tender. no. tata consulting engineers … no... · - design calculation for operating and...
TRANSCRIPT
TENDER. NO. TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: Title
Master Index SHEET i OF i
ISSUE
R0
BHARAT PETROLEUM CORPORATION LIMITED
REQUEST FOR QUOTATION
NIT No. 6758A-TCE/BPCL-RFQ-002
RFQ NO: TCE.6758A-B-300-002
BUTANE PRE HEATER
Owner : BHARAT PETROLEUM CORPORATION LIMITED
Project : BLENDING UNIT
Location : URAN, MUMBAI (INDIA)
Job No. : TCE.6758A
TATA CONSULTING ENGINEERS LIMITED RAJ PLAZA, 2ND FLOOR, L.B.S. MARG, VIKHROLI (WEST)
MUMBAI – 400 083. INDIA. TEL 91-22-66472111 Fax 91-022-66472000
EMAIL: [email protected]
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 1 of 118
TENDER. NO. TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: Title
Master Index SHEET i OF iii
ISSUE
R0
MASTER INDEX
TO
BIDDING DOCUMENT FOR BUTANE PRE HEATER
BHARAT PETROLEUM CORPORATION LIMITED, URAN, MUMBAI
(BIDDING DOCUMENT NO: TCE-6758A-B-300-002)
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 2 of 118
TENDER. NO. TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: Title
Master Index SHEET ii OF iii
ISSUE
R0
PART – I: GENERAL & COMMERCIAL
SL. NO.
SPECIFICATION NO. REV NO. DESCRIPTION NO. OF SHEETS
1. Acknowledgement & Intention To Bid (to be sent immediately after down loading of the tender)
2
2. TCE.6758A-B-300-002 R0 Instructions To Bidders 28
3. TCE.6758A-B-300-002 R0 Bidder‟s Qualification Criteria 1
4. TCE.6758A-B-300-002 R0 Concurrent Assignments and Experience list
2
5. TCE.6758A-B-300-002 R0 Deviation List 2
6. TCE.6758A-B-300-002 Integrity Pact 4
7. TCE.6758A-B-300-002 R0
ANNEXURE-I TO SPC Scope of Work
2
8. TCE.6758A-B-300-002 R0
ANNEXURE-II TO SPC Scope of Supply
3
9. TCE.6758A-B-300-002 R0 Quality Management System 6
10. TCE.6758A-B-300-002 R0 General Purchase Conditions 36
11. TCE.6758A-B-300-002 R0 Special Purchase Conditions 11
12. TCE.6758A-B-300-002 Approved Vendor List 8
13. TCE.6758A-B-300-002 R0 Commercial Questionnaire 10
14. TCE.M4-903 R5 Drawings, Engineering Documents and Instruction Manuals
6
15. TCE.M4-907 R7 Spares and Maintenance Tools and Tackles
2
16. TCE.M4-914 R7 Progress Schedule and Reports 3
17. TCE.6758A-954 R0 Schedule of Distribution of Drawings and Documents
2
18. TCE.6758A-B-300-002 R0 Performance Guarantee Parameters 3
19. TCE.6758A-B-300-002 R0 Schedule Of Price 5
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 3 of 118
TENDER. NO. TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: Title
Master Index SHEET iii OF iii
ISSUE
R0
PART II - TECHNICAL SL. NO. SPECIFICATION NO. REV NO. DESCRIPTION NO. OF
SHEETS
1. TCE.6758A-B-300-002 R0 Technical Specification - Process 17
2. TCE.6758A-300-SK-8602 R0 Schematic Diagram of Butane Pre Heater 1
3. TCE.6758A-B-300-002 R0 Data sheet for Butane Pre Heater 1
4.
TCE.M4-203-51 R4
Write-up on Induction motors for Hazardous area Data Sheet A1 Data Sheet A2 Data Sheet B Data Sheet C
7 5 3 2 1
5.
TCE.M4-203-71 P0
Variable Speed AC Drives Data Sheet A1 Data Sheet A2 Data Sheet A3
2 6 1
6. TCE.6758A-300-PP-1551 R0 Piping Material Specification 3
7. TCE.6758A-B-300-001 R0 Painting Specification 3
8. TCE.6758A-104-02 R0 Thermal Insulation for Cold Surfaces Insulation data sheet
7 2
9. TCE.6758A-134-01 R0 Welding Specification for Piping Systems 24
10. TCE.M4-405-01 R5 Supply and Fabrication of Structural Steel 12
11. TCE.M4-904 R9 Shop Inspection and Tests 7
12. TCE.6758A-SE-800 R0 Shop Inspection requirement for Air Cooled Heat Exchangers 9
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 4 of 118
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED SECTION:
TCE.6758A-B-300-002 SHEET OF 4
ISSUE R0
PART II
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 5 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 1 OF 17
Table of Contents
1. GENERAL INFORMATION…………………………………………………………….2
2. METEROLOGICAL DATA…................................................................................2
3. PROCESS DESCRIPTION…..............................................................................2
4. EQUIPMENT SPECIFICATIONS…...........................................................................................3
5. INSPECTION AND TESTING…..........................................................................3
6. GUARANTEE…...................................................................................................3
7. PERFORMANCE GURANTEE….........................................................................4
8. SCOPE OF SUPPLY…........................................................................................4
9. EXCLUSIONS FROM VENDOR’S SCOPE OF SUPPLY…................................8
10. INSTRUCTIONS TO BIDDER…..........................................................................8
11. APPROVED LIST OF VENDORS…....................................................................10
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 6 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 2 OF 17
12. 1. GENERAL INFORMATION
12.1. Item No. : 10E005A & 10E005B
12.2. Project : Propane & Butane Blending
12.3. Customer : Bharat Petroleum Corp. Ltd.
12.4. Location : Uran, Maharashtra
12.5. Supplier : By vendor
12.6. Model No. : By vendor
12.7. Quotation No. & Date : By vendor
2. METEROLOGICAL DATA 2.1. Site Altitude : 7.5 m above Mean Sea Level
2.2. Seismic Zone Factor : ZONE IV
2.3. Seismic Coefficient : 0.05
2.4. Ambient Temperature : 10ºC (min), 40ºC (max)
2.5. Barometric Pressure : 1.02 kg/cm²a (min), 1.04kg/cm²a (max)
2.6. Design Wet Bulb Temperature: 29ºC
2.7. Relative Humidity : 60% (min). 95% (max)
2.8. Rainfall : 408 mm in 24 hours (Daily Maximum) Design Hourly Rainfall Avg. 2000 mm (3 months – mid June to mid Sept)
2.9. Wind : 50 m/s (Design Wind Load)
3. PROCESS DESCRIPTION Liquid Butane at (-) 4 degree C from Butane Storage Tank shall be pumped (using Butane Transfer Pump) through Butane Preheater (10E005A or B whichever is in operation) to heat Butane from (-) 4 deg C to a temperature of 15 deg C to be blended with propane and loaded into tanker. This preheater shall be located in open area. The Butane shall be heated using forced draft of air. Vendor shall provide required number of fans to blow air on the preheater side with VFD.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 7 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 3 OF 17
4. EQUIPMENT SPECIFICATIONS
Design Code – ASME Section VIII Div I, API-661, Latest Edition
Material of Construction:
Material Standard Specifications Tubes SA 213 TP 304 ASME By Vendor
Fins SB 209 ALLOY 1060 (Aluminum)
Dimension: By Vendor Fin Pitch: By Vendor Bond Type: Tension wound Wrapped L. Fin Frequency: By Vendor
Header SA 240, Type 304 ASME
Dimension: By Vendor Flange: 300 # RF Type: Plug Type Conn. Tube: Expanded & Seal welded Sht: SA 240 Gr. 304 Gasket: SS 304 spwd Corr. Allowance: 0 mm
Nozzle Pipes on tube side Headers
SA 312 Type 304 ASME Inlet Nozzle: By Vendor
Outlet Nozzle: By Vendor
Nozzle Flange on tube side SA 182 Type 304 ASME 300 # RF
Inlet line size: 200 mm (MOC – LT CS) Outlet line size: 200 mm (MOC – LT CS)
5. INSPECTION AND TESTING: 5.1. Vendor to submit Q.A. Plan for approval by TCE. All Inspection & Testing will
be carried out as per Approved QAP.
5.2. Material Test Certificates.
5.3. Following Tests shall be carried out at the works: - Checking of X-Ray report. - D.P. Test - Ultrasonic Test - Final Hydro test/ Pneumatic Test - Dimensional Checking
For detailed QAP refer to TCE.6758A-SE-800 R0
6. GUARANTEE: 6.1. Vendor shall guarantee the performance of Butane preheater against all defects
including Thermal Rating & Mechanical Design for a period of 12 months from the date of commissioning or 18 months from the date of supply whichever is earlier. Should any defect in design material, workmanship develop during the first year of operation, but not later than 18 months from the date of delivery, the supplier agrees to make all the necessary or desirable repairs or replacement of the defective equipments free of charge.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 8 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 4 OF 17
6.2. Vendor shall guarantee the performance of the Butane Preheater. - Thermal & Mechanical Design - Total Power Consumption in kWh: At Design Duty. - Equipment vibration level: As per clause No. 7.32 (Vibration Testing) of API 661
7. PERFORMANCE GUARANTEE 7.1. Performance test will be carried out at site. 7.2. Outlet temperature of Butane at the exit flange of Butane Pre-heater shall be
15 °C ± 2 °C at the design flow rate given in the data sheet. 7.3. Power Consumption.
8. SCOPE OF SUPPLY / WORK: Butane Pre-heater: 2 Nos. (1 working and 1 standby) as per attached datasheet.
The Vendor's scope of supply / work shall be, but not limited to, Thermal design, Complete mechanical & structural design, Detailed Engineering and preparation of fabrication drawings, Fabrication, Supply, Transportation. Supervision services for Erection, Pre-commissioning and Commissioning for Butane Air Preheater 10E005A & B with fans, and associated structures (bolted type) to site of M/s Bharat Petroleum Corporation Ltd. Uran.
8.1. DESIGN & ENGINEERING:
8.1.1. Thermal and Mechanical Design, design code calculations, structure design of Pre Heater and associated auxiliaries including detailed engineering.
8.1.2. Detail Engineering includes:
Preparation / completion of data sheets (with graphs & scale drawings wherever applicable) for:
- Pre Heater
- Fans
- Motors & VFD
- Vibration switches
- Temperature transmitter (with field indication) with RTD and Thermowell at inlet and outlet of Butane Pre-heater.
- Thermocouple to measure the skin temperature of fins, 2 no. of RTD with temperature transmitter per bundle along with integral display with mounting facility on fin.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 9 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 5 OF 17
- Structural design of columns, frames, operating and maintenance platforms
along with staircase (cage ladder is not acceptable).
8.1.3. Engineering Calculations
- Thermal Design
- ASME Code (Mechanical Design) Calculations
- Seismic Force & Wind Load Calculations
- Design calculations for structural including tube bundle frame
- Design calculation for operating and maintenance platform along with staircase (Cage ladder is not acceptable).
- Lifting and Tailing Lug Calculations
- Nozzle External Forces & Moment Analysis
- Belt Selection Calculation
8.1.4. Drawings:
8.1.4.1. Detailed fabrication drawings of bundle and frame including tube bundle drawing with material specifications stating all thickness, dimensions, component details, actual corrosion allowance available, amount of increased header thickness if used for nozzle reinforcement, all the main welds, nozzle locations and orientation, internals, accessories and tube to tube sheet joint details.
8.1.4.2. General arrangement of Air Fin Coolers shall indicate the major dimensions, maintenance, space required, weight of heaviest maintenance item to be lifted etc.
8.1.4.2. Structural drawings of columns, frames, operational and maintenance platforms along with staircase (cage ladder is not acceptable).
8.1.4.3. Foundation drawings and Foundation load data.
8.2. MATERIAL SUPPLY:
8.2.1. Tube bundles including tube bundle guards, nozzles, plenum chambers.
8.2.2. Headers
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 10 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 6 OF 17
8.2.3. Fan Assembly along with Motors and it's mounting including the
interconnection like belt/couplings and control switches, vibration cut out switches. Variable Speed drives have been included in Vendor’s scope.
8.2.4. Complete supporting arrangement (bolted type) including supporting structure/column, operating and maintenance platforms along with staircase (Cage ladder is not acceptable), handrails and any other part not stated here but required for performing the intended service.
8.2.5. All foundations bolts, shims, embedded parts for all equipment.
8.2.6. All necessary blind flanges along with stud/bolt, nuts and gaskets, cl ips and spares.
8.2.7. Name plate and earthing connections.
8.2.8. Cleats for Fire proofing of all structural members as per OISD norms.
8.2.9. Vibrating switches for fan motors.
8.2.10. Thermocouple to measure the skin temperature of fins, 2 no. of RTD with temperature transmitter per bundle along with integral display with mounting facility on fin.
8.2.11. Temperature transmitter (with field indication) with RTD and Thermowell at inlet and outlet of Butane Pre-heater.
8.2.12. Interconnecting piping and isolation valves as per attached diagram TCE.6758A-300-SK-8602 and piping material specification.
8.2.13. Insulation of interconnecting piping as per attached diagram TCE.6758A-300-SK-8602 and insulation specification.
8.3. SITE ACTIVITIES:
8.3.1. Transportation of all Material
8.3.2. Supervision services during installation, Pre- commissioning and commissioning per diem basis.
8.3.3. Providing performance guarantee.
8.4 GENERAL:
8.4.1. For design of preheater, design minimum ambient temperature shall be 18 deg C at 60% RH. However the selected fans shall be suitable for maximum ambient temperature of 45 deg C.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 11 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 7 OF 17
8.4.2. Tube bundle assemblies including header boxes, tubes, plugs etc. shall be
designed, fabricated and tested in accordance with ASME section VIII, Division 1.
8.4.3. Butane pre-heater shall be suitable for mounting in open space.
8.4.4. Butane pre-heater shall have 20% extra surface area in-built.
8.4.5. Tube to tube sheet joint to be seal welded & expanded as per API 661 CL. 9.3
8.4.6. Vendor should calculate and consider maximum condensation load to over come pressure drop for estimating fan motor power required for maximum developed fan head and guarantee the same.
8.4.7. Supply of all mandatory spares, commissioning spares for preheater shall be as mentioned below; however mandatory spares, commissioning spares for motor, VFD shall be as mentioned in respective specifications.
Commissioning spares
- Nozzle gaskets: 100 %
- Plug gaskets- 1%
- Header Plugs: 2%
- 10% nuts & bolts for all equipments
Mandatory spares
- Nozzle gaskets: 200 %
- Plug gaskets- 20%
- Header Plugs: 20%
- Set of blades for one fan
- 1 No. belt
And special tools and tackles required for erection, site assembly and maintenance for the equipment.
8.4.8. Additional items (including mechanical, electrical and instrumentation and controls) not specified in this enquiry but recommended by Vendor for safe, reliable, smooth and efficient operation of the preheater.
8.4.9. Prime coating & finish paint, export packing, and rust prevention for long storage at site as per attached painting specification.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 12 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 8 OF 17
8.4.10. All documents / drawings as per the Vendor document requirements
attached.
8.4.11. Fans & motors are placed at top of the bundle to avoid fall of condensed water on motor. As air is becoming colder & denser, air flow is made from top to bottom i.e. counter current flow. Also bundles to be placed at height of 6 / 7 m to facilitate easy out go of cooled air and to minimize cold air recirculation.
9. Vendor to provide detailed operating manual mentioning procedure, instructions for the start & stop operation of preheater. Also manual shall contain how to break ice formation if any before/ after starting / shutting the unit daily.
9. EXCLUSIONS FROM VENDORS SCOPE OF SUPPLY:
9.1. Supply of all utilities.
9.2. Civil Works: Civil foundations based on Vendor inputs and design
9.3. Electrical: All cabling.
9.4. Operating personnel for start-up and commissioning.
9.5. Land for stores.
10. INSTRUCTION TO BIDDER:
10.1. The components procured by the Vendor shall generally be as per the sub-vendors mentioned in the attached vendor list. In case for any component sub-vendor is not specified in the list, Vendor shall obtain approval from owner / TCE prior to procurement.
10.2. Vendor’s quotation shall be in full confirmation with purchaser’s requirements.
Unless exception, deviations or alternative are clearly defined and listed by Vendors, the requirements and conditions of this specification shall be deemed accepted by Vendor
10.3. Vendor shall guarantee performance of the Pre Heater for the parameters as specified in technical specification. Vendor shall also guarantee the equipment against defective workmanship & material.
10.4. Variable Speed drives have been specified for preheater. For the air preheater, all the fans in the air bay shall have a variable speed drive system.
10.5. Induction motor shall be supplied as per specification.
10.6. Variable Speed drives have been included in Vendor’s scope (as per specifications
attached for VFD).
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 13 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 9 OF 17
10.7. For maintenance of fan motors minimum head room of 2200 mm shall be kept.
Noise level is within 85 dBA at 1 m from equipment. Vendor shall provide proper safe guards for motors to avoid ingress of rainwater into the motor.
10.8. No. of fans per bay shall be 2.
10.9. Vendor to provide Vibration cut out switch for each fan drive.
10.10. Positioning of lifting lugs shall be such that horizontal balance of tube bundle is obtained.
10.11. Vendor to design & supply supporting structure & platforms for accessing Pre Heater. Platform shall be designed for load of 250 kg/m2.
10.12. Vendor to clearly give exact supporting details of preheater for structure. Pipe supports for inlet/outlet piping shall be as informed by TCE during detail engineering.
10.13. Fire proofing shall be provided for all structural members as per OISD requirements by purchaser, however vendor to provide necessary cleats for the same.
10.14. The allowable loads on Air Cooled Heat exchangers due to external piping shall minimum meet two (2) times the values stated in API 661 / ISO 13706.
10.15. One (1) 2” vent shall be provided at the highest point on the inlet header and one
(1) 2” drain at the lowest point in the outlet header of each Tube Bundle. These
Vents & Drains shall be provided with Blind Flange.
10.16. The size of Thermowell shall be 1½” flanged. Thermowell rating and MOC shall be
compatible to respective Pre Heater design.
10.17. Vendor to provide location & necessary mounting facility for thermocouple on fin surface to measure the skin temperature.
10.18. The area of plot for pre-heater shall be indicated by vendor considering optimum design parameters.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 14 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 10 OF 17
11. APPROVED LIST OF VENDORS - Mechanical Sr.No. Item Vendors
1 Seamless SS
Tubes
REMI (INDIA) SANDWIK INDIA JINDAL INDIA SAW PIPES HEAVY METAL SUMITOMO JAPAN NIPPOR B OEKI JAPAN RATNAMANI METALS & TUBES
2 Plates
ESSAR STEEL LTD. TISCO LTD JINDAL INDIA STEEL AUTHORITY OF INDIA LTD. THYSSEN GERMANY VDM KRUPP GERMANY
3 SS Pipes
SHRIRAM METAL METAL INDIA RATNAMANI METALS & TUBES LTD, MUMBAI RAJENDRA MECHANICAL INDUSTRIES LTD, MUMBAI REMI PROCESS PLANT & MACHINERY LTD.
4 Forged Flanges
AMFORGE INDUSTRIES, MUMBAI PIPEFIT ENGINEERS,VADODARA CHAUDHRY HAMMER WORKS LTD, GHAZIABAD SAWAN ENGINEERS, VADODARA PARMAR TECHNO FORGE, PUNE ECHJAY INDUSTRIES LTD PARAMOUNT FORGE, PANVEL
5 Gaskets
GOODRICH GASKET PVT LTD, MUMBAI IGP ENGINEERS LTD, CHENNAI JAY GAKSETS PVT LTD, VASAI(E) MADRAS INDUSTRIAL PRODUCTS,CHENNAI STARFLEX SEALING INDIA PVT LTD,MUMBAI
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 15 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 11 OF 17
6 Plugs AEP LTD INDIA MULTI FASTERNERS INDIA HANDWIN INDIA
7 Vibration Switch FIRST INERTIA METRIX USA MURPHY UK
LIST OF MANUFACTURERS FOR ELECTRICAL ITEMS
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
1.0 VVVF Drives Siemens ABB Danfoss Allen Bradley (Rockwell Automation) Yaskawa Schneider Electric
2.0 Motors L.V.- (Hazardous Area) ABB Marathon Electric Motors (India) Ltd. (Formerly Alstom Ltd) Bharat Bijlee Ltd. Crompton Greaves Ltd. BHEL Kirloskar Ansaldo, Italy Siemens / Loher, Germany Cemp, Italy Mitsubishi, Japan Fuji, Japan
3.0 Switchgear/Switchboard L.V. Siemens Larsen & Toubro Schneider Electric ABB Danfoss
4.0 Panel (Enclosures) Siemens Larsen & Toubro Schneider Electric ABB Danfoss Rittal
5.0 9 Air circuit breakers L & T Siemens Schneider Electric (M&G)
6.0 MCCB’s L & T Siemens Schneider Electric (M&G)
7.0 0 Switch Disconnector Fuse Unit (SDF) And Switch Disconnector Isolator
Siemens Schneider Electric L&T
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 16 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 12 OF 17
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
8.0 0 Change-over switch Havells (euroload) C&S Areva GE Power Kraus & Naimer Siemens BCH L&T
9.0 1 MCB / RCCB / RCBO / MPCB / MCB Isolators
Siemens Schneider Electric Legrand Moeller ABB
10.0 31 LV capacitors (APP) Universal Cables
ABB Malde Epcos Aswani
11.0 LV Series Reactors For Capacitors Manohar Brothers WHEPL Epcos
12.0 2. LV Epoxy resin cast CTs / PTs Indcoil
Precise Silkaans ABB Pragati AE Huphen Crompton Greaves
13.0 Meters
13.1 1 Digital Meter – Ammeter & Voltmeter
Schneider Electric (Conzerv) AE Rishabh Schneider Electric (Power Measurement (ION) Circutor Siemens Massibus
13.2 Electromechanical – Ammeter & Voltmeter
Automatic Electric MECO IMP Rishabh
13.3 Load Manager / Multi Function Meter / kWh
Schneider Electric (Conzerv) Circutor Rishabh Schneider Electric (Power Measurement (ION) Alpha (ABB) Schlumberger SEMS (Secure)
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 17 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 13 OF 17
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
14.0 1 Contactors
14.1 AC Power Contactor (shall be heavyduty)
Siemens ABB L&T BCH Schneider Electric (Telemecanique)
14.2 DC Power Contactor BCH BHEL Siemens L&T Schneider Electric
14.3 1 Auxiliary contactors Siemens L & T Schneider Electric (Telemecanique)
15.0 1 Time switch GIC Theben Siemens Schneider Electric Legrand
16.0 15.
Timers GIC Theben BCH Siemens Electronic Automation Pvt Ltd. Minilec L&T Legrand Schneider Electric
17.0 Time Delay Relay Areva ABB Siemens BCH L&T Omron PLA
18.0 1 Overload relay
18.1 Electronic / Microprocessor based overload relay
Siemens ABB Schneider Electric
18.2 Bi-metal / Overload Relay Siemens Schneider Electric L&T
18.3 0 Thermister relay Alstom/ Minilec/ Insta controls
19.0 Pushbuttons Siemens Schneider Electric (Telemecanique) Teknic Controls L&T
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 18 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 14 OF 17
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
BCH Areva
20.0 8 Cables
20.1 8. LT Power Cables/ Earthing Cable Universal Cables Ltd.
