tender phases

Upload: mou777

Post on 04-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Tender Phases

    1/4

    March 2009

    This article will touch on some of the fundamental legal aspects of the tendering process relating to construction and

    engineering projects and offer some guidance on how best to avoid problems during this crucial stage of contract

    formation.

    Tendering for large and complex construction or engineering projects can be a very expensive exercise for employers

    and tenderers alike. However, it would be money well spent if the objectives of tendering were achieved.

    Most industry players will agree that the main objectives of tendering is two fold: firstly, the tendering process enables

    the employer to secure a suitable contractor to carry out the intended works at a competitive price; secondly, the

    process provides a level platform for participating tenderers to understand the requirements of the intended works

    and the various risks involved in carrying out the works before deciding on their bid price.

    In a heated construction market such as Dubai was recently, parties do not often appreciate the legal aspects of the

    tendering process. During the previous frenzied market conditions, stakeholders of the construction industry were too

    engrossed in negotiating and closing deals as quickly as they would after the tender closing dates. From our

    experience there have been instances where parties have compromised on the legal issues during the tender

    process for fear of missing the set milestones of a particular project.

    The tender processThe tendering process in the construction and engineering industry has developed into a very comprehensive and

    complex procurement process. It often involves many steps and procedures which tenderers must undertake and

    numerous conditions that must be satisfied before they are eligible to move to the next stage of the process.

    The following provides the different phases of a tendering process.These phases were extracted from a guideline

    prepared by the International Federation of Consulting Engineers (FIDIC) (see The FIDIC Contracts Guide First

    Edition 2000). This outline of phases also illustrates a typical tendering process for a construction project in the UAE:

    Pre-qualification phase

    At this phase the employer will set its selection criteria (for example, contractors who are experienced in a specific

    type of engineering works) and invites prospective tenderers who satisfy the said criteria to submit their details and

    capabilities. The objective of this phase is to enable the employer to select suitable contractors to proceed to the next

    phase.

    The tender invitation phase

    The employer issues an invitation to the shortlisted contractors (those who were selected from the pre-qualification

    phase) or to the public at large (if no pre-qualification phase was carried out) to participate in the tender process.

    The tender clarifications and addenda phase

    During this phase, each of the tenderers is expected to raise any queries in relation to the tender documents or the

    requirements of the employer to enable them to price their offer or bid. In responce, the employer will issue written

    clarification to the queries. The employer may also issue tender addendums amending any part of the tender

    documents. Tender site visits are usually carried out during this phase.

    The tender offer or bid submission phase

    Tenderers submit their offers or bids before the stipulated deadline along with the required tender security.

    The tender opening and post tender clarification phase

    The employer opens and evaluates the offers or bids and seeks clarifications from the tenderers regarding their offers

    or bids (if necessary).

    The award phase

    The employer issues a letter of acceptance to the successful tenderer.

    The formalisation of contract phase

  • 7/30/2019 Tender Phases

    2/4

    The successful tenderer signs a formal agreement with the employer for the execution of the project.

    With regards to public procurement in the UAE, there are laws which govern public procurement processes. In the

    Emirate of Dubai, Law No.6 of 1997 regulates contracts with the government departments of Dubai. Law No.6 sets

    out the various methods of procuring contractors by the Government of Dubai which include public and closed tender

    processes. This law also prescribes the procedures by which tenders are to be conducted. The prescribed tender

    procedures are generally in accord with the phases set out above.

    The two-stage contract

    From a legal perspective, an invitation to tender or a request for tender (RFT) document should be framed in such a

    way that it does not create any legal relationship between the invitor (the employer) and any prospective tenderers at

    large. Unless and until the prospective tenderers have participated in the tender process, there should not be any

    legal relationship between the invitor and each of the prospective tenderers.

    The common understanding is that a contract will come into existence if and when the invitor or the employer issues

    a letter of acceptance or letter of award in response to the tender. However due to the complexity of the construction

    tender process, each of the parties participating in the process, including the invitor, will be bound by a set of

    obligations throughout the process. The fact that tenderers are required to furnish tender securities or tender bonds is

    an indication that there is a contract in place. The typical tendering process for a construction or engineering project

    is in effect, from a legal perspective, a two-stage contract.

