technical specifications - d.n. higgins
TRANSCRIPT
TECHNICAL SPECIFICATIONS FOR
SHALLOW WELLS UPGRADE
TABLE OF CONTENTS
Description Section
Measurement and Payment 01270
Submittals 01300
Administrative Requirements 01310
Preconstruction Video 01315
Quality Control 01400
Temporary Facilities and Controls 01500
Mobilization 01505
Site Clearing and Preparation 02110
Excavation, Trenching and Backfill 02315
Erosion and Sedimentation Control 02370
Sodding 02590
Piping General 02600
Fittings 02610
Polyvinyl Chloride (PVC) Pipe 02616
Injection Wells 02632
Valves 02800
Concrete 03300
Protective Coatings 09900
FDEP Bureau of Water Facilities Funding Supplementary Conditions FDEP
Geotechnical Exploration Appendix "A"
FDEP Permit Appendix "B"
01270
SECTION 01270
MEASUREMENT AND PAYMENT
Part I. GENERAL
1.01 Description
A Payment for all Work done in compliance with the Contract Documents, inclusive
of furnishing all manpower, equipment, materials, and performance of all operations
relative to construction of this project, will be made under Pay Items listed herein.
Work for which there is not a Pay Item will be considered incidental to the Contract and
no additional compensation will be allowed.
B The Contractor shall take no advantage of any apparent error or omission in the
Drawings or Specifications, and the Engineer shall be permitted to make corrections and
interpretations as may be deemed necessary for fulfillment of the intent of the Contract
Documents.
C The Engineer will make measurements and determinations as necessary to
classify the work within pay items and determine the quantities for pay purposes.
D Where pay item numbers are shown on the bid form, they generally follow FDOT
pay item number formatting; however, they are only provided in order to use them for
pay application purposes. FDOT pay item descriptions do not apply; utilize the
descriptions on the bid form and within this section to determine the work associated
with each pay item.
Part II. PAY ITEMS
2.01 Mobilization
A Work Includes preparatory work and operations in mobilizing for beginning work
on the project, including, but not limited to, those operations necessary for the
movement of personnel, equipment, supplies and incidentals to the project site.
Mobilization shall not exceed 5% of the total Bid.
B Bonds, insurance and taxes as required by the General Conditions.
2.02 Preconstruction Video
A Work Includes preconstruction documentation via videotaping plus all digital
color photographs necessary to pick up detail not easily visible or apparent on the
videotape. This work is considered incidental to the rest of the work and is not paid for
as a separate line item.
01270
2.03 Maintenance of Traffic
A Work Includes the construction and maintenance of any necessary detour
facilities; the providing of necessary facilities for access to residences and businesses
along the project; the furnishing, installation and maintenance of traffic control and
safety devices during construction; daily inspections of the traffic control devices
(including nighttime inspections); replacement of all equipment and devices found not
to be conforming with approved standards during the inspection; the control of dust,
and any other special requirements for safe and expeditious movement of traffic as may
be called for on the plans. The term “Maintenance of Traffic” shall include all such
facilities, devices, and operation as are required for the safety and convenience of the
public as well as for minimizing public nuisance; all as required by the FDOT, the
Engineer and the Owner. This work shall also consist of the removal of existing
pavement markings necessary in order to implement traffic control, temporary signs,
and the removal or relocation of existing signs in order to implement traffic control. This
item also includes any adjustments necessary to the traffic control devices under
emergency conditions. This work is considered incidental to the rest of the work and is
not paid for as a separate line item.
2.04 Erosion and Sediment Control
A Work Includes preparation and implementation of stormwater pollution
prevention control plan, including monitoring, inspecting, and reporting, providing
erosion and sediment control measures, preparing and filing EPA NPDES NOI and NOT
forms, and providing required contractor certifications. This work is considered
incidental to the rest of the work and is not paid for as a separate line item.
2.05 Silt Fence
A Work Includes installation and maintenance of silt fence per FDOT Index No. 102.
This work is considered incidental to the rest of the work and is not paid for as a
separate line item.
2.06 Shallow Wells Upgrade
A Work Includes all labor and materials necessary for installation of two (2) class V
waste water disposal injection wells, any required testing, completion reports, piping,
valves, appurtenances, and abandonment of two (2) existing Class V wells as shown on
the construction drawings. Including all field verifications, layout, shoring, bracing,
disposal of unsuitable or excess material, site clean-up and restoration of damaged sod
and pavement damaged during the installation.
B Unit of measurement is Lump Sum.
Part III. EXECUTION - NOT USED
END OF SECTION
01300
SECTION 01300
SUBMITTALS
PART I - GENERAL
1.0 Construction Schedules
1.01 The CONTRACTOR shall submit two copies of Progress Schedules indicating the starting and
completion dates of the various stages of the work and estimated payments during the next three
months to the ENGINEER. The proposed Progress Schedules shall be submitted to the ENGINEER
prior to the preconstruction meeting. The CONTRACTOR shall distribute copies of the Progress
Schedules during the preconstruction meeting for discussion. The Progress Schedules shall be
updated by the CONTRACTOR and submitted to the ENGINEER, as a part of applications for
progress payments, through completion of the Work. Failure to update progress schedule may be
the basis for rejection of applications for progress payments.
1.02 The CONTRACTOR, if applicable, shall submit two copies of Schedules of Value of the work to
the ENGINEER. A preliminary Schedule of Values shall be submitted by the CONTRACTOR prior to
the preconstruction meeting. A final Schedule of Values, prepared in accordance with Article 14.1
of the General Conditions and presented in sufficient detail to serve as the basis for payments
during construction, shall be submitted to the ENGINEER for approval at least ten (10) days prior to
submitting the first Application for payment.
1.1 Applications For Payment
1.11 The CONTRACTOR shall submit Applications for payment to the ENGINEER in accordance
with the provisions of Article 14 of the General Conditions. Applications for Payment shall be
made on forms provided by or approved by the ENGINEER.
1.2 Shop Drawings, Product Data and Samples
1.21 The CONTRACTOR shall submit shop drawings, product data and samples, as required by the
individual Specification Sections and for ALL materials used in the Project, to the ENGINEER for
review in accordance with the provisions of Paragraphs 6.24 through 6.28, inclusive, of the General
Conditions. The CONTRACTOR shall submit and maintain a submittal log with a list of all submittals
for the Project together including review status, submittal dates, review dates etc.
1.22 Shop drawings shall be presented in a clear and thorough manner. Details shall be identified
by reference to Contract Drawing Number and Detail and Contract Specification Section and Page
Number.
1.23 The product data shall be presented in a clear and thorough manner, identified the same as
the shop drawings. Included with the information shall be performance characteristics and
01300
capacities depicting dimensions and clearances required. The manufacturer's standard schematic
drawings and diagrams shall be modified to delete information which is not applicable to the work.
Manufacturer's standard information shall be supplemented to provide information specifically
applicable to the work.
1.24 Samples shall be of sufficient size and quantity to clearly illustrate functional characteristics
of the product with integrally related parts and attachment devices depicting full range of color,
texture and pattern.
1.25 The CONTRACTOR shall make submittals in accordance with the approved schedule, and in
such sequence as to cause no delay in the work or in the work of any CONTRACTOR. No damages
will be awarded or extension of time granted due to the shop drawing and product data review
process.
1.26 The CONTRACTOR shall submit an entire package of shop drawings and product data
information for major items of work so that the ENGINEER can review the package as a unit.
1.27 The number of submittals required shall be six (6) copies of each shop drawing or product
data information sheet. Submittals shall contain the following information:
1. Field dimensions, clearly identified as such.
2. Relation to adjacent or critical features of the work or materials.
3. Applicable standards, such as ASTM or Federal Specification Numbers.
4. Identification of deviations from Contract Documents.
5. Identification of revisions on re-submittals.
6. CONTRACTOR'S stamp indicating as a minimum the Project Title, Date of
Submission, Date of Previous Submission, and Contract Specification Section
Reference which shall be initialed or signed, certifying the review and approval of
submittal per General Conditions, verification of products, field measurements and
field construction criteria, and coordination of the information within the submittal
with requirements of the work and of Contract Documents.
1.28 The ENGINEER shall affix a stamp and initials or signature and indicate confirmation or
requirements for re-submittal. The ENGINEER shall return to the CONTRACTOR three (3) copies of
the product data information for distribution or for resubmission.
1.29 The CONTRACTOR shall make all corrections or changes in the submittals required by the
ENGINEER and resubmit. The CONTRACTOR shall indicate any changes which have been made
other than those requested by the ENGINEER.
1.3 Specification Section Requirements
1.31 Miscellaneous schedules, field reports, test reports, affidavits, certificates, permits,
agreements and other items identified in the Technical Specification Sections, or as requested by
01300
the ENGINEER shall be submitted to the ENGINEER in duplicate. As a minimum, these submittals
should be identified with the Project File, Date of Submission, and Contract Specification Section
Reference.