NICCO KEC International Ltd Cable Corporation Of India Ltd Finolex INCAB Polycab LAPP
20.2 8. LT Control Cables LAPP
Polycab NICCO Universal Cables Ltd. KEC International Ltd Finolex INCAB KEI
20.3 7 HFFR wires (including panel wiring) Finolex Polycab LAPP RR Kabel
21.0 10 Alarm Annunciators (solid state type with LED illumination) / Facia Annunciator
Digicont Industrial Instruments & Controls Procon Inst. (P) Ltd MTL India Pvt. Ltd. Rochester Instruments System Ltd. IDECIZUMI Minilec IICP Proton Electronics Alstom Yashmun ICA Ronan (Waree)
22.0 Semiconductor Fuse Areva Siemens Ferraz Bussman GE
23.0 12 HRC fuse (Power & Control) L & T
Siemens GE Power Bussman Technoelectric
24.0 Hazardous Area Items Baliga Lighting Equipment Pvt. Ltd FCG Flameproof Control Gear Pvt. Ltd. R. Stahl
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 19 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 15 OF 17
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
Cooper - Crouse Hinds Sudhir Switchgear Pvt. Ltd. (For Junction Box)
25.0 10 Cable glands
25.1 Cable Glands (safe area - double seal cone grip type)
Comet Braco Baliga R. Stahl Crouse Hinds Siemens
25.2 Polyamide Cable Glands Lapp Hensel Gewiss
25.3 Cable Glands / Cable Plugs / Stoppers (Hazardous Area)
Same make as certification valid with corresponding hazardous area equipment. (Comet/ Baliga/ R. Stahl / FCG Flameproof Control Gear Pvt. Ltd. / Cooper - Crouse Hinds)
26.0 1 Cable lugs Dowells / Comet
27.0 Terminal Block / Connectors Wago / Connectwell / Pheonix / Elmex
28.0 Relays
28.1 Protective relays (Numerical Type) ABB Siemens GE Multilin SEL SEG Schneider Electric Areva
28.2 Protective relays (Electromechanical Type)
ABB Siemens GE Areva
28.3 2 Auxiliary Relay Areva ABB Siemens VA Tech L & T
28.4 Electronic circuit Relay OEN Omron Allen Bradley PLA
29.0 23 Control / selector switch Kraus n Naimer
Kaycee GE Power controls L&T Siemens Areva
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 20 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 16 OF 17
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
ABB Schneider Electric
30.0 5 Cable termination kits Raychem RPG 3M
31.0 2 Control transformer Indcoil Precise Silkaans NEC Gauss Electricals
32.0 35 Voltage / Power / Current / Frequency / Energy Transducer
ABB AEP Siemens Areva Schneider Electric (Conzerv) Rishabh Masibus
33.0 3 Encoders Hubner Honeywell Turck
34.0 3 Limit Switch BCH Honeywell Siemens Jay Balaji Wago
35.0 GI Conduit / Pipes AKG Zenith SAIL TATA Steel Jindal
36.0 Casing Capping Precision Circle ARK Mody
37.0 Single Phasing Preventer Siemens Minilec Alstom Schneider Electric L & T
38.0 Non-insulated Copper Earthing conductors
Gupta Industrial Corporation (Vasai, Mumbai) Bharat Wires & Ropes Diamond Cables
39.0 0 Indicating Lamps (Multi-chip LED) Binay Teknic Controls Vaishno Siemens L & T Schneider Electric BCH Areva
40.0 0 Decorative switches, sockets and M K Electric
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 21 of 118
TCE.6758A-300-B-002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE UP
TECHNICAL SPECIFICATION SHEET 17 OF 17
SL. NO.
DESCRIPTION OF EQUIPMENT MANUFACTURER
metal boxes (single plate arrangement)
Anchor Crabtree
41.0 Non metallic enclosures (including Industrial Receptacles & LPBS)
Rittal Hensel SCAME Menekkes Bals Siemens Schneider Electric BCH PCE Legrand Gewiss
42.0 FRP cable Trays Ercon Composites Kemrock Industries Indiana Sintex Sumip Composites
43.0 .0 Luminaire (including IP65 luminaires)
Philips Crompton Greaves Bajaj Wipro Lighting
44.0 Lamps Philips GE Osram Sylvania
45.0 Ballast Philips Crompton Greaves Bajaj ATCO
46.0 Choke (for VVVFD) Siemens ABB Danfoss Allen Bradley (Rockwell Automation) Yaskawa
47.0 Power Supply Unit Siemens MTL Aplab Pheonix Cosel
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 22 of 118
CONSULTING ENGINEERS LIMITEDMUMBAI
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 23 of 118
Plant Code UAN Page
ItemRev. R0
Doc. No.S.N. Rev. S.N. Rev. S.N. Rev.
1 22 332 23 * 34 Plug type3 24 * 354 m³ 25 * 36 *5 * 26 37 *6 Total
Extendm2 * 27 38
7 Bare Tube
m2 * 28 398 - 29 * 409 30 4110 31 4211 32 4312 4413 * 45 5414 * 46 5515 * 47 5616 m3/hr * 48 * 5717 Static
PressummWC
* 49 * 58 * deg C18 Mass
Vel. kg/h m2
50 * 5919 Altitude
above m 7.5
MSL51 * 60
20 °C 52 * 6121 °C 18 for thermal design 53 62636465666768697172 Kg/c
m2 g737475 Kg/c
m2 g76 kg/h77 kg/h78 kg/h79 kg/h80 kg/h81828384858687888990919293949596979899
100101102103104105106107108 MECH
ANICA109 Fan ,
Manuf. * Model 117 124
110 Fan RPM * 118 125
111Fan Dia.,mm
* 119 * 126
112 Pitch, mm MAP 120 127 Ratio
113 121
114 122 128
115 123 129 Yes
116
130
131
-
*
-VAPOUR/GAS
-
****
-
*
-
* *
*
------
-
Remarks : 1. DDE-Information will be provided by supplied during detailed engineering Cells with * shall be filled by Air Preheater Vendor
- -
No. / Bay *
*
Speed Reducer, Type
Driver RPM
**
*
587.72.331
0.09840.1779
--
*
Support (Structure)
*
Manuf//Model *
---
*
Motor Supply
Power consumpt on per fan
Driver, Type/ Manuf.
No.of Fan / Bay 2
*
0.0002
*
1484275.091 / *
0.5
-
Variable Speed Drive.
Open Close Lockup
---
--
Phase
*
°C
°C
Enclosure
Included in Vendor's scope
Flameproof
TUBE
-418.02
15
600.7
Gas
*
mmWC / mmWC*
*Al.(SB209Gr.1060)**
Yes / NoPlug Type
KJ/kg
144168-
SS 304 spwd0.0 mm
--
LIQUID
cPW/m-K
Kg/cm2 g°C
SHELL SIDE
-144168
SA182F304
Fin , TypeFin matlFin OD/Thick.No. of Fins / metreNo. / Bundle
Length mmTransverse Pitch
Tube Thickness
**300 # RF
Inlet Nozzle, No./Size
Fin Design Temp
OD / ID mm
Outlet Nozzle, No./SizeRating & Facing
Gasket Material
Surface PreparationCorrosion allowance
BaysBundle Frame
Deg
-
Stamp Yes IHeader Box Type
As per code25 kg/cm2 g
Outlet
Gas
- 45 / +55
kg/m3
*
°C -
No. / BayNo. of RowsArrangement
In Parallel / In SeriesIn Parallel / In Series
°C -
BPCL
Solidification point
Mass enthalpy
Area Ratio
No. of Bays
TypeSize of Unit
ASMEB16.5
TATA CONSULTING ENGINEERS LTD.
LPG Storage & Handling
10E005A / B
Arrangement Horizontal / Vertical2 (1W + 1S)
Tube Length TypeTUBE BUNDLE HEADER
Customer
SA240 ,SS304
Yes / NoAuto / Manual
SA213Gr. 304
Inlet
MaterialNo. of PassesSlopePlug Material
AIR AT 18 DEG C
Condensation enthalpy
Dynamic viscosityThermal conductivitySpecific heatDensityMolar weight
Condensation temperature
Design pressureTest pressure
AGMA Rating
Heat duty, Design Case(Overall) Heat transf. coeff., max/calc.
Effective mean temperature differenceNumber of passesHeat transfer coefficient, Finned Tube / Bare Tube
*Hub Matl.
KW/Driver
Volt
Fouling factor
*Fan Blade MOC
* / *
*
*
2
*
No. of Fans/Bay
No. of Blades
m/sKg/cm2
*
*
*
Pressure drop , admissible / calculatedVelocity (mean)
Cycle *
Fan Capacity M3/hr *
kg/kmolkg/m3
Kcal/kg °CKcal/hr.Kg °CcP°CKcal/kg
Kcal/m2.hr.°C
°CKcal/hrKcal/m².h.°C
-----
m2.hr.°C/Kcal
DATA SHEET FOR BUTANE AIR PREHEATER (Fin Tube Heat Exchanger)
Quantity (operating/stand-by)
Forced Draft
Flanges acc. to
PaintingWeight, delivery kg
Control Action on Air Failure - Fan Pitch Min. Max. Lockup Louvres :
Blade Angle, Deg. *
Developed Head mm WC
--
TUBE SIDEInlet Outlet
LiquidLiquid
Butane
OPERATING CONDITIONS PER UNIT
Weight, water filled kgWeight with process fluid kg
Inspection by TCE / BPCLAs per attached Spec.
18 for thermal designDesign Dry Bulb Temp.Design Ambient, Min.
Design code API661,ASME
*
Volume Flow/ Fan
Vibration Switches
Bundles
Seamless / Welded*
Louvres
Material
Mass flow, total
Mass flow, liquid,
Thermal conductivity
Normal Boiling Point (nbp)
Dynamic viscosity
DensitySpecific heat
Mass flow,( Water Vapour)
Operating Pressure
Mass flow, Air
Process fluid
Physical condition , in / out(S)oliClass of hazard : ZONE II, Gas Group : IIA, Temp Class T3pH-value
Allowable Pressure Min/Nor/Max.Design temperature
Allowable Temperature Min / Nor / Max.
**
-
-
*
*
**
Operating temperature
Mass flow, inerts
--
KJ/kg-°C 2.1990.10120.2137
*
*
Fan Head mmWCAs per code
*
-
-
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 24 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
1
ISSUE
R4
TITLE
1.0 SCOPE
1.1 This specification covers the design, material, construction features, manufacture, inspection and testing at the VENDOR’s/his SUB-VENDOR’s works, delivery to site and performance testing of three phase squirrel cage induction motors to be used in hazardous areas for general purposes.
1.2. Separate specification (TCE.M4-203-02) when enclosed covers the additional requirements, any or all of which shall be complied with as specified in Data Sheet - A1, A2.
2.0 CODES AND STANDARDS
2.1 The design, material, construction, manufacture, inspection, testing and performance of induction motors shall comply with all currently applicable statutes, regulations and safety codes in the locality where the equipment will be installed. The equipment shall also conform to the latest applicable standards. Nothing in this specification shall be construed to relieve the VENDOR of this responsibility.
2.2 Motors shall conform to the latest applicable standards specified in Data Sheet-A2. In case of conflict between the standards and this specification, this specification shall govern.
3.0 DRIVEN EQUIPMENT
3.1 When this specification forms part of the driven equipment specification, information not given in the Data Sheet-A will be governed by the driven equipment specification.
3.2 Motors shall be capable of satisfactory operation for the application and duty as specified in the Data Sheet-A1 and as required by the driven equipment.
4.0 PERFORMANCE AND CHARACTERISTICS
4.1 Motors shall be capable of giving rated output without reduction in the expected life span when operated continuously under either of the following supply conditions as specified in Data Sheet-A1.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 25 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
2
ISSUE
R4
TITLE
Supply Condition I II
a) variation of supply voltage 6% 10% from rated voltage
b) Variation in supply frequency 3% 5% from rated frequency
c) Combined voltage and frequency 6% 10% variation 4.2 Motors shall be suitable for full voltage direct-on-line starting or star-
delta starting or any other method of starting as specified in the Data Sheet-A1.
4.3 Motors shall be capable of starting and accelerating the load with the applicable method of starting, without exceeding acceptable winding temperatures, when the supply voltage is in the range of 85% of the rated motor voltage to maximum permissible voltage specified in Data Sheet-A1.
4.4 The locked rotor current of the motor shall not exceed 600% of full load current (subject to tolerance as per the applicable standard) unless otherwise specified.
4.5 Motors shall be designed to withstand 120% of rated speed for two minutes without any mechanical damage, in either direction of rotation.
4.6 The motor vibrations shall be within the limits specified in applicable standards unless otherwise specified for the driven equipment.
4.7 Except as mentioned herein, the guaranteed performances of the motor shall be met with tolerances specified in applicable standard.
5.0 INSULATION
5.1 Any joints in the motor insulation such as at coil connections or between slot and end winding sections, shall have strength equivalent to that of the slot sections of the coil.
5.2 The insulation shall be given tropical and fungicidal treatment for successful operation of the motor in hot, humid and tropical climate. The tropicalising treatment shall be as per the applicable standard.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 26 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
3
ISSUE
R4
TITLE
6.0 TEMPERATURE RISE
6.1 The highest temperature attained under practical conditions of operations within the rating of the motor by any part or any surface shall not exceed the values given in Table below in IS:13346.
TABLE
Class Maximum Surface Temperature oC ------- ----------------------
T1 450 T2 300 T3 200 T4 135 T5 100 T6 85 These temperature rises are acceptable for an ambient temperature of
40 Deg. C. The temperature rises for other ambient conditions shall be as specified in Data Sheet-A1.
6.2 For motors specified for outdoor installation account shall be taken of heating due to direct exposure to solar radiation.
7.0 CONSTRUCTIONAL FEATURES
7.1 The following types of motors shall be used in hazardous area, depending upon the requirement given in data sheet A1 of this specification.
a) Flameproof construction type Ex `d’
b) Increased safety type Ex `e’
c) Non sparking fan Ex `n’
7.1.1 The constructional feature shall meet the requirements specified in respective IS & BS which are mentioned in Data Sheet A1 and A2 of this Section D of TCE-M4-203-51.
7.2 GENERAL FEATURES
7.2.1 The motor construction shall be suitable for easy disassembly and
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 27 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
4
ISSUE
R4
TITLE
reassembly. The enclosure shall be sturdy and shall permit easy removal of any part of the motor for inspection and repairs.
7.2.2 Motors weighing more than 25 kg. shall be provided with eyebolts, lugs or other means to facilitate safe lifting.
7.2.3 The motor bars shall not be insulated in the slot portion between the iron core laminations and the bars.
7.2.4 Except as noted, horizontal motors shall be foot mounted type and vertical motors shall be flange mounted type.
7.2.5 Unless otherwise approved, motors shall be designed to permit convenient access for drilling vertically through motor feet or mounting flange for installation of Purchaser’s dowel pins after motors are mounted with the driven equipment.
7.2.6 When the motor is supplied with driven equipment including a common base (bed place, channels etc.). The VENDOR shall ensure that such bed plate is adequately braced to keep vibrations and misalignment within satisfactory limits.
7.2.7 The motor name plate shall clearly indicate the type of enclosure, protection and gas group classification as per IS:13346
7.2.8 The test certificates shall be furnished from testing authorities like CMRS-Dhanbad, DGMS, DGFASLI-Mumbai or equivalent.
7.2.9 The motor shall be energy efficient if stated in Data Sheet A1.
8.0 BEARINGS
8.1 Greased ball bearings or greased roller bearings shall be of reputed make subject to the PURCHASER’s approval. The life expectancy of the bearing shall be stated.
8.2 The bearings shall be so constructed that the loss of lubricating fluid is kept to a minimum and greasing shall be possible without any dismantling operation.
8.3 The bearings shall prevent dirt and water from getting into the motor. Bearing lubricant shall not find access to the motor windings.
8.4 The bearings shall permit running of the motor in either direction of rotation.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 28 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
5
ISSUE
R4
TITLE
8.5 If the bearings are oil lubricated, a drain plug shall be provided for draining residual oil and oil level sight guage shall be provided to show precise oil level required for stand-still and running conditions.
8.6 Unless otherwise approved, bearing lubricating system shall be such that no external forced oil or water is necessary to maintain the required oil supply or keep bearing temperature within design limits.
8.7 When pressure oiling is required for horizontal motors, bearings shall be of sleeve type arranged for pressure oiling supplied from the lubrication system of the driven machine, with ring oiling for starting and emergency duty. The ring oiling system shall be adequate for at least 10 minutes, without the pressure oiling system in operation. Oil sight flow gauges shall be provided to indicate oil flow from each bearing.
8.8 Lubricants shall be selected for prolonged storage and normal use of the motors in tropical climate and shall contain corrosion and oxidation inhibitors. Grease shall have suitable bleeding characteristics to minimise setting.
8.9 Sleeve bearing for use with motors having flexible couplings with limited end play, shall have adequate axial end play to permit assembly so as to prevent transmitting of thrust from driven equipment to motor bearings.
9.0 TERMINAL BOX
9.1 Terminal boxes shall be of same construction type as that of motor body construction designed for outdoor service, to eliminate entry of dust and water. Gaskets of neoprene or approved equivalent shall be provided at cover joints and between box and motor frame.
9.2 The terminal box shall be suitable for top and bottom entry of cables.
9.3 Unless otherwise approved, the terminal box shall be capable of being turned through 360 Deg. in steps of 90 Deg. in case of increased safety type Ex `e’ and non sparking fan type Ex `n’ motors.
9.4 The terminals shall be of the stud type with necessary plain washers, spring washers and check-nuts. They shall be substantially designed for the current carrying capacity and shall ensure ample phase to phase and phase to ground clearances.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 29 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
6
ISSUE
R4
TITLE
9.5 Suitable flame proof cable glands shall be supplied by the motor vendor to match Purchaser’s cables whenever specified in data sheet A1.
10.0 PAINT AND FINISH
10.1 Motor external parts shall be finished and painted to produce a neat and durable surface which would prevent rusting and corrosion. The equipment shall be thoroughly degreased, all rust, sharp edges and scale removed and treated with one coat of primer and finished with two coats of gray enamel paint.
10.2 The motor fan shall also be painted to withstand corrosion.
11.0 HEATING DURING IDLE PERIODS
11.1 For motors rated 30 kW & above rating, anticondensation heaters and separate auxiliary terminal box for heaters will be provided.
11.2 Whenever specified in Data Sheet A1 for motors rated below 30 kW, during idle periods, the stator winding will be connected to a 24 V single phase, 50 Hz, AC supply for heating and elimination of moisture. The supply will be connected between any two terminals for a delta connected motor and between one terminal and other for a star connected motor. The VENDOR shall clearly bring out in his offer if there is any objection to the above method of heating, stating reasons thereof.
12.0 ACCESSORIES
12.1 Two independent earthing points shall be provided on opposite sides of the motor, for bolted connection of the PURCHASER’s earthing conductors, as specified in the Data Sheet-A. These earthing points shall be in addition to earthing stud provided in the terminal box.
12.2 Except when otherwise specified, the motors shall be provided with a bare shaft extension having a key slot and a key at the driving end.
12.3 When the motor half coupling is supplied by the PURCHASER or driven equipment vendor, the motor vendor shall strictly adhere to the dimensional requirements and other instructions related to accessory.
13.0 TESTS
13.1 Motor shall be subjected to all the routine tests as per applicable standard in the presence of the PURCHASER’s representative. Copies
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 30 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 7 OF 4
7
ISSUE
R4
TITLE
of test certificates of type and routine tests, as specified in the distribution schedule, shall be furnished for the PURCHASER’s approval.
13.2 All the meters, instruments, devices used for the testing purpose shall be properly calibrated by standard authorised agencies which shall be traceable to National standards. For each such instrument proper validity of calibration shall be documented by Vendor.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 31 of 118
SPECIFICATION NO.
TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A1 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 1 OF 5
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
.R4
1.0 APPLICATION: Butane Preheater Fan
2.0 NUMBER OF UNITS: As per respective package 3.0 TYPE OF MOTOR:
SQUIRREL CAGE
4.0 TYPE OF CONSTRUCTION: Flameproof type ex 'd'
5.0 SUPPLY SYSTEM FAULT LEVEL: 36MVA, 50kA 6.0 SUPPLY NEUTRAL : Effectively Earthed 6.1 COMPLIANCE WITH TCE-M2-203-
02 IS REQUIRED NO
6.2 IF YES ,WHICH CLAUSE Not applicable 7.0 RATED OUTPUT: (*)
8.0 RATED VOLTAGE 415 V 9.0 NUMBER OF PHASES &
FREQUENCY: 3 PHASE, 50 Hz
10.0 SUPPLY CONDITION (REF CL NO. 4.1 OF TCE.M4-203-51)
II
11.0 SYNCHRONOUS SPEED (*)
12.0 TYPE OF DUTY(IS 325 OR IS 12824)
(*) S1
13.0 DUTY DESIGNATION (IS 325 OR IS 12824)
(*)
14.0 CYCLIC DURATION FACTOR: Not applicable 15.0 CYCLES PER HOUR: (*) 16.0 MOMENT OF INERTIA: (*) kg-m2 17.0 METHOD OF STARTING: VVVFD (with bypass DOL) 18.0 STARTING TORQUE % Full load torque 19.0 PULL OUT TORQUE % Full load torque 20.0 CLASS OF INSULATION: F 21.0 REF AMBIENT TEMPERATURE 45 0C (Design Ambient
Temperature : 500C) 22.0 TEMPERATURE RISE BY
THEROMOMETER/WDG RES 75 0C (Corresponding to Class B
Insulation)
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 32 of 118
SPECIFICATION NO.
TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A1 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 2 OF 5
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
.R4
23.0 MAXIMUM SURFACE TEMPERATURE CLASSIFICATION (IS:8239):
T4
24.0 LOCATION: Outdoor A) HAZARDOUS AREA DIVISION
(IS5572 OR EQUIVALENT:) Zone2
B) GROUP CLASSIFACTION AS PER IS:2148 (FOR FLAME-PROOFENCLOSURES HAVING HAZARDOUS GAS)
IIA/IIB
C) WHETHER SUITABILITY FOR HAZARDOUS DUST REQUIRED:
No
IF YES, TYPE OF DUST : 25.0 ATMOSPHERE: Humid & Extremely corrosive (Coastal
salt laden). 26.0 TYPE OF COOLING (IS:6362) TEFC 27.0 DESIGNATION FOR DEGREE OF
PROTECTION (IS:4691): IP41/IP43/IP54/IP55
IP65
28.0 TERMINAL BOX A) LOCATION AS SEEN FROM NON- DRIVE END RIGHT/LEFT B) RATING SHORT TIME CURRENT: KA (RMS) DURATION:SECS. 0.21 DYNAMIC
KA (PEAK)
(*) 50 KA (RMS)
0.25 SECS 127.5 KA (PEAK)
29.0 EXTERNAL CABLE DETAILS A) TYPE B) NUMBER OF CORES
(#) 4 Core
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 33 of 118
SPECIFICATION NO.
TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A1 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 3 OF 5
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
.R4
C) SIZE: D) WHETHER FLAMEPROOF CABLE GLAND BY VENDOR
YES/ NO
Yes
30.0 EARTHING CONDUCTORS A) MATERIAL: B) SIZE:
AL, PVC insulated earthing cable As per motor rating (#)
31.0 SHAFT ORIENTATION: VERTICAL/HOLLOW VERTICAL (*)
32.0 MOUNTING SYMBOL (IS :2253 OR EQUIVALENT)
(*)
33.0 TYPE OF COUPLING DIRECT FLEXIBLE (*) 34.0 WHETHER HALF COUPLING
REQUIRED: YES/NO (*)
35.0 ROTATION AS SEEN FROM NON-DRIVEN END
CLOCKWISE/ANTICLOCKWISE (*)
36.0 TYPE OF BEARING DRIVE END/NON DRIVE END (*) 37.0 WHETHER BED PLATE
REQUIRED YES/NO (#)
38.0 WHETHER RAIL REQUIRED NO 39.0 COLOUR SHADES OF PLANT IF
SPECIAL Shade 632 as per IS 5
40.0 CTS FOR DIFFERENTIAL PROTECTION REQUIRED
NO
41.0 VIBRATION DETECTORS REQUIRED
NO
42.0 SPACE HEATERS FOR MOTORS REQUIRED
YES
43.0 WHETHER 24 V WINDING HEATING REQUIRED
NO
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 34 of 118
SPECIFICATION NO.
TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A1 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 4 OF 5
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
.R4
44.0 $ CT PARTICULARS A) 3 CTS, ONE IN THE NEUTRAL LEAD OF EACH PHASE B) RATIO C) CLASS P. S. D) KNEE POINT VOLTAGE E) MAX. R. C. T. SECONDARY WINDING, F) MAX. EXCITING CURRENT AT 1/2 KPV G) CLASS OF INSULATION
(KPV) OHMS
NOT APPLICABLE
NOTES: 1 Drawings should be submitted for review as follows: General Arrangement within 2 weeks after award of contract
2 Details marked thus (*) will be decided and intimated by the bidder based on driven equipment characteristics
3 Data marked thus (#) will be intimated to vendor after Placement of order. 4 Data marked thus (^) will be decided and intimated by the bidder.
5 VVVFD driven motors shall be inverter duty. These motors & VVVFD combinations should be certified as a combination for Zone-2, Gas group IIA/IIB, T4 application.
6 The bearings shall be sealed for life and having life of >20000hrs. The bearings shall have C3 clearance.
7 Motor terminal box shall be suitable for internal earthing using 4th core of the incoming power cable.
8 Motors shall have earthing terminals for internal as well as external earthing.
9 Cable shall be 4C, Al/Cu conductor, PVC insulated, Extruded FRLS PVC inner & outer sheathed, Armoured cable.
10 FRP Canopy shall be provided for all motors.
11 Starting current shall not exceed 7.2 times of Motor full load current (max.) (Inclusive
of IS/IEC tolerance).
12 The winding overhang shall be epoxy coated.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 35 of 118
SPECIFICATION NO.
TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A1 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 5 OF 5
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
.R4
13 All constituent of the motor shall be suitable for highly corrosive, salt laden coastal
environment. Special focus shall be on windings, insulators, terminals, hardware
(including washers) and space heaters.
14 The paint shall be: One coat of inorganic zinc silicate primer with an average dry
film thickness (DFT) of 75 microns after initial surface preparation. One coat of
high build MIO epoxy with a minimum dry film thickness of 125 microns. One coat
of polyurethane finish with minimum dry film thickness of 40 microns.
15 Terminal box for space heater shall be independent of motor terminal box.
16 All items shall meet the requirements as specified in IS 5571 & 5572 alongwith
IS/IEC 60079.
17 In case aluminium housing is provided, it shall be of copper free aluminium.
18 IECEx alongwith ATEX certified items OR BIS licenced items conforming to IS/IEC
– 60079-1 are acceptable. The motors shall be PESO approved. All the hazardous
equipment shall be certified for use in Zone-2. Applicable statutory approval
certificates shall be submitted along with bid.
19 The VVVFD driven motors shall also be provided with temperature detector/PTC
Thermistors based protection to ensure that the surface temperature does not
exceed temperature class. The terminals, clearance and enclosure shall be
suitable for VVVFD application. Separate terminal box shall be provided for
thermistor termination.
20 The cable route length between VVVFD and motor shall be ~400m. Hence, the cable, filter/reactor/choke, terminal and other related components shall be suitably selected to avoid impact of dv/dt & df/dt and any resulting travelling wave.
21 Motor data-sheets shall be filled & submitted for each application/equipment.
22 The fan & cowl shall be of non-sparking, non-corrosive and anti-static material.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 36 of 118
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A2 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 1 OF 3
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
. R
4
1. INDUCTION MOTORS – THREE PHASE
IS-325 BS-4999 IEC-60034
2. SPECIFICATION FOR THREE
PHASE INDUCTION MOTORS WITH TYPE OF PROTECTION ‘N’ (NON SPARKING FAN TYPE)
IS-9628
3. SPECIFICATION FOR
CONSTRUCTION & TESTING OF ELECTRICAL APPARATUS WITH TYPE OF PROTECTION ‘E’ (INCREASED SAFETY MOTORS)
IS/IEC 60079-7
4. FLAMEPROOF ENCLOSURES OF
ELECTRICAL APPARATUS IS/IEC 60079-1
5. MEASUREMENT AND
EVALUATION OF VIBRATION OF ROTATING ELECTRICAL MACHINES
IS-12075 BS-4999-142IEC-60034-9
7. DEGREE OF PROTECTION
PROVIDED BY ENCLOSURE FOR ROTATING ELECTRICAL MACHINERY
IS-4691 BS-4999-150 IEC-60034-5
8. CLASSIFICATION OF
HAZARDOUS AREAS FOR ELECTRICAL INSTALLATION
IS-5572 IEC-79
9. DESIGNATION FOR TYPES OF
CONSTRUCTION AND MOUNTING ARRANGEMENT OF ROTATING ELECTRICAL MACHINES
IS-2253 IEC-60034-7
10. ROTATING ELECTRICAL
MACHINES : TERMINAL MARKINGS AND DIRECTION OF ROTATION
IS/IEC 60034-8
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 37 of 118
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A2 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 2 OF 3
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
. R
4
11. DESIGNATION OF METHODS OF COOLING FOR ROTATING ELECTRICAL MACHINES
IS-6362 BS-4999-106 IEC-60034-6
12. GUIDE FOR TESTING THREE
PHASE INDUCTION MOTORS IS-4029
13. DIMENSIONS OF SLIDE RAILS
FOR ELECTRIC MOTORS IS-2968
14. GENERAL REQUIREMENT FOR
ELECTRICAL APPARATUS FOR EXPLOSIVE GAS ATMOSPHERES
IS/IEC 60079-0
15. TYPE OF DUTY AND CLASSES
OF RATING ASSIGNED TO ROTATING ELECTRICAL MACHINES
IS-12824
16. INDUCTION MOTORS- ENERGY EFFICIENT, THREE PHASE, SQUIRREL CAGE- SPECIFICATION
IS-12615
17. ROTATING ELECTRICAL MACHINES
IS-4722
18. GUIDE FOR TESTING INSULATION RESISTANCE OF ROTATING MACHINES
IS-7816
19. GUIDE FOR SELECTION AND INSTALLATION OF ELECTRICAL EQUIPMENT FOR HAZARDOUS AREAS (OTHER THAN MINES)
IS-5571
20. GUIDANCE FOR THE DESIGN
AND PERFORMANCE OF A.C. MOTORS SPECIFICALLY DESIGNED FOR CONVERTER SUPPLY
IEC 60034-25
21.
PERMISSIBLE LIMITS OF NOISE LEVEL FOR ROTATING ELECTRICAL MACHINES
IS-12065
BSEN 60034-9
IEC 60034-9
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 38 of 118
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - A2 TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS AREA SHEET 3 OF 3
REV. NO. PPD. BY BY JOB NO. CLIENT: BHARAT PETROLEUM CORPORATION LIMITED
DATE CKD. BY BSY REV. BY DATE 13-04-2012 6758A PROJECT: BLENDING UNIT
PROJECT AT URAN LPG PLANT
TCE FORM 330 R3
ISS
UE
NO
. R
4
19. CAGE INDUCTION MOTORS WHEN FED FROM CONVERTERS – APPLICATION GUIDE
IEC-34-17
20.
ADJUSTABLE SPEED ELECTRICAL POWER DRIVE SYSTEM- EMC REQUIREMENTS AND SPECIFIC TEST METHODS.
BS-EN-61800
IEC-61800
21.
ELECTRICAL INSTALLATIONS DESIGN, SELECTION AND ERECTION
60079-14
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 39 of 118
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - B TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS
AREA SHEET 1 OF 2
ENQUIRY /SPECIFICATION NO.
SR.NO. ITEM BIDDER
NOTE TO BIDDER
1. ITEMS WHICH DEVIATE FROM THE SPECIFICATION SHOULD BE MARKED SIGNATURE
WITHIN ASTERISK(*) (DETAILS TO BE GIVEN IN SCHEDULE OF DEVIATIONS) OF BIDDER 2. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A COPY SHALL
BE ENCLOSED WITH EACH COPY OF THE BID. DATE
TCE FORM 294 R3
ISS
UE
NO
.R4
1.0 Application/Designation 2.0 Manufacturer 3.0 Type of construction 4.0 Applicable standards 5.0 Rated a) Output kW b) Speed RPM 6.1 Type of Duty (CI.10.2 of IS 325 OR
CL-9.3 OF IS 4722)
6.2 Duty Designation (CI.10.3 OF IS 325 OR CL-9.3 OF IS-4722)
7.0 Supply conditions a) 1) Rated voltage V 2) No. of phases 3) Frequency Hz b) Allowable Variations in 1) Voltage % 2) Frequency % 3) Combined % c) Permissible Unbalance in Supply
Voltage %
8.0 Current a) Full Load Amps b) Starting % FL c) Thermal Current Limit Itn d) Dynamic Current Limit Idyn 9.0 Full Load Efficiency % 10.0 Full Load Power Factor 11.0 Method of Starting 12.0 Torque a) Starting % Flt
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 40 of 118
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION D
DATA SHEET - B TCE-M4-203-51 INDUCTION MOTORS FOR HAZARDOUS
AREA SHEET 2 OF 2
ENQUIRY /SPECIFICATION NO.
SR.NO. ITEM BIDDER
NOTE TO BIDDER
1. ITEMS WHICH DEVIATE FROM THE SPECIFICATION SHOULD BE MARKED SIGNATURE
WITHIN ASTERISK(*) (DETAILS TO BE GIVEN IN SCHEDULE OF DEVIATIONS) OF BIDDER 2. THIS DATA SHEET SHALL BE FILLED UP COMPLETELY AND A COPY SHALL
BE ENCLOSED WITH EACH COPY OF THE BID. DATE
TCE FORM 294 R3
ISS
UE
NO
.R4
b) Maximum % Flt 13.0 Class of Insulation 14.0 a) Ref. Ambient temp. 0 C b) Temp. rise by res. Method 0 C 15.0 Type of Enclosure Ex'd'/Ex'e'/Ex'n' 16.0 Degree of Protection(IS 4691 or
equivalent)
17.0 Suitable for Outdoor Operation Yes/No 18.0 Normal winding connection Star/Delta 19.0 Type & No. of terminals brought out 20.0 Winding Suitable for 24V Winding
heating Yes/No
21.0 Shaft Orientation 22.0 Dimensional Dwg. Enclosed Yes/No 23.0 CMRS(Dhanbad) certification
Enclosed Yes/No
24.0 Temperature Class T1/T2/T3/T4/T5/T6 25.0 Time tE for Increased safety motors Secs 26.0 Suitability for hazardous dust Yes/No 27.0 Flameproof Cable gland provided ? Yes/No a) If Yes, suitable upto what size of
cable 3Cx mm2
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 41 of 118
TCE FORM NO. 329R5
SPEC.NO. TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE-M4-203-51
INDUCTION MOTORS FOR HAZARDOUS AREA (GENERAL PURPOSE)
SHEET OF 1 OF 4
1
ISSUE
R4
TITLE
DATA SHEET - C
DATA TO BE FURNISHED BY THE VENDOR AFTER THE AWARD OF CONTRACT
1. Type and Frame Size :
2. Starting Time :
2.1 With 100% voltage at terminals
2.2 With 85% voltage at terminals
2.3 With 80% voltage at terminals
3. Safe stall time at 100% rated voltage and under hot condition.
4. Time tE for Increased Safety Motors.
5. Type and size of cable for which flameproof cable gland is provided in the terminal box:
6. Type of bearings and expected life.
7. Total weight of motor (kg)
8. Motor GD2 :
9. Motor outline dimension drawing (Number of copies as per distribution schedule)
10. Type and routine test certificates (Number of copies as per distribution schedule)
11. CMRS certification copy.
12. DRAWINGS
12.1 Vendor shall submit drawings within the time stipulated in Purchase Order for review by Engineer.
12.2 Vendor shall allow minimum 4 weeks for approval of drawings by Engineer while working out the manufacturing schedule.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 42 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A1 - VARIABLE SPEED AC DRIVES (GENERAL REQUIREMENTS) SHEET 1 OF 2
SL. NO. ITEM UNIT
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
GENERAL REQUIREMENT
1.0 Type of Drive Inverter (IGBT) controlled AC drives.
1.1 Application Butane Preheater Fan
1.2 Type of duty (cl. 3.4) Class II
1.3 Quadrants of operation I
2.0 Quantity As per respective package
3.0 Power supply 415 V, 3ph, N,50Hz
4.0 Variation voltage 415 V + 10%
5.0 Variation in Frequency 50 Hz + 5%
6.0 Combined voltage and frequency variation
10%
7.0 Environmental Conditions Coastal Mumbai
7.1 Location Indoor
a) Whether in air conditioned room No
b) If No:
7.2 Average ambient temperature 0 C 45
7.3 Design ambient temperature 0 C 50
7.4 Relative humidity % 85
7.5 Vibration As per IEC/EN 60068-2-6
8.0 Type of cooling for drive panel Natural air / Fan cooled
If water cooled, is DM water required Not Applicable
If yes, quantity of DM water ------ litres/minute
9.0 Cable
a) Size and type Later, Al conductor, PVC insulated, extruded FRLS PVC inner & outer sheath, armoured, 1100V grade
b) Entry Bottom
10.0 Dimensions Bidder to decide
11.0 Types of Protection
11.1 Instantaneous over current Yes
11.2 Motor overload protection Yes
11.3 Over voltage / under voltage Yes
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 43 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A1 - VARIABLE SPEED AC DRIVES (GENERAL REQUIREMENTS) SHEET 2 OF 2
SL. NO. ITEM UNIT
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
11.4 Momentary power loss Yes
11.5 Stall prevention Yes
11.6 Ground fault Yes
11.7 Inverter Overload Yes
11.8 Open Phase Yes
11.9 Fuse protection Yes
11.10 Fin Overheat Yes
12.0 Control characteristics for both AC/DC
a) Control Method IGBT with PWM technique
b) Freq. control range Bidder to decide and furnish
c) Accelerate/decelerate time Bidder to decide and furnish
13.0 Harmonics Limitations
a) Voltage Harmonics Load side and source side
It shall be as per IEEE- 519 guidelines and Bidder to indicate the figure of the drive offered (for PCC definition, harmonics on input side of drive shall be considered, even though PCC definition is normally not applied to standalone drive)
b) Current Harmonics on Source side
14.0 Controls on Drive Panel
a) Start / Stop YES ( However it shall have facility to block the start )
b) Speed Raiser / Lower YES ( However it shall have facility to block the same by software programming)
c) Auto / Manual Yes
d) Local / Remote Yes
e) DOL by-pass Yes (Coordinate with Fan motor manufacturer for suitability of the starting on DOL)
f) Emergency Stop Yes
g) Any other Stop from DCS, start Permissive.
Communication Protocol RS-485.
Feedback signals to DCS- Motor Running, stop, O\L Trip, other.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 44 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A2 VARIABLE SPEED AC DRIVES
SHEET 1 OF 6
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
INVERTER CONTROLLED AC DRIVES
1.0 a) Starting/rated torque Butane Preheater Fan Bidder to decide
b) Type of converters IGBT based PWM
c) Inverter capacity at specified pf Bidder to decide
d) Rated Current Bidder to decide
e) Load power factor 0.8
f) Max. continuous current Same as rated current
g) Rated voltage with number of phases
415V, 3 phase
h) Rated frequency 50Hz
i) Converter Bridge Full wave IGBT controlled (Bidder to take necessary measures to limit the harmonics as per IEEE 519 guidelines)
j) Single Quadrant/Two quadrant/ Four Quadrant
Single Quadrant
2.0 Control Characteristics
2.1 Speed Control
a) Rated speed 1500 rpm. Shall be adjustable from 50 to 100%
b) Speed ratio -
c) Constant torque/constant power Fan application
d) Speed accuracy +/-0.1%
e) Closed loop/open loop Closed loop (based on Butane temperature feedback)
f) If tachogenerator used (for
closed loop)
No
g) Accel./Deccel. Time Bidder to decide and furnish
h) Type of tacho-generator Not applicable
- If analogue, then reference signal mA/mV
j) Is remote operation required Yes
- If yes, is it through Stop from VVVFD panel. Start & Stop command from remote(LPBS near motor)
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 45 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A2 VARIABLE SPEED AC DRIVES
SHEET 2 OF 6
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
k) Type of control
3.0 Braking Not Applicable
a) Type of braking
b) Braking Torque
4.0 Miscellaneous
Soft-start Yes
Flying restart Yes
Auto restart No
Kinetic Buffering Bidder to decide
5.0 Indication on Drive Panel (minimum)
a) Motor running Yes
b) Motor stopped / trip Yes
c) AC mains ‘ON’ Yes
d) System Ready to start Yes
e) VSD system fault Yes
6.0 Metering
Digital Display of the following Minimum parameters on the Drive Panels:-
a) Input AC Voltage Yes
b) Input AC Frequency Yes
c) Input AC Current Yes
d) Output Voltage Yes
e) Output Current VSD/Bypass Yes
f) Output Frequency Yes
g) Motor speed Yes
Necessary transducers shall be
Provided with 4-20mA output for
indicating motor speed & current
in DCS
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 46 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A2 VARIABLE SPEED AC DRIVES
SHEET 3 OF 6
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
NOTES:
1. VVVFD panel will include protections for Butane Preheater Fan motor & VVVFD bypass DOL.
2. Panel shall have stop command provision.
3. The advanced control panel (withdrawable programming/monitoring unit) shall be provided. Also, the VVVFD shall be suitable for interface with automation system based on Modbus TCP/IP. Any related hardware & software to enable this shall be included.
4. VVVFD is located in safe area. VVVFD is being applied for control of hazardous area motors for Butane Preheater Fans. Accordingly, the VVVFD should have been type tested along with the motor being offered by the Butane Preheater Fan manufacturer. The VVVFD shall meet the requirements of IS 5571 for control of hazardous area equipment. VVVFD-Motor combination shall have PESO approval and CMRS/ATEX/IECEx certification. Also, type test certificates/heat run test shall be submitted with the offer.
5. All items shall meet the requirements as specified in IS 5571 & 5572 alongwith IS/IEC 60079.
6. IECEx alongwith ATEX certified items OR BIS licenced items conforming to IS/IEC – 60079-1 are acceptable for hazardous area. All the items used in hazardous area shall be PESO approved. All the hazardous equipment shall be certified for use in Zone-1.
7. The project site has salt laden corrosive coastal environment and very high level of humidity (located adjacent to a reservoir). Accordingly all the electronics and insulation and space heater shall be applied/selected.
8. Enclosure shall be of shade RAL 7035. Paint & hardware shall be suitable for coastal area.
9. Butane Preheater Fan are Inverter (VVVFD) driven. The motors offered should have been tested/certified for use with the selected VVVFD for Zone-2 application. Also, the motors shall be provided with thermistor based protection to ensure that the surface temperature is limited. The terminals, clearance and enclosure shall be suitable for VVVFD application.
10. Necessary interface modules/relays necessary to trip the motor based on Thermistor sensed overload shall be provided.
11. Filters/chokes as required to feed motor located at a distance of ~400m shall be provided.
12. All motor feeders shall be Type-II co-ordinated
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 47 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A2 VARIABLE SPEED AC DRIVES
SHEET 4 OF 6
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
13. Essential & Recommended spares with quantity & their Unit Prices shall be furnished by
the bidder in their offer. 20% of the actual installed quantity of each type & rating of the following items:
A) Power Fuse (HRC) B) Control Fuse (HRC) C) Semiconductor Fuse D) Push Button unit E) Indicating lamps (each colour) F) Thermistor relay G) Door keys H) Control Terminal Blocks/connectors
14. Price quoted shall be inclusive of the Commissioning spares. 15. The panel shall be extensible on both sides. Cable entry shall be bottom.
16. The bus bars in all panels shall be Aluminium, 50kA for 1sec. Current density for
busbars shall be max. 0.8 A/mm². The main busbars (Horizontal as well as vertical) shall have uniform current ratings. Busbars shall be provided with colour coded heat shrunk PVC sleeves.
17. Cable supporting arrangement shall be provided in the Cable chamber/Cable alley.
18. Panel shall have Panel illumination lamp (CFL) and Space heater with adjustable thermostat, MCB.
19. Operating height shall be restricted between 250mm to 1800mm from finished floor level.
20. All indicating lamps shall be of multichip LED type.
21. All Multifunction meters shall be static type with modbus TCP-IP communication protocol to DCS. Ammeters & Voltmeters shall be Analogue type with selector switch.
22. All MCCBs/MPCBs shall be provided with extended rotary handle.
23. At least 20% spare terminals shall be provided in the terminal block. Each terminal shall be suitable for terminating min. 2x2.5sqmm wire.
24. Each Motor feeder shall have ON-OFF-Trip indication, overload reset button & Emergency STOP push button.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 48 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A2 VARIABLE SPEED AC DRIVES
SHEET 5 OF 6
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
25. One Marshalling Terminal Box (MTB) shall be provided in the panel. Number of contacts to be wired upto the MTB and terminal arrangement in MTB shall be as per control schematic diagram. Terminals in MTB shall be arranged in two groups labelled ‘A’ & ‘B’, physically separated from each other. Group ‘A’ shall comprise of terminals for all outgoing potential free contacts from board & Group ‘B’ shall comprise terminals for all incoming commands/interlocks from control room. Separate removal gland plate shall be provided for each MTB.
26. Control supply for Panel space heater, panel illumination lamp & socket shall be 230 V AC through control transformer.
27. Each compartment shall be provided with the door with suitable interlocks such that door cannot be opened unless MCCB is in off position. Also interlock defeat facility shall be provided.
28. Start of motor is envisaged only from Field. However, Motor Stop shall be possible from Field, MCC and DCS.
29. Local push button station shall have Start & Stop push button. Stop push button shall be mushroom head, Red colour, and stayput type.
30. Refer Approved Vendor List enclosed elsewhere in the tender for Make of components.
31. Panel wiring shall be done with HFFR wires of 1100V grade.
32. Phase reversal protection shall be provided.
33. All instrument transformer and control transformer shall be Cast resin type.
34. VVVFD shall be suitable to run motor at a speed low enough for the preheater to achieve performance with minimal energy consumption.
35. The panel shall be fan cooled with redundant fans. Alarm shall be generated in case of insufficient ventilation of the panel.
36. Ventilation shall be through louvers provided with dust pad/filter.
37. Runhour readings shall be generated for each fan.
38. All components shall be rated to take into consideration effects of harmonics being generated.
39. Following tests/checks shall be performed on Drive Panel: A) Drive System Efficiency (including all system constituents such as filters)
@100%, 75% and 50% inverter loading B) Measurement of THD(V & I) @100%, 75% and 50% inverter loading C) Measurement of acoustic noise @100%, 75% and 50% inverter loading D) Temperature Rise test
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 49 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A2 VARIABLE SPEED AC DRIVES
SHEET 6 OF 6
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
E) Dimensional & Visual Checks F) Paint thickness G) IR measurement H) HV Test (min. 2.5kV for 1min.) I) Operational Checks
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 50 of 118
SPECIFICATION NO. TCE.M4-203-71
TATA CONSULTING ENGINEERS LIMITED SECTION: D
DATA SHEET A3 VARIABLE SPEED AC DRIVES
SHEET 1 OF 1
SL. NO. ITEM
REV. NO. P0 JOB NO.
