tenant improvement scheduling

8

Click here to load reader

Upload: ronald-rhodes

Post on 21-Jun-2015

172 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Tenant improvement Scheduling

ID Task Mode

Task Name Duration Start Finish Predecessors

1 Pilkington Tenant Improvement Schedule 26 days? 6/12/08 7/17/082 LEASE RELATED ATIVITIES 3 days? 6/12/08 6/16/083 Sign Letter of Intent to Start Design 1 day? 6/12/08 6/12/084 Lease Review 1 day? 6/13/08 6/13/08 35 Execute Lease Agreement 1 day? 6/16/08 6/16/08 46 DESIGN DEVELOPMENT 10 days? 6/17/08 6/30/087 Preliminary Design Development (SD) 1 day? 6/17/08 6/17/08 58 Provide Racking Plan (Pilkington) 1 day? 6/18/08 6/18/08 79 Approve Space Plan (Moves 1,2,3) 1 day? 6/18/08 6/18/08 7

10 Approve Space Plan (Move 4) 1 day? 6/18/08 6/18/08 711 Approve Preliminary Warehouse Space Plan (Dock Locations) 1 day? 6/18/08 6/18/08 712 Design Development (Moves 1,2,3) 1 day? 6/19/08 6/19/08 913 Design Development (Move 4) 1 day? 6/19/08 6/19/08 1014 Engineered Racking Drawings (Pilkington) 1 day? 6/19/08 6/19/08 815 Office Allowance Budget Approval 1 day? 6/20/08 6/20/08 9,1216 Finalize Interior Finishes 1 day? 6/20/08 6/20/08 12,1317 Bid and Award MEP Design Build Subcontracts 1 day? 6/23/08 6/23/08 15,1618 MEP Design Documents 1 day? 6/24/08 6/24/08 1719 Approval of Final Design Documents (Pilkington) 1 day? 6/25/08 6/25/08 1820 Bid/Award General Trades/Finishes Packages 1 day? 6/26/08 6/26/08 1921 Reconcile Office/Warehouse Allowance Budget 1 day? 6/27/08 6/27/08 2022 Submit Permit Drawings (Moves 1,2,3) 1 day? 6/30/08 6/30/08 2123 Submit Permit Drawigs (Move 4) 1 day? 6/30/08 6/30/08 2124 PERMITS 8 days? 6/20/08 7/1/0825 State of Ohio Building Permit (Moves 1,2,3) 1 day? 7/1/08 7/1/08 2226 State of Ohio Building Permit (Move 4) 1 day? 7/1/08 7/1/08 23

T W TJun 8, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 1

Project: Tenant Improvement RonDate: 11/5/13

Page 2: Tenant improvement Scheduling

ID Task Mode

Task Name Duration Start Finish Predecessors

27 Racking Plan Review 1 day? 6/20/08 6/20/08 1428 CONSTRUCTION (MOVES 1,2,3) 19 days? 6/23/08 7/17/0829 Warehouse Power/Lighting 5 days? 7/2/08 7/8/0830 Install Electrical Panel 1 day? 7/2/08 7/2/08 2531 Install Lighting 1 day? 7/3/08 7/3/08 3032 Connect Lighting to Panel 1 day? 7/4/08 7/4/08 3133 Install Outlets 1 day? 7/7/08 7/7/08 3234 Electrical Inspection 1 day? 7/8/08 7/8/08 3335 Tenant Racking 1 day? 6/23/08 6/23/08 2736 Rough Framing/Carpentry 6 days? 7/2/08 7/9/0837 Frame Walls 1 day? 7/2/08 7/2/08 2538 Install Ceiling Grid 1 day? 7/7/08 7/7/08 37,4239 Install Rough Drywall 1 day? 7/8/08 7/8/08 3840 Install Doors 1 day? 7/9/08 7/9/08 3941 Office MEP Rough-in 2 days? 7/3/08 7/4/0842 Install Rough Mechanical Systems in Office 1 day? 7/4/08 7/4/08 4543 Install Rough Electrical in Office 1 day? 7/3/08 7/3/08 3744 Electrical Inspection 1 day? 7/4/08 7/4/08 4345 Install Rough Plumbing in Office 1 day? 7/3/08 7/3/08 3746 Plumbing Inspection 1 day? 7/4/08 7/4/08 4547 Tenant Cabling 3 days? 7/3/08 7/7/0848 Install Phone Lines 1 day? 7/3/08 7/3/08 3749 Install Data Lines 1 day? 7/4/08 7/4/08 4850 Install Cable 1 day? 7/7/08 7/7/08 4951 Drywall/Finishes/Ceilings 3 days? 7/8/08 7/10/0852 Finish Drywall 1 day? 7/8/08 7/8/08 44,50