1.4 Manufacturer's Operation And Maintenance Data
1.41 The CONTRACTOR shall furnish five (5) copies of all operation and maintenance data required
by the various Technical Sections. Prior to 50 percent completion of the Project, the CONTRACTOR
shall have submitted one (1) acceptable copy to the ENGINEER for review.
1.42 The operation and maintenance data shall be bound in a suitable three-ring binder(s). A
Table of Contents shall be provided in the front of each binder to list the various sections of the
Manual.
1.43 The information to be provided in each section for each piece of equipment and project
component shall include but not be limited to: detailed equipment drawings; sections cut through
all of the major equipment and sub-assemblies; installation and operational procedures; complete
wiring and piping schematics; lubrication materials and procedures; maintenance procedures; and
parts lists complete enough to permit identification of parts by nomenclature, number and use.
1.44 At the front of each section a maintenance schedule shall be provided for each piece of
equipment in the section. The schedule shall display the daily, weekly, monthly, semi-annual,
annual or fraction thereof, lubrication and preventative maintenance required in order to meet
warranty conditions and the manufacturer's recommendations for optimum performance and life
of the unit. A common schedule format is to be developed and used for all of the sections.
1.5 Photographs
1.51 When required in the Contract the CONTRACTOR shall furnish the ENGINEER a total of four
(4) prints, two (2) black and white and two (2) color photographs each month during construction
of the project. Prints shall be 8 inches x 10 inches and shall be inserted in transparent sheet
protection suitable for binding. All photographs shall be taken at such times and of such views as
the ENGINEER directs. The following information shall be placed on the back of the photos: job
name, contract number, description of view and date of photograph. The CONTRACTOR, at the
completion of the job, shall submit to the ENGINEER all negatives.
1.52 The CONTRACTOR shall submit photographs monthly along with the Application for progress
payment as described in Article 14 of the General Conditions.
1.6 Audio-Video Survey
1.61 When required in Contract, the CONTRACTOR shall furnish the ENGINEER with an "Audio-
Video Survey" record of the existing conditions prior to the start of construction. CONTRACTOR
01300
must enlist the services of a firm having a minimum of one years experience in audio-video
recording of construction projects.
1.62 Complete coverage shall include all surface features located within the public right-of-way,
easement areas and adjacent private properties up to building line when such properties lie within
the zone of influence of construction and will be supported by appropriate audio description made
simultaneously with video coverage. Such coverage shall include but not be limited to all existing
driveways, sidewalks, curbs, ditches, roadways, landscaping, trees, culvert, headwalls and retaining
walls, or buildings located within such zone of influence.
1.63 When conventional wheeled vehicles are used, the distance from the camera lens to the
ground shall be not less than twelve (12) feet to ensure proper perspective.
1.64 All recording must be made on continuous running audio- video DVD’s.
1.65 Audio-video to be on DVD standard format suitable for play-back on video color equipment
and standard computers.
1.66 Houses and buildings shall be identified visually by house number, when visible, in such a
manner that structures of the proposed system can be located by reference. In all instances,
however, location shall be identified by audio or visual means at intervals not to exceed 100 linear
feet in the general direction of travel.
1.67 The rate of speed in the general direction of travel of the conveyance used during taping shall
not exceed 30 feet/minute. Panning rates and zoom-in, zoom-out rates shall be controlled
sufficiently such that stop action during play-back will produce clarity of detail of the object
viewed.
1.68 All recording shall be done during times of good visibility. No recording shall be done during
periods of visible precipitation, or when more than 10% of the ground area is covered with
standing water, unless otherwise authorized by the OWNER.
1.69 Any recorded coverage not acceptable to OWNER shall be re-recorded at no additional
charge.
1.70 The audio-video recording shall be done prior to placement of materials or equipment on the
construction area and furnished at a minimum of one week prior to the preconstruction meeting.
1.71 To preclude the possibility of tampering or editing in any manner, all video recordings must,
by electronic means, display continuously and simultaneously generated transparent digital
information to include the date and time of recording, as well as the corresponding engineering
stationing numbers. The date information will contain the month, day, and year. For example,
10/5/92, and be placed directly below the time information. The time information shall consist of
01300
hours, minutes, and seconds, separated by colons. For example 10:35:18. This transparent
information will appear on the extreme upper left hand third of the screen.
END OF SECTION
01310
SECTION 01310
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 Section Includes
Meetings, construction progress documentation, submittals, record documents
1.02 Preconstruction Meeting
The Owner will schedule a preconstruction meeting prior to beginning the Work
to review shop drawing procedures, submittal requirements, and construction
administration requirements (project coordination and communication). The
Contractor shall bring to the preconstruction meeting the proposed construction
schedule, which will be reviewed with the Owner during the meeting.
1.03 Definitions
A. Shop Drawings - Shop drawings are original drawings, prepared by the
Contractor, a subcontractor, supplier, or distributor, which illustrate some
portion of the Work; showing fabrication, layout, setting, or erection details.
Shop drawings shall be prepared by a qualified detailer and shall be identified by
reference to sheet and detail numbers on the Contract Drawings
B. Product Data - Product data are manufacturer's standard schematic drawings
and manufacturer's catalog sheets, brochures, diagrams, schedules,
performance charts, illustrations, and other standard descriptive data. Catalog
sheets, brochures, etc., shall be clearly marked to identify pertinent materials,
products, or models.
C. Samples - Samples are physical examples to illustrate materials, equipment, or
workmanship and to establish standards by which work is to be evaluated.
1.04 Submittal Requirements
A. Prior to submission, thoroughly check shop drawings, product data, and samples
for completeness and for compliance with the Contract Documents. Verify all
field measurements, quantities, dimensions, specified performance criteria,
01310
fabrication, shipping, handling, storage, assembly, installation, and safety
requirements.
B. Coordinate the submittals with the requirements for other related work.
C. Notify the Engineer, in writing at the time of submission, of deviations in
submittals from the requirements of the Contract Documents. The Contractor's
responsibility for deviations in submittals from the requirements of the Contract
Documents is not relieved by the Engineer's review of submittals, unless the
Engineer gives written acceptance of specific deviations.
D. Submit at least six (6) copies of each shop drawing and product data. The
specific number of copies required of all submittals will be determined during
the preconstruction meeting. Submit the number of samples indicated in the
individual Specification Sections.
E. Where a specific product manufacturer and model number is listed in individual
specification sections and is proposed by the Contractor to be used, full
submittal of product data is not required. In this case, submit in letter format
the name of the product, manufacturer, model number, specification section,
and name of project. Certify the identified product is proposed to be used in the
project.
F. Shop drawings, product data, and samples shall be accompanied by a letter of
transmittal referring to the name of the project and to the specification page
number and/or Drawing number for identification of each item. Submittals for
each type of work shall be numbered consecutively, and the numbering system
shall be retained throughout all revisions.
G. Submittals shall bear the Contractor's stamp of approval certifying that they
have been checked and indicate appropriate specification section and/or
drawing location. Submittals without the Contractor's initialed or signed
certification stamp and submittals which, in the Engineer's opinion, are
incomplete, contain numerous errors or have not been properly checked, will be
returned unchecked by the Engineer for resubmission.
H. Begin no work which requires submittals until return of submittals with Engineer
stamp and initials or signature indicating the submittal has been approved.
1.05 Engineer Review of Submittals
A. Engineer’s review and approval of submittals will not extend to means, methods,
techniques, sequences, procedures of construction or to safety precautions.
01310
B. The review and approval of a separate item will not indicate approval of the
assembly in which the item functions. Engineer’s review and approval of
submittals shall not relieve Contractor from responsibility for any variation from
the requirements of the Contract Documents.
C. The Engineer will review submittals with reasonable promptness. The Engineer's
review of submittals shall not be construed as a complete check and shall not
relieve the Contractor from responsibility for complete compliance with the
Contract requirements.
D. No corrections, changes, or deviations indicated on submittals reviewed by the
Engineer shall be considered as a change order.
E. Where review of submittals is required by the Owner of other agencies, the
Engineer will forward the appropriate submittal(s) to these parties after Engineer
review. Once review of all parties is complete, the submittal(s) will be returned
to the Contractor reflecting the review of all parties
F. If the submittal is not satisfactory, one copy of the submitted item will be
retained by the Engineer and all other copies returned to the Contractor for
appropriate action.
G. In the event a third submittal is required, due to previous submittals of
incomplete or incorrect data or not in compliance with the Contract Documents,
the Contractor will be charged one-half of the cost incurred by the Engineer for
the review of the third submittal. The Contractor shall bear the total cost
incurred by the Engineer for all subsequent reviews. The Engineer costs charged
to the Contractor will be at the cost plus rate generally charged by the Engineer
and will be deducted by the Owner from payments due to the Contractor.
H. Distribution of copies of acceptable submittals will be as mutually determined by
the Contractor, Owner, and Engineer on an individual item basis during or
following the preconstruction conference.
1.06 Progress Meetings
A. The frequency of progress meetings shall be determined during the
preconstruction meeting. As a minimum, progress meetings shall be held once
per month during construction.