TCE.
6758A
CLIENT: BHARAT PETROLEUM CORPORATION LIMITED PPD. BY BY
CHD. BY BSY PROJECT: BLENDING UNIT PROJECT AT URAN LPG PLANT DATE 13-04-12
TCE FORM NO. 330 R2
NOTE : EQUIPMENT, ASSOCIATED ACCESSORIES, COMPONENTS/PARTS, RAW MATERIAL AND TESTS SHALL IN GENERAL CONFORM TO IS /IEC.
1. Specification for metal clad base materials for printed circuits for use in electronic and telecommunication Equipment
IS:5921
2. Specification of Transformers and Inductors (Power, Audio, Pulse and Switching) for Electronic Equipment
IS:6297
3. Safety code for Semiconductor rectifier equipment
6619
4. Specification for printed wiring Board IS:7405
5. Essential rating & characteristics Semiconductor devices
IS: 3700 IEC:146
6. Basic climate for mechanical durability tests for electronic components
IS:9000
7. Low-voltage switchgear & control gear – General Rules
IS:13947
8. Environmental requirements of semiconductor devices and integrated circuits
IS:6553
9. Ambient temp. of electronic Equipment IS:9676
10. Terminal for electronic equipment IS:4007
11. Busbars and Busbar connections IS:5082 BS:159
12. Code of practice for earthing IS:3043 BS:CP:1013
13. Current transformers IS:2705 BS:3938 IEC:185
14. Potential transformers IS:3156 BS:3941 IEC:185
15. Power transformers IS:2026 BS:171 IEC:75
16. Indicating meters IS:1248 BS:89 IEC:51
17. Semiconductor Converters IEC:146
18. Code of practice for electric wiring installation
IS:732
19. IEEE Recommended practice and requirements for harmonics control in power system.
IEEE-519
20. Adjustable speed electrical drive system IEC-61800
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 51 of 118
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: Write-up
TCE.6758A-300-PP-1551 PIPING MATERIAL SPECIFICATION GRADE : BE57C SHEET : 1 OF 3
SERVICE :- PROPANE, BUTANE AND LPG
P-T
R
ATI
NG
TEMP. ºC -45 -29 CA (mm) :- 1.5
PR. kg/cm2 g 35.32 35.32 FLANGE FACING:- RF, 125 RA
NOM. PIPE SIZE NB 15 20 25 40 50 80 100 150 200 250 300 350
OUTSIDE DIA. mm 21.3 26.7 33.4 48.3 60.3 88.9 114.3 168.3 219.0 273.0 323.9 355.6
THICKNESS MM 3.73 3.91 4.55 5.08 3.91 5.49 6.02 7.11 6.35 6.35 6.35 7.92
NOM. PIPE SIZE NB 400
OUTSIDE DIA. mm 406.4
THICKNESS mm 7.92
LINE JOINT 40 NB & BELOW :- SW COUPLING
50 NB & ABOVE:- BUTT WELDED
ITEM
NOMINAL PIPE
SIZE RANGE NB
MATERIAL SPECIFICATION
DIMENSIONAL
STANDARD REMARKS
PIPES
15 – 40 ASTM A 333 GR. 6 ASME B-36.10 PE, SEAMLESS, SCH 80
50 – 150 ASTM A 333 GR. 6 ASME B-36.10 BE, SEAMLESS, SCH 40
200 – 400 ASTM A 333 GR. 6 ASME B-36.10 BE, SEAMLESS, SCH 20
NIPPLES 15 – 40 ASTM A 333 GR. 6 ASME B-36.10 PBE, SEAMLESS
BW
FI
TTIN
GS ELBOWS (90°/ 45°-
1.5D), CAPS, REDUCERS (ECC. / CONC.), TEES (EQUAL / RED.)
50 – 350 ASTM A 420 GR. WPL 6 ASME B-16.9 BW (THK. TO MATCH PIPE THK.)
SW
FI
TTIN
GS
ELBOWS (90°/ 45°), TEES (EQUAL / RED.), COUPLING (FULL / HALF/RED.)
15 – 40 ASTM A 350 GR LF2 CLASS 1
ASME B-16.11 SW
SWAGE (CONC. / ECC.) 15 – 80 ASTM A 350 GR LF2
CLASS 1 BS-3799 PBE (THK. TO MATCH PIPE THK.)
UNIONS 15 – 40 ASTM A 350 GR LF2 CLASS 1 BS-3799 SW
BRANCH CONNECTION 15 – 350 --- --- REFER BRANCH CONNECTION CHART
FLANGES
15 – 40 ASTM A 350 GR LF2 CLASS 1 ASME B-16.5 SW, 300, RF / 125 AARH
50 – 150 ASTM A 350 GR LF2 CLASS 1 ASME B-16.5 WN, 300, RF / 125 AARH, SCH 40
200 – 400 ASTM A 350 GR LF2 CLASS 1 ASMB B-16.5 WN, 300, RF / 125 AARH, SCH 20
BLIND FLANGES 15 – 400 ASTM A 350 GR LF2 CLASS 1 ASME B-16.5 300, RF / 125 AARH
STUD BOLTS 15 – 400 ASTM A 320 GR.L7 ASME B-18.2
REV. NO. R0 PPD. BY: SS JOB NO. CLIENT: BPCL, Uran ISSUE DATE 30-03-12 CHD. BY: KR TCE. PROJECT: PMC SERVICES FOR R0 REV. BY SS DATE: 30-03-12 6758A BLENDING UNIT AT URAN
TCE FORM NO. 087 R5 FILE NAME: 6758APP1551R0.DOC
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 52 of 118
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION: Write-up
TCE.6758A-300-PP-1551 PIPING MATERIAL SPECIFICATION GRADE : BE57C SHEET : 2 OF 3
ITEM NOMINAL PIPE SIZE RANGE
NB
MATERIAL SPECIFICATION
DIMENSIONAL STANDARD
REMARKS
HEAVY HEX. NUTS 15 – 400 ASTM A 194 GR. 4 ASME B 18.2
GASKETS 15 – 400 SP. WND SS304 + GRAFIL
ASME B 16.20 – ASME B 16.5 4.5MM THK, SPIRAL, 300
THREADED FITTINGS :- CAPS
15 – 40 ASTM A 333 GR. 6 ASME B-16.11 SCREWED
TYPE OF VALVE
SIZE RANGE MATERIAL PR.
RATING TYPE OF ENDS
SPECIFICATION OR
TAG NUMBER REMARKS
NB BODY TRIM ANSI
GLOBE VALVE 15 – 40 A350 GR
LF2 CLASS 1
SS 304 800 SW, 800, B-16.11 G63 DMN. STD :- API-602
Note 1
GLOBE VALVE 50 – 250 ASTM A352 GR. LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH T33 DMN. STD :- BS-1873
GLOBE VALVE 300 – 400 ASTM A352 GR. LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH T33 DMN. STD :- B-16.34,
Note 2
CHECK VALVE 15 – 40 A350 GR
LF2 CLASS 1
SS 304 800 SW, 800, B-16.11 C63 DMN. STD :- API-602
CHECK VALVE 50 – 400 ASTM A352 GR. LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH C33 DMN. STD :- BS-1868
BALL VALVE 15 – 40 A350 GR
LF2 CLASS 1
SS 304 800 SW, 800, B 16.11 B33 DMN. STD :- ISO-
17292, Note 1
TYPE OF SPECIALITY
SIZE RANGE
NB
MATERIAL PR. RATING
ANSI
TYPE OF ENDS
SPECIFICATION OR
TAG NUMBER REMARKS
BODY TRIM & INT
STRAINER - 15 – 40 A350 GR
LF2 CLASS 1
INT: SS304 800 SW SP1–XXX Y-TYPE
STRAINER – 50 – 150 A 350 GR LCB INT: SS304 300 WN, RF SP2–XXX Y – TYPE
STRAINER – 200 – 400 A 350 GR LF2 CL 1 INT: SS304 300 WN, RF SP2–XXX Y – TYPE
NOTES:- 1. With 100 mm pipe piece on each side. 2. With Gear Operator 3.
REV. NO. R0 PPD. BY: SS JOB NO. CLIENT: BPCL, Uran ISSUE DATE 30-03-12 CHD. BY: KR TCE. PROJECT: PMC SERVICES FOR R0 REV. BY SS DATE: 30-03-12 6758A BLENDING UNIT AT URAN
TCE FORM NO. 087 R5 FILE NAME: 6165APP1551R0.DOC
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 53 of 118
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: Write-up
TCE.6758A-300-PP-1551 PIPING MATERIAL SPECIFICATION GRADE :
BE57C SHEET: 3 OF 3
BRANCH CONNECTION CHART
SIZE
BRANCH inch/mm
RUN 15 20 25 40 50 80 100 150 200 250 300 350 400
15 T
20 RT T
25 RT RT T
40 RT RT RT T
50 SL RT RT RT T
80 SL SL SL SL RT T
100 SL SL SL SL RT RT T
150 SL SL SL SL WL RT RT T
200 SL SL SL SL WL WL RT RT T
250 SL SL SL SL WL WL RT RT RT T
300 SL SL SL SL WL WL WL RT RT RT T
350 SL SL SL SL WL WL WL RT RT RT RT T
400 SL SL SL SL WL WL WL RT RT RT RT RT T
LEGEND : T - STRAIGHT TEE RT - REDUCING TEE C - HALF COUPLING TL -THREADOLET SL - SOCKOLET WL - WELDOLET P - PIPE TO PIPE N - NIPOLET
R - REINFORCED
REV. NO. R0 PPD. BY: SS JOB NO. CLIENT: BPCL, Uran ISSUE DATE 30-03-12 CHD. BY: KR TCE. PROJECT: PMC SERVICES FOR R0 REV. BY SS DATE: 30-03-12 6758A BLENDING UNIT AT URAN
FILE NAME: 6758APP1551R0.DOC TCE FORM NO. 088 R3
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 54 of 118
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
TCE.6758A-B-300-002
SECTION : D
PAINTING SPECIFICATION SHEET 1 OF 3
ISSUE R0
1.0 SCOPE
1.1 This specification establishes the minimum requirements for surface preparation, application and inspection of painting for carbon steel pipes, equipment and supports. Painting shall be applied for corrosion protection, service / temperature indication and warning for specific hazards.
1.2 Stainless steel surfaces, both insulated and non-insulated and galvanized steel items shall not be painted. Machined parts of operating equipment and gasket contact surfaces shall also not be painted.
1.3 The CONTRACTOR shall submit a detailed plan for surface preparation and painting for review in specific cases where painting shall be as per “Manufacturer’s Standard”.
2.0 CODES & STANDARDS
IS8629 : Code of practice for protection of iron and steel structures from atmospheric corrosion.
ISO 8501.1/1S: Preparation of steel substrates before application of paints and related products
SSPC : Steel Structure Painting Council – Surface preparation specification
3.0 SURFACE PREPARATION
3.1 Surface preparation of new steel surfaces includes removal of mill scale together with all rust and surface contaminants, such as grease, dirt and all pollutants.
3.2 All weld spatters, rough welds and sharp edges shall be removed or ground smooth prior to blast cleaning.
3.3 All insulated pipes - The surfaces shall be mechanically cleaned to St3 degree. Very thorough cleaning with wire brush shall be done
3.4 All structures
3.4.1 The surfaces shall be blast cleaned to SA 2½ - “Near white blast cleaning” as in ISO 8501.1/1S.
3.4.2 Blast cleaned surfaces shall provide good adhesion for the primers but shall not show excessive roughness. Anchor pattern shall be RZ: 40-70 for zinc silicate primer and RZ: 35-50 for all other primers.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 55 of 118
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
TCE.6758A-B-300-002
SECTION : D
PAINTING SPECIFICATION SHEET 2 OF 3
ISSUE R0
3.4.3 Blast cleaning shall not be executed when the surface temperature is less than 30C above dew point of surrounding air or the relative humidity is above 90%. Compressed air used for blast cleaning shall be free from water, oil or other contaminants.
3.5 Blast cleaning shall be executed using abrasives like steel / malleable iron shots, steel / crushed chilled iron grit or chopped steel wire.
4.0 PAINTING
4.1 All insulated pipes shall be applied with one coat of inert Pigment / Epoxy resin based aromatic / polyurethane as binder-Resin of 50 m DFT.
4.2 All structures shall be applied with primer coat of modified aluminium epoxy mastic of 100 m DFT / Intermediate coat of MIO/Epoxy resin of 75 m DFT followed by final two coats of inert Pigment / Epoxy resin based aliphatic / polyurethane as binder-Resin of 40 m DFT each.
4.3 Care shall be taken to ensure that the quality of prepared surface shall not deteriorate before application of paint.
4.4 Sufficient time, as recommended by the paint manufacturer shall be provided for curing of paint before application of next coat of paint. All painted surfaces shall be cured at ambient temperatures.
4.5 Primer, intermediate and finish coats shall be fully compatible and appropriate paint materials shall be obtained from the same paint manufacturer.
4.6 Any type of paint, crayon or tape shall not be used for colour coding of stainless steel surfaces. Solvents used for cleaning the stainless steel surfaces shall be free of chlorides.
4.7 Piping and equipment shall be painted as per colour code provided by the ENGINEER / OWNER.
4.8 In cases where shop coating has been damaged while handling, damaged and blistered coating shall be removed by blast cleaning wherever possible or by hand or power tool cleaning. Edges of breaks shall be feathered and specified number of primer and finish coats shall be applied.
5.0 INSPECTION AND TESTS
5.1 Visual examination of surface preparation shall be carried out in accordance with ISO 8501.1/1S. Profile checks for prepared surface shall be using “Profilometer” or comparator films.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 56 of 118
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
TCE.6758A-B-300-002
SECTION : D
PAINTING SPECIFICATION SHEET 3 OF 3
ISSUE R0
5.2 DFT check for intermediate and final coating layers shall be carried out and offered for ENGINEER / OWNER’s examination also. Acceptance criteria shall be as per SSPC-PA 2.
5.3 Painted portions shall be checked for porosity and adhesion visually. If the number of pores per square metre exceeds three, entire area shall be blast cleaned and painted again.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 57 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 1 OF 7
ISSUE
R2
1.0 SCOPE
1.1 This specification covers the technical requirements and essential particulars for
the supply, application and finishing of the complete thermal insulation for cold
equipment, piping systems, air-conditioning ducts etc. for temperatures between
ambient and (-) 80oC and also for dual temperatures (both hot and cold) service
with hot temperature above ambient and up to 230oC. Unless specified otherwise
in section C and/or data sheet A, the scope of supply of the CONTRACTOR shall
include, but not be limited to, the following items :
(a) Insulation materials of all types as specified and required
(b) Insulation adhesives, vapour barriers and finishing materials of all types as
specified and required
(c) Auxiliary materials such as binding and lacing wires, wire netting, bands,
screws, pop rivets etc., as specified and required
(d) Angles, clamps, lugs etc. for supporting insulation
(f) Any other material as may be required for making the insulation complete
2.0 CODES AND STANDARDS
2.1 The supply and application of thermal insulation and finishing covered under this
specification shall comply with all currently applicable statutes, regulations and
safety codes in the locality where it is to be applied. The materials and application
shall also conform to the latest editions of the codes and standards listed. Nothing
in this specification shall be construed to relieve the CONTRACTOR of this
responsibility.
2.2 The following are some of the codes and standards relevant to this specification :
IS 737 Wrought Aluminium and Aluminium Alloy Sheet and Strip for
General Engineering Purposes
IS 3144 Mineral Wool Thermal Insulation Materials - Method of Test
IS 14164 Industrial Application and Finishing of Thermal Insulation
Materials at Temperatures above (-) 800C and up to (+) 750
0C
BS 5608 Preformed Rigid Polyurethane (PUR) and Polyisocyanurate
(PIR) Foams for Thermal Insulation of Pipework and Equipment
BS 5970 Thermal Insulation of Pipework and Equipment (in the
Temperature Range (-) 1000C to (+) 870
0C )
3.0 MATERIALS
3.1 GENERAL
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 58 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 2 OF 7
ISSUE
R2
3.1.1 All materials shall be new and fresh, incombustible, fire retardant, rot-proof, non-
hygroscopic, vermin proof, fungus proof, non-injurious to health, chemically
inert, non-corrosive to steel and aluminium (even if soaked in water for extended
periods) and shall be guaranteed to withstand continuously and without
deterioration the minimum and maximum temperatures to which these shall be
subjected to under the specified applications.
3.1.2 The insulation materials and any component of the finished insulation job shall
not react chemically, singly or in combination, with water or moisture to form
substances that are more actively corrosive to applied surface than water or
moisture alone.
3.1.3 In order to protect the workers from the hazards of insulation materials, suitable
protective gadgets shall be provided. Required safety precautions shall be taken
during handling and application of insulation.
3.1.4 The insulation material shall be kept dry at all times during transport, storage and
installation. Decking and covering tarpaulins alone are not adequate for any
length of time and shall not be allowed except in extreme emergencies and only
for short period. Stacking of insulation materials directly on ground shall not be
done. No wet insulation shall be installed. If wet insulation is present, it shall be
removed and replaced with new dry insulation. The insulation may be protected
with plastic film but shall be vented to prevent sweating.
3.2 INSULATION MATERIALS
The insulation material shall be one or more of the following types as specified in
data sheet A.
SL.
NO.
INSULATION MATERIAL STANDARD DENSITY,
Kg/M3
TEMP. RANGE, 0C
MATERIAL
CODE
1. Rigid polyurethane / Polyisocyanurate foam BS 5608 32 (-)80 to 110 PUR/ PIR
3.3 INSULATION ADHESIVES
The insulation adhesive shall be one or more of the following types as specified
in data sheet A.
Material Description Material Code
3.3.1 Hot bitumen of grade 85/25 or 85/40 conforming to IS 702 shall
be uniformly applied at 1.5 Kg/M2 on the surface to be insulated.
A similar layer shall also be applied on the inside surface of the
insulation. This material shall not be used for stainless steel
surfaces.
BIT
3.3.2 MAS 83 with 0.5 mm wet film thickness shall be uniformly
applied at 0.5 lit/M2 by trowelling. MAS 83 shall not be used
with polystyrene as insulation material. MAS 83 can be used
MAS 83
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 59 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 3 OF 7
ISSUE
R2
Material Description Material Code
only between (-) 46 and (+) 149oC.
3.4 VAPOUR BARRIERS
The vapour barrier shall be one or more of the following types as specified in data
sheet A.
Material Description Material Code
3.4.1 MAS 130 with 1.02 mm wet film thickness primer coat at 1.0
lit/M2 and 2.25 mm wet film thickness finish coat at 2.5 lit/M
2
shall be uniformly applied over the insulation by spatula or
trowelling. MAS 130 shall not be used with polystyrene as
insulation material. MAS 130 can be used only between (-) 40
and (+) 60oC.
MAS 130
3.5 FINISHING MATERIALS
The finishing material shall be one or more of the following types as specified in
data sheet A.
Material Description Material Code
3.5.1 Aluminium sheet as per IS 737, designation 31000, condition
H3.
AL1
(a) Insulation outside diameter 150 to 450 mm - sheet
thickness 20 SWG
(b) Insulation outside diameter below 150 mm - sheet
thickness 22 SWG
(c) Equipment - sheet thickness 18 SWG
3.6 AUXILIARY MATERIALS
3.6.1 Binding and Lacing Wires
Binding and lacing wire shall be annealed GS 24 SWG.
3.6.2 Wire Netting
Wire netting shall be with GS 24 SWG wire and 20 mm hexagonal opening.
3.6.3 Bands
(a) For securing insulation material : 24 SWG GS, 20 mm wide
(b) For securing aluminium and GS : 24 SWG anodised
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 60 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 4 OF 7
ISSUE
R2
sheets aluminium or
SS 304, 20 mm wide
3.6.4 Screws
Screws shall be of self-tapping type and shall be of aluminium or stainless steel
for aluminium sheets and GS for GS sheets.
3.6.5 Pop Rivets
Pop rivets shall be of aluminium or stainless steel for aluminium sheets and GS
for GS sheets.
4.0 APPLICATION
4.1 GENERAL
4.1.1 The application of insulation shall be made in a professional manner. The
insulation shall be applied to all surfaces when these are at ambient temperature.
Ample provision shall be made for the maximum possible thermal movement and
the insulation shall be applied in a manner which shall avoid breaking or
telescoping due to alternate periods of contraction and expansion. A single layer
of insulation shall not be more than 75 mm thick.
4.1.2 Insulation shall be applied after all leak tests on equipment and piping are over
and the section of the plant has been specifically released by the PURCHASER
for such work. If insulation has to be applied before the leak test, all welded and
flanged joints shall be left exposed and insulated after satisfactory completion of
the leak test.
4.1.3 All surfaces to be insulated shall be clean and dry before the insulation is applied.
The surfaces shall be cleaned of all foreign material such as scale, dirt, rust and
paint, by the use of steel wire brushes and steel scrapers, where necessary. Where
a surface is not free of paint the CONTRACTOR shall notify the PURCHASER
of the condition for remedial action. The insulation shall be applied after remedial
action, suggested by the PURCHASER, has been taken by the CONTRACTOR.
One coat of primer paint shall be applied and allowed to dry before application of
insulation.
4.1.4 After cleaning and application of one coat of primer paint on the surface to be
insulated, the insulation adhesive shall be applied for fluid operating temperatures
between 200C and (-) 20
0C. Insulation material of required thickness shall be
stuck to the surface with joints staggered. The adjoining sections shall be tightly
pressed together. All the joints shall be sealed with adhesive material. Voids, if
any, shall be packed with suitably cut pieces of insulation material. Vapour
barrier and insulation finish shall be applied as per paras 3.4 and 3.5 or 4.5
respectively.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 61 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 5 OF 7
ISSUE
R2
4.1.5 Where multilayer insulation is provided, insulation adhesive shall be used
between two layers, based on temperature criterion given in para 4.1.4.
4.1.6 If aluminium or GS sheet is specified as finishing material, all joints shall be
sealed with bitumastic paint and made effectively weather and water-proof. For
temperatures between (-) 40 and (+) 120oC, MAS 94 may also be used as sealant.
MAS 94 shall, however, not be used with polystyrene as insulation material. All
flat surfaces shall be adequately sloped to prevent pools of water collecting. The
sheet shall be protected internally with 2 coats of bitumastic paint.
4.1.7 All actions shall be taken to complete the application of finishing on exposed
surfaces covered with insulation before closing the day's work. If this is not
practicable, adequate precautions shall be taken to protect the insulation from
weather, for example by wrapping it with polythene sheet, roofing felt or other
approved material.
4.2 PIPES, PIPE FITTINGS, VALVES AND SPECIALITIES
4.2.1 All vertical pipes shall be provided with suitable insulation supports to prevent
the insulation from collapsing due to its own weight. Any welding required,
shall be carried out by the CONTRCATOR with the prior permission of the
PURCHASER and only under his direct supervision. Where welding is not
permitted, suitable clamped supports shall be used. The insulation shall be
applied starting from bottom up. Mattress type insulation materials shall be
clamped from top.
