Dyersburg Hwy.) From Old SR-104 to West of SR-188 (***) (IA)

5.0 Construction 0.0 0.0 CN

8

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

4 Dyer 124213.00 SR-211 From US-412 in Dyersburg to SR-77 in Newbern (IA)

6.3 Environmental Studies

ENV. 0.0 PE

1 Grainger 118733.00 SR-32 US-25E

(Dixie Hwy.) Off-setting Intersection at SR-131 (IA)

0.4 Construction CN 0.0 0.0

2 Hamilton 124072.00 I-24 From Near I-59 to Near US-27 (IA) 10.0 Right-of-Way 0.0 0.0 ROW

2 Hamilton 112833.00 I-24 Interchange Modification of I-24 and SR-2 (Broad St.) / SR-58 (Market St.) (IA)

1.6 Construction CN 0.0 0.0

2 Hamilton 114174.00 I-75 Interchange Modification at I-24 (Design Build) (IA)

0.4 Construction CN 0.0 0.0

2 Hamilton 123105.00 I-75 Interchange Modification at Hamilton Place Mall (IA)

2.2 Right-of-Way 0.0 0.0 ROW

2 Hamilton-Bradley

124081.00 I-75 From North of US-64 to Near US-74 (IA) 7.9 Right-of-Way 0.0 0.0 ROW

9

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

2 Hamilton 124080.00 SR-8 US-127

From Near SR-27 (Suck Creek Road) to North of South Palisades Drive. (Mountain Rd.) (IA)

3.1 Right-of-Way 0.0 ROW 0.0

2 Hamilton 112152.02 SR-317 (Bonny Oaks Drive), From Industry Drive to Near Adamson Circle (IA)

1.1 Right-of-Way 0.0 0.0 ROW

2 Hamilton 112152.03 SR-317 (Bonny Oaks Drive), From Near Adamson Circle to West of Bonnyshire Drive (IA) (#2 Priority)

1.0 Right-of-Way ROW 0.0 0.0

2 Hamilton 112152.04 SR-317 (Bonny Oaks Drive), From West of Bonnyshire Drive to Near I-75 (IA) (#1 Priority)

2.1 Construction 0.0 CN 0.0

2 Hamilton 112524.01 SR-317 From Near SR-321(Ooltewah-Ringgold Road) to Near Layton Lane (IA) (#4 Priority)

3.1 Construction 0.0 CN 0.0

2 Hamilton 124077.00 SR-320 From East of Bel-Air Rd. to Near SR-321 (Ooltewah-Ringgold Rd.) (IA)

1.5 Right-of-Way 0.0 ROW 0.0

2 Hamilton 124078.00 SR-321 From Near SR-320 (East Brainerd Rd.) to Near SR-317 (Apison Pk.) (IA)

4.5 Right-of-Way 0.0 0.0 ROW

10

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

4 Hardeman-Madison

101599.00 SR-18 From SR-100 in Hardeman County to North of Medon/Malesus Road (IA)

7.5 PE PE 0.0 0.0

1 Hawkins 101394.00 SR-31 (Flat Gap Rd.) From Mooresburg to Adams Lane (***) (Re-budgeted-ROW) (IA)

4.3 Right-of-Way 0.0 ROW 0.0

4 Henderson 100321.01 SR-459 US-412

(Lexington Bypass), From US-412 (SR-20), West of Lexington to Near SR-22, South of Lexington(***) (IA)

4.4 Construction CN 0.0 0.0

4 Henderson 100321.02 SR-459 US-412

(Lexington Bypass), From Near SR-22, South of Lexington to Near SR-20 (US-412), East of Lexington (***) (IA)

2.4 Construction 0.0 0.0 CN

4 Henry 101886.02 SR-54 Near Smith Road in Paris to Crossland Road/ Brannon Lane (North of Puryear) (IA)

9.5 PE PE 0.0 0.0

3 Hickman 123079.00 SR-100 SR-100 and SR-48 Intersection Improvements (IA)

0.1 PE PE 0.0 0.0

1 Knox-Sevier 124474.00 I-40 ITS Expansion From Near Strawberry Plains Pike (Exit 398) Interchange to Near SR-66 (Sevierville, Exit 407) Interchange (IA)