B. The Contractor and Owner shall attend the progress meetings.
C. The Contractor shall provide a meeting agenda and keep minutes of each
progress meeting.
01310
1.07 Record Drawings
A. As the Work progresses, the Contractor shall be responsible for recording
information on the approved Contract Documents concurrently with
construction progress. This field copy shall be maintained in the field office in
clean and legible condition. It shall be available for inspection by the Owner or
Engineer at any time. It shall also be provided to the Engineer as shown in item
1.07.F.
B. Mark on the Contract Drawings all changes in direction, elevation and location of
structure, piping, equipment, electrical, and mechanical work.
C. If requested, mark on the Specifications the manufacturer, trade name, catalog,
and supplier of each product actually installed, and mark changes made by
Change Order or Field Order.
D. All Record Drawings shall be prepared by Contractor in ACAD format using base
drawings provided by Engineer. As-built information shall be field verified,
measured, certified, signed and sealed by the Contractor’s licensed Surveyor
who will be responsible for the accuracy of all dimensions and elevations.
E. The as-built information shown on the Record Drawings is to include, but not be
limited to, the following:
1. Horizontal locations and vertical elevations for all installed utility lines and
storm structures including but not limited to manholes, valves, inlets and
cleanouts, etc.
2. Distance along pipelines between valves.
3. Vertical elevations of all pipelines at crossing of potable water mains
(whether the water main is existing or new) in order to document that the
minimum required vertical separation has been met.
4. Utility pipeline tied horizontally to edge of pavement and right-of-way lines,
located every 200-ft. plus all changes in horizontal offset.
5. Horizontal and vertical data for any construction that deviates from the
approved engineering drawings.
6. Where the plans contain specific horizontal location data, such as station and
offset, the as-built drawings are to reflect the actual horizontal location.
01310
7. Where the plans contain specific vertical elevation data, the as-built drawings
are to reflect the actual measured vertical elevation.
F. Deliver to Engineer one set of Record Drawings signed and sealed by
Contractor’s surveyor plus one electronic copy (ACAD format) of the drawings.
Also deliver the original red-line field copy to the Engineer. Surveyed record
drawings must be included each month with payment application packet.
END OF SECTION
01315
SECTION 01315
PRECONSTRUCTION VIDEO
PART 1 GENERAL
1.01 Description
Provide continuous color audio-video recording along the entire length of all
proposed work prior to construction to serve as a record of pre-construction
conditions. Supplement audio-video recordings with color photographs (digital)
for areas which require details not ascertainable on the recording.
1.02 Related Requirements
Section 01300 - Administrative Requirements
1.03 Qualifications
The preconstruction audio-video recording shall be of professional quality that
will clearly log an accurate visual description of existing conditions. Any portion
of the recording not acceptable for the determination of the existing conditions
shall be re-recorded at no additional cost to the Owner.
PART 2 PRODUCTS
2.01 General
The total audio-video recording system and the procedures employed in its use
shall be such as to produce a finished product that will fulfill the technical
requirements of the project. The video portion of the recording shall produce
bright, sharp, clear pictures with accurate colors and shall be free from
distortion, tearing, rolls or any other form of picture imperfection. The audio
portion of the recording shall produce the commentary of the camera operator
with proper volume, clarity, and be free from distortion. The recording system
shall utilize EIA standard video and NTSC compatible color.
2.02 Camera
The color video camera used in the recording system shall have EIA Standard:
NTSC type color - 1.0 V 75 Ohms.
2.03 Recorder
01315
The recording shall be made in standard DVD format. The recorder shall record
the color signal with a minimum horizontal resolution of 525 lines, 60 fields;
NTSC color signal; RF modulated - 72dB.
2.04 DVD Media
The DVD media used for the recordings shall be high quality, high resolution,
media able to be played back on any computer or standard DVD player. The DVD
media shall be new and thus shall not have been used for any previous
recording.
2.05 Video Tape Playback Compatibility
The recorded DVD’s shall be compatible for playback with any standard DVD
player or computer.
PART 3 EXECUTION
3.01 General
A. The recordings shall contain coverage of all surface features located within the
construction's zone of influence. The construction's zone of influence shall be
defined (1) as the area within the permanent and temporary easements or right-
of-way, and areas adjacent to these areas which may be affected by routine
construction operations, and (2) by the direction of the Owner. The surface
features within the construction's zone of influence shall include, but not be
limited to, all roadways, pavements, curbs, driveways, ponds, sidewalks,
culverts, headwalls, retaining walls, buildings, landscaping, trees, shrubbery, and
fences. Of particular concern shall be the existence of any faults, fractures, or
defects. Recorded coverage shall be limited to one side of the street at any one
time and shall include all surface conditions located within the zone of influence
of construction supported by appropriate audio description.
B. The recording of each video segment shall be a simultaneously recorded with the
audio recording. This audio recording, exclusively containing the commentary of
the camera operator, shall assist in viewer orientation and in any needed
identification, differentiation, clarification, or objective description of the feature
being shown in the video portion of the recording. The audio recording also shall
be free from any conversations between the camera operator and any other
production technicians.
C. All DVD’s shall be permanently labeled and shall be properly identified by project
title, number and date of recording.
01315
D. Each DVD shall have a log of that media’s contents. The log shall describe the
various segments of coverage contained on that video tape in terms of the
names of streets or easements, coverage beginning and end, directions of
coverage, and video unit counter/segment numbers.
3.02 Recording Schedule
A. The recording shall be performed prior to the placement of any construction
materials or equipment on the proposed construction site.
B. The Contractor shall coordinate the recording with the construction schedule so
that those portions of the construction that will be completed first will be
recorded first. The recording company shall deliver the video tape recordings to
the Owner upon their completion. Upon delivery of the DVD’s, transfer of
ownership of those DVD’s shall be made to the Owner.
3.03 Visibility
All recordings shall be performed during times of good visibility. No recording
shall be done during periods of significant precipitation, mist, or fog. The
recording shall only be done when sufficient sunlight is present to properly
illuminate the subject, and to produce bright, sharp video recordings of those
subjects. No taping shall be performed when more than 10% of the area to be
taped contains debris or obstructions unless otherwise authorized by the
Engineer.
3.04 Continuity of Coverage
A. In order to increase the continuity of the coverage, the coverage shall consist of
a single, continuous, unedited recording which begins at one end of a particular
construction area. However, where coverage is required in areas not accessible
by conventional wheeled vehicles and smooth transport of the recording system
is not possible, such coverage shall consist of an organized, interrelated
sequence of recordings at various positions along that proposed construction
area (e.g., wooded easement area).
B. The average rate of travel during a particular segment of coverage (e.g.,
coverage of one side of the street) shall be directly proportional to the number,
size, and value of the surface features within that construction area's zone of
influence.
3.05 Camera Height and Stability
01315
When conventional wheeled vehicles are used as conveyances for the recording
system, the distance between the camera lens and the ground shall not be less
than 10 feet. The camera shall be firmly mounted, such that transport of the
camera during the recording process will not cause any unsteady picture.
3.06 Camera Control
Camera pan, tilt, zoom-in, and zoom-out rates shall be sufficiently controlled
such that recorded objects will be clearly viewed during video tape playback. In
addition, all other camera and recording system controls, such as lens, focus, and
aperture, video level, pedestal, chroma, white balance, and electrical focus, shall
be properly controlled or adjusted to maximize recorded picture quality.
3.07 Viewer Orientation Techniques
The audio and video portions of the recording shall maintain viewer orientation.
To this end, overall establishing views and visual displays of all visible house and
building addresses shall be utilized. In easements where the proposed
construction location will not be readily apparent in the video tape viewer, highly
visible yellow flags shall be placed in such a fashion as to clearly indicate the
proposed centerline of construction.
3.08 Areas to be Recorded
A. The Contractor shall be able to televise and record areas with paved roads, along
easements, through parks, lawns, and open fields and inside buildings. When
recording on private property, the Contractor shall give the Owner sufficient
prior notice of such entry so that property owners may be advised of, and their
permission obtained for, the work.
B. At no time shall the Contractor be allowed to use any electrical circuits within
private property building structure. All recording shall be done during regular
business hours, unless otherwise specified by the private property owner or the
Engineer. The Contractor shall enter and leave private property in a professional
and orderly, workmanlike manner.
END OF SECTION
01400
SECTION 01400
GENERAL QUALITY CONTROL
Part I. GENERAL
1.01 DESCRIPTION OF REQUIREMENTS
(A) Definitions:
(i) Specific quality control requirements for the work are indicated throughout the
Contract Documents. In particular, quality control provisions for manufactured
products are specified in individual work sections and in other related sections of the
specifications; and are not repeated in this section. The requirements of this section
are primarily related to the performance of the work beyond the furnishing of
manufactured products. The term "Quality Control" includes, but is not necessarily
limited to, inspection and testing and associated requirements. This section does not
specify or modify the Engineer's duties relating to Contract quality review and
observation.