4.2.2 All pipe fittings, valves and specialities shall be covered with the same type and
thickness of insulation as specified for the adjoining pipe. On pipe fittings,
insulation outside diameter shall be same as the outside diameter of adjacent pipe
insulation. Unless specified otherwise in section C, valves and specialities of 100
mm NB and larger sizes shall be provided with removable box type insulation.
Box shall be fabricated from sheet material specified for adjoining pipes. Pipe
insulation on adjoining flanges shall be stopped at one bolt length plus 25 mm
before flange to permit removal of the bolts and nuts. The insulation shall be
applied after the finish has been applied over insulation on the adjacent piping.
Flanged joints shall also be insulated with removable type of boxes. Arrangement
shall be similar to that for valves.
4.2.3 The sheets shall be installed with the longitudinal lap joints at 450 below the
horizontal for horizontal pipes and the joints sealed with bitumastic paint.
4.2.4 On vertical pipes the sheets shall be applied working from bottom up. Each
section of sheets shall have a minimum overlap of 50 mm longitudinally and
circumferentially. Each circumferential joint shall be made weather-proof by
securing with a band of sheet material and sealing with bitumastic paint.
Longitudinal lap joints shall be fixed with screws or pop rivets at approximately
150 mm centres.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 62 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 6 OF 7
ISSUE
R2
4.2.5 Valves shall be insulated up to and including their bonnet flange.
4.3.1 Weather hoods shall be provided for insulated piping passing through roof and
external walls.
4.3.2 EQUIPMENT
4.3.3 Where the insulation material is in the mattress form, cleats in the form of wire
nails or nuts or angles and flats for supporting the insulation material, shall be
welded to the equipment by others. If wire nails are to be used as insulation
cleats, these shall be bent and secured with the metal fabric of the mattress, after
the insulation has been applied. Where insulation cleats are in the form of M6
and M10 nuts, the CONTRACTOR shall supply and install bolts of suitable
length for fixing the insulation. The insulation applied to equipment shall be
reinforced with wire netting. One course of wire netting shall be applied to the
surface of the equipment and each layer of insulation shall be backed up with
wire netting. All irregularities of the surface shall be filled and levelled over with
insulating cement. All mattress joints shall be butted tightly and the mattresses
shall be secured with 20 mm wide 24 SWG GS bands at 450 mm centres. After
banding, all mattress edges shall be laced tightly.
4.3.4 All equipment, unless specified otherwise, shall have a smooth aluminium or GS
sheet finish as specified in data sheet A, applied in a manner similar to that
specified for piping. For fixing of aluminium or GS sheets, wooden spacer rings
at 1000 mm centres shall be fixed to the equipment by the CONTRACTOR. All
vertical and horizontal sheets shall be overlapped a minimum of 75 mm. The
lapped joints of adjoining sections of sheets shall be secured with screws or pop
rivets. On all equipment above 2500 mm diameter and flat surfaces, the sheet
shall be further secured by circumferential bands at approximately 1000 mm
centres. Each sheet joint shall be sealed with bitumastic paint. The roof sections
shall overlap the side walls to prevent water seepage between insulation and the
equipment wall. Side wall sheets shall be securely banded at intersections of the
side wall and roof sections.
4.3.3 All equipment manholes, hatches, bolted or screwed cover plates, flanged ends
etc. shall have removable box type insulation, with same thickness of insulation
as for adjacent surfaces. Insulation adjoining such equipment openings shall be
tapered towards these openings to permit removal of bolts, screws, heads, covers
or plates with no damage to adjacent surface insulation or cover.
4.3.4 Nozzles and other connections on tanks and other equipment shall be insulated in
the same manner as the pipes.
4.3.5 Pump casing shall be completely insulated with removable type of boxes
fabricated from the specified sheet material. Proper care shall be taken to
maintain continuity of vapour barrier between static and removable portion of
insulation.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 63 of 118
TCE.6758A-E-590-001
TATA CONSULTING ENGINEERS LIMITED SECTION: D SUBSECT D8
INSULATION SPECIFICATION FOR COLD INSULATION
SHEET 7 OF 7
ISSUE
R2
4.3.6 Name plates on equipment shall not be insulated. Proper care shall be taken to
eliminate seepage of moisture from such un-insulated portions into the insulating
material.
4.4 CONTRACTION JOINTS IN INSULATION
Depending on the type of insulation material used and the operating temperature,
contraction joints shall be provided for equipment or pipes to prevent rupturing or
buckling when the cold surface contracts.
5.0 MEASUREMENT
5.1 Measurement of insulation over equipment and piping shall be as per IS 14164.
6.0 MISCELLANEOUS
Approval of the PURCHASER shall be obtained of samples of all materials and
necessary test certificates of approved national laboratories, before despatching
these to site. Insulation shall not be applied until specific release is given by the
PURCHASER.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 64 of 118
TATA CONSULTING ENGINEERS LIMITED SECTION : D8
. DATA SHEET A
TCE.6758A-E-590-001
THERMAL INSULATION FOR COLD SURFACES SHEET : 1 OF 2
(CARBON STEEL EQUIPMENT & PIPING)
1. AMBIENT TEMPERATURE : 45 OC 13.
2. 14.
3. 15.
4. 16.
5. 17.
6. INSULATION MATERIALS 18.
6.1 EQUIPMENT: EP/PUR/PIR/PF/LRG/U150 19.
6.2 PIPING SYSTEMS : EP/PUR/PIR/PF/LRG/ 20.
PSG/U150 21.
6.3 AIR-CONDITIONING DUCT : EP/PUR/ 22.
PIR/PF/LRG/U150 23.
6.4 24.
6.5 25.
7. INSULATION ADHESIVES : BIT/CPRX/ 26.
MAS 83 27.
8. VAPOUR BARRIERS : VB1/ALF/MAS 130 28.
9. FINISHING MATERIALS 29.
9.1 EQUIPMENT : FC/AL1/GS1/MAS 134
9.2 PIPING SYSTEMS:FC/AL1/GS1/MAS 134 30. TEST CERTIFICATES FOR ALL
9.3 AIR-CONDITIONING DUCT : FC/AL1/ MATERIALS REQUIRED : YES/NO
GS1/MAS 134 31.
9.4 32.
9.5 33.
10. INSULATING CEMENT MATERIAL: 34.
SAME AS THE BASIC INSULATION 35.
MATERIAL 36.
11. 37.
12. 38.
NOTES
1.
REV. NO. PPD. BY : BSR JOB NO. CLIENT: BPCL, URAN
DATE CHD. BY : KR TCE. PROJECT: BLENDING PROJECT IN
URAN LPG BOTTLING PLANT REV. BY DATE : 30-03-12 6758A
GE
NE
RA
L
CO
MP
AN
ION
SP
EC
IFIC
AT
ION
S (
NO
TE
-1)
ISS
UE
NO
. R
4
MA
TE
RIA
LS
TE
ST
S A
ND
IN
SP
EC
TIO
N
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 65 of 118
TATA CONSULTING ENGINEERS LIMITED SECTION : D8
DATA SHEET A1
TCE.6758A-E-590-001
THERMAL INSULATION FOR COLD SURFACES SHEET : 2 OF 2
(CARBON STEEL EQUIPMENT & PIPING)
INSULATION THICKNESSES IN mm FOR INSULATION MATERIALS
PUR,PIR AND PF
OPERATING
TEMP. oC AMB.
TO 19 TO
9 TO -1 TO
-11 TO
-21 TO
-31 TO
-41 TO
-51 TO
-61 TO
-71 TO
PIPE SIZE
MmNB 20 10 0 -10 -20 -30 -40 -50 -60 -70 -80
15 20 20 30 40 40 50 65 75 75 100 125
20 20 20 30 40 40 65 65 75 75 100 125
25 20 20 30 40 50 65 75 75 100 100 125
40 20 30 40 50 65 75 75 75 100 100 125
50 20 30 40 50 65 75 75 75 100 125 150
65 30 30 40 65 65 75 75 100 100 125 150
80 30 30 40 65 65 75 75 100 100 125 150
100 30 40 40 65 75 75 100 100 125 125 150
125 40 40 40 65 75 75 100 125 125 150 175
150 40 40 65 65 75 100 100 125 125 150 175
200 AND ABOVE AND
FLAT SURFACES
40 50 75 100 125 150 150 150 175 200 225
NOTES
1. INSULATION THICKNESSES SPECIFIED DO NOT INCLUDE THICKNESS OF FINISHING
MATERIALS SUCH AS CEMENT SAND PLASTER, ALUMINIUM OR GS SHEET, BINDING AND
LACING WIRES, WIRE NETTING AND BANDS ETC.
2. FOR INSULATION THICKNESS FOR TAIL END AIR-CONDITIONING DUCT AND EVAPORATIVE
COOLING SYSTEM ETC. REFER SECTION C OF THE ENQUIRY DOCUMENT.
REV. NO. PPD. BY : BSR JOB NO. CLIENT: BPCL, URAN
DATE CHD. BY : KR TCE. PROJECT: BLENDING PROJECT IN
URAN LPG BOTTLING PLANT REV. BY DATE : 30-03-12 6758A
ISS
UE
NO
. R
4
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 66 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
1
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
1.0 SCOPE 1.1 This specification shall apply to site fabrication of all welded joints in
carbon steel, low alloy steel and stainless steel for LPG Marketing Terminal Project. Site fabrication also covers any fabrication in a shop set-up at site.
1.2 The welded joints include the following:
(a) All butt welding joints of the longitudinal and circumferential type for attachments in piping, castings and forgings of all components
(b) Socket welding and fillet joints
(c) All types of branch welds
(d) Any other joints not specifically covered above
1.3 For welding of materials not covered by this specification, reference shall
be made to specific project requirements covered in other section of enquiry specification.
2.0 CODES AND STANDARDS 2.1 The welding of all piping systems including equipment, welding
consumables, preheating, postweld heat treatment, other auxiliary functions and welding personnel shall comply with all currently applicable statutes, regulations and safety codes in the locality where the systems are to be installed. Nothing in this specification shall be construed to relieve the CONTRACTOR of this responsibility. Specifically, the latest editions of the codes and standards listed in following paragraphs shall apply :
(a) ASME B31.3 - Pressure Piping Code for Process Piping (b) Indian Boiler Regulations (IBR) (c) ASME Boiler and Pressure Vessel Code (BPV Code), Section II
Part C - Material Specifications for Welding Rods, Electrodes and Filler Materials
(d) ASME Boiler and Pressure Vessel Code (BPV Code), Section V -
Non-Destructive Examination (e) ASME Boiler and Pressure Vessel Code (BPV Code), Section IX -
Welding and Brazing Qualifications (f) Standards of the Pipe Fabrication Institute
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 67 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
2
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
(g) BS 2633-Specification for Class I Arc Welding of Ferritic Steel Pipe
work for Carrying Fluids (h) Any other codes and standards specified in Section C of enquiry
specification. 2.2 The codes and standards listed in para 2.1 form an integral part of this
specification. In the event of conflict between this specification and the codes and standards, the more stringent shall govern.
2.3 If no specific requirements are given in this specification, the requirements
of the applicable code shall govern. 3.0 WELDING PROCESSES 3.1 The following welding processes shall be used for shop-fabricated and
field- fabricated piping systems :
(a) Gas Tungsten Arc Welding (GTAW)
(b) Shielded Metal Arc Welding (SMAW) Welding by oxyacetylene process shall not be used. 3.2 GTAW process shall be used for the following :
(a) On butt welds in carbon steels, in sizes 40 mm and smaller in all passes for 300 class and higher systems (in case butt welds are required) and for steam tracers. Also refer Table 1.
(b) On butt welds in alloy steels for the root pass in all sizes (c) On butt welds in stainless steels for the root pass in all sizes 3.3 SMAW process shall be used for the following:
(a) On butt welds in carbon steel, in sizes 50 mm and larger, for the filler passes
(b) On butt welds in low alloy steel for the filler passes in all sizes (c) On butt welds in stainless steel for the filler passes in all sizes 3.4 For carbon steel piping, in sizes 40 mm and smaller, where butt welding is
required, the entire butt welding including root pass may be carried out by SMAW process in 150 class piping systems except for steam tracers.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 68 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
3
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
3.5 For IBR systems, all processes used shall be as approved by the IBR inspector.
3.6 Other welding processes such as submerged arc welding are also
acceptable provided the process is properly qualified and approval obtained from the PURCHASER.
3.7 All butt welds shall be considered as full penetration welds. 3.8 Table 1 gives recommendations for welding procedures to be used for
carbon, low alloy and austenitic stainless steels. Welding from inside of the pipe after back gouging and chipping is not envisaged. However, if the CONTRACTOR proposes to use such a method, a detailed written procedure shall be submitted for the PURCHASER’s approval.
4.0 WELDING CONSUMABLES 4.1 The CONTRACTOR shall provide, at no additional cost, all the welding
consumables such as electrodes, filler wires, oxygen, acetylene, argon etc., in order to complete the welding in all respects. The consumables shall be from reputed and approved manufacturers. All the consumables shall be approved by the PURCHASER.
4.2 The electrodes and filler wires shall be of the class specified in the
welding electrode chart. 4.3 Electrode qualification test records shall be submitted for PURCHASER’s
approval. The CONTRACTOR shall also submit batch test certificates from the electrode manufacturer for physical and chemical tests.
4.4 Electrodes shall be in sealed containers and adequate care shall be taken
for storage, strictly in accordance with the manufacturer’s recommendations.
4.5 Electrodes, which have been removed from the original containers, shall
be kept in ovens as per the manufacturer’s recommendations and, once these are taken out, shall be consumed within the time limits stipulated by the manufacturer. Care shall be taken in handling the electrodes to prevent any damage to the flux covering. Portable ovens shall be used for carrying the electrodes from the main oven to the field.
4.6 The electrodes, filler wires and flux used shall be free from
contaminations such as rust, oil, grease and such foreign matter. 4.7 Low hydrogen electrodes shall be used for weld joints in carbon steel if
the wall thickness exceeds 19 mm, except that non-low hydrogen electrodes shall be permitted for the root pass.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 69 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
4
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
4.8 E 6010 electrodes may be used for root pass of butt welds and for fillet
welds in carbon steel. 4.9 Refer Table 1 for welding specifications and electrodes. 5.0 WELDING QUALIFICATIONS 5.1 Qualification of the welding procedures to be used and the performance of
welders and welding operators shall conform to the requirements of the BPV Code, Section IX. For IBR systems, these shall also meet the requirements of IBR.
5.2 No production welds shall be undertaken until the qualification
requirements are completed to the satisfaction of the PURCHASER. 5.3 When impact testing is required by the code or by the specification, these
requirements shall be met in qualifying welding procedures. 5.4 The CONTRACTOR shall be responsible for qualifying any welding
procedure and welders intended to be used. The CONTRACTOR shall submit the Welding Procedure Specification (WPS) for acceptance by the PURCHASER. After approval by the PURCHASER, the procedure qualification test shall be carried out by the CONTRACTOR, at his own expense, duly witnessed by the PURCHASER. A complete set of test results shall be submitted to the PURCHASER for approval immediately after successful completion of procedure qualification test. All tests as required by the BPV code Section IX or IBR shall be carried out. The WPS shall require re-qualification if any of the essential variables or supplementary variables is altered.
5.5 Welders shall be qualified in accordance with BPV Code, Section IX or
IBR, as applicable. The qualification shall be carried out in the presence of the PURCHASER. Only those welders who are qualified and approved by the PURCHASER shall be used on the job. For IBR systems, approval of the local IBR inspector shall be obtained by the CONTRACTOR.
5.6 Welders shall always keep their identification cards with them and shall
produce them on demand. The CONTRACTOR shall issue the identity cards after the same are duly certified by the PURCHASER. Welder, who is not in possession of the identity card, shall not be allowed to work.
5.7 The CONTRACTOR shall use forms as per BPV code, section IX, form
QW-482, form QW-483 and form QW-484. Other forms are also acceptable subject to approval by the PURCHASER.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 70 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
5
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
5.8 Unless agreed otherwise, the CONTRACTOR shall advise the PURCHASER, in writing, at least three (3) weeks before any welder is employed on the work, the names and qualifications of the proposed welders and welding supervisors. It shall be the CONTRACTOR’s responsibility to ensure that all welders employed by him or his SUB-CONTRACTORS, on any part of the CONTRACT either in the CONTRACTOR’s/his SUB-CONTRACTOR’s works or at site are fully qualified as required by the code. Each welder shall qualify for all types of welds, positions and materials or material combinations he may be called upon to weld.
5.9 Should the PURCHASER require to test or retest any welder, the
CONTRACTOR shall make available, at no extra cost to the PURCHASER, the men, equipment and materials for the tests. The cost of testing the welds shall be borne by the CONTRACTOR.
5.10 Welding supervisors shall have qualifications such as engineering degree
or engineering diploma in welding technology with adequate knowledge of non-destructive testing and a minimum of five (5) years of experience in supervising welding of pipe joints.
5.11 All welding, including the tacking up of all welds shall be carried out by
approved welders. Any weld made by other than an approved welder shall be cut out and re-welded.
5.12 For purposes of identification and to enable tracing full history of each
joint, each welder employed on the work shall be given a designation. The welder’s designation and the date on which the joint was made, shall be stamped on the relevant piping and marked on the relevant drawings also. Copies of the drawings so marked shall be furnished to the PURCHASER for record purposes. For austenitic stainless steels, welder’s designation shall be applied with water-proof paint that is not detrimental to the pipe. Alternatively, record charts may be used.
5.13 For each welder, a record card shall be maintained showing the
procedures for which he is qualified. These cards shall note the production welds, the date of the welding done, the type of defects produced and their frequency. The record shall be reviewed once in a week by the PURCHASER and those welders whose work required a disproportionate amount of repair shall be disqualified from welding. Requalification of welders disqualified more than three (3) times shall be entirely at the discretion of the PURCHASER.
6.0 PREPARATION FOR WELDING 6.1 Surfaces to be welded shall be smooth, uniform and free from fins, tears
and other defects, which would adversely affect the quality of the weld.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 71 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
6
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
All welding faces and adjoining surfaces, for a distance of at least 150 mm from the edge of the welding groove or 12 mm from the toe of the fillet in the case of socket welded or fillet welded joints shall be thoroughly cleaned of rust, scale, paint, oil or grease, both inside and outside.
6.2 Joints for welding, whether socket welding or butt welding shall be as per
the project piping material specifications. 6.3 Butt joints shall be prepared as per ANSI B16.25 unless specified
otherwise. For piping under the purview of IBR, these shall be as per IBR. Any other end preparation which meets the WPS is acceptable.
6.4 Internal misalignment shall be reduced by trimming but such trimming
shall not reduce the finished wall thickness below the required minimum wall thickness. Root opening of the joint shall be within the tolerance limits of the WPS.
6.5 Fillet welds, socket welds and welded - on branch connections shall be as
per ASME B31.3 or in accordance with IBR for IBR systems. 6.6 Reinforcing pads and saddles shall have a good fit with the parts to which
they are attached. A vent hole shall be provided on the side of any pad or saddle to reveal leakage in the weld and to allow venting during welding and heat treatment. Pad or saddle shall be added after the branch weld has undergone examination and necessary repairs.
6.7 The ends shall be prepared by machining, grinding or flame cutting.
Where flame cutting is used, the effect on the mechanical and metallurgical properties of the base metal shall be taken into consideration. Flame cutting of alloy steel pipes is not allowed. However, flame cutting of carbon steel pipes is permitted. Wherever practicable, flame cutting shall be carried out by machine. Machine flame-cut edges shall be substantially as smooth and regular as those produced by edge planing and shall be cleaned free of slag. Manual flame cutting shall be permitted only where machine flame cutting is not practicable and with the approval of the PURCHASER, and such surfaces shall be ground or dressed to a smooth finish as required by the specification and to the satisfaction of the PURCHASER. Slag, scale or oxides shall be removed by grinding to bright metal at least two (2) mm beyond the burnt area.
6.8 Thermal cutting of carbon steel piping shall be performed under the same
conditions of preheating and postweld heat treatment as for the welding of each class of material. However, post-weld heat treatment is not required when :
(a) The heat affected zone produced by thermal cutting is removed by
mechanical means immediately after cutting. However, in any case,
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 72 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
7
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
all remaining slag, scale or oxides shall be removed by grinding to bright metal at least two (2) mm beyond the burnt area, or
(b) Thermal cutting is part of fabrication, manufacturing or erection
sequence leading to a weld end preparation where welding immediately follows.
6.9 On austenitic stainless steels, plasma cutting, machining or grinding
methods may be used for edge preparation. Cut surfaces shall be machined or ground smooth after plasma cutting.
6.10 Before fitting up the weld joint, the profile and dimensions of the weld end
preparation shall be checked by the PURCHASER. If the specified tolerances are exceeded, this shall be corrected (with prior approval) by grinding, machining or any other method acceptable to the PURCHASER.
6.11 Fit-ups shall be examined by the PURCHASER prior to welding the root
pass. 7.0 TECHNIQUE AND WORKMANSHIP 7.1 Components to be welded shall be aligned and spaced as per the
requirements of the code and WPS. Special care is required when GTAW process is employed.
7.2 Alignment and spacing shall be achieved using suitable wires to maintain
the gap. These shall be removed after tack welding. The ends to be welded shall be held using suitable clamps, yokes or other devices which will not damage the surfaces in any manner. It shall be ensured that welding operations do not result in distortions.
7.3 Tack welds at the root joint, for maintaining joint alignment, shall be made
only by qualified welders or welding operators and with filler metal equivalent to that used in the root pass. Tack welds shall be fused with the root pass weld, except that those which have cracked shall be removed. Peening is prohibited on the root and final passes of a weld. The required preheat shall be maintained prior to tack welding.
7.4 No welding shall be carried out if there is any impingement in the weld
area of rain, snow, excessive wind or if the weld area is wet. 7.5 Irrespective of the class of steel, root runs shall be made without
interruption other than for changing the electrodes or to allow the welder to reposition himself. Root runs made in the shop may afterwards be allowed to cool by taking suitable precautions to ensure slow cooling e.g. by wrapping in a dry asbestos blanket. Welds made at site shall not be
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 73 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
8
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
allowed to cool until the thickness of weld metal deposited exceeds one third of the final weld thickness or 10 mm, whichever is greater.
7.6 When welding alloy steels, it is strongly recommended that interruption of
welding be avoided. Where such interruption is unavoidable, either the pre-heat shall be maintained during the interruption or the joint shall be wrapped in dry asbestos blankets to ensure slow cooling. Before recommencing welding, preheat shall be applied again.
7.7 Welded-on bridge pieces and temporary attachments shall preferably be
avoided. Where approved by the PURCHASER, these may be used. Material of these shall be compatible with material with which they are temporarily welded. All such pieces shall be removed after welding of pipe joints and the weld area ground flush. These areas shall be subject to liquid penetrant or magnetic particle examination for high yield strength materials (YS > 3200 kg/cm2) or when the component thickness exceeds 20 mm or for P3 and P4 group materials. These pieces shall be welded by qualified welders and with electrodes compatible with the parent pipe material. The preheating requirements of pipe material shall be applied and maintained during the welding of attachments. These temporary attachments shall be removed by grinding, chipping, sawing or by arc or flame gouging. When arc or flame gouging is used, at least three (3) mm of metal shall be left around the pipe surface which shall be removed by grinding.
7.8 The arc shall be struck only on those parts of parent metal where weld
metal is to be deposited. When inadvertent arc-strikes are made on the base metal surfaces outside the joint groove, the arc-strikes shall be removed by grinding and shall be examined by liquid penetration or magnetic particle examination procedures.