9.7 Construction CN 0.0 0.0

11

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

1 Knox 124473.00 SR-62 (Oak Ridge Hwy.) From SR-131 to Schaad Road (IA)

4.2 Environmental Studies

ENV. 0.0 PE

1 Knox 100241.03 SR-115 US-129

(Alcoa Hwy.) From Near Woodson Drive to Near Cherokee Trail Interchange (IA)

1.3 Construction CN 0.0 0.0

1 Knox 123073.00 SR-162 (Pellissippi Pkwy) Interchange at SR-62 (Oak Ridge Hwy) in Solway (IA)

0.5 PE PE 0.0 ROW

4 Lake, Obion 124583.00 SR-21 From SR-78 to SR-22 (IA) 5.6 PE PE 0.0 0.0

3 Lincoln 124496.00 SR-10 (Huntsville Hwy.) From SR-110 to South of Elk River (IA)

1.4 Environmental Studies

ENV. 0.0 PE

4 Madison 114149.01 I-40 From East of SR-5 (US-45) to Near SR-1 (US-70) in Jackson (IA)

4.6 Construction 0.0 CN 0.0

4 Madison 114149.03 I-40 From West of SR-20 (US-412, Hollywood Drive) to West of SR-186 (US-45 ByPass) (IA)

1.6 Construction 0.0 0.0 CN

12

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

4 Madison 101599.01 SR-18 (Bolivar Hwy.) From North of Medon-Malesus Road to US-45 (SR-5) in Jackson (***) (IA)

6.3 Construction 0.0 0.0 CN

4 Madison 109926.00 SR-186 US-45BP

(Southern Bypass) SR-186 from SR-1 (Airways Blvd.) to SR-5 (So Highland Ave.) in Jackson (IA)

5.3 Right-of-Way 0.0 0.0 ROW

2 McMinn 124087.00 I-75 Interchange Improvements at SR-30 and SR-305 (IA)

0.1 Right-of-Way ROW 0.0 CN

1 Monroe 102380.01 SR-322 (Sweetwater Vonore Rd.) From Sweetwater-Vonore Road to Sheppard Road (***) (IA)

7.1 Right-of-Way 0.0 ROW 0.0

1 Monroe 102380.02 SR-322 (Sweetwater Vonore Rd.) From Sheppard Road to SR-72 (***) (IA)

2.3 Construction 0.0 CN 0.0

3 Moore 123070.00 SR-55 SR-55 Near the Intersection of Goodbranch Rd. to Near Moore County High School (IA)

0.2 Right-of-Way 0.0 ROW 0.0

1 Morgan 124516.03 SR-62 From Near Rock Bridge Rd. to Near SR-61 (IA) 4.7 Environmental Studies

ENV. 0.0 PE

13

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

4 Obion 101342.00 I-69 PROP

From South of SR-21 (Troy-Rives Road) to South of US-51 (IA)

4.6 Construction 0.0 0.0 CN

4 Obion 101343.01 I-69 PROP

From South of SR-3 to South of SR-5 (IA) 2.9 Paving 0.0 0.0 PV

4 Obion 101344.01 I-69 PROP

From South of SR-5 to West of SR-21 (IA) 4.0 Paving 0.0 0.0 PV

4 Obion 101345.00 I-69 PROP

From West of SR-21 to SR-3 (US-51) Near Mayberry Road (IA)

4.9 Construction CN 0.0 0.0

4 Obion 124745.00 I-69 From Rogers Rd in Kentucky to SR-3 (US-45W & US-51) in Obion County (IA)

5.0 Environmental Studies

ENV. 0.0 PE

4 Obion 101888.00 SR-5 US-45W

From Allie Campbell Road to US-51 (SR-3) in Union City (***) (IA)

2.8 Construction 0.0 0.0 CN

3 Perry 111109.03 SR-13 4 spot improvements at locations B, C, D & F From SR-20 to South of the Humphreys County Line (IA)