1.02 QUALITY ASSURANCE
(A) General Workmanship Standards:
(i) Except as more definitively specified in other sections of the specifications, comply
with the recognized workmanship quality standards within the industry as applicable
to each unit of work, including ANSI standards where applicable. It is a requirement
that each category of tradesman or installer performing the work be pre-qualified, to
the extent of being familiar with the applicable and recognized quality standards for
his category of work, and being capable of workmanship complying with those
standards.
1.03 SUBMITTALS
(A) Refer to Section 01300 for the general submittal requirements applicable to inspection
and test reports, project photographs, damage surveys, quality control samples,
maintenance agreements, guaranties, warranties, and similar documentation of quality
compliances as required. Refer to the individual work sections of the specifications for
specific certification and submittal requirements.
(B) Copies and Distribution: Where inspection and test reports and certifications are
required by governing authorities, provide additional copies as required, and, where
required, send copies directly from inspection or testing agency to governing authority.
1.04 PRODUCT DELIVERY-STORAGE-HANDLING
(A) Materials, supplies, and equipment delivered to the site shall be inspected for damage,
unloaded, and stored with a minimum of handling. Delivered items shall not be stored
directly on the ground. Handle, store and protect materials and products, including
fabricated components, by methods and means recommended by the manufacturer
which will prevent damage, deterioration and losses (and resulting delays), thereby
01400
ensuring highest quality results as the performance of the work progresses. Control
delivery schedules so as to minimize unnecessary long-term storage at the project site
prior to installation. Periodically exercise equipment stored in accordance with the
manufacturer's recommendations.
(B) The Engineer may refuse to accept, or sample for testing, materials, supplies, or
equipment that have been improperly or unsuitably stored.
(C) Materials, supplies or equipment found defective or unfit for use shall not be
incorporated in the work and shall immediately be removed from the construction or
storage site and replaced with new materials, supplies or equipment by the Contractor
at no additional cost to the Owner.
(D) If, instead of requiring removal and replacement of defective items, the Owner (and,
prior to approval of final payment, also the Engineer) prefers to accept the defective
item(s), he may do so. In such case, if acceptance occurs prior to approval of final
payment, a change order shall be issued incorporating the necessary revisions in the
Contract Documents, including appropriate reduction in the Contract price; or if the
acceptance occurs after approval of final payment, an appropriate amount shall be paid
by the Contractor to the Owner.
1.05 RESPONSIBILITY FOR INSPECTIONS AND TESTS
(A) Contractors Responsibility:
(i) It will be the Contractor's responsibility to employ and pay for the services of certified
independent testing laboratories. In addition, the Contractor shall pay for all retests
required due to failure to meet specifications.
1) The certified independent testing laboratories qualifications, test procedures, forms
and quality control program shall be submitted to the Utilities Engineer for review
and approval.
2) No failure of test agencies, whether engaged by the Owner or Contractor, to perform
adequate inspections or tests or to properly analyze or report results, shall relieve
the Contractor of responsibility for the fulfillment of the requirements of the
Contract Documents. It is recognized that the required inspection and testing
program is intended to assist the Contractor, Owner, Engineer and governing
authorities in the nominal determination of probable compliances with requirements
for certain crucial elements of work. The program is not intended to limit the
Contractor in his regular quality control program, as needed for general assurance of
compliances.
(ii) Afford access and reasonable time in the construction sequence for Owner's
inspections and tests to be performed. Cooperate with agencies and provide
incidental labor and services needed for the removal and delivery of test samples, and
for inspections and taking measurements. Provide patching and restoration services
where test samples have been removed.
01400
(B) Test Agency Responsibilities:
(i) Test agencies, regardless of whether engaged by the Owner or Contractor, are not
authorized to change or negate the requirements of the Contract Documents. Each
agency shall coordinate its assigned work with the construction schedule as
maintained by the Contractor, and shall perform its work promptly so as not to delay
the work avoidably. Observations (by agencies) having a bearing on the work shall be
reported to the Engineer, in the most expeditious way possible, and shall be recorded
in writing by the agency. Agency personnel shall not interfere with or assume the
duties of the Contractor.
Part II. PRODUCTS
2.01 EQUIPMENT AND MATERIALS
(A) All equipment and materials furnished under these specifications shall be new and
unused.
Part III. EXECUTION
3.01 INSTALLATION
(A) Pre-Installation Conferences:
(i) Well in advance of the installation of every major unit of work which requires
coordination with other work, meet at the project site with installers and
representatives of manufacturers and fabricators who are involved in or affected by
the unit of work, and in its coordination or integration with other work which has
preceded or will follow. Advise Engineer of scheduled meeting dates. At each
meeting, review the progress of other work and preparations for the particular work
under consideration including, but not limited to, the requirements of the Contract
Documents, options, related change orders, purchases, deliveries, shop drawings,
product data, quality control samples, possible conflicts, compatibility problems, time
schedules, weather limitations, temporary facilities, space and access limitations,
structural limitations, governing regulations, safety, inspection and testing
requirements, required performance results, recording requirements, and protection.
Record the significant discussions of each conference, and the agreements and
disagreements, along with the final plan of action. Distribute record of meeting
promptly to everyone concerned, including the Engineer.
(ii) The Contractor shall not proceed with the work if the associated pre-installation
conference cannot be concluded successfully. Instigate actions to resolve
impediments to the performance of the work, and reconvene the conference at the
earliest date feasible.
(B) Installer's Inspection of Conditions:
01400
(i) The Contractor shall require the Installer of each major unit of work to inspect the
substrate to receive the work, and the conditions under which the work will be
performed, and to report (in writing to the Contractor) unsatisfactory conditions. The
Contractor shall not proceed with the work until unsatisfactory conditions have been
corrected in a manner acceptable to the Installer.
3.02 INSTALLATION QUALITY CONTROL
(A) Manufacturer's Instructions:
(i) Where installations include manufactured products, the Contractor shall comply with
the manufacturer's applicable instructions and recommendations for installation, to
whatever extent these are more explicit or more stringent than applicable
requirements indicated in the Contract Documents.
(B) The Contractor shall inspect each item of materials or equipment immediately prior to
installation, and reject damaged and defective items.
(i) The Contractor shall provide attachment and connection devices and methods for
securing work properly as it is installed; true to line and level, and within recognized
industry tolerances if not otherwise indicated. Allow for expansions and building
movements. Provide uniform joint widths in exposed work, organized for best
possible visual effect. Refer questionable visual effect choices to Engineer for final
decision.
(ii) The Contractor shall recheck measurements and dimensions of the work, as an integral
step of starting each installation.
(iii) The Contractor shall install work during conditions of temperature, humidity,
exposure, forecasted weather, and status of project completion which will ensure the
best possible results for each unit of work, in coordination with the entire work.
Isolate each unit of work from incompatible work, as required to prevent
deterioration.
(iv) The Contractor shall coordinate enclosure (closing-in) of work with required
inspections and tests, so as to avoid the necessity of uncovering work for that purpose.
(C) Mounting Heights:
(i) Except as otherwise indicated, the Contractor shall mount individual units of work at
the industry-recognized standard mounting heights, for the applications indicated.
Refer questionable mounting height choices to the Engineer for final decision.
(D) Adjust, clean, lubricate, restore marred finishes, and protect newly installed work, to
ensure that it will remain without damage or deterioration during the remainder of the
construction period.
END OF SECTION
01500
SECTION 01500
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
PART I - GENERAL
1.0 Land For CONTRACTOR'S Use
1.01 Site Access and Parking - The CONTRACTOR shall maintain driveways a minimum of 15 feet
wide between and around combustible materials in storage and mobilization areas.
1.02 The CONTRACTOR shall maintain traffic areas free as possible of excavated materials,
construction equipment, products and debris.
1.03 The CONTRACTOR shall not utilize existing parking facilities for construction personnel or for
CONTRACTOR'S vehicles or equipment, unless written permission from OWNER of parking facility
is obtained.
1.04 Private or Public Roads, Sidewalks and Parking Areas - The CONTRACTOR shall at all times
provide emergency access to property in the vicinity of the construction for police and fire
equipment, ambulances or other emergency vehicles to protect life, health and property.
1.1 Traffic Maintenance and Control
1.11 Road Closing - No street, road or section thereof shall be closed to through traffic unless
otherwise provided for on the Plans, Specifications, or authorized by the agency with jurisdiction
over the roads. Prior to the closing a street, road, or section thereof, the CONTRACTOR shall
provide the ENGINEER with a copy of a detour Plan approved by the agency having jurisdiction
over the roads.
1.12 In the event roads or streets are to be closed, the CONTRACTOR shall notify the local fire
department, police department, local road authority, ambulance and emergency services, and
public school system daily as to what streets will be partly blocked or closed, the length of time the
streets will be blocked or closed and when the streets will be reopened to traffic.
1.13 Maintaining Traffic - The CONTRACTOR shall provide Maintenance of Traffic plans for all area
where construction will impede the normal flow of traffic. These MOT plans shall be submitted
and approved by the ENGINEER prior to the work commencement. Construction signs and MOT
control devices shall not be placed on utility poles or other existing signs or poles.
