    Terminology used in Contract Documentation

    Parties

    Employer : The person or body that commissions the construction

    Clients Representative : The person appointed by the Employer to liaise with the Design Team and Project Manager.

    Adjudicator : The person who gives rulings on Employer Contractor disputes and is preferably a different person to the Project Manager.

  • 2/24/2014

    2

    Parties Contractor : The firm that has been contracted

    to construct the Works Subcontractor : A firm that has a contract with

    the main Contractor to provide labor, materials or products.

    Arbitrator : The Arbitrator is the person to whom the

    Employer and Contractor can refer their disputes to and be bound by the Arbitrators decision.

    The Arbitrator cannot be the same person as the Project Manager.

    Documents

    Contract Documentation : Pre-qualification, Tender and Contract

    Documents collectively.

    This term includes all documents prepared by the Design Team.

    Prequalification Documents : Prequalification documents exchanged between

    the Employer/Designer and potential tenderers prior to selection of list of tenderers.

  • 2/24/2014

    3

    Documents

    Tender Documents : The Documents sent to the selected tenderers to

    enable them to price the construction.

    Also termed as Invitation to Tender.

    Instructions to Tenderers : The term is self-explanatory but only covers

    procedures up to Acceptance of Tender.

    For this reason, it is not a Contract Document.

    Documents

    Tender : The documents that have been completed by a tenderer and are then returned to the Employer for consideration

    (i.e Evaluation). Bid : US equivalent to Tender. Normally not used

    in Contract documentation, since contract documentation deals with written offer. The word Bid in UK English tends to be used to describe both verbal and written offers.

    Offer : Another alternatives to Tender not normally used in contract documentation for the same reason as Bid

  • 2/24/2014

    4

    Documents

    Bill Of Quantities : Civil Engineers and designers using the FIDIC

    Conditions and the UK building designers use the term Bill Of Quantities.

    Addenda : Changes to tender Documents after they have

    been sent to the tenderers and prior to Acceptance.

    Variation Order : Project Managerss order for alternations,

    additions and omissions to the Works

    Tender Document :Essential Elements

    1. Instructions to Tenderer(ITT)

    2. Tender Data Sheet(TDS)

    3. General Conditions of Contract(GCC)

    4. Particular Conditions of Contract(PCC)

    5. Tender Form

    6. Bill Of Quantities(BOQ)

    7. General Specification

    8. Particular Specification

    9. The Drawings

  • 2/24/2014

    5

    The purpose of this section is to instruct the tenderer or bidder about general rules and regulation.

    It is almost same for all tender.

    It should not have any details, for example, here it is said to deposit tender security, but the amount of tender security is not written here.

    Instructions to Tenderer(ITT)

    The ITT provides generalized information the particular data (information) is provided TDS.

    Here the amount of tender security is written (say, 2-3% of project cost)

    Amount of required turnover that the tenderer is to fulfill is specifically mentioned.

    Tender Data Sheet(TDS)

  • 2/24/2014

    6

    It is almost same for all tender

    Here general conditions are written only, not particularly/specifically

    Some items of GCC clause are- Definitions

    Arbitrators

    JVCA

    Risk

    Compensation Events

    Performance Security etc.

    General Conditions Of Contract(GCC)

    Particular Conditions Of Contract(PCC)

    It varies from tender to tender.

    The specific rules of GCC are given here; say the amount of compensation, the performance security is written here.

  • 2/24/2014

    7

    Tender Form

    It varies from tender to tender.

    Bill of Quantities(BOQ)

    BOQ contains all items for works and supplies for construction, testing, commissioning to be done by the contractor.

    It is used to calculate the contract price.

    The contractor is paid for each item of work done at a rate as quoted in the BOQ

  • 2/24/2014

    8

    BoQ provides sufficient information on the quantities of Works to be performed to enable Tenders to be prepared efficiently and accurately;

    BoQ provides a priced BOQ for use in the periodic valuation of Works executed.

    General Specifications

    General specification are written

    General Specification may include:

    General site requirement

    Health and safety

    Measures against environmental pollution

    Security measures

  • 2/24/2014

    9

    Particular Specification

    It contains particular specificaion.

    Example : Strength and other properties of steel

    Strength of concrete

    Specification of bricks

    Specification of electrical items

    Etc.

    The Drawings

    This portion contains drawing work.

    It gives detailing for the task.

  • 2/24/2014

    10

    Flow Chart of Tendering Process

    Tender Notice

    Interested bidder buy

    tender documents

    Tender Submission

    Tender Evaluation by

    Tender Evaluating Committee

    Outcome of Tender Evaluation

    Rejected Tenderer

    Non-Response Tenderer

    Substantially Responsive Tenderer

    Responsive Tenderer

    (Cont. to next page)

    Obtain clarification and make responsive or nonresponsive

    Lowest Bidder/Tenderer

    Invited to ContractNOA

    Contractor

    ContractSign

    (cont. from prev. page)

    No

    Yes

    Approval from

    HOPE

    Cancel the process& Arrange Re-tender

  • 2/24/2014

    11

    Criteria for Tender Evaluation

    Preliminary Security

    Tender and goods are eligible

    Minimum general experience

    Minimum similar contract type experience

    Minimum liquid asset

    VAT & IT related certificate

    Valid trade license

    Criteria for Tender Evaluation

    Preliminary Security

    All pages duly signed

    Price schedule

    Tender validity period

    Completed tender submission sheet

    Tender security

  • 2/24/2014

    12

    Criteria for Tender Evaluation

    Detailed Examinations Check for qualification and experience of key

    personnel.

    Check for adequacy of plants and equipments

    Check for general experience

    Check for similar contract type experience

    Check for bank certificate for liquid asset

    Check for annual average turnover from audit report

    Check for arithmatic correction of prices quotted

    Check for credit facility available