T W TJun 8, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 2

Project: Tenant Improvement RonDate: 11/5/13

Page 3: Tenant improvement Scheduling

ID Task Mode

Task Name Duration Start Finish Predecessors

53 Paint Walls 1 day? 7/9/08 7/9/08 5254 Paint Doors 1 day? 7/10/08 7/10/08 53,4055 Install Ceiling Tiles 1 day? 7/9/08 7/9/08 38,5256 Install Flooring 1 day? 7/10/08 7/10/08 5357 MEP Finishes 2 days? 7/7/08 7/8/0858 Finish Mechanical Systems 1 day? 7/7/08 7/7/08 4259 Finish Electrical 1 day? 7/7/08 7/7/08 4460 Final Electrical Inspection 1 day? 7/8/08 7/8/08 5961 Finish Plumbing 1 day? 7/7/08 7/7/08 4662 Final Pluming Inspection 1 day? 7/8/08 7/8/08 6163 Final Inspections/ Life Safety 1 day? 7/11/08 7/11/08 62,60,56,54,3564 Certificate of Occupancy 1 day? 7/14/08 7/14/08 6365 Substantial Completion 1 day? 7/15/08 7/15/08 6466 Punch List 1 day? 7/16/08 7/16/08 6567 Tenant Relocation (Move 1) 1 day? 7/17/08 7/17/08 6668 Tenant Relocation (Move 2) 1 day? 7/17/08 7/17/08 6669 Tenant Relocation (Move 3) 1 day? 7/17/08 7/17/08 6670 CONSTRUCTION (MOVE 4) 19 days? 6/12/08 7/8/0871 Warehouse Power/Lighting 5 days? 7/2/08 7/8/0872 Install Electrical Panel 1 day? 7/2/08 7/2/08 2573 Install Lighting 1 day? 7/3/08 7/3/08 3074 Connect Lighting to Panel 1 day? 7/4/08 7/4/08 3175 Install Outlets 1 day? 7/7/08 7/7/08 3276 Electrical Inspection 1 day? 7/8/08 7/8/08 3377 Tenant Racking 1 day? 6/23/08 6/23/08 2778 Rough Framing/Carpentry 1 day? 6/12/08 6/12/08

T W TJun 8, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 3

Project: Tenant Improvement RonDate: 11/5/13

Page 4: Tenant improvement Scheduling

ID Task Mode

Task Name Duration Start Finish Predecessors

79 Frame Walls 1 day? 6/12/08 6/12/0880 Install Ceiling Grid 1 day? 6/12/08 6/12/0881 Install Rough Drywall 1 day? 6/12/08 6/12/0882 Install Doors 1 day? 6/12/08 6/12/0883 Dock Pit Pour Back 1 day? 6/12/08 6/12/0884 Install Dock Equipment 1 day? 6/12/08 6/12/0885 Tenant Cabling 1 day? 6/12/08 6/12/0886 Install Phone Lines 1 day? 6/12/08 6/12/0887 Install Data Lines 1 day? 6/12/08 6/12/0888 Install Cable 1 day? 6/12/08 6/12/0889 Drywall/Finishes/Ceilings 1 day? 6/12/08 6/12/0890 Finish Drywall 1 day? 6/12/08 6/12/0891 Paint Walls 1 day? 6/12/08 6/12/0892 Paint Doors 1 day? 6/12/08 6/12/0893 Install Ceiling Tiles 1 day? 6/12/08 6/12/0894 MEP Finishes 1 day? 6/12/08 6/12/0895 Finish Mechanical Systems 1 day? 6/12/08 6/12/0896 Finish Electrical 1 day? 6/12/08 6/12/0897 Final Electrical Inspection 1 day? 6/12/08 6/12/0898 Finish Plumbing 1 day? 6/12/08 6/12/0899 Final Pluming Inspection 1 day? 6/12/08 6/12/08

100 Substantial Completion 1 day? 6/12/08 6/12/08101 Punch List 1 day? 6/12/08 6/12/08102 Final Inspections/ Life Safety 1 day? 6/12/08 6/12/08103 Certificate of Occupancy 1 day? 6/12/08 6/12/08104 Tenant Relocation (Move 4) 1 day? 6/12/08 6/12/08

T W TJun 8, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 4

Project: Tenant Improvement RonDate: 11/5/13

Page 5: Tenant improvement Scheduling

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SJun 8, '08 Jun 15, '08 Jun 22, '08 Jun 29, '08 Jul 6, '08 Jul 13, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 5

Project: Tenant Improvement RonDate: 11/5/13

Page 6: Tenant improvement Scheduling

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SJun 8, '08 Jun 15, '08 Jun 22, '08 Jun 29, '08 Jul 6, '08 Jul 13, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 6

Project: Tenant Improvement RonDate: 11/5/13

Page 7: Tenant improvement Scheduling

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SJun 8, '08 Jun 15, '08 Jun 22, '08 Jun 29, '08 Jul 6, '08 Jul 13, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 7

Project: Tenant Improvement RonDate: 11/5/13

Page 8: Tenant improvement Scheduling

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SJun 8, '08 Jun 15, '08 Jun 22, '08 Jun 29, '08 Jul 6, '08 Jul 13, '08

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 8

Project: Tenant Improvement RonDate: 11/5/13