1.14 Existing Signs - No stop sign, traffic control or warning device shall be taken down until the
agency having jurisdiction over the roads has been notified and arrangements for the immediate
reinstallation has been made. The CONTRACTOR shall provide temporary signs, traffic control
devices, warning devices, or watchmen continuously from the time the item is removed until it is
01500
reinstalled. All signs removed shall be replaced with signs meeting requirements of the agency
having jurisdiction over the roads.
1.2 Temporary Utility Services
1.21 Electricity and Lighting - The CONTRACTOR shall be responsible for and pay all costs for the
installation and removal of circuit and branch wiring, with area distribution boxes located so that
power and lighting is available throughout the construction by the use of construction-type power
cords and shall pay all costs of electrical power used.
1.22 Electrical wiring and distribution shall conform to the National Electrical Code.
1.23 Use of Water - The CONTRACTOR shall acquire any and all permits, post any bonds and pay
all fees required by the local agency having jurisdiction prior to using any hydrant as the source of
water, and reimburse the local agency for all water consumed during course of the contract at the
current rate.
1.24 Sanitary Provisions - The CONTRACTOR shall be responsible for installation, maintenance and
removal of temporary sanitary facilities for use of construction personnel. All rules and regulations
of the State and local health officials shall be observed, with precautions taken to avoid creating
unsanitary conditions.
END OF SECTION
01505
SECTION 01505
MOBILIZATION
Part I. GENERAL
1.01 GENERAL
A Mobilization shall include the obtaining of all permits; moving onto the site of all
equipment; temporary buildings, and other construction facilities; and implementing
security requirements; all as required for the proper performance and completion of the
WORK. Mobilization shall include the following principal items:
(i)Moving on to the site of all CONTRACTOR’s equipment required for first month
operations.
(ii)Installing temporary construction power, wiring, and lighting facilities.
(iii)Developing construction water supply.
(iv)Providing field office trailer for the CONTRACTOR, complete with all furnishings normal
to a field office and all utility services including telephones.
(v)Providing all on-site communication facilities, including cellular phone for the
Superintendent.
(vi)Providing on-site sanitary facilities and potable water facilities.
(vii)Arranging for and erection of CONTRACTOR’s work, site access, and storage.
(viii)Obtaining all required permits.
(ix)Having all OSHA required notices and establishment of safety programs.
(x)Having the CONTRACTOR’ Superintendent at the job site full time.
(xi)Submitting initial submittals.
(xii)Audio-Visual pre-construction record as described in Section 01315.
(xiii)Project identification and signs.
Part II. PRODUCTS - NOT USED
Part III. EXECUTION – NOT USED
END OF SECTION 01505
02110
SECTION 02110
SITE CLEARING
Part I. GENERAL
1 .01 DESCRIPTION OF WORK
(A) The extent of site clearing shall be limited to clearing those trees and brush necessary to
provide access to the construction site. All trees, which will not interfere with
construction, shall be protected from damage. Cost to protect trees, shrubs and etc. is
incidental to the project cost.
(B) Site clearing work includes, but is not limited to, the following:
(i) Protection of existing trees.
(ii) Removal of trees and other vegetation.
(iii) Muck.
(iv) Asphalt.
(v) Curb and Gutter.
(vi) Culvert Pipes.
(vii) General Pipes.
(viii) Other types of obstructions (direct or indirect) with the construction of the project.
This does not limit to only conflicts shown on the plans.
1 .02 JOB CONDITIONS
(A) The Contractor shall:
(i) Protection of Existing Improvements:
1) Provide protection necessary to prevent damage to existing improvements indicated
to remain in place.
2) Protect improvements on adjoining properties and on the Owner's property.
3) Restore damaged improvements to their original condition, as acceptable to parties
having jurisdiction.
02110
(ii) Protection of Existing Trees and Vegetation:
1) Protect existing trees and other vegetation indicated to remain in place, against
unnecessary cutting, breaking or skinning of roots, skinning and bruising of bark,
smothering of tress by stockpiling construction materials or excavated materials
within drip lines, excess foot or vehicular traffic, or parking of vehicles within drip
line.
2) Provide temporary guards to protect trees and vegetation to be left standing.
3) Water trees and other vegetation to remain within the limits of the Contract work as
required maintaining their health during the course of construction operations.
4) Provide protection for roots over ½-inch diameter cut during construction
operations. Coat the cut faces with emulsified asphalt, or other acceptable coating,
formulated for use on damaged plant tissues. Temporarily cover exposed roots with
wet burlap to prevent roots from drying out; cover with earth as soon as possible.
Part II. PRODUCTS – NOT USED
Part III. EXECUTION
1 .01 SITE CLEARING
(A) General:
(i) The Contractor shall remove vegetation, improvements, or obstructions interfering
with installation of new construction.
(ii) The Contractor shall carefully and cleanly cut roots and branches of trees indicated to
be left standing, where such roots and branches obstruct new construction.
(B) Removal of Improvements:
(i) The Contractor shall remove above-grade and below-grade improvements necessary
to permit construction, and other work as indicated.
(C) DISPOSAL OF WASTE MATERIALS
(i) Burning on Owner's Property:
1) Burning is not permitted on the Owner's property.
02110
(ii) Removal from Owner's Property:
1) The Contractor shall remove waste materials and unsuitable and excess topsoil from
the Owner's property and dispose of legally.
END OF SECTION
02315-1
SECTION 02315
EXCAVATION, TRENCHING AND BACKFILL
PART 1 GENERAL
1.01 Section Includes
A. General excavation and fill for roads, general site work
B. Sheeting, shoring and bracing
C. Compaction
1.02 Related Sections
A. Section 02370 - Erosion and Sedimentation Control
1.03 References
A. American Association of State Highway and Transportation Officials (AASHTO) latest
edition:
1. AASHTO M145 - Classification of Soils and Soil Aggregate Mixtures
2. AASHTO T180 - Moisture-Density Relations of Soils Using a 10-lb Rammer and
18-in Drop
B. American Society for Testing and Materials (ASTM) latest edition:
1. ASTM D1557 - Laboratory Compaction Characteristics of Soil Using Modified
Effort
2. ASTM D2487 - Classification of Soils for Engineering Purposes
C. Occupational Safety and Health Administration (OSHA) Regulations, including:
1. Part 1926 Subpart P – Excavations
1.04 Horizontal Directional Drilling Alternate to Trenching
HDD can be used for the forcemain that runs parallel to the roadways in lieu of open trenching
as described herein. If the contractor elects to use HDD in lieu of trenching, then the
requirements of Section 02405, Horizontal Directional Drilling apply.
02315-2
1.05 Definitions
A. Backfill = material placed in newly excavated areas to the topsoil, paving sub-grade, or
foundation level.
B. Influence Area = the area within lines sloped downward at 45degrees from the outer
edges of paving, foundations, and utility lines.
1.06 Quality Assurance
A. Field density testing frequencies:
1. One test for each 100 square feet or fraction thereof of backfill around and
under structures.
2. One test per lift per each change in type of fill.
3. One test per 1000 square feet of pavement subgrade
4. One test per each 12” layer, every 300 feet of pipe
1.07 Preconstruction Requirements
Precondition surveys and vibration monitoring are required for those areas where residential
structures are within 100 feet of the proposed construction.
PART 2 PRODUCTS
2.01 General
The contractor shall examine the site and undertake subsurface investigations, including soil
borings, before commencing the work. Key Largo Wastewater Treatment District will not be
responsible for presumed or existing soil conditions in the work area.
Contractor shall locate existing utilities in the areas of work. If utilities are to remain in place,
the contractor shall provide adequate means of protection during earthwork operations. Should
uncharted or incorrectly charted piping or other utilities be encountered during excavation, the
contractor shall consult the owner of such piping or utility immediately for directions. Payment
for damage and repair to such piping or utilities is the contractor's responsibility.
It is intended that previously excavated materials conforming to the following requirements be
utilized wherever possible.
2.02 Materials
A. Acceptable materials (suitable material): AASHTO M145 classification A-1, A-3, A-2-4, A-
2-6; ASTM D2487 classification GW, GP, GM, SM, SW, SP; unless otherwise disapproved
within the Soil and Subsurface investigation reports. No more than 5% of acceptable
materials shall pass the number 200 sieve.
02315-3
B. Unacceptable materials (unsuitable material): AASHTO M145 classification A-2-5, A-2-7,
A-4, A-5, A-6, A-7, A-8; ASTM D2487 classification GC, SC, ML, MH, CL, CH, OL, OH, PT;
unless otherwise approved within the Soil and Subsurface investigation reports. Bedding
rock material Shall be FDOT, size no. 57 as defined in the Florida Department of
Transportation, Standard Specifications for Road and Bridge Construction, Section 901,
Article 901-l.4, Table l.
C. Controlled low strength material (“excavatable flowable fill”) shall meet the
requirements of FDOT specification section 121, with a 28-day compressive strength of
80-100 psi.