2.1 Construction 0.0 CN 0.0

14

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

3 Perry 111109.01 SR-13 3 Spot Improvements at (E,H,K), From SR-20 to South of the Humphreys County Line (IA)

1.4 Construction 0.0 CN 0.0

2 Putnam 112538.00 SR-136 (S. Jefferson Ave.) From Near I-40 to Near SR-111 (IA)

2.2 Construction 0.0 CN 0.0

2 Rhea 109410.00 SR-30 (Old Washington Hwy.) From US-27 (SR-29) to West of the Tennessee River Bridge (IA)

8.0 Right-of-Way 0.0 0.0 ROW

3 Rutherford 124683.00 I-24 I-24 Ramp Improvements Exits 66, 70, 81, 84, and 89 (IA)

3.0 Environmental Studies

ENV. PE 0.0

3 Rutherford 104004.02 SR-99 (New Salem Highway), From I-24 to SR-96 (Old Fort Parkway) in Murfreesboro (IA)

1.4 Construction 0.0 CN 0.0

1 Scott 101414.00 SR-29 US-27

(Lon Foust Hwy.) From North of Wolf Creek Road to Old US-27 at Robbins (***) (Re-Budgeted-ROW) (IA)

3.7 Right-of-Way 0.0 ROW 0.0

1 Sevier 124788.00 SR-449 EXT

(Veterans Blvd.) From SR-35 to Robert Henderson Road (IA)

2.0 Right-of-Way 0.0 ROW 0.0

15

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

1 Sevier 124789.00 SR-XXX (Jake Thomas Connector) From SR-449 to SR-73 (US-321/441) (IA)

2.0 Construction 0.0 CN 0.0

1 Sevier 100989.00 SR-73 US-321

(East Pkwy.) From Near Buckhorn Road to East of SR-416 (Phase 2) (***) (IA)

1.4 Right-of-Way 0.0 0.0 ROW

1 Sevier-Jefferson

101401.01 SR-35 US-411

(Newport Hwy.) From Near Sims Road in Sevier County to Near SR-92 (Dickey Road) in Jefferson County (IA)

3.8 Construction 0.0 0.0 CN

4 Shelby 107913.00 I-240 Interchange at Airways Blvd (IA) 0.5 Construction 0.0 CN 0.0

4 Shelby, Fayette

124755.00 I-269 ITS Expansion on SR-385/I-269 from I-40 Southward to the Mississippi State Line (IA)

20.0 PE 0.0 PE 0.0

4 Shelby 101609.01 SR-1 US-70

(Summer Avenue) From I-40 to 0.1 Mile North of Sycamore View Road (IA)

1.7 Construction 0.0 0.0 CN

4 Shelby 100339.02 SR-4 US-78

(Lamar Ave.) From South of Shelby Drive to Near Raines/Perkins Road Interchange (IA)

1.9 Construction 0.0 0.0 CN

16

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

4 Shelby 100340.00 SR-4 US-78

(Lamar Ave.) From Near Raines Road/Perkins Road Interchange to Getwell Road (SR-176) (IA)

1.8 Right-of-Way ROW 0.0 0.0

4 Shelby, Fayette

124759.00 SR-385 ITS Expansion from MM 7 to MM 15 (IA) 8.3 PE PE 0.0 CN

1 Sullivan 124590.00 I-81 ITS Expansion along I-81 between I-26 (Exit 57) Interchange and Virginia State Line (IA)

18.8 PE 0.0 PE 0.0

3 Sumner 106634.02 SR-109 PROP

(Proposed SR-109 Portland Bypass) from SR-52, west of Portland, to existing SR-109, north of Portland (IA)

3.3 Right-of-Way 0.0 ROW 0.0

3 Sumner 106634.03 SR-109 PROP

(Proposed SR-109 Portland Bypass) from existing SR-109, south of Portland, to SR-52, west of Portland.(IA)

3.9 Right-of-Way 0.0 ROW 0.0

1 Washington 112456.00 I-26 Interchange at SR-354 (Exit 17) (IA) 0.8 Construction CN 0.0 0.0

1 Washington, Sullivan

124663.00 SR-36 (Fort Henry Dr.) From SR-75 to I-81 (IA) 3.5 Environmental Studies

ENV. 0.0 PE

17

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

1 Washington 112834.01 SR-93 (Sullivan Gardens Parkway) From North of Davis Road to North of Fire Hall Road (TPR Option 5, Spot Improvement) (IA)