    The first stage contract

    The first stage begins when the employer issues an invitation to tender or RFT. By issuing the invitation, the employer

    is making an offer to each of the prospective tenderers to enter into the first stage contract or the "tendering contract".

    The underlying obligation of the employer under this contract is its promise to consider each of the bids that the

    tenderers submit in accordance with the terms of the tender invitation. In consideration of the employer's promise,

    each tenderer will deploy its resource to participate in the tender process and in turn promises to execute the project

    in accordance with its bid should the employer accepts it. Therefore, it can be argued that individual tendering

    contract commences when each tenderer begins to participate in the tender process.

    It is common industry practice for employers to include in the tender invitation a document usually labelled as the

    'Instructions to Tenderers' or the 'Conditions of Tendering'. These documents will set out the obligations of the parties

    during the tender process for a fixed period of time or until a specified event occurs (the conditions of tendering).

    It is crucial for all parties to understand and appreciate their obligations during the tender process. Depending on the

    terms of the conditions of tendering, a tenderer may be disqualified from the tender process if it fails to comply with

    the conditions. On the other hand any breach on the part of the employer may entitle the aggrieved tenderer to

    recover damages. Therefore, it is not surprising to find in the conditions of tendering a host of rights that favour the

    employers. Some of these rights are discussed below.

    Employers' overriding rights

    As mentioned earlier, it is the promise of the employers that they will evaluate and consider the individual bid

    submitted by each of the tenderers. Therefore in the absence of any express terms to the contrary the employers are

    obliged to evaluate the bids and award the project to the successful tenderers. Otherwise, the employers may be

    liable to the tenderers for the wasted costs and expenses incurred in participating in the tender process.

    However, it is not uncommon to find a term in the conditions of tendering which provides that the employer will not be

    bound to accept the lowest priced bid. Given the current economic climate, employers may also include in the

    conditions of tendering an absolute right for them to suspend or cancel the tender process at any time. With such

    discretionary rights, the employers would be able to reconsider the timing or feasibility of their projects should they

    need more time to secure the necessary funding, or if the market turns for the worse.

    Other additional rights that employers might set out in the conditions of tendering include the right to vary the

    procedure and timing of the tender process and the right to waive any irregularity in the bids. At times, these rights

  • 7/30/2019 Tender Phases

    3/4

    seem to have gone beyond what is necessary and reasonable at the expense of transparency and fairness to the

    tenderers.

    Ultimately, employers need to be mindful of the overriding requirements of good faith under UAE law whenever they

    exercise their rights pursuant to the conditions of tendering. They must bear in mind that one of the main objectives of

    tendering is to provide an equal platform for all tenderers to compete fairly. In this context, all tenderers must be

    treated equally and fairly by the employer throughout the tender process. For example, each of the tenderers shouldbe given the same information and clarification within the same time as any other tenderers during the process.

    Otherwise the tender process may be seen as a sham and the eventual exercise of the employer's right in turning

    down unsuccessful bids could be construed as an exercise of bad faith.

    To avoid any allegation of unfairness and bad faith, employers, (including their consultants especially those who are

    responsible for conducting the tender process), must ensure that each of the tenderers receives equal treatment and

    opportunity as any other tenderer. If there is any additional information which has arisen either in response to a query

    of one of the tenderers or late information that has not been included in the tender invitation, then the employer must

    ensure that such information is disseminated to all tenderers in a timely manner (unless the information is only

    relevant to a specific tenderer who needs it in order to be able to submit an alternative offer as allowed under the

    conditions of tendering).

    The procedure for disseminating information to all tenderers is often set out in the conditions of tendering and isusually done by way of conducting site visits, convening tender clarification meetings and issuing various tender

    documents such as addendums, clarifications and a collection of questions and answers.

    In the context of disseminating information, we consider that the practice of interactive tendering should be

    encouraged, whereby interactive sessions are built into the tender process giving each of the tenderers the

    opportunity to discuss and clarify the requirements of the employers and perhaps to further develop the specifications

    or project brief contained in the tender documents. Such sessions can also be implemented after the tender closing

    date as long as each of the tenderers is given an equal opportunity to revise its offer or bid after taking into

    consideration any information arising from these sessions.

    Whilst the interactive sessions must be conducted in strict confidence in order to protect the know-how of the

    tenderers, transparency and fairness must prevail such that any material information or errors discovered during the

    sessions are shared amongst the tenderers by way of issuing further tender clarifications or addenda. Carefulplanning and staging of such sessions will promote a truly competitive and effective tendering process.