The CONTRACTOR shall, upon request by Key Largo Wastewater Treatment District, make an
appropriate sample of this material available for testing by Key Largo Wastewater Treatment
District or its designated representative.
2.03 Sheeting, Shoring, and Bracing
A. The structural strength and safety of all sheeting, shoring and bracing shall be the sole
responsibility of the Contractor. Repair any damage resulting from failure to provide
adequate supports.
B. Provide timber work, shoring, bracing, sheeting, and sheet piling where necessary to
retain banks of excavations, prevent cave-in of adjacent ground, prevent displacement
of utilities and structures, and to protect public safety.
C. Contractor is solely responsible for the design, installation, and operation of dewatering
systems and their safety and conformity with local codes and regulations.
PART 3 EXECUTION
3.01 General Construction Requirements
A. Provide suitable temporary drainage channels for any water that may flow along or
across the work as specified hereafter.
B. Provide barriers, warning lights and other protective devices at all excavations during
and after normal working hours. Open excavations must be properly barricaded and
include warning tape around the area. Areas must also be “secure and safe”, if any areas
remain open after working hours. The public must be protected from unsafe and open
excavation areas.
C. Sidewalks, roads, streets, and pavements shall not be blocked or obstructed by
excavated materials, except as authorized by the Engineer, in which case adequate
temporary provisions must be made for satisfactory temporary passage of pedestrians,
and vehicles. Minimize inconvenience to public travel or to tenants occupying adjoining
property.
02315-4
D. Where necessary to place excavated material adjacent to buildings, erect barriers to
keep earth at least 4' from such buildings. Earth deposited on lawns shall be promptly
and carefully removed to preserve the turf. All trees, shrubs, and landscaping shall be
protected. Boring and jacking shall be used, if necessary, except where written
permission is granted to remove trees and shrubs.
E. If open excavations cross existing rigid surfacing, the surfacing shall be removed for a
minimum width of eighteen (18) inches beyond the anticipated edge of the excavation
per the FDOT standard detail on the Drawings. The pavement break shall be sawed to
insure a straight joint. Surface replacement shall match existing surfacing except as
otherwise indicated on the Drawings. Where open excavation is allowed along or across
public roadways, excavation, backfill, and surface replacement shall conform to the
requirements of all permits applicable thereto. In no case shall surface replacement
edges bear on less than 24" of undisturbed soil.
F. The contractor is expected to contain all construction activities within the property
boundary, right of way and easements, and other areas designated for construction. All
areas disturbed during construction shall be restored to equal or better condition,
including but not limited to grassing, landscaping, sidewalks, mailboxes, utilities, etc. No
seeding is permitted within the FDOT right-of-way, sod and restore all disturbed areas
as existing in accordance with FDOT permit and maintain for 30 days. At no time shall
the contractor disturb surrounding properties or travel on surrounding properties
without written consent from the property owner. Any repair or reconstruction of
damaged areas in surrounding properties shall be repaired by the contractor on an
immediate basis. All costs for repairs shall be the responsibility of the contractor and no
extra compensation shall be provided.
3.02 Preparation
A. Identify required lines, levels, contours, and datum.
B. Locate and identify existing utilities that are to remain and protect from damage.
C. Notify utility companies when working in close proximity to existing utilities
D. Protect plant life, lawns, fences, existing structures, sidewalks, paving, and curbs from
excavating equipment and vehicular traffic.
E. Protect benchmarks, property corners, and other survey monuments from damage or
displacement. If marker needs to be removed it shall be referenced by licensed land
surveyor and replaced, as necessary, by same.
F. Prior to placing fill in low areas, such as previously existing ditches, ponds, or lakes,
perform following procedures:
02315-5
1. Drain water out by gravity with ditch having flow line lower than lowest
elevation in low area. If drainage cannot be performed by gravity ditch, use
adequate pump to obtain the same results.
2. After drainage of low area is complete, remove mulch, mud, debris, and other
unsuitable material by using acceptable equipment and methods that will keep
natural soils underlying low area dry and undisturbed.
3. If proposed for fill, muck, mud, and other materials removed from low areas
shall be dried on-site by spreading in thin layers for observation by Engineer.
Material shall be inspected and, if found to be suitable for use as fill material,
shall be incorporated into lowest elevation of site filling operation, but not
under building or pavement subgrade or within 10'-0" of perimeter of building
subgrade or paving subgrade. If, after observation by Engineer, material is
found to be unsuitable, unsuitable material shall be removed from site.
3.03 Sheeting, Shoring, and Bracing
A. Furnish, install, and maintain, without additional compensation, sheeting, bracing,
trench boxes and other shoring support required to keep excavations within the
easement provided, to support the sides of the excavation, and to prevent any
movement which may damage adjacent pavements or structures, damage or delay the
work, or endanger life and health. Voids outside the supports shall be immediately
filled and compacted.
B. Sheeting, where required, shall be driven below the bottom of excavation so the lowest
set of whalers and struts are above the bottom of the excavation to allow necessary
working room.
C. The Engineer may direct in writing that supports in trenches be cut off at any specified
elevation, in which case Contractor shall be paid for the supports left in place.
D. Contractor may leave in place, to be embedded in the backfill of the excavation, any or
all supports for the purpose of preventing injury to persons or property, whether public
or private. However, no supports which are within 4' of the ground or pavement
surface may be left in place without written permission of the Engineer. No extra
payment will be made for supports left in place at the Contractor's option.
E. All supports not left in place shall be removed in such manner as to avoid endangering
the piping, structures, utilities or property, whether public or private. All voids left by
the withdrawal of sheeting shall be immediately filled and compacted.
F. The right of the Engineer to order supports left in place shall not be construed as
creating an obligation on his part to issue such orders. Failure by the Engineer to
exercise this right shall not relieve the Contractor from total liability for damages to
persons or property resulting from the failure of the Contractor to leave in place
sufficient supports to prevent any caving or moving of the ground adjacent to the
excavation.
02315-6
3.04 Excavation
A. Do not excavate for any structure until that structure is scheduled for construction.
Excavate only to the depth and dimensions necessary for the construction. Slope sides
of excavations in accordance with OSHA requirements and the recommendations
contained within the project geotechnical report.
B. All such excavations shall conform to the elevations and dimensions shown on the
drawing within a tolerance of plus or minus 0.10 feet and extending a sufficient distance
from footings and foundations to permit placing and removing form work, installation of
services and other construction, inspection or as shown on the Drawings. In excavating
for footings and foundations, care shall be exercised not to disturb the bottom of the
excavation. Bottoms shall be trimmed to required lines and grades to leave a solid base
to receive concrete.
C. The bottom of all excavations shall be undisturbed earth unless otherwise indicated,
and shall be approved by the Engineer before any subsequent work is started. Over
excavate a minimum of 2 feet where excavations occur within unsuitable soils, and
replace over excavated material with suitable soils.
D. Excavations carried below depths indicated on the Drawings without the previous
approval of the Engineer shall be filled with 2500 psi concrete or flowable fill to the
correct level at the expense of the Contractor.
E. Maintain excavations in good order. If the bearing capacity of the foundation soils is
reduced because the excavation is allowed to remain open prior to commencing work,
the weathered soil shall be removed and replaced with 2500 psi concrete or flowable fill
at the Owner’s discretion at the expense of the Contractor.
F. All suitable materials removed from excavation areas shall be used for the project.
Excess excavated suitable material shall be stockpiled on site at a location of the
Owner’s choosing, and shall become the property of the Owner, unless otherwise
indicated on the Drawings.
G. Suitable onsite excavated materials containing silty or slightly clayey to clayey fine sands
shall be sufficiently dried by surface spreading and discing if necessary, or by mixing
with cleaner fine sands prior to placement in fill areas.
H. Unsuitable materials within the influence area of construction shall be excavated,
removed from the site, and disposed, unless otherwise indicated on the Drawings.
I. Excavations shall be kept dry, compacted, and stable to a depth two feet below the
bottom of the excavation.
J. If portions of the bottom of excavations consist of material unstable to such a degree
that, in the opinion of the Engineer, it cannot adequately support the construction, the
bottom shall be over excavated and stabilized with approved coarse granular
02315-7
stabilization material. Depth of stabilization shall be as directed by the Engineer.
Stabilization materials shall be incidental to the Contract.
3.05 Trenching
A. Sides of trenches shall be kept as nearly vertical as possible from the trench bottom to a
level of one foot above the top of the pipe. Slope sides of trenches in accordance with
OSHA requirements and the recommendations contained within the project
geotechnical report.
B. Excavate trenches to depth indicated or required for indicated flow lines and invert
elevations. Over excavate trenches a minimum of 2 feet where excavations occur within
unsuitable soils, and replace over excavated material with suitable soils.
C. Where rock is encountered, carry excavation 6 inches below scheduled elevation and
backfill with a 6 inch layer of crushed stone or gravel prior to installation of pipe.
D. For pipes or conduit 6 inches or larger, and other work indicated to receive subbase,
excavate to subbase depth indicated, or, if not otherwise indicated, to 6 inches below
bottom of work to be supported.