0.8 Construction CN 0.0 0.0

3 Williamson 100289.00 SR-96 (Franklin Rd.) From East of SR-252 (Wilson Pike) to I-840 (***) (IA)

6.1 Right-of-Way ROW 0.0 0.0

3 Williamson 124870.00 SR-397 (Mack Hatcher Pkwy.) from SR-96 East of Franklin to US-31(SR-6, Columbia Pike) South of Franklin (South Quadrant) (IA)

3.2 Environmental Studies

ENV. 0.0 PE

3 Wilson 115791.00 I-40 From SR-109 to I-840 (IA) 3.6 Construction CN 0.0 0.0

18

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

S Statewide Recurring PE PE PE PE

S Statewide Ferry Service across the Tennessee River, OP OP OP SR-69A to SR-147, Benton and Houston

S Statewide Incident Management OP OP OP

S Statewide OP OP OP

S Statewide Resurfacing, National Highway System Recurring Construction CN CN CN

S Statewide National Highway System Bridge Projects Recurring Construction CN CN CN

S Statewide Resurfacing, Federal State Route Recurring Construction CN CN CN

S Statewide State Route Bridge Projects Recurring Construction CN CN CN

S Statewide Rockfall Mitigation Program Recurring Construction CN CN CN

S Statewide Spot Safety Improvement Program Recurring Construction CN CN CN

S Statewide Wetland and Stream Mitigation Recurring PE PE PE PE

S Statewide Tennessee Environmental Streamlining Recurring PE PE PE PE Agreement (TESA)

S Statewide State Route Multi-Modal Access Initiative Construction CN CN CN

Advance Engineering, Functional Design, Aerial Surveys & Mapping, Etc.

Recurring Operations

Recurring Operations

ITS/TMC Operations, Utilities, Maintenance, etc. Recurring Operations

19

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

County

Description

S Statewide State Funded Program: Urban Transit Operating Assistance Bristol, Chattanooga, Clarksville, Jackson, Johnson City, Knoxville Memphis,

Nashville, Kingsport, Morristown, Murfreesboro, Cleveland, Oak Ridge, Franklin, Gatlinburg,

Pigeon Forge, and Sevierville

Capital/ Operating CA/OP CA/OP CA/OP

S StatewideFederal Transit Administration Formula

Program (5303- Metropolitan Transportation Planning Program) and State Matching Funds

– Bristol, Chattanooga, Clarksville, Jackson,Johnson City, Knoxville, Memphis, Nashville,

Kingsport, Morristown, Murfreesboro, Cleveland.

Planning PL PL PL

S Statewide Federal Transit Administration Formula Program (5304) and State Matching Funds–

Statewide Transit PlanningPlanning PL PL PL

Large Urban Areas Federal Transit Administration Formula

Program (5307) State Matching Funds – Large Urbanized Areas – Chattanooga, Knoxville,

Memphis, Nashville Capital Assistance

Capital/ Operating CA/OP CA/OP CA/OP

TRANSIT PROJECTS

TyPE of Work

20

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

Small Urban Areas Federal Transit Administration Formula Program

(5307) State Matching Funds – Small Urbanized Areas Capital and Operating Assistance –

Bristol, Cleveland, Clarksville, Jackson, Johnson City, Kingsport, Morristown, Murfreesboro

Capital/ Operating CA/OP CA/OP CA/OP

Madison Federal Transit Administration Formula Program (5307) State Matching Funds Small Transit

Intensive Cities Performance Apportionment: Jackson

Capital/ Operating CA/OP CA/OP CA/OP

Shelby, Hamilton

Federal Transit Administration Formula Program (5329) and State Matching Funds

State Safety OversightOversight OS OS OS

Shelby, Hamilton,Davidson,

Wilson

Federal Transit Administration Formula Program (5337) State Matching Funds State of

Good Repair: Memphis-Trolley System & Chattanooga-Incline Railway & Nashville-

Davidson County - Star

Capital CA CA CA

Large Urban Areas

Federal Transit Administration Formula Program (5339) State Matching Funds Bus &

Bus Facilities - Large Urbanized Areas - Chattagnooga, Knoxville, Memphis,

Nashville/Davidson County

Capital CA CA CA

Small Urban & Statewide Federal Transit Administration Formula

Program (5339) and State Matching Funds Bus & Bus Facilities - Small Urbanized Areas -