7.9 Oxides shall not be permitted to form during welding or heat treatment or
both, on the internal surfaces of pipes which will not be subsequently cleaned. Inert gas purging is an acceptable method to prevent such oxidation. All joints in materials which contain more than 1¼% chromium shall be purged to assure that less than 1% of oxygen is present on the joint underside before initiation of the welding. The purging operation shall be maintained for a minimum of two (2) passes.
7.10 Argon gas used in GTAW process for shielding and purging shall be at
least 99.95% pure. Purging shall be carried out at a flow rate depending on diameter of pipe until at least five (5) times the volume between dams is displaced. In no case shall the initial purging period be less than 10 minutes. After initial purging, the flow of the backing gas shall be reduced to a point where only a slight positive pressure prevails. Any dams used in purging shall be fully identified and removed after welding and accounted
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 74 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
9
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
for in order to avoid leaving them in the system. The rate of flow for shielding purposes shall be established in the procedure qualification.
7.11 Thorough check shall be exercised to maintain the required inter-pass
temperature. 7.12 All equipment necessary to carry out the welding, for supporting of the
work, for preheating and post weld heating including thermal insulation for retaining the heat and for the protection of the welder shall be provided by the CONTRACTOR at no extra cost. All necessary precautions shall be taken during cutting and welding operations. It shall be ensured that proper ventilation is available in the welding area and adequate protective gear such as goggles, masks, gloves, protection for the ears and body are used at all times. For guidelines refer ANSI standard Z49.1, “Safety in Welding and Cutting”.
7.13 After deposition, each layer of weld metal shall be cleaned with a wire brush to remove all slag, scale and defects, to prepare for the proper deposition of the next layer. The material of wire brush shall be compatible with pipe material. Stainless steel materials shall be cleaned with grinding wheels or stainless steel brushes which have not been used on other materials. Either aluminium oxide or silicon carbide grinding wheels shall be used. Special care shall be taken to secure complete and thorough penetration of the fusion zone into the bottom of the weld. It is recommended that the root run be checked by liquid penetrant or magnetic particle procedures for critical process piping.
7.14 Upon completion of welding, the joints shall be wrapped in dry asbestos
blankets to ensure slow cooling, unless post-weld heat treatment is applied immediately.
7.15 No welding or welded parts shall be painted, plated, galvanised or heat
treated until inspected and approved by the PURCHASER. Welds shall be prepared and ground in such a way that the weld surfaces merge smoothly into the base metal surface.
7.16 Except where necessary to grind flush for non-destructive examination,
reinforcement for butt welds may be provided. The height of such reinforcement shall meet the requirements of the code. The reinforcement shall be crowned at the centre and tapered on each side of the joined members. The exposed surface of the weld shall be ground where required to present a workmanlike appearance and shall be free from depressions below the surface of the joined members. The exposed surface of the butt welds shall be free from undercuts greater than 0.5 mm in depth, overlaps or abrupt ridges or valleys and shall merge smoothly into the pipe surface at the weld toe. However, undercuts shall not encroach on the minimum section thickness.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 75 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
10
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
7.17 Repair of weld metal defects shall meet the requirements of the code. 7.18 Any weld repair shall be subject to the approval of the PURCHASER. 7.19 In the event of several unsuccessful repair attempts or if the
PURCHASER feels that a satisfactory repair is not feasible, the joint shall be completely remade.
7.20 IDENTIFICATION OF WELDS Wherever code symbol stamps are required on carbon steel and ferritic
alloy steel piping they shall be applied directly to the pipe with low stress dotted design metal die stamps or to a small stainless steel plate especially provided for such marks. These plates shall be lightly tack welded to the pipe using electrodes, of diameter three (3) mm or less, of the type specified for the material. Before making the required tack weld, the pipe material in the immediate surrounding area shall be preheated, as required, by electric means or propane or natural gas burners. Cooling shall take place under asbestos insulation in a draft-free area. Stress relieving of these welds is not required. Steel stamping directly on the surface of alloy steel piping with other than low stress die stamps shall not be used.
7.21 SEAL WELDS 7.21.1 Seal welding shall be carried out by qualified welders and in accordance
with approved drawings. 7.21.2 Threaded joints that are to be seal welded shall be made without the use
of thread lubricating compound. Seal weld shall cover all exposed threads.
7.22 WELD ENCROACHMENT AND MINIMUM DISTANCE BETWEEN
WELDS 7.22.1 Welded joints, more specifically longitudinal welds, shall be placed not
closer than 50 mm to opening or branch welds, reinforcements, attachment devices or from supports, etc. In case of deviation, the PURCHASER may specify additional non-destructive examination.
7.22.2 The longitudinal welds of two adjacent pipes or components shall be
staggered by at least 30o. The minimum distance between welds shall be 50 mm or three (3) times the wall thickness, whichever is greater. Longitudinal welds shall not be situated at the bottom of the pipe. Intersection of welds shall be avoided as far as possible. If such welds are present, they shall be subject to suitable Non-Destructive Testing (NDT) at the discretion of the PURCHASER.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 76 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
11
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
8.0 PREHEATING 8.1 Preheating prior to tack welding, welding and thermal cutting shall be used
as a means of crack prevention and improving weld reliability. The general requirements of post-weld heat treatment also apply to preheating.
8.2 Preheating shall be used as per the recommendations of ASME B31.3,
Table 330.1.1. For IBR systems, the requirements of IBR shall govern. Preheating of austenitic stainless steels is not required, except at low ambient temperatures, in which case a minimum preheat temperature of 10oC is recommended. Table 2 gives the requirements of preheating for commonly used materials.
8.3 The preheating zone shall extend 75 mm or a distance equal to four (4)
times the material thickness, whichever is greater, beyond the edge of the weld.
8.4 The preheat temperature shall be measured at least 75 mm away from
the weld preparation. 8.5 Where preheating is specified, welding shall continue without interruption.
In case interruption cannot be avoided, preheating shall be continued for at least thirty (30) minutes after interruption. Also refer para 8.9.
8.6 Oxy-acetylene preheating shall not be applied. 8.7 For preheating, fuel gas/air torches, burner systems (high velocity gas or
oil burners) or electrical heating may be used either locally or in a furnace. For preheating above 250oC, electric heating (resistance or inductive heating) is preferred.
8.8 Approved temperature - indicating crayons, thermocouples or digital
contact pyrometers shall be used to measure preheat and interpass temperatures. A calibration report of the pyrometers and thermocouples shall be available.
8.9 When the preheat temperature is 150oC or higher, the metal shall be
maintained at or above the preheat temperature until the weld is completed.
8.10 The welding of groove welds in low alloy steels of P-3 to P-5 groups with
wall thickness of 19 mm or greater may only be interrupted, provided at least 10 mm of weld metal is deposited, or 25% of the welding groove is filled, whichever is greater. If the welding is interrupted prior to the above, the weld area shall be adequately covered with insulating material to ensure slow cooling. After cooling and before welding is resumed, visual
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 77 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
12
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
examination of the weld shall be performed to assure that no cracks are formed. Required preheat shall be applied before welding is resumed.
9.0 POSTWELD HEAT TREATMENT Post-weld heat treatment shall meet the requirements of para 331 of
ASME B31.3. For IBR systems, post-weld heat treatment shall be as per IBR. Table 3 summarises the post-weld heat treatment requirements for commonly used materials.
9.1 GENERAL REQUIREMENTS 9.1.1 A complete automatic temperature recording shall be made of preheating
and stress relieving operations. Where propane gas burners or electrical resistance coils are employed, a complete temperature record of the preheating and stress relieving operation shall be made by means of a box type potentiometer. Other means of recording temperatures are permissible subject to the PURCHASER’S approval.
9.1.2 Stress relief may be local or full furnace. Local stress relief shall be
performed with electric induction or electric resistance coils. Suitable gas burning equipment using natural gas or propane may be employed.
9.1.3 At no time during a stress relieving/preheating cycle shall any water or liquid cooling medium be employed.
9.1.4 Where members being joined are unequal in thickness, the dimension of
the heavier section shall govern the selection of width of the heated band and the duration of the holding period.
9.1.5 For local stress relief, using electrical methods, a minimum of two (2)
thermocouples tack-welded to the surface and potentiometers shall be used on the pipe under at least four (4) layers of asbestos paper. The hot junctions of the thermocouples shall be located on either side of the joint at least 12 mm from the edge of the joint but no further away than 100 mm. When employing induction heating, at least six (6) turns of induction cable shall be used on each side of the weld. Induction coils shall be wrapped on top of the asbestos paper protecting the thermocouples with the first turn approximately 150 mm from the centre of the weld.
9.1.6 Local stress relief using gas torches or ring burners may be employed.
However, the procedure shall be limited to pipes below 100 mm NPS and shall be approved by the PURCHASER.
9.1.7 The stress relieving temperature shall be maintained for a period of time
proportioned on the basis of one (1) hour per 25 mm of wall thickness of the thickest section at the joint, but in no case less than one (1) hour.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 78 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
13
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
9.1.8 For tubing joints and socket welded joints, pads, bosses, branch welds and couplings, one (1) thermocouple shall be positioned at a minimum distance of two (2) pipe wall thicknesses from the weld.
9.1.9 Piping on both sides of any joint shall be adequately supported throughout
the preheating, welding and stress relieving operations to prevent distortion. When a butt welded joint is to be post-weld heat treated and the piping is cold-sprung, the forces required to position the pipes shall be maintained by external means until the completion of the heat treatment procedure.
9.1.10 All heating and cooling must be performed in still air. 9.1.11 The governing thickness for the post-weld heat treatment shall be the
thicker of the two components joined by welding. For deviations from this requirement for branch welds, fillet welds etc., reference shall be made to the applicable paragraph of ASME B 31.3.
9.1.12 The CONTRACTOR shall submit a detailed written procedure for the post-
weld heat treatment for the approval of the PURCHASER. 9.2 CARBON STEEL 9.2.1 Welded joints in carbon steel piping systems shall be stress relieved,
upon completion of the welding operation, in accordance with Table 3. 9.2.2 When local stress relief is employed, the welded joint shall be heated to a
temperature of not less than 625°C the temperature level shall be maintained between 625°C and 675°C, one (1) hour per 25 mm of wall thickness but in no case less than one (1) hour. The weld area shall then be allowed to cool undisturbed in still air to a temperature not exceeding 315°C. All welded joints in pipe sizes 100 mm and larger, shall be heated by means of electric induction coils or resistance heating. Welded joints in pipes smaller than 100 mm shall be stress relieved by means of electrical resistance coils or suitable propane or natural gas torches only.
9.2.3 Heating and Cooling Carbon steels, after having reached their specific stress relief
temperatures, may be cooled in the furnace or under wraps, i.e., leaving the induction coils or resistance heaters and insulation in place. This means that, at the stress relief temperatures, the power to the furnace or heating coils may be shut off and cooling takes place in the furnace or with all insulation and coils remaining on the pipe. For furnace stress relief, the doors of the furnace may be opened after the power is shut off, at or below 315°C. Thermocouples controlling the temperatures shall remain during the cooling cycle so that excessive cooling, if it occurs, can
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 79 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
14
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
be observed and immediately corrected. The stress relieving coils and insulation shall only be removed after the piping has cooled to below 315°C or if stress relieved in a furnace the pipe may be removed from the furnace and permitted to cool in still air at a temperature not below 10°C.
9.3 ALLOY STEEL 9.3.1 All welds in alloy steel piping shall be stress relieved after the welding
operation in accordance with Table 3. Immediately after welding, the material shall be wrapped in asbestos and allowed to cool.
9.3.2 Local Stress Relief All welded joints in pipes 100 mm size and larger shall be locally stress
relieved by means of electric induction coils or resistance heating. Welded joints in smaller pipe sizes shall be stress relieved by means of electric resistance coils or suitable propane or natural gas torches only.
9.3.3 For full furnace stress relief of a welded assembly, the entire fabricated
section shall be heated uniformly to the temperature specified. The temperature shall be maintained for a period of time proportioned on the basis of one (1) hour per 25 mm of wall thickness of the piece having the greatest wall thickness in the furnace charge, but, in no case, less than one (1) hour.
9.4 AUSTENITIC STAINLESS STEEL Welded joints in austenitic stainless steel piping need not be stress
relieved after welding. 9.5 The rate of heating and cooling during stress relieving operations shall not
exceed 315°C per hour up to a thickness of 50 mm at the weld. 10.0 ELECTRODES 10.1 The specification and size of the electrodes, voltages and amperages,
thickness of beads and number of passes shall be as specified in the approved welding procedure or otherwise agreed in writing. Only basic coated electrodes shall be used, which will deposit weld metal having the same or higher physical properties and similar chemical composition to the members being joined. For each batch of approved brand, certificate showing compliance with the specification shall be submitted to the PURCHASER for review before being released for use. All electrodes shall be purchased in sealed containers and stored properly to prevent deterioration. All low hydrogen electrodes, after baking as per the manufacturer’s recommendations, shall be stored in ovens kept at 80 to 100°C before being used. Recommendations of the electrode
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 80 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
15
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
manufacturer shall be strictly followed. Until the electrodes are taken out for welding, they shall be stored in portable ovens. The electrodes shall not be exposed to open atmosphere.
10.2 For welding of all grades of steel and alloys by the GTAW process, a 2%
thoriated tungsten electrode conforming to SFA-5.12-86 EWTh-2 (AWS-A5.12-80, EWTh-2) classification shall be used.
10.3 All electrodes to be used on alloy and carbon steel shall conform to BPV
Code Section II Part C or any other equivalent code. 10.4 As welding electrodes deteriorate under adverse conditions of storage
leading to dampness in the electrode coating, they shall normally be stored in dehumidified air-conditioned rooms or in hot boxes or ovens in their original sealed containers whose temperatures shall be maintained within specified limits. The condition of electrodes shall be frequently inspected. Electrodes with damage to coating shall not be used. Electrodes shall remain identified until consumed. It is preferable to procure low hydrogen electrodes in hermetically sealed containers and preserve them without damage to the containers.
10.5 The type of electrodes used shall be only those recommended by the
manufacturer for the use in the position in which the welds are to be made. Electrodes which have the areas of flux covering broken away or damaged shall not be used.
10.6 Table 1 gives recommendations on electrodes to be used for carbon, low
alloy and austenitic stainless steels. 11.0 INSPECTION AND TESTING 11.1 The PURCHASER shall have free access to inspect welding or any other
related operations at any time and at any stage of fabrication. 11.2 The PURCHASER may require non-destructive testing of any weld for
reasons other than those given in the specification. The responsibility for the cost of such testing shall be mutually decided between the PURCHASER and the CONTRACTOR.
11.3 The CONTRACTOR shall inform the PURCHASER when the weld
preparation and setting up for welding of various members selected by the PURCHASER is in progress so that the PURCHASER can inspect the assembly before welding starts.
11.4 The responsibilities of the PURCHASER’s representative shall in no way
reduce the CONTRACTOR’s responsibilities to ensure that the work is carried out in accordance with the specification.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 81 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
16
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
11.5 Any examination by non-destructive methods on low alloy steels shall be performed after post-weld heat treatment.
11.6 For a welded branch connection, the examination of and any necessary
repairs shall be completed before any reinforcing pad is added. 12.0 EXAMINATION OF WELDS 12.1 Examination refers to the quality control functions performed by the
CONTRACTOR during fabrication, erection and testing. 12.2 As a minimum, the following shall be examined by visual examination :
(a) Materials and components to ensure that these are as per the specification and are free from defects. If defects are noticed on “free-issue” items, these shall be brought to the notice of the PURCHASER without delay.
(b) Joint preparation and cleanliness (c) Preheating as applicable (d) Fit-up, joint clearance, and internal alignment prior to joining
(e) Variables specified by the welding procedure, including filler
material, position and electrode (f) Condition of the root pass after cleaning - external and where
accessible, internal (g) Slag removal and weld condition between passes (h) Appearance of the finished joint
12.3 Acceptance for the visual examination shall be as per ASME B 31.3 or IBR as applicable.
12.4 Other types of examination shall be as defined in Tables 4 and 5, unless
otherwise mentioned in section C of enquiry specification. For the purpose of examination, fluids are categorised, in accordance with ASME B 31.3, as Category D, Normal Service and Category M and supplemented by other requirements.
13.0 QUALIFICATION AND CERTIFICATION OF NON-DESTRUCTIVE
EXAMINATION PERSONNEL
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 82 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
17
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
13.1 The CONTRACTOR’s examining personnel shall have training and experience commensurate with the needs of the specified examinations. NDT supervisors/ examiners shall be qualified at level II or above.
13.2 The CONTRACTOR shall make available to the PURCHASER copies of
certificates of qualification of the examiners he proposes to use for the PURCHASER’s approval.
14.0 METHODS OF EXAMINATION The methods of examination used, radiographic (RT), liquid penetrant
(PT) or magnetic particle (MT), shall be in accordance BPV Code, Section V.
15.0 ACCEPTANCE STANDARDS 15.1 Levels of acceptance of defects in welds shall be in accordance with
ASME B 31.3. 15.2 For IBR piping, the levels of acceptable defects shall be as per IBR. 16.0 REPAIR WELDING 16.1 All defects in welds requiring repair shall be removed by flame or arc
gouging, grinding, chipping or machining. The major repairs may involve :
(a) Cutting through the weld (b) Cutting out a length of pipe containing the weld, or (c) Removing the weld metal down to the root depending upon the
magnitude of the defects.
16.2 After removing the defect, the welds shall be examined by the same non-destructive testing methods as specified for the original weld and the same acceptance criteria shall hold good.
16.3 All the repair welds shall be made using the same or other specified
welding procedures as those used in making the original welds including preheating and stress relieving if originally required.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 83 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
18
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
TABLE 1
WELDING SPECIFICATION CHART
SL. NO.
BASE MATERIAL P. NO.
WELDING PROCESS FILLER MATERIAL GAS NOTES
ROOT FILLER ROOT FILLER PURGING
SHIELDING
1.0 CARBON STEELS
1.1
SIZES 40 mm AND/OR 3 mm THK
1 GTAW GTAW ER 70S2 OR
ER 70S3
ER 70S2 OR
ER 70S3
- - 1
1.2
SIZES 50 mm THK 19 mm
1 SMAW SMAW E 6010 E 6013 - -
1.3
SIZES 50 mm THK 19 mm
1 GTAW SMAW ER 70S2 OR
ER 70S3
ER 7018 OR
ER 7016
- - 2
2.0 LOW ALLOY STEELS
2.1
1¼% Cr ½% Mo
4 GTAW SMAW ER 80S B2
E8016/E 8018-B2
- -
2.2
2¼% Cr 1% Mo
5 GTAW SMAW ER90S B3
E9015/ E 9016/ E 9018-B3
ARGON ARGON 3 to 8
3.0 AUSTENITIC STAINLESS STEELS
3.1
TYPE 304 (304L)
8 GTAW GTAW for THK 4.5 mm
ER 308 (ER 308L)
ER 308 (ER 308L)
ARGON ARGON 3 to 8
SMAW for THK > 4.5mm
E 308 (E 308L)
3.2
TYPE 316 (316L)
8 GTAW GTAW for THK 4.5 mm
ER 316 (ER316L)
ER 316 (ER 316L)
ARGON ARGON 3 to 8
SMAW for THK > 4.5mm
E 316 (E 316L)
3.3 TYPE 321 8 GTAW GTAW for
THK 4.5mm
ER 321/ ER 347
ER321/ ER 347
ARGON ARGON 3 to 8
SMAW for THK > 4.5mm
E321/E347
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 84 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
19
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
TABLE 1 (CONTD.)
SL. NO.
BASE MATERIAL
P. NO.
WELDING PROCESS
FILLER MATERIAL GAS NOTES
ROOT FILLER ROOT FILLER PURGING SHIELDING 4.0 STAINLESS
STEEL TO CARBON STEEL
4.1 SS 304/321 8 to 1
GTAW/ SMAW
SMAW ER309
ER309
- -
4.2 SS 316 8 to 1
ER310Mo E310Mo - -
NOTES 1. For 300 and higher class systems. For 150 class systems, refer para 3.4. For
fillet welds SMAW process with E6013 can be used. 2. Low hydrogen electrodes shall also be used for critical systems such as
chlorine, hydrogen, caustic and similar toxic inflammable fluids and also whenever the wall thickness exceed 19 mm.
3. The argon shielding gas flow rate shall not be less than 0.34 m3/hr. 4. Nitrogen can be used as an alternative to argon for purging purpose only. 5. For fillet welds, electrode can be used instead of filler wire. 6. For GTAW process, electrode shall be 2% thoriated tungsten. 7. Initial purging prior to welding process shall be a minimum of five (5) times the
volume between dams or ten minutes minimum whichever is higher. When welding commences, the purge gas flow shall ensure that the gas pressure is only marginally higher than atmospheric pressure to ensure no roof concavity.
8. Back purging using argon/nitrogen shall be maintained for a minimum of two
passes. 9. Electrodes / filler wires manufactured by reputed firms duly approved by the
PURCHSER shall only be used. 10. Electrodes shall have at least the same or higher physical properties and
similar chemical composition to the members being joined. 11. Read the table in conjunction with para 3.0
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 85 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
20
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
TABLE - 2
PREHEAT REQUIREMENTS
SL. NO.
BASE MATERIAL P. NO. NOMINAL WALL
THICKNESS , mm
SPECIFIED MINIMUM TENSILE
STRENGTH, MPa
RECOMMENDED MINIMUM PREHEAT
TEMPERATURE, ° C
1. CARBON STEEL 1 25 490 10
2. LOW ALLOY STEEL - 1¼% Cr ½% Mo
4 ALL ALL 149
3. LOW ALLOY STEEL - 2¼%Cr 1% Mo
5 ALL ALL 177
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 86 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
21
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
TABLE 3
POSTWELD HEAT TREATMENT REQUIREMENTS
SL. NO
.
BASE MATERIAL P. NO.
NOMINAL WALL
THICKNESS,
mm
SPECIFIED MINIMUM TENSILE
STRENGTH, MPA
METAL TEMPERATURE
RANGE ° C
BRINELL
HARDNESS
MAX.
1. CARBON STEEL 1 19 ALL NONE -
2. CARBON STEEL 1 > 19 ALL 625-675 -
3. LOW ALLOY STEEL 1¼% Cr ½% Mo
4 13 490 NONE -
4. LOW ALLOY STEEL 1¼% Cr ½% Mo
4 > 13 ALL 704 to 746 225
5. LOW ALLOY STEEL 2¼% Cr ½% Mo
5 13 490 NONE -
6. LOW ALLOY STEEL 2¼% Cr ½% Mo
5 > 13 ALL 704 to 760 241
7. AUSTENITIC STAINLESS STEELS
8, 9 ALL ALL NONE -
NOTES 1. In IBR systems, in carbon steels, postweld heat treatment is also required,
when the carbon percentage exceeds 0.25%, at the temperature range of 600 +/- 20°C.
2. All low alloy steel welds in IBR systems shall be postweld heat treated at the
temperature range of 620 to 660° C for 1 1/4% Cr 1/2% Mo steels and at a range of 660 to 750°C for 2 1/4% Cr 1% Mo steels.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 87 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
22
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
TABLE 4 WELD EXAMINATION (OTHER THAN ‘IBR’)
SL. NO.