    Tenderers' risks

    In most conditions of tendering there are different types of disclaimers that protect the employers. Employers will

    usually disclaim any responsibilities for the accuracy or correctness of information provided in tender documents.

    Depending on the time and budget constraints of the particular employer and the scope and nature of the intended

    works, it is always advisable for employers to include in their tender document the amount and details of information

    that are reasonably sufficient for tenderers to appreciate the risks that they will be undertaking if they are successful.

    This will certainly promote and encourage tenderers to put in their most competitive prices.

    Conversely, if the tenderers are to carry the burden of making their own investigations and enquiries as to the

    accuracy and correctness of the information contained in the tender documents, then subject to the risk appetite of

    the individual tenderer, most tenderers would likely add on a premium to their bid or offer prices to cover the risks ofany inaccurate or incorrect tender information along with other associated risks.

    It is also a common requirement for tenderers to assume the risks of any misinterpretation, error or mistake on their

    part in construing the information given in the tender documents and in pricing their bids. In this respect, it is highly

    advisable for tenderers to ensure that they clearly and accurately record the assumptions and interpretations that

    they have adopted in pricing or formulating their bids. These assumptions and interpretations should then be

    discussed with the employer during tender clarification meetings. If the employer finds it necessary, the appropriate

    addendum or clarification may be issued to all tenderers in order to remove or minimise any ambiguity in the tender

  • 7/30/2019 Tender Phases

    4/4

    documents.

    The second stage contract

    The second stage sets in when the employer, after due consideration of the tender bids, issues its acceptance of the

    successful bid. Depending on the conditions of tendering, it is usually upon the issuance of the said acceptance that a

    construction contract between the employer and the successful tenderer is created.

    The conditions of tendering would usually specify the event upon which the second stage contract, i.e. the

    construction contract is deemed to have come into existence. For example, it may be provided that the construction

    contract will deemed to have commenced on the day the successful tenderer receives the employer's letter of

    acceptance. And it is usually provided that until a formal agreement is executed between the parties the letter of

    acceptance shall form a binding contract between them.

    However, for the employer's acceptance to be binding on the successful tenderer, the terms of the acceptance must

    in substance correspond with the essential terms of the tenderer's bid. Otherwise there cannot be a meeting of minds

    between the employer and the tenderer in order to form a contract. What could be an essential term to a contract is

    dependent on the nature of the transaction itself. In relation to construction contracts, the contract price and time for

    completion would be two obvious terms that are essential to the transaction.

    A letter of acceptance that does not correspond with the successful tenderer's offer will amount to a counter-offer.The tenderer would then be in the position to either accept or reject the employer's acceptance. However, before the

    tenderer rejects the employer's purported acceptance it must be careful in determining whether the employer's terms

    of acceptance are, in substance, different from its own offer or bid, otherwise the employer may encash the tender

    security or bond on the basis that the tenderer has failed to comply with its obligation under the tendering contract.

    The tenderers also need to be aware that there would be no obligations on their part to proceed with the construction

    contract if they do not agree with the new terms introduced in the employer's letter of acceptance. In this situation

    they must refrain from conducting or acting in such a way as if a contract has been formed otherwise they may be

    deemed to have accepted the new terms.

    Conclusion

    As highlighted above, it is very important for parties to be aware of their respective legal obligations during the tender

    process. Any inadvertent default on their part may give the other party the right to claim compensation. To take anextreme view, a defaulting employer may be liable to a disgruntled tenderer for the loss of chance of profits that the

    tenderer may have earned but for the employer's breach of its tender obligations. On the other hand, a tenderer who

    refuses to be bound by its bid may be liable to the employer for the difference between its tender price and the higher

    contract price of another tenderer who the employer eventually engages. Therefore the stakes are high for both the

    employers and the tenderers if they choose to ignore the legal aspects of the tendering process.

    As the global financial crisis grips hold of the UAE construction market, parties should take the opportunity to revisit

    their practices either in their implementation of the tender process or in their respond to tender invitations. Even

    though it seems that the construction market in the UAE is currently in a depressed stage, it is certainly an opportune

    time for employers to capitalise on the lower construction costs and for infrastructure projects to catch-up with the

    building industry.