Bristol, Cleveland, Clarksville, Jackson, Johnson City, Kingsport, Morristown, Murfreesboro

Capital CA CA CA

21

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

Large Urban Areas

Federal Transit Administration Formula Program (5310) State Matching Funds Elderly & Disabled Capital Assistance Program Eligible private non-profit and public agencies – Large

Urbanized Areas – Chattanooga, Knoxville, Memphis, Nashville

Capital/ Operating CA/OP CA/OP CA/OP

Small Urban & Rural

Federal Transit Administration Formula Program and State Matching Funds Elderly &

Disabled Capital Assistance Program(5310) Eligible private non-profit and public agencies

Capital/ Operating CA/OP CA/OP CA/OP

S Statewide Federal Transit Administration Formula Program (5311) and State Matching Funds Rural Transit Assistance Program: First Tennessee Human

Resource Agency (HRA), East TN HRA, Southeast TN HRA, Upper Cumberland HRA,

Mid-Cumberland HRA, Northwest TN HRA, Delta HRA, South Central TN Development District, Southwest TN HRA, Gatlinburg, and Pigeon

Forge

Capital/ Operating/

AdministrationCA/OP/AD CA/OP/AD CA/OP/AD

S Statewide Federal Transit Administration Formula Program and State Matching Funds Rural (5311-RTAP) and Urban Transit Assistance

Program and Student Intern Program

Training & Technical

AssistanceTR/TE/AS TR/TE/AS TR/TE/AS

S Statewide Federal Transit Administration Formula Program (5309) and State Matching Funds Anticipated

Competitive Capital GrantsCapital CA CA CA

Urban Areas Federal Highway Administration Funds Flexed to Federal Transit Administration

Formula Program (CMAQ) State Matching Funds

Capital/ Operating CA/OP CA/OP CA/OP

S Statewide State Funded Program: Swipe and Ride Program for State Employees

Purchased Service PS PS PS

Large Urban Areas

State Funded Program: Regional Commuter Transportation Assistance Operating OP OP OP

22

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

Statewide Competitive Multimodal Program Capital CA/OP/AD CA/OP/AD CA/OP/AD

Urban Areas State Funded Program: Critical Trips Program Operating Assistance: Urban Areas Operating OP OP OP

Anderson, Bledsoe, Blount,

Bradley, Campbell, Cannon, Carter, Claiborne, Clay, Cocke, Coffee, Cumberland,

DeKalb, Fentress, Franklin, Grainger, Greene, Grundy,

Hamblen, Hamilton, Hancock, Hawkins, Jackson, Jefferson,

Johnson, Knox, Lawrence, Lewis, Loudon, McMinn, Macon, Marion, Meigs, Monroe,

Morgan, Overton, Pickett, Polk,

Putnam, Rhea, Roane, Scott,

Sequatchie, Sevier, Smith, Sullivan,

Unicoi, Union, Van Buren, Warren,

Washington, White.

Federal Transit Administration Formula Program and State Matching Funds Rural

(5311) Appalachian Transit Assistance

Capital/ Operating/

AdministrationCA/OP/AD CA/OP/AD CA/OP/AD

23

TENNESSEE DEPARTMENT OF TRANSPORTATIONPROPOSED FISCAL YEARS 2019‐2021

PROPOSED COMPREHENSIVE MULTIMODAL PROGRAMApril 5, 2018

Reg County PIN Route Description Length Phase 19 20 21

County Description

Air Carrier Airports (Chattanooga, Knoxville, Memphis, Nashville, Tri-Cities AI AI AI

S Statewide Programs AI AI AI

S General Aviation Airport Planning AI AI AI

S General Aviation Airport Eng., Constr., Preservation

AI AI AI

S General Aviation Airport Safety and Security AI AI AI

Statewide Airport Improvements

Statewide Airport Improvements

Statewide Airport Improvements

AVIATION PROJECTS

TyPE of Work

Hamilton, Knox, Shelby, Davidson, Sullivan Airport Improvements

Statewide Airport Initiatives

24

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase1 ANDERSON US‐25W (SR‐9) US‐HWY. 25W BRIDGE OVER BULL RUN CREEK 16.1 PE, ROW, CONST