FLUID SERVICE CATEGORY AS PER
ASME B 31.3
TYPE OF EXAMINATION
EXTENT OF EXAMINATION
GIRTH BUTT WELD
SOCKET AND FILLET WELDS
BRANCH WELDS (FABRI-CATED)
FABRICATED MITRES /
REDUCERS
ATTACH MENT
WELDS
1.0 CATEGORY D VISUAL 100% 100% 100% 100% 100%
LT/MT - - 5% - -
RT (ABOVE GROUND)
10% - - 10% -
RT (UNDER GROUND)
100% - - - -
2.0 NORMAL VISUAL 100% 100% 100% 100% 100%
RT 10% - - 10% -
LT/MT - 10% 10% - 10%
3.1 CATEGORY M & PIPING GRADE – BE57C (Propane / Butane / LPG SERVICE)
VISUAL
RT
LT/MT
100%
100%
100% (FOR ROOT RUN)
100%
-
100%
100%
-
100%
100%
100%
100% (FOR ROOT RUN)
100%
-
100%
3.2 HIGH PRESSURE (ASME 600 CLASS AND HIGHER)
3.3 CRITICAL SERVICES SUCH AS CHLORINE, CAUSTIC, HYDROGEN AND OTHERS AS DEFINED IN SECTION-C
3.4 LOW TEMPERATURE [<(-)80°C]
3.5 SEVERELY CYCLIC AS PER ASME B 31.3
NOTES Fluid services are categorised as follows (as per ASME B 31.3) 1. Category D : Fluid is non-flammable, non-toxic, and not damaging to human
tissues, and design pressure is 1.035 M Pag(150 psig) and design temperature is 186°C and not below (-) 20°C.
2. Category Normal : Not Category D, not category M, not “high pressure” as per ASME B31.3 and not subject to severe cycling as defined in ASME B 31.3.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 88 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
23
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
3. Category M : Toxic Services which can damage human tissue after a single exposure even if prompt remedial measures are taken.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 89 of 118
SPEC. NO.
TATA CONSULTING ENGINEERS LIMITED SECTION: D TCE.6758A-B-300-001
WELDING SPECIFICATION FOR EQUIPMENT AND PIPING SYSTEM
SHEET OF 24 OF 4
24
ISSUE R0
TITLE
TCE FORM NO.329 R3 FILE NAME: 6165APP1568R0.DOC
TABLE 5
WELD EXAMINATION (IBR PIPING)
SL. NO.
ANSI PRESSURE CLASS
NOM PIPE SIZE, mm
TYPE OF EXAMINATION
EXTENT OF EXAMINATION
GIRTH BUTT WELD
SOCKET AND
FILLET WELDS
BRANCH WELDS
FABRICATED
ATTACHMENT WELDS
1. ALL ALL VISUAL 100% 100% 100% 100%
2. 150 AND 300
100 RT 10% - - -
50 to 80 RT 2% - 2% -
40 LT/MT - 2% - -
3. 600 AND HIGHER
50 RT 100% - - -
40 LT/MT NOTE 2
100% 100% 10%
NOTES
1. The extent of examination shown above is minimum and any additional requirement as required by ‘IBR’ shall also be considered.
2. For root runs of butt welds in sizes 50 mm (100%)
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 90 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 1 of 1
REV.NO R1 R2 R3 ISSUE
INITIALS SIGN INITIALS SIGN INITIALS SIGN INITIALS SIGN
PPD.BY CKD.BY R5 APP.BY DATE
TCE FORM 329 R3
SUPPLY AND FABRICATION OF STRUCTURAL STEEL
FILE NAME : M4-405-01(R5).DOC
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 91 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 1 of 11
Issue No.R5
TCE FORM 329 R3
1.0 SCOPE 1.1 This specification covers the general requirements for supply where specified,
fabrication and delivery at site of structural steel. Section C covers the specific requirements for the project. The two parts are complementary and are to be read together for a correct interpretation of the provisions of this specification. Where requirements of the two parts conflict, those of Section C shall govern.
1.2 This specification also covers design of all connections and substituted members,
preparation of all shop fabrication drawings, inspection and shop painting of structures.
2.0. APPLICABLE CODES & SPECIFICATIONS The following specifications, standards and codes are made a part of this
specification. All standards, specifications and codes of practices referred to herein shall be the latest editions including all applicable official amendments and revisions.
In case of discrepancy between this specification and other documents referred to
herein, this specification shall govern. a) Materials i) IS : 808 Dimensions for Hot Rolled Steel sections ii) IS : 814 Covered Electrodes for Manual Metal Arc Welding
of Carbon and Carbon Manganese Steel iii) IS : 1161 Steel Tubes for structural purposes iv) IS : 1239 Mild steel tubes, tubulars and other Wrought steel
fittings Part 1 - Mild steel tubes Part 2 - Mild steel Tubulars and other wrought steel
pipe fittings v) IS : 1363 Hexagon Head Bolts,Screws and Nuts of product ( Parts 1 to 3) Grade C (Size range M5 to M64) vi) IS : 1367 Technical Supply Conditions for Threaded Fasteners (All Parts) vii) IS : 1852 Rolling and Cutting Tolerances for Hot Rolled Steel
Products viii) IS : 1977 Structural Steel (Ordinary Quality)
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 92 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 2 of 11
Issue No.R5
TCE FORM 329 R3
xi) IS : 2062 Steel for General Structural Purposes x) IS : 2074 Ready Mixed Paint, Air drying, Red Oxide Zinc
Chrome and Priming xi) IS : 3502 Steel Chequered Plate xii) IS : 3757 High Strength Structural Bolts • xiii) IS : 5369 General Requirements for Plain Washers and Lock
Washers xiv) IS : 5372 Taper Washers for Channels xv) : 5374 Taper Washer for I Beams xvi) IS : 6610 Heavy Washers for Steel Structures xvii) IS : 8500 Structural Steel-microalloyed (medium and high
strength qualities) b) Codes Of Practice i) IS : 800 Code of Practice for General Construction in Steel ii) IS : 801 Code of practice for use of Cold formed light gauge
steel structural members in general building construction iii) IS : 803 Code of practice for design, fabrication and erection of
vertical mild steel cylindrical welded storage tanks iv) IS : 806 Code of practice for use of steel tubes in general
building construction v) IS : 816 Code of Practice for use of Metal Arc Welding for
General construction in Mild Steel vi) IS : 822 Code of Procedure for Inspection of Welds vii) IS : 1182 Recommended Practice for Radiographic examination of
Fusion - Welded Butt Joints in Steel Plates viii) IS : 1200 Method of Measurement in Building Civil Engineering
Works ix) IS : 1477 Code of Practice for Painting of (Parts 1 & 2) Ferrous
Metals in Buildings
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 93 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 3 of 11
Issue No.R5
TCE FORM 329 R3
x) IS : 2595 Code of Practice for Radiographic Testing xi) IS : 3658 Code of Practice for Liquid Penetrant Flaw Detection xii) IS : 4000 High strength bolts in Steel Structures - Code of Practice xiii) IS : 5334 Code of Practice for Magnetic Particle Flaw Detection
of Welds xiv) IS : 7215 Tolerances for Fabrication of Steel Structures xv) IS : 9595 Recommendations for Metal Arc Welding of Carbon and
Carbon Manganese Steel 3.0 STEEL MATERIALS Steel materials shall comply with the specifications laid down under clause 2.0
and/or as called for on the design drawings. All materials used shall be new, unused and free from defects. Steel conforming to IS:1977 shall be used only for the following : Fe310-0(St 32-0) : for general purposes such as door/ window frames,
grills, steel gates, handrails, fence posts, tee bars and other non-structural use.
Fe410-0(St 42-0) : for structures not subjected to dynamic loading other
than wind loads such as: Platform roofs, foot over bridges, building, factory
sheds etc. Fe410-0(St 42-0) : grade steel shall not be used a) if welding is to be employed for fabrication. b) if site is in severe earthquake zone. c) if plastic theory of design is used. 4.0 USE OF STEEL SUPPLIED BY THE PURCHASER The VENDOR/CONTRACTOR shall use steel supplied by the PURCHASER
judiciously and to the best advantage so as to minimise splicing and wastage. All steel materials remaining after completion of the report, whether in the form of balance pieces or unutilised prime steel, shall be returned to the PURCHASER's stores by the VENDOR/CONTRACTOR at his own cost. An unaccountable
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 94 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 4 of 11
Issue No.R5
TCE FORM 329 R3
wastage upto a maximum of 1% of the fabricated steel will be allowed. This wastage does not include the balance cut lengths/pieces of steel returned to the PURCHASER.
5.0 DRAWINGS PREPARED BY THE OWNER 5.1 Design drawings will be furnished to the VENDOR/CONTRACTOR and all
drawings so furnished shall form a part of this specification. These design drawings prepared by the ENGINEER will show all the, levels,forces on members where shall necessary, size and orientation of each member, location/size of openings, to enable the VENDOR/CONTRACTOR to prepare drawings for fabrication and erection. It shall be clearly understood that these drawings are not intended to show connection details, thickness of members, cuts, notches, bends and such other details.
5.2 The ENGINEER reserves the right to make changes. Revisions to drawings, even
after release for preparation of shop drawings, are very likely to be made to reflect additional data/details received and updated requirements. Revisions to drawings and any new drawings made to include additional work by the VENDOR/CONTRACTOR shall be considered a part of this specification and contract. The PURCHASER shall not entertain IS any extra claims on this account.
5.3 Where the fabrication drawings are to be furnished by the ENGINEER, he will
issue to the VENDOR/CONTRACTOR the required copies of such drawings in the sequence required for the fabrication of the components in the order they will be required to be erected at site. Such drawings will be issued in such numbers as required for the VENDOR/CONTRACTOR to adhere to the project schedule.
5.4 Should the VENDOR/CONTRACTOR during the execution of his work, find
discrepancies in the information furnished by the ENGINEER, he shall refer such discrepancies to the ENGINEER before proceeding with such work.
6.0 DRAWINGS PREPARED BY THE VENDOR/CONTRACTOR 6.1 The VENDOR/CONTRACTOR shall prepare all fabrication and erection drawings
for the entire work. All the drawings for the entire work shall be prepared in metric units. The drawings shall preferably be of one standard size and the details shown there in shall be clear and legible.
6.2 The VENDOR/CONTRACTOR shall not commence detailing unless ENGINEER's
design drawings are officially released for preparation of shop drawings. The VENDOR/CONTRACTOR shall be responsible for the correctness of all fabrication drawings. Fabrication drawings shall be revised by the VENDOR/CONTRACTOR to reflect all revisions in design drawings as and when such revisions are made by the ENGINEER.
6.3 All fabrication drawings shall be submitted to the ENGINEER for approval.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 95 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 5 of 11
Issue No.R5
TCE FORM 329 R3
6.4 No fabrication drawings will be accepted for ENGINEER's approval unless checked and approved by the VENDOR/CONTRACTOR's qualified structural engineer and accompanied by an erection plan showing the location of all pieces detailed. The VENDOR/CONTRACTOR shall ensure that connections are detailed to obtain ease in erection of structures and in making field connections.
6.5 Fabrication shall be started by the VENDOR/ CONTRACTOR only after
ENGINEER's approval of fabrication drawings. Approval by the ENGINEER of any of the drawings shall not relieve the VENDOR/CONTRACTOR from the responsibility for correctness of engineering & design of connections, workmanship, fit of parts, details, material, errors or omissions of any and all work shown thereon. The ENGINEER's approval shall constitute approval of the size of members, dimensions and general arrangement but shall not constitute approval of the connections between members and other details.
6.6 The drawings prepared by the VENDOR/CONTRACTOR and all subsequent
revisions etc. shall be at the cost of the VENDOR/CONTRACTOR for which no separate payment will be made.
7.0 FABRICATION 7.1 General All workmanship and finish shall be of the best quality and shall conform to the
best approved method of fabrication. All materials shall be finished straight and shall be machined/ground smooth true and square where so specified. All holes and edges shall be free of burrs. Shearing and chipping shall be neatly and accurately done and all portions of work exposed to view shall be neatly finished . Unless otherwise directed/ approved, reference may be made to relevant IS codes for providing standard fabrication tolerance. Material at the shops shall be kept clean and protected from weather.
7.2 Connections 7.2.1 Shop/field connections shall be as per approved fabrication drawings. 7.2.2 In case of bolted connections, taper washers or flat washers or spring washers
shall be used with bolts as necessary. In case of high strength friction grip bolts, hardened washers be used under the nuts or the bolt heads whichever are turned to tighten the bolts. The length of the bolt shall be such that atleast one thread of the bolt projects beyond the nut, except in case of high strength friction grip bolts where this projection shall be atleast three times the pitch of the thread.
7.2.3 In all cases where bearing is critical, the unthreaded portion of bolt shall bear on
the members assembled. A washer of adequate thickness may be provided to
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 96 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 6 of 11
Issue No.R5
TCE FORM 329 R3
exclude the threads from the bearing thickness, if a longer grip bolt has to be used for this purpose.
7.2.4 All connections and splices shall be designed for full strength of members or
loads indicated on ENGINEER's design drawings. Column splices shall be designed for the full tensile strength of the minimum cross section at the splice.
7.2.5 All bolts , nuts, washers, electrodes, screws etc. shall be supplied/brought to site
10% in excess of the requirement in each category and size. Rates shall cover the cost of this extra quantity.
7.2.6 All members likely to collect rain water shall have drain holes provided. 7.3 Straightening All materials, shall be straight and, if necessary, before being worked shall be
straightened and/or flattened by pressure and shall be free from twists. Heating or
forging shall not be resorted to without the prior approval of the ENGINEER in
writing. 7.4 Cutting, punching, drilling, welding and fabrication tolerances shall be generally
as per relevant IS codes. 7.5 Rolling And Forming Plates,channels, R.S.J. etc., for circular bins, bunkers, hoppers, gantry girders,
etc., shall be accurately laid off and rolled or formed to required profile/ shape as called for on the drawings. Adjacent sections shall be match-marked to facilitate accurate assembly, welding and erection in the field.
7.6 High Strength Friction Grip Bolting 7.6.1 Inspection after tightening of bolts shall be carried out as stipulated in the
appropriate standards depending upon the method of tightening and the type of bolt used.
7.7 Welding 7.7.1 Welding procedure shall be submitted to ENGINEER for approval. Welding shall
be entrusted to only qualified and experienced welders who shall be periodically tested and graded as per IS 817, IS:7310 (Part 1) and IS:7318 (Part 1).
7.7.2 While fabricating plated beams and built up members, all shop splices in each
component part shall be made before such component part is welded to other parts of the members. Wherever weld reinforcement interferes with proper fit-up
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 97 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 7 of 11
Issue No.R5
TCE FORM 329 R3
between components to be assembled for welding, these welds shall be ground flush prior to assembly.
7.7.3 Approval of the welding procedure by the ENGINEER shall not relieve the
CONTRACTOR of his responsibility for correct and sound welding without undue distortion in the finished structure.
7.7.4 No welding shall be done when the surface of the members is wet nor during
periods of high wind. 7.7.5 Each layer of a multiple layer weld except root and surfaces runs may be
moderately peened with light blows from a blunt tool. Care shall be exercised to prevent scaling or flaking of weld and base metal from overpeening.
7.7.6 No welding shall be done on base metal at a temperature below -5 Deg.C. Base
metal shall be preheated to the temperature as per relevant IS codes. 7.7.7 Electrodes other than low-hydrogen electrodes shall not be permitted for
thicknesses of 32 mm and above. 7.7.8 Inspection of Welds All welds shall be inspected for flaws by any of the methods described under
clause 8 "Inspection". The choice of the method adopted shall be determined by the PURCHASER/ENGINEER.
7.7.9 The correction of defective welds shall be carried out as directed by the
ENGINEER without damaging the parent metal. When a crack in the weld is removed, magnetic particle inspection or any other equally positive means as prescribed by the ENGINEER shall be used to ensure that the whole of the crack and material upto 25 mm beyond each end of the crack has been removed. Cost of all such tests and operations incidental to correction shall be to the VENDOR/CONTRACTOR's account.
7.8 Tolerances The dimensional and weight tolerances for rolled shapes shall be in accordance
with IS:1852 for indigenous steel and equivalent applicable codes for imported steel. The tolerances for fabrication of structural steel shall be as per IS:7215.
7.9 End Milling Where compression joints are specified to be designed for bearing, the bearing
surfaces shall be milled true and square to ensure proper bearing and alignment. 8.0 INSPECTION 8.1.1 The VENDOR/CONTRACTOR shall give due notice to the
PURCHASER/ENGINEER in advance of the works getting ready for inspection. All rejected material shall be promptly removed from the shop and replaced with
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 98 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 8 of 11
Issue No.R5
TCE FORM 329 R3
new material for the PURCHASER's/ENGINEER's approval/ inspection. The fact that certain material has been accepted at the VENDOR/CONTRACTOR's shop shall not invalidate final rejection at site by the PURCHASER/ENGINEER if it fails to conform to the requirements of these specifications, to be in proper condition or has fabrication inaccuracies which prevents proper assembly nor shall it invalidate any claim which the PURCHASER may make because of defective or unsatisfactory materials and/or workmanship.
8.1.2 No materials shall be painted or despatched to site without inspection and
approval by the PURCHASER/ ENGINEER unless such inspection is waived in writing by the ENGINEER.
8.1.3 The VENDOR/CONTRACTOR shall provide all the testing and inspection
services and facilities for shop work except where otherwise specified. 8.1.4 For fabrication work carried out in the field the same standard of supervision
and quality control shall be maintained as in shop fabricated work. Inspection and testing shall be conducted in a manner satisfactory to the ENGINEER.
8.2 Inspection and tests on structural steel members shall be as set forth below : 8.2.1 Material Testing If mill test reports are not available for any steel materials the same shall be got
tested by the VENDOR/CONTRACTOR to the ENGINEER's satisfaction to demonstrate conformity with the relevant specification.
8.3 Tests on Welds 8.3.1 Magnetic Particle Test Where welds are examined by magnetic particle testing, such testing shall be
carried out in accordance with relevant IS codes. If heat treatment is performed, the completed weld shall be examined after the heat treatment. All defects shall be repaired and retested. Magnetic particle tests shall be carried out using alternating current. Direct current may be used with the permission of the ENGINEER.
8.3.2 Liquid Penetrant Inspection In the case of welds examined by Liquid Penetrant Inspection, such tests shall
be carried out in accordance with relevant IS Code. All defects shown shall be repaired and rechecked.
8.3.3 Radiographic Inspection
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 99 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 9 of 11
Issue No.R5
TCE FORM 329 R3
All full strength butt welds shall be radiographed in accordance with the recommended practice for radiographic testing as per relevant IS code.
8.4 Dimensions, Workmanship & Cleanliness Members shall be inspected at all stages of fabrication and assembly to verify
that dimensions, tolerances, alignment, surface finish and painting are in accordance with the requirements shown in the VENDOR/CONTRACTOR's approved fabrication drawings and the ENGINEER's drawings.
8.5 Test Failure In the event of failure of any member to satisfy inspection or test requirement, the
CONTRACTOR shall notify the ENGINEER or his authorised representative. The VENDOR/CONTRACTOR must obtain permission from the ENGINEER before repair is undertaken. The quality control procedures to be followed to ensure satisfactory repair shall be subject to approval by the ENGINEER.
8.6 The ENGINEER has the right to specify additional testing as he deems
necessary, and the additional cost of such testing shall be borne by the PURCHASER, only in case of successful testing.
8.7 The VENDOR/CONTRACTOR shall maintain records of all inspection and testing
which shall be made available to the ENGINEER or his authorised representative.
9.0 SHOP MATCHING For structures like bunkers, tanks, etc. shop assembly is essential. For other
steel work, such as columns along with the tie beams/bracings may have to be shop assembled to ensure satisfactory fabrication, obtaining of adequate bearing areas etc. if so desired by the ENGINEER. All these shop assemblies shall be carriedout by VENDOR/CONTRACTOR at no extra cost to the PURCHASER.
10.0 DRILLING HOLES FOR OTHER WORKS As a part of this Contract, holes in members required for installing equipment or
steel furnished by other manufacturers or other contractors shall be drilled by the VENDOR/CONTRACTOR at no extra cost to the PURCHASER. The information for such extra holes will be supplied by the PURCHASER/ENGINEER.
11.0 MARKING OF MEMBERS 11.1 After checking and inspection, all members shall be marked for identification
during erection. This mark shall correspond to distinguishing marks on approved erection drawings and shall be legibly painted and stamped on it. The erection
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 100 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 10 of 11
Issue No.R5
TCE FORM 329 R3
mark shall be stamped with a metal dye with figures at least 20 mm high and to such optimum depth as to be clearly visible.
11.2 All erection marks shall be on the outer surface of all sections and near one
end, but clear of bolt holes. The marking shall be so stamped that they are easily discernible when sorting out members. The stamped marking shall be encircled boldly by a distinguishable paint to facilitate easy location.
11.3 Erection marks on like pieces shall be in identical locations. Members having
lengths of 7.0 m or more shall have the erection mark at both ends. 12.0 ERRORS Any error in shop fabrication which prevents proper assembling and fitting up of
parts in the field by moderate use of drift pins or moderate amount of reaming will be classified by the ENGINEER as defective workmanship. In case ENGINEER rejects such material or defective workmanship, the same shall be replaced by the materials and workmanship conforming to the ENGINEER's requirements by VENDOR/CONTRACTOR free of cost at site.
13.0 PAINTING 13.1 All fabricated steel material, except those galvanised shall receive protective
paint coating as specified in specification No. TCE.M4-405-04. 13.2 Galvanising of fabricated steel wherever specified, shall be as per TCE.M4-405-05
14.0 METHOD OF MEASUREMENT 14.1 For the purpose of payment, the weight of the actual completed structures shall
be calculated from the approved drawings for different items of work. The VENDOR/CONTRACTOR shall submit to the PURCHASER relevant material list containing weight of each item.
14.2 No allowances will be permitted for bolts, nuts, washers, studs, screws etc,
galvanizing, welding or for rolling margins. One tonne for the purpose of payment shall mean ONE METRIC TONNE i.e. 1000 Kg.
14.3 The weight of a member made out of standard rolled section such as beams,
channels, angles, etc. shall be based on the standard IS:808 without deductions for holes, notches, bevel cuts, etc. Where a component consists of a cut joist or channels, the full weight of the rolled section shall be considered only if more than half the depth of the original section is used. Otherwise, only half the section unit weight shall be considered for calculation of the weight of the components.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 101 of 118
Spec No. TCE CONSULTING ENGINEERS LIMITED Section : D
TCE. M4-405-01 SUPPLY AND FABRICATION OF STRUCTURAL STEEL
Sh 11 of 11
Issue No.R5
TCE FORM 329 R3
Deductions shall be made in the weight of gussets/plates for cuts and notches of 900 sq. cm. or larger.
14.4 For gussets/plates used in trusses, bracings, columns, beams, etc, the area
shall be that of the minimum circumscribing rectangle except as stated in 14.3 above.
14.5 The weight of any built-up members shall be based on the weight of each
component.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 102 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 1 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
1.0 SCOPE This specification covers the requirements for Shop Inspection and Tests to be
carried out by the PURCHASER/CONSULTANT/INSPECTION AGENCY. 2.0 GENERAL 2.1 The plant and equipment covered by the PURCHASE ORDER/CONTRACT
shall be subjected to inspection and testing. The VENDOR/CONTRACTOR shall provide all services to establish and maintain quality of workmanship in his works and that of his SUB-VENDOR’s/SUB-CONTRACTOR’s works to ensure the mechanical accuracy of components, compliance with approved drawings, identification and acceptability of all materials, parts and equipment.