E. Except as otherwise indicated, excavate for pressure piping so top of piping is minimum
42 inch below finished grade.
F. Unsuitable excavated materials shall be removed from the site and properly disposed,
unless otherwise indicated on the Drawings.
G. Grade bottoms of trenches as indicated, notching under pipe bells to provide solid
bearing for entire body of pipe.
H. Trench bottoms shall be kept dry, compacted, and stable to a depth two feet below the
bottom of the trench.
I. Dig trenches to the uniform width required for particular item to be installed,
sufficiently wide to provide ample working room. Provide 9 -12 inch clearance on each
side of pipe or conduit.
J. If more than one pipe is to be installed in a trench, the pipes shall be spaced a minimum
of one foot apart for pipes 4 inches and larger.
K. If portions of the bottom of trenches consist of material unstable to such a degree that,
in the opinion of the Engineer, it cannot adequately support the pipe or structure, the
bottom shall be over excavated and stabilized with approved coarse granular
stabilization material. Depth of stabilization shall be as directed by the Engineer.
Stabilization materials shall be incidental to the Contract.
3.06 Trench Backfilling
02315-8
A. Following placement of pipe and inspection of joints, install tamped bedding material.
Place bedding fill materials in layers of 6 inch loose depth.
B. All bedding and backfill material shall be suitable soils or flowable fill. Backfill material
within 1 foot of pipe and appurtenances shall not contain rock or stone larger than 2
inch diameter. If a sufficient quantity of suitable material is not available from the
trench or other excavations within the site, provide additional suitable material or
flowable fill.
C. After completion of bedding and preliminary approval of piping and testing, the pipe
shall be covered to a point one foot above the top of the pipe for the full trench width,
placed in layers of 8 inch loose depth.
D. Place backfill over pipe. Where trench is within the influence area of roadways,
structures, foundations, or slabs, place backfill in layers of 8 inch loose depth. In all
other areas, place backfill in layers of 12 inch loose depth.
E. Take necessary precautions not to cause settlement or damage to adjacent slabs, walls,
structures, or foundations. Place backfill and fill materials evenly adjacent to structures,
without wedging against structures or displacement of piping or conduit.
3.07 Minor Structural Excavation and Backfilling
A. Minor structures are defined as manholes, junction boxes, inlets, valve vaults, vacuum
pits and meter vaults. Do not excavate for any structure until that structure is
scheduled for construction. Excavate only to the depth and dimensions necessary for
the construction.
B. The bottom of all excavations shall be undisturbed earth unless otherwise indicated,
and shall be approved by the Engineer before any subsequent work is started. Over
excavate a minimum of 2 feet where excavations occur within unsuitable soils, and
replace over excavated material with suitable soils.
C. Excavations carried below depths indicated on the Drawings without the previous
approval of the Engineer shall be filled with 2500 psi concrete or flowable fill at the
Owner’s discretion to the correct level at the expense of the Contractor.
D. Maintain excavations in good order. If the bearing capacity of the foundation soils is
reduced because the excavation is allowed to remain open prior to commencing work,
the weathered soil shall be removed and replaced with 2500 psi concrete or flowable fill
at the Owner’s discretion at the expense of the Contractor.
E. Do not backfill until new concrete has properly cured, coatings have been approved, and
any required tests have been accepted.
02315-9
F. Fill within the influence area of roadways, structures, foundations, or slabs, shall be
placed in layers of 8 inch loose depth. In all other areas, place fill in layers of 12 inch
loose depth.
G. Exercise care during backfilling operations to avoid any puncture, break or other
damage to waterproofing systems, if any. Backfill adjacent to waterproofing in the
presence of the Engineer.
H. Where backfilling is required on both sides of structures, backfill and compact
simultaneously on opposite sides in even layers. Other backfilling sequences shall be as
specifically noted.
3.08 Filling
A. All fill material shall be suitable soils or flowable fill. Fill placed within 1 foot of
structures shall not contain rock or stone larger than 2 inch diameter. If a sufficient
quantity of suitable material is not available from other excavations within the site,
provide additional suitable material or flowable fill.
B. Fill within the influence area of roadways, structures, foundations, or slabs, shall be
placed in layers of 8 inch loose depth. In all other areas, place fill in layers of 12 inch
loose depth.
C. Take necessary precautions not to cause settlement or damage to adjacent slabs, walls,
structures, or foundations. Place fill materials evenly adjacent to structures, without
wedging against structures.
D. Where filling is required on both sides of structures, fill and compact simultaneously on
opposite sides in even layers.
3.09 Compaction
A. Unless otherwise indicated, the type of equipment and number of passes required to
obtain the specified degree of compaction shall be determined at the site, subject to the
approval of the Engineer.
B. The contractor shall control soil compaction during construction to provide the
percentage of maximum density specified. The contractor and KLWTD shall be provided
copies of all soils testing reports, prepared by a GEOTECHNICAL/SOILS ENGINEER,
demonstrating compliance with these specifications.
3.10 Testing and Cleanup
A. Before compaction, moisten or aerate each layer as necessary to provide optimum moisture
content. Do not place backfill or fill material on surfaces that are muddy, frozen, or contain
frost or ice.
02315-10
B. In general, one compaction test shall be taken for each 12” layer of fill for each 300 feet of
pipe or between manholes, whichever is less. Compaction tests around structures shall be
taken every 100 square feet for each 12” layer of fill. Compaction tests shall be taken at
staggered locations and elevations throughout the length of the pipe section or around the
perimeter of the structure. KLWTD may determine that more compaction tests are required
to certify the installation depending on field conditions.
C. Water shall not be allowed into the filled and compacted area until density tests have
determined that the compacted area meets the specification minimum requirements.
D. Noncohesive soils shall be compacted with vibrating roller or equivalent; cohesive soils shall
be compacted with sheeps-foot roller, pneumatic tamping, or approved equivalent, unless
otherwise indicated.
E. Provide for testing and cleanup as soon as practicable, so these operations do not lag far
behind pipe installation. Perform preliminary cleanup and grading operations immediately
after backfilling.
F. All surplus excavated material shall be disposed of by the Contractor.
3.11 Field Quality Control
A. The following minimum soils compaction requirements are applicable to all work unless
a greater degree of compaction is required by the permitting authority or special
requirement of the Engineer.
a. When existing trench bottom has a density less than 95% of the maximum dry
density as determined by AASHT0/T-180, the CONTRACTOR shall compact to
required percentage of maximum density.
b. Fill or undisturbed soil from the bottom of the pipe trench to grade shall be
compacted to a minimum density of 95% of the maximum dry density as
determined by AASHTO T-180.
c. Fill under and around structures and paving, and to the extent of the excavation
shall be compacted to a minimum density of 98% of the maximum dry density
as determined by AASHTO T-180.
END OF SECTION
02370-1
SECTION 02370
EROSION AND SEDIMENTATION CONTROL
PART 1 GENERAL
1.01 Section Includes
Designing, providing, maintaining, removing temporary erosion and sedimentation controls.
1.02 Related Sections
A. Section 02230 - Site Preparation
B. Section 02240 - Dewatering
C. Section 02315 - Excavation, Trenching, and Backfilling
1.03 References
A. Florida Department of Transportation (FDOT) Standard Specifications for Road and
Bridge Construction and Roadway and Traffic Design Standards, latest editions:
1. Index No. 102 - Baled Hay or Straw Barriers and Silt Fences
2. Index No. 103 - Turbidity Barriers
3. Specification 300 - Prime and Tack Coats for Base Courses
1.04 Owner’s Instructions / Sequencing
A. Owner has authority to limit surface area of erodible earth material exposed by clearing
and grubbing, excavation, trenching, borrow and embankment operations. Owner also
has authority to direct Contractor to provide immediate permanent or temporary
erosion and sediment control measures.
B. Contractor shall respond to erosion and sediment control maintenance requirements or
implement additional measures to control erosion ordered by Owner or governing
authorities within 48 hours or sooner if required at no additional cost to the Owner.
C. Contractor will be required to incorporate permanent erosion control features into
project at earliest practical time to minimize need for temporary controls.
PART 2 PRODUCTS
2.01 Erosion Control
A. Seeding and Mulching
02370-2
B. Sodding
C. Hydro-seeding
D. Coarse Aggregate
E. Prime Coat - Per FDOT Specification 300
2.02 Sedimentation Control
A. Silt Fence - Per FDOT Index No. 102
B. Floating Turbidity Barriers - Per FDOT Index No. 103
C. Hay Bales - Per FDOT Index No. 102
PART 3 EXECUTION
3.01 Erosion Control
A. Maintain temporary erosion control systems as directed by Owner or governing
authorities to control erosion and siltation during life of contract.
B. Permanently grass cut slopes as excavation proceeds to extent considered desirable and
practical.