3 BEDFORD 0A664 OLD HWY. 64 BRIDGE OVER STOKES BRANCH 0.113 PE, ROW, CONST

4 BENTON 0A156 MT. ZION CHURCH RD. BRIDGE OVER SULPHUR 

CREEK

0.084 PE, ROW, CONST

2 BLEDSOE 02174 OLD HWY. 28 BRIDGE OVER SWAFFORD BRANCH 4.39 PE, ROW, CONST

2 BRADLEY 0A062 BRYMER CREEK RD. BRIDGE OVER BRYMER CREEK 2.979 PE, ROW, CONST

2 CANNON 0A332 CURTIS GEORGE RD. BRIDGE OVER WILMORE 

CREEK

0 PE, ROW, CONST

4 CARROLL 0A393 HOLLOW ROCK BRANCH RD. BRIDGE OVER 

HOLLOW ROCK BRANCH

0.344 PE, ROW, CONST

1 CARTER 04833 SOUTHSIDE RD. BRIDGE OVER GAP CREEK 1.14 PE, ROW, CONST

1 CARTER 0A765 DENNIS COVE RD BRIDGE OVER LAUREL FORK 

CREEK

4.52 PE, ROW, CONST

1 CARTER 0B085 POWELL RD. BRIDGE OVER HAMPTON CREEK 0.015 PE, ROW, CONST

1 CLAIBORNE 0A051 Y HOLLOW RD. BRIDGE OVER CLEAR FORK 0.057 PE, ROW, CONST

1 COCKE 02513 BRIARTHICKET RD. BRIDGE OVER KNOB CREEK 2.95 PE, ROW, CONST

1 COCKE 0A276 STOKLEY CEMETERY RD. BRIDGE OVER TRAIL 

FORK BIG CREEK

0.008 PE, ROW, CONST

25

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase2 COFFEE 00918 WATTENDORF MEMORIAL HWY. BRIDGE OVER 

A.E.D.C. RD. / I‐24

7.67 PE, ROW, CONST

4 CROCKETT 0A078 REYNOLDS RD. BRIDGE OVER POND CREEK 1.082 PE, ROW, CONST

4 CROCKETT 0A191 WARREN RD. BRIDGE OVER BRANCH OF CYPRESS 

CREEK

1.894 PE, ROW, CONST

3 DAVIDSON US‐431/70/70S (SR‐1) BROADWAY BRIDGE OVER BRDWY /11TH AVE S & 

CSX RR

17.29 PE, ROW, CONST

4 FAYETTE 01442 LA GRANGE RD. BRIDGE OVER BRANCH 9.39 PE, ROW, CONST

4 FAYETTE 0A129 SARDIS DR. BRIDGE OVER BRANCH N. FK. WOLF 

RIVER

2.464 PE, ROW, CONST

4 FAYETTE 0A149 BUFORD ELLINGTON RD. BRIDGE OVER NORTH 

FORK CREEK

0.295 PE, ROW, CONST

2 FENTRESS SR‐85 WILDER RD. BRIDGE OVER EAST FORK OBEY RIVER 5.67 PE, ROW, CONST

2 FRANKLIN 0A406 OLD DECHERD RD. BRIDGE OVER WAGNER CREEK 0.259 PE, ROW, CONST

4 GIBSON 00860 CONCORD‐CADES RD. BRIDGE OVER MAYS CREEK 6.5 PE, ROW, CONST

4 GIBSON 0A254 WILDCAT LANE RD. BRIDGE OVER LOCUST GROVE 

CREEK

1.459 PE, ROW, CONST

4 GIBSON 0A349 THETFORD RD. BRIDGE OVER BRANCH OF 

RUTHERFORD FK.