2.2 For supply of systems, the VENDOR/CONTRACTOR shall, at the start of the
PURCHASE ORDER/CONTRACT, furnish a total list of items in his scope of work. This list, giving a brief description of the item, quantity, names of probable SUB-VENDORS/SUB-CONTRACTORS, and a blank column for agency for final approval of drawings and documents, shall be submitted for approval by PURCHASER/CONSULTANT. The blank column shall be filled by PURCHASER/CONSULTANT. The list shall be submitted within two weeks from the date of Letter of Intent.
2.3 For systems and major items such as pressure and load bearing items,
machineries etc., the VENDOR/CONTRACTOR shall furnish quality plan giving details of checks and tests to be conducted by them on material, process, sub-assembly and assembly. These shall include requirements as prescribed in the applicable specifications, codes and statutory requirements. The quality plan shall be reviewed by the PURCHASER/CONSULTANT and the stages to be witnessed and verified shall be indicated by the PURCHASER/CONSULTANT in the approved quality plan.
2.4 The VENDOR/CONTRACTOR shall give the PURCHASER/CONSULTANT
written notice of any material being ready for testing as per format enclosed. The clear notice period shall be seven (7) days for local inspection and fifteen (15) days for outstation inspection. Such tests shall be to the VENDOR’s/CONTRACTOR's account except for the expenses of the PURCHASER/CONSULTANT. The PURCHASER/CONSULTANT, unless the inspection of the tests is virtually waived, shall fix a date for inspection with the VENDOR/CONTRACTOR and attend such tests within fifteen (15) days of the date on which the equipment is notified as being ready for test and inspection failing which, the VENDOR/CONTRACTOR may proceed with the tests and shall forthwith forward to the PURCHASER/CONSULTANT duly certified copies of tests in triplicate. If the VENDOR/CONTRACTOR fails to offer the equipment for inspection as per the agreed date, he is liable to pay for the time and expenses for the infructuous visit of the PURCHASER/CONSULTANT.
2.5 In all cases where inspection and tests are required whether at the premises or
works of the VENDOR/CONTRACTOR or of any SUB-VENDOR/SUB-CONTRACTOR or at laboratory, the VENDOR/CONTRACTOR, except where otherwise specified, shall provide free of charge all facilities such as labour,
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 103 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 2 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
materials, electricity, fuel, water, stores, test bed, apparatus and instruments, laboratory tests etc. as may be required by the PURCHASER/CONSULTANT to carry out effectively such tests of the equipment in accordance with the PURCHASE ORDER/CONTRACT and shall give facilities to the PURCHASER/ CONSULTANT to accomplish testing.
2.6 The PURCHASER/CONSULTANT shall at all working hours have access to all
parts of the VENDOR’s/CONTRACTOR's and his SUB-VENDOR’s/SUB-CONTRACTOR's factory where the items of the plant are being prepared, for carrying out inspection activities as deemed necessary. A set of the relevant latest approved drawings with approval marking of the PURCHASER/ CONSULTANT and drawings for proprietary items shall be made available by the VENDOR/CONTRACTOR to the PURCHASER/CONSULTANT, for reference during inspection.
2.7 In the case of stage inspection hold points, the VENDOR/CONTRACTOR shall
proceed from one stage to another only after the component is inspected by the PURCHASER/CONSULTANT and written permission given to proceed further. The same procedure shall be adopted for any rectifications and repairs suggested by the PURCHASER/CONSULTANT.
2.8 The PURCHASER/CONSULTANT shall have the right to inspect any
machinery, material, structures, equipment or workmanship furnished or used by the VENDOR/CONTRACTOR and may reject any which is defective or unsuitable for the use and purpose intended, or which is not in accordance with the intent of the PURCHASE ORDER/CONTRACT. The VENDOR/ CONTRACTOR, upon demand by the PURCHASER/CONSULTANT, shall remedy or replace at the VENDOR’s/CONTRACTOR's expense such defective or unsuitable items of the plant, or the PURCHASER/CONSULTANT may, at the expense of the VENDOR/CONTRACTOR, remedy or replace such defective or unsuitable items of the Plant.
2.9 All principal mill test reports, the VENDOR/CONTRACTOR inspection and tests
reports, test certificates and test curves shall be supplied for all inspection and tests carried out including other records such as stress relieving charts, radiographic charts and other non-destructive testing records in accordance with the provisions of the PURCHASE ORDER/CONTRACT, duly certified by the main VENDOR/CONTRACTOR. The PURCHASER/CONSULTANT shall reserve the right to call for certificates of origin and test certificates for all raw material and equipment at any stage of manufacture.
2.10 The PURCHASER/CONSULTANT shall within fifteen (15) days from the date of
inspection as defined herein give notice in writing to the VENDOR/ CONTRACTOR of any non-conformance pertaining to all or any equipment and workmanship which in his opinion is not in accordance with the PURCHASE ORDER/CONTRACT. The VENDOR/CONTRACTOR shall give due consideration to such objections and shall either make the modifications that may be necessary to meet the said objections or shall confirm in writing to the PURCHASER/CONSULTANT giving reasons therein that no modifications are necessary to comply with the PURCHASE ORDER/CONTRACT.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 104 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 3 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
2.11 When the factory tests and documentation have been satisfactorily completed at the VENDOR’s/CONTRACTOR's or SUB-VENDOR's/CONTRACTOR's works, the PURCHASER/CONSULTANT shall issue acceptance note or shipping release note or a certificate to this effect within fifteen (15) days after completion, but if the tests are not witnessed by the PURCHASER/ CONSULTANT, the certificate or comments thereof shall be issued within fifteen (15) days of the receipt of the VENDOR’s/CONTRACTOR's test certificate by the PURCHASER/CONSULTANT. Failure of the PURCHASER/ CONSULTANT to take such an action shall not prevent the VENDOR/ CONTRACTOR from proceeding with the work. The completion of these tests or the issue of the certificates shall not bind the PURCHASER/ CONSULTANT to accept the equipment, should it, on further tests after erection, be found not to comply with the PURCHASE ORDER/CONTRACT.
2.12 None of the plant and the equipment to be furnished or used in connection with
the PURCHASE ORDER/CONTRACT shall be despatched until shop inspection, satisfactory to the PURCHASER/CONSULTANT has been made. However, such shop inspection and/or certification shall not relieve the VENDOR/CONTRACTOR of his responsibility for furnishing the plant and the equipment conforming to the requirements of the PURCHASE ORDER/ CONTRACT nor prejudice any claim, right or privilege which the PURCHASER/ CONSULTANT may have because of the use of defective or unsatisfactory items. Should the PURCHASER/CONSULTANT waive the right to inspect any item, such waiver shall not relieve the VENDOR/CONTRACTOR in any way from his obligation under the PURCHASE ORDER/CONTRACT. In the event of the PURCHASER’s/CONSULTANT's inspection revealing poor quality of goods, the PURCHASER/CONSULTANT shall be at liberty to specify additional inspection procedures, if required, to ascertain the VENDOR/CONTRACTOR's compliance with the equipment specifications.
3.0 SUB-ORDERS AND SUB-CONTRACTS 3.1 In order to facilitate the inspection of bought-out materials and plant, the
VENDOR/CONTRACTOR shall submit for approval, three (3) copies of all sub-orders and sub-contracts placed by him as soon as these are issued. Copies of any drawings referred to in the sub-order or sub-contracts shall also be submitted, unless agreed otherwise by the PURCHASER/CONSULTANT.
3.2 The sub-orders, sub-contracts and drawings referred to above shall include all
components which are subjected to electrical and mechanical pressure or stress when the plant is in operation, and also auxiliaries and spares which are to be directly despatched to site from the SUB-VENDOR’s/SUB-CONTRACTOR's works.
3.3 All sub-orders and sub-contracts of the main VENDOR/CONTRACTOR shall
clearly be marked with the main VENDOR’s/CONTRACTOR's name and the PURCHASER’s/CONSULTANT’s name and the PURCHASE ORDER/ CONTRACT reference. These shall include the following statement:
The plant or the equipment which is the subject of this PURCHASE ORDER/
CONTRACT shall comply in every respect with the requirements of the
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 105 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 4 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
PURCHASER’s/CONSULTANT's technical specifications and shall be subject to inspection and tests to the satisfaction of the PURCHASER/CONSULTANT.
3.4 For the purpose of this para, it is obligatory on the VENDOR/CONTRACTOR
that he advises his SUB-VENDOR/SUB-CONTRACTOR of the pertinent clauses in this specification when ordering bought-out plant, equipment or materials. In particular, the VENDOR/CONTRACTOR shall advise every SUB-VENDOR/SUB-CONTRACTOR that he is required to supply design calculations, drawings, inspection reports and test certificates strictly in accordance with this specification and technical information for inclusion in the Instruction Manual as specified in Section E of the Enquiry Document. The SUB-VENDORS/SUB-CONTRACTORS should also be reminded that they shall include with their offer all tools and appliances necessary for proper maintenance and all spare parts in accordance with Section E of the Enquiry Document. Itemised prices of the recommended spare parts shall be submitted together with the appropriate part numbers and drawings.
3.5 Sub-ordering and sub-contracting for major items such as pressure and load
bearing items, machinery etc. can be done only with the approval of the PURCHASER/CONSULTANT.
4.0 MATERIAL TESTS 4.1 In the event of the PURCHASER/CONSULTANT being supplied with the
certified particulars of tests which have been carried out for the VENDOR/ CONTRACTOR by the supplier of material, the PURCHASER/CONSULTANT may, at his own discretion, accept the same as proper evidence of compliance with the requirements of appropriate specifications for the materials.
4.2 The VENDOR/CONTRACTOR is to provide test pieces as required by the
PURCHASER/CONSULTANT to enable him to determine the quality of material supplied under the PURCHASE ORDER/CONTRACT. If any test piece fails to comply with the requirements, the PURCHASER/CONSULTANT may reject the entire lot of material represented by the test piece.
4.3 Critical materials used in manufacture of the equipment and construction of the
plant covered by the PURCHASE ORDER/CONTRACT may also be subjected to one or more of the Non-Destructive Tests (NDT) as called for in the enquiry document or as mutually agreed. Salvaging of material due to unacceptable defect is to be attempted by the VENDOR/CONTRACTOR only after getting specific concurrence from the PURCHASER/CONSULTANT and according to the approved procedures.
5.0 WELDING 5.1 All welding involved in construction and fabrication of the plant and items
covered under the PURCHASE ORDER/CONTRACT shall be carried out in accordance with specifications and applicable codes.
5.2 Welding procedures and welders' qualifications shall be approved by the
PURCHASER/CONSULTANT. Where applicable, welders shall be tested as
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 106 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 5 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
detailed in codes specified for pipe welding, vessel welding and structural welding and appropriate to the corresponding weld position using test pieces of appropriate parent metal to be used on the job. The PURCHASER/ CONSULTANT shall have the right to have any welder re-tested at any time during the PURCHASE ORDER/CONTRACT.
5.3 Recommendations of applicable codes shall be followed for non-destructive
tests, wherever applicable. 5.4 Copies of all welding procedures, procedure qualification records, welders'
performance qualification certificates, post-heating and stress relieving records, NDT records and other test results shall be made available upon request of the PURCHASER/CONSULTANT.
6.0 FABRICATION AND INSPECTION Fabrication and inspection procedures for vessels, heat exchangers, pipes,
tubes and valves etc. shall be in accordance with procurement specifications, quality plan, applicable codes or any other approved equal.
7.0 TESTS AT MANUFACTURER'S WORKS 7.1 GENERAL The tests at works shall include electrical, mechanical and hydraulic tests in
accordance with the appropriate clauses of Statutory Regulation, relevant codes and standards and approved drawings and specifications and in addition any test called for by the PURCHASER/CONSULTANT to ensure that the plant being supplied fulfils the requirements of the specifications. The VENDOR/ CONTRACTOR shall carry out all the shop tests and inspections specified under individual items of the equipment in Section-D of the enquiry document, in addition to those normally required as per codes and standards. For items not covered by any code or specifically mentioned in the specifications, the tests are to be agreed with by the PURCHASER/CONSULTANT. If considered necessary by the PURCHASER/CONSULTANT, multi-part assemblies shall be fully erected and tested in the works prior to packing and despatch to the site.
7.2 TEST CERTIFICATES Test certificates including test records, performance curves and balancing
certificates shall be supplied according to the Distribution Schedule. All the tests shall be carried out in accordance with the provisions of the PURCHASE ORDER/CONTRACT.
All test certificates must be endorsed with sufficient information to identify the
material or the equipment to which the certificates refer, and must carry at the top right hand corner the identification of the PURCHASER/CONSULTANT and the PURCHASE ORDER/CONTRACT.
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 107 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 6 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
7.3 CALIBRATION All instruments used for critical measurement such as pressure gauges for leak
tests, instruments for measuring performance parameters; instruments for precision dimension measurements shall have valid calibration certificates traceable to national standards. This means that the calibrating agency engaged by the VENDOR/CONTRACTOR shall use instruments which are in turn calibrated by Government approved agencies and such information shall be recorded in the calibration certificate issued by the calibrating agency by giving the certificate number, date and date of validity of the certificate given by the Government approved agency.
FORMAT FOR INSPECTION REQUEST FROM THE
VENDOR/CONTRACTOR To, TATA CONSULTING ENGINEERS LIMITED,
Attn: Mr/Ms
PROJECT MANAGER Dear Sir/Madam, Items detailed below are ready for inspection. Please arrange inspection and
confirm the date. 1. PURCHASER 2. PROJECT 3. PURCHASE ORDER/CONTRACT
REFERENCE NUMBER
4. CONSULTANT (TCE) REFERENCE
NUMBER
5. SUB-VENDOR/SUB-CONTRACTOR 6. SUB-VENDOR’s/SUB-CONTRACTOR’s
ADDRESS
7. PLACE OF INSPECTION AND ADDRESS 8. CONTACT PERSON, PHONE, FAX AND
E-MAIL ID
9. DESCRIPTION OF ITEM AND QUANTITY 10. NATURE OF INSPECTION REQUIRED
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 108 of 118
SPEC. NO. TCE.M4-904
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SHOP INSPECTION AND TESTS SHEET 7 OF 7
ISSUE R9
TCE FORM NO. 329 R5 FILE NAME: M4904R9.DOC
11. PROPOSED DATES 12. WEEKLY HOLIDAY We confirm that the items have been fully inspected and tested by us. All stages
of inspection as per approved quality plan have been carried out by us and all material test certificates, quality control records and test reports and valid calibration reports of measuring and testing instruments with traceability to national level are ready with us.
Thanking you and awaiting your confirmation, Yours faithfully, Note 1 Following clear notice periods (Date of Receipt at TCE to Date of
Inspection) are required: (a) Local Inspection - 7 days (b) Outstation Inspection - 15 days Note 2 Weekly Holidays for TCE - Saturday and Sunday cc: Purchaser cc: Sub-Vendor/Sub-Contractor
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 109 of 118
TATA Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 1 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report Sub
VENDOR VENDOR Inspection Agency
1.0
Heat treatment, NDT and other procedures including tube expansion/ welding and mockup test and air / hydro test or both.
Documented Proceedures
100%
ASME Sec IIA / IIB, Sec VIII Div-I, Sec V/
Spec / Drawings
ASME Sec IIA/ IIB, Sec VIII
Div.1, Sec V / Spec /
Drawings
Document - W R
2.0 MATERIALS INSPECTION
2.1
MATERIALS AT MILLS Plates, Pipes, Tubes, Tube sheets, Forging, Fittings Fasteners etc. * (To be procured from reputed manufacturers under Third Party Inspection)
Chemical analysis, Mechanical properties, Additional Tensile on hub, Bend test, (Including impact test of plates / forging , Hardness check, Heat treatment if applicable) Non Destructive Test as applicable, Visual & dimensional inspection.
100%
ASME Sec II A / Spec / Drawings
,SA 388 ASME Sec VIII Div II.
ASME Sec II A / Spec/
Drawings / SA 388,
ASME Sec VIII Div II.
Mill Test Certificates W W / R * W / R*
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 110 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 2 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report
Sub VENDOR VENDOR Inspection
Agency
2.2 Aluminium fin material Chemical & size lot Spec /
Drawing Spec / Drawing Insp. Report W R
R
2.3
MATERIALS AFTER RECEIPT (for Pressure Parts) Plates ( Header Box / Tube Sheet), Pipes for nozzle, Forgings, Plugs, Tubes, Fittings, Fasteners, Gaskets etc.
Review of test certificates markings, Visual & dimensional inspection, Identification, Correlation & transfer of identity.
100% ASME Sec. II
A / PO / Drawing
ASME Sec. II A / PO / Drawing
Material Clearance
Record W W R
2.4
Non Pressure Parts (C Frames, tube spacers, plenum chambers, support structurals etc.)
Review of test Certificates 100%
ASME Sec II A / B Spec /
Drawings
ASME Sec II A / B Spec /
Drawings
Insp. Report W R R
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 111 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 3 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report Sub
VENDOR VENDOR Inspection Agency
2.5 Motors, pulleys, belts, fans & vibration switches
Review of test Certificates 100% Spec /
Drawing Spec / Drawing Insp. Report W R R
Visual & Dimensional Inspection (pitch, height, length of unfined potion, straightness, etc
100% Drawing / SpecDrawing,
ASME Sec.VIII-1
Insp. Report W R R
3.0 Tube Fining
Pull out test Sample Spec Spec Test report W R R
4.0 WPS & PQR
4.1 PQR Welding parameters 100% ASME Sec IX / Spec.
ASME Sec IX / Spec. WPS / PQR - W R
4.2 WPQ Welding parameters 100% ASME Sec IX / Spec.
ASME Sec IX / Spec. WPQ - W R
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 112 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 4 OF 9
ISSUE R0
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report
Scope of Inspection
Sub VENDOR VENDOR Inspection
Agency
4.3 Tube to Tube Sheet Welding
Chemical & mechanical properties
100% Spec / Drawing
Spec / Drawing - W W
4.4 Welding consumable
Chemical & mechanical properties
All batches
ASME Sec II C / Spec.
ASME Sec II C / Spec.
Batch test certificates - W R
5.0
INSPECTION DURING FABRICATION
Visual & Dimensional inspection, weld edge, Root gap. Offset, cleanliness etc
100% Drawing / ASME Sec.VIII-1
Drawing,/ ASME Sec.VIII-1
Insp. Check List - W R 5.1
Weld Edge preparation & set up of side plates including tube sheet & past partition plates MT / PT of weld
edges as applicable 100% Drawing / Spec
ASME Sec V / Spec Insp. Check List - W R
5.2
Intermediate Insp. of welds
Visual / interpass temp. / PT insp. after chipback
100% Drawing Drawing Insp. Check List - W R
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 113 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 5 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report Sub
VENDOR VENDOR Inspection Agency
Visual inspection for reinforcement, Undercuts, surface defects etc.
100% Drawing, ASME Sec.VIII-1
Drawing, ASME Sec.VIII-1
Insp. Check List - W R
Nondestructive Test as applicable 100% ASME VIII-1
/ Spec ASME Sec V NDT Report - W R 5.3 Inspection of Completed welds
PWHT 100% ASME VIII-1 / Spec
Cust. Spec / Drawing HT Chart - W R
Hardness test
Each weld seam & as per spec / Drawing
Spec / Drawing
Cust. Spec/ Drawing Insp. Report - W W / R
Inspection of Completed welds (contd.) Production test
coupon Testing
As per Spec / Drawing
ASME Sec VIII-1
ASME Sec VIII-1 Insp. Report - W W / H
5.4
Structural ( Plenum chambers, support assly. etc.)
Dimensions, match marking and completeness of assembly
Drawing Drawing Cust. Spec / Drawing Insp. Report - W W / R
6.0 MACHINING / DRILLING
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 114 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 6 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report
Sub VENDOR VENDOR Inspection
Agency
6.1 Tube Sheet
Hole dia, drift, surface finish, grove depth, ligament check and positional accuracy
100% Drawing, TEMA-R
Drawing, TEMA-R Insp. Report - W W
6.2 Plug sheet Threading, finish, ligament check and positional accuracy
100% Drawing, TEMA-R
Drawing, TEMA-R Insp. Report - W W
7.0 ASSEMBLY
7.1 Tube bundle -C Frame assly before tube insertion
Completeness of assembly Drawing Drawing STANDARD Insp. Report - W W
7.2 Final assembly after tubes insertion
Alignment, completeness of assembly
Drawing Drawing STANDARD Insp. Report - W W / R
7.3 Tube to Tube Sheet Expansion / Welding
% Thinning, Length of Expansion, finish & hardness / visual, distortion & DP of welds
Random Spec. Spec. Insp. Report - W W
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 115 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 7 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report
Sub VENDOR VENDOR Inspection
Agency
8.0 FINAL INSPECTION
8.1 Visual and Dimensional Insp. of Tube Bundles
Dimensions, completeness of assembly
100% Drawing Drawing Insp. Report - W H
8.2 Air test of Tube to Tube Sheet joints leak Check 100% Drawing /
Spec Drawing / Spec Insp. Report - W R
8.3 Hydrostatic Test leak Check 100%
ASME Sec. VIII-1 / Spec / Drawing
Drawing / Spec Insp. Report - W R
8.4 Surface preparation / cleaning
Visual insp. for workmanship 100% Drawing /
Spec
ASME Sec. VIII-1 / Drawing / Spec
Insp. Report - W R
8.5
Pickling & Passivation/ Painting/ Hot Dip Galvanising ( Headers & Frames ) etc.
Visual insp. for workmanship 100% Drawing /
Spec Spec. Insp. Report - W R
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 116 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 8 OF 9
ISSUE R0
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report Sub
VENDOR VENDOR Inspection Agency
8.6 Final Stamping of equipment and marking etc
Verifying stamping details
Name plate & Rub off stamping
Drawing Drawing Name Plate/ Rub-off - W H
8.7 Drying of equipment Cleanliness Full Equipment
Drawing / Spec
Drawing / Spec Insp. Report - W R
8.8 Nitrogen Filling N2 pressure & non return valve
Full Equipment
Drawing / Spec
Drawing / Spec Insp. Report - W R
8.9 Trial run at shop (if required)
Dimensional accuracy, clearances etc
Structurals, plenum chamber along with fan and its mountings etc
Drawing / Spec
Drawing / Spec Insp. Report - W H
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 117 of 118
TCE Consulting Engineers Limited SECTION: D
SHOP INSPECTION REQUIREMENTS FOR AIR COOLED HEAT EXCHANGERS (TCE.6758A-SE-800) SHEET 9 OF 9
ISSUE R0
1.0 LEGEND H- Hold (Offer for Witness & obtain clearance) W-Witness R- Review PO- Purchase Order PR- Purchase Requisition
2.0 All the NDT / Leak testing / Heat treatment / Special manufacturing procedures have to be specially approved or only previously approved procedures have to be used. In case of conflict between purchase specification, contract documents and Shop Inspection Requirements more stringent conditions shall be applicable. This document describes generally the requirements pertaining to all types of Air cooled Heat Exchangers. Requirements specific to the item are only applicable.
3.0 APPLICABLE CODES & SPECIFICATIONS 3.1 TEMA
3.2 Specification for Air Cooled Heat Exchangers
3.3 Other Standards / Specifications enclosed with MR / RFQ / Enquiry Specification / BID document
Scope of Inspection
Sr. No
Inspection Activity & Component Characteristics Quantum
of check Reference Document
Acceptance standard
Format of report Sub
VENDOR VENDOR Inspection Agency
9.0 DOCUMENTATION
Verification & Compilation of inspection & test records for submission to customer
100% Spec. (VDR) Spec. Q.C. Dossier - W H
NIT NO. 6758A_TCE/BPCL_RFQ_002 Page 118 of 118