1.39 PE, ROW, CONST

3 GILES 0A068 WATERS SMITH RD. BRIDGE OVER BIG CREEK 0.02 PE, ROW, CONST

26

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase1 GRAINGER 0A365 BLUFF RD. BRIDGE OVER RICHLAND CREEK 0.093 PE, ROW, CONST

1 GREENE 03863 E. CHURCH ST. BRIDGE OVER BRANCH 1.72 PE, ROW, CONST

1 GREENE 0A682 PAINT MOUNTAIN RD. BRIDGE OVER LOWER 

PAINT CREEK

4.987 PE, ROW, CONST

2 HAMILTON I‐24 I‐24 BRIDGE OVER SOU RWY (ABANDONED) 10.36 PE, ROW, CONST

4 HARDEMAN 0A191 NEWSTEAD DR. BRIDGE OVER BRANCH 0.157 PE, ROW, CONST

4 HARDIN SR‐128 HWY. 128 BRIDGE OVER TENN. RIVER (PICKWICK 

DAM)

0.84 PE, ROW, CONST

4 HARDIN 0A232 IRVIN RD. BRIDGE OVER CHOATE CREEK 0.188 PE, ROW, CONST

4 HARDIN 0A308 NICHOLS DR. BRIDGE OVER HORSE CREEK 0.195 PE, ROW, CONST

1 HAWKINS 0A352 AFG RD. BRIDGE OVER SOUTHERN RAILWAY 0.447 PE, ROW, CONST

1 HAWKINS 0A765 WALKERS CHURCH RD. BRIDGE OVER ROBERTSON 

CREEK

0.813 PE, ROW, CONST

4 HENRY 0A118 KUYKENDALL RD. BRIDGE OVER SANDY BRANCH 0.48 PE, ROW, CONST

4 HENRY 0A210 RED TOP HILL RD. BRIDGE OVER BLOOD RIVER 2.08 PE, ROW, CONST

3 HICKMAN 01846 TOTTYS BEND RD. BRIDGE OVER DUCK RIVER 5.73 PE, ROW, CONST

27

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase3 HICKMAN 0A170 WASHER RD. BRIDGE OVER MILL CREEK 0 PE, ROW, CONST

3 HICKMAN 0A756 BARNHILL LN. BRIDGE OVER HALEY CREEK 0.04 PE, ROW, CONST

3 HOUSTON 0A018 HURRICANE LANDING RD. BRIDGE OVER 

HURRICANE CREEK

1.107 PE, ROW, CONST

3 HUMPHREYS I‐40 I‐40 BRIDGE OVER BUFFALO RIVER 6.26 PE, ROW, CONST

3 HUMPHREYS I‐40 I‐40 BRIDGE OVER BUFFALO RIVER 6.26 PE, ROW, CONST

3 HUMPHREYS 0A276 TATEM LN. BRIDGE OVER BLUE CREEK 0.092 PE, ROW, CONST

3 HUMPHREYS 0A279 WEED LN. BRIDGE OVER BLUE CREEK 0.17 PE, ROW, CONST

3 HUMPHREYS 0A281 CROCKETT MURPHREE LN. BRIDGE OVER NFA 

A281 / I40

0.031 PE, ROW, CONST

1 JEFFERSON 02453 LOST CREEK RD. BRIDGE OVER LEWIS CREEK 7.54 PE, ROW, CONST

1 JEFFERSON 02500 ZIRKLE RD. BRIDGE OVER KOONTZ CREEK 1.39 PE, ROW, CONST

1 JOHNSON 0A375 SLIMP BRANCH RD. BRIDGE OVER ROAN CREEK 0.336 PE, ROW, CONST

4 LAKE 02155 FREE BRIDGE RD. BRIDGE OVER RUNNING 

REELFOOT BAYOU

5.93 PE, ROW, CONST

4 LAUDERDALE 0A064 FAYE BARFIELD RD. BRIDGE OVER BRANCH OF 

HATCHIE RIVER

0.718 PE, ROW, CONST

28

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase4 LAUDERDALE 0A110 TURKEY HILL RD. BRIDGE OVER BRANCH 1.757 PE, ROW, CONST

4 LAUDERDALE 0A140 OLDS RD. BRIDGE OVER BRANCH 1.909 PE, ROW, CONST

4 LAUDERDALE 0A291 PARCHMAN RD. BRIDGE OVER BRANCH 1.557 PE, ROW, CONST

3 LAWRENCE 0A197 PLEASANT VALLEY RD. BRIDGE OVER DRY 

WEAKLEY CREEK

1.073 PE, ROW, CONST

4 MADISON 0A092 TURNER LOOP BRIDGE OVER BRANCH 0.646 PE, ROW, CONST

4 MADISON 0A166 GEORGE ANDERSON RD. BRIDGE OVER 

OVERFLOW

3.286 PE, ROW, CONST

2 MARION 02153 ORME RD. BRIDGE OVER DRY CREEK 0.58 PE, ROW, CONST

3 MAURY 01924 SEAVY HIGHT RD. BRIDGE OVER FOUNTAIN CREEK 1.07 PE, ROW, CONST

3 MAURY 0A570 OLD SOWELL MILL PK. BRIDGE OVER DUCK RIVER 1.05 PE, ROW, CONST

2 MEIGS 0A733 W. MEMORIAL DR. BRIDGE OVER DECATUR 

BRANCH

0.37 PE, ROW, CONST

3 MONTGOMERY 00975 DOTSONVILLE RD. BRIDGE OVER CUMMINGS 

CREEK

7.9 PE, ROW, CONST

3 MONTGOMERY 0A009 SULPHUR SPRINGS RD. BRIDGE OVER SULPHUR 

BRANCH

1.568 PE, ROW, CONST

4 OBION 02122 OLD TURNPIKE RD. BRIDGE OVER OLD OBION 

RIVER BED

5.19 PE, ROW, CONST

29

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase3 PERRY 00921 S. MILL ST. BRIDGE OVER BUFFALO RIVER 0.22 PE, ROW, CONST

3 ROBERTSON 05353 EXPERIMENT STATION RD. BRIDGE OVER 

WARTRACE CREEK

0.61 PE, ROW, CONST

3 RUTHERFORD US‐231 (SR‐10) S. CHURCH ST. BRIDGE OVER CSX RAILROAD 12.63 PE, ROW, CONST

1 SCOTT 0A137 ANGEL VALLEY RD. BRIDGE OVER JELLICO CREEK 0.006 PE, ROW, CONST

1 SEVIER 0A852 SPRUCE LN. BRIDGE OVER ROARING FORK CREEK 0.107 PE, ROW, CONST

3 SMITH 0A039 FRIENDSHIP HOLLOW LN. S. BRIDGE OVER 

LANKFORD BRANCH

2.996 PE, ROW, CONST

1 SULLIVAN 0A353 OLD CARDEN HOLLOW RD. BRIDGE OVER BACK 

CREEK

0.445 PE, ROW, CONST

4 TIPTON 00808 BRIDE RD. BRIDGE OVER MATHIS CREEK 5.07 PE, ROW, CONST

1 UNICOI 0A601 LOCUST LN. BRIDGE OVER SOUTH INDIAN CREEK 0.039 PE, ROW, CONST

1 UNION 0A122 BOWER HOLLOW RD. BRIDGE OVER BULL RUN 

CREEK

2.129 PE, ROW, CONST

1 WASHINGTON 02575 TELFORD‐NEW VICTORY RD. BRIDGE OVER LITTLE 

LIMESTONE CREEK

0.14 PE, ROW, CONST

1 WASHINGTON 0B099 LITTLE CASSI CREEK RD. BRIDGE OVER CASSI 

CREEK

0.769 PE, ROW, CONST

3 WAYNE 0A303 ROCKY FORD RD. BRIDGE OVER HOLLY BRANCH 0.14 PE, ROW, CONST

30

TENNESSEE DEPARTMENT OF TRANSPORTATION PROPOSED  FISCAL YEAR 2019COMPREHENSIVE STATE ROUTE AND OFF‐SYSTEM BRIDGE PROGRAM

April 5, 2018

Region County Route Termini LM Phase3 WILLIAMSON US‐31 (SR‐6) E. MAIN ST. BRIDGE OVER HARPETH RIVER 12.51 PE, ROW, CONST

3 WILLIAMSON SR‐96 (FRANKLIN RD.) 3RD AVE. S BRIDGE OVER 

HARPETH RIVER

10.74 PE, ROW, CONST