C. Grass all disturbed areas within 7 days of initial disturbance. Type of grassing shall be as
follows: temporary grassing to be sodding at all drainage structures, retention areas,
swales and ditches, and where slopes are steeper than 5:1. Temporary grassing can be
seed and mulch at all other locations unless otherwise indicated in the drawings or
specifications.
D. Erosion control of areas to be paved shall meet the following:
1. Install subgrade and base course materials within 48 hours of the removal/open
cutting of existing pavement consisting of streets, driveways, or sidewalk. Install
final surface courses within 14 days after removal of existing pavement.
2. Areas to receive asphalt shall receive erosion control measures no later than 48
hours after installation of base course. Temporary erosion control consists of
placement of a bituminous prime coat and sanding the surface. Permanent erosion
control consists of placement of the structural course.
3. Areas to receive concrete paving shall be either protected with a layer of FDOT
coarse aggregate material or shall be paved within 48 hours of installation of the
subgrade.
E. Dirt roads are to be stabilized and compacted within 7 days of the completion of
trenching and grading activities.
02370-3
3.02 Sedimentation Control
A. Install prior to construction.
B. Inspect every two weeks during construction.
C. Remove any sediment build-up.
D. Repair and reinstall any damaged or missing sediment control measures. Install
additional measures if inspection reveals additional sedimentation control is necessary.
E. Rough excavate and grade any proposed stormwater ponds at the start of site grading
activities. Direct site runoff to the ponds to minimize runoff to offsite areas.
END OF SECTION
02590-1
SECTION 02935
SODDING
Part I. GENERAL
1 .01 Scope
A The work to be performed under this section includes furnishing and installing all sod,
fertilizer, and other required materials as shown on the plans and as specified.
1 .02 Basis of Measurement and Payment
A Payment will be based on actual S.Y. placed for the unit price shown on the Bid Form.
1 .03 Referenced Standards
A FDOT Specifications shall mean the Florida Department of Transportation "Standards
Specifications for Road and Bridge Construction" 2010 edition unless specifically noted
otherwise.
Part II. PRODUCTS
1 .01 Materials
A Sod shall meet the requirements of Section 981-2 of the FDOT Specifications and shall
consist of Bahia grass unless shown otherwise on the drawings, or unless adjacent lawns
are of a different type.
B Fertilizer shall be as specified in Section 982 of FDOT Specifications.
Part III. EXECUTION
1 .01 Installation
A Sod shall be placed in accordance with Section 575 of FDOT Specifications and
perpendicular to the angle of sloped areas with edges in close contact, with the rows
staggered to minimize erosion. All sod will be placed within 72 hours of cutting unless
authorized by the ENGINEER. Sod will be pegged in place on slopes steeper than 3
horizontal to 1 vertical.
B All sodded areas shall be watered and maintained by the CONTRACTOR until final
acceptance of the project by the OWNER. Any washouts or other areas where sod
END OF SECTION
02600-1
SECTION 02600
PIPING – GENERAL
Part I. GENERAL
1 .01 DESCRIPTION OF WORK
(A) The work covered by this section and the related sections following consists of providing all
labor, equipment, material and supplies and performing all operations required to install the
various piping, valves, accessories, and fire hydrant assemblies for waterlines as specified and
shown on the drawings.
(B) Related Work Specified Elsewhere:
(i) Section 02315 - Excavation and Fill
(ii) Section 02614 - Ductile Iron Pipe
(iii) Section 02616 – Polyvinyl Chloride Pipe (PVC)
(iv) Section 02800 - Valves
(v) Section 02610 – Fittings
1 .02 SUBMITTALS
(A) Submittals for the various types of pipe and fittings are specified in the individual sections.
(B) Shop drawings or catalog cuts shall be submitted for all valves, boxes and restrained joints.
(C) Record drawings shall be submitted in accordance with the requirements of Section 01300 -
Submittals, and Paragraph 4 of Section 01700 - Project Closeout. The type of pipe used shall
also be noted on the drawings.
(D) Pipe elevations shall be submitted as specified under "Installation", in this Section.
(E) The manufacturer shall furnish a sworn affidavit that the pipe, fittings and lining furnished under
the Contract or Agreement comply with all applicable provisions of the ANSI and/or AWWA
Standards.
(F) Reports on pressure and leakage tests shall be submitted by the Contractor.
(G) Reports on bacteriological tests shall be submitted by the Contractor.
1 .03 JOB CONDITIONS
(A) Interruptions to utility service shall be minimized. The Contractor shall submit plans and
schedules to the Engineer for approval by the proper authority before any shutdown or any
interruption in service takes place.
Part II. PRODUCTS – NOT USED
Part III. EXECUTION
1 .01 INSPECTION
(A) All pipes shall be subject to inspection at the factory by the Engineer or Owner. The Contractor
shall provide a production schedule in sufficient time so plans can be made for in-plant
inspection of the pipe or fittings during production, should it be required.
(B) Special markings shall be plainly marked on the applicable pipe indicating the weight, proper
02600-2
location of the pipe or fitting in the line by reference to layout drawings and schedules, class of
pipe, casting period, manufacturer's mark and year pipe was produced.
1 .02 TESTS
(A) All tests shall be made in the presence of the Owner or Engineer unless waived in writing. The
Contractor shall notify the Engineer in sufficient time when tests are being conducted to allow
for travel time to the manufacturer's plant.
1 .03 INSTALLATION OF UNDERGROUND PIPING
(B) Excavation, trenching and backfilling for the installation of underground piping system shall be
as specified in Section 02222 - Trenching, Backfilling and Compacting. Pipe shall be laid in a level
trench. Irregularities shall be smoothed out or filled in with sand and tamped. Holes shall be
scooped out where the bells occur leaving the entire barrel of the pipe bearing on the pipe bed.
Locate tape shall be installed 18" below finished grade. It shall state "Caution, buried potable
main below" for water, "Caution, buried force main below" for force main, and "Caution, buried
gravity main below" for sewer.
(C) Laying of the pipe shall be commenced immediately after the excavation is started, and every
means must be used to keep pipe laying closely behind the trenching. The Engineer may stop
trenching when, in his opinion, the trench is open too far in advance of the pipe laying
operation. Pipe may be laid in the best manner adapted to securing speed and good results. It
shall, however, be in accordance with the manufacturer's instructions and recommendations.
Damaged or unsound pipe or fittings will be removed and replaced by the Contractor at no
additional cost to the Owner. Before jointing of the pipe, all lumps, blisters, excess coating
material or oil shall be removed from the bell and spigot ends of the pipe. Waterlines shall be
thrust-blocked or restrained to prevent movement of lines under pressure. Restraints or
concrete thrust-blocking shall be furnished by the Contractor. Concrete shall be a minimum
2,500 psi. For ductile iron pipe, thrust or anchor blocks or restrained joints shall be installed at
all bends, tees, crosses, wyes, plugs, and reducers as shown in details of typical thrust and
anchor block placements on the drawings. The number of feet of pipe with restrained joints
necessary for each size pipe shall be as shown on the Standard Detail drawings.
(D) Where there is no adequate natural foundation upon which to construct a pipe bed, the pipe
shall be constructed on a prepared stabilized subgrade or rock bedding of Class I materials as
defined in ASTM D2321. Unsuitable subgrade materials shall be replaced or stabilized as
described in Section 02222. Gravel or graded limerock used for pipe bedding, when ordered in
writing, shall be paid for under bid item for such material. Where dewatering is required, Class I
materials shall be used as described in ASTM D2321.
(E) Pipe and fittings shall be strung out for 1 day’s construction along the route of construction with
the spigots pointing in the direction of the flow. Pipe shall be placed where it will cause least
interference with traffic. Pipe shall be handled by mechanical equipment. Before the pipe is
lowered into the trench, it shall be swabbed or brushed out to insure that no dirt or foreign
material gets into the finished line. Trench waters shall be kept out of the pipe and the pipe
kept closed by means of a test plug whenever work is not in progress. The Contractor shall
provide the means for dewatering the trench and the cost thereof shall be included in the price
for installing the pipe.
(F) Deflections from a straight line or grade made necessary by vertical curves or horizontal curves
or offsets shall not exceed the manufacturer's recommendations. If the specified or required
alignment requires deflection in excess of those recommended, the Contractor shall either
provide special bends as approved by the Engineer or a sufficient number of shorter lengths of
pipe to provide angular deflections within the required limit.
(G) All joints shall be watertight and any leaks or defects discovered shall be immediately repaired
02600-3
to the satisfaction of the Engineer. Any pipe which has been disturbed after being laid shall be
taken up, the joints cleaned and the pipes properly relaid. Any superfluous material inside the
pipe shall be flushed or removed by means of an approved follower or scraper after joints are
made. Installation of fittings and pipe joints shall be in strict accordance with the
manufacturer's recommendations.
(H) Where water mains are stubbed out, in addition to thrust blocks, the stubouts shall be
restrained to the tee.
(I) For the protection of exposed reinforcing in anchor blocks, and any all-thread restraint methods,
the Contractor shall furnish and apply two coats of Koppers Bitumastic No. 505 protective
coating.
(J) Before backfilling, the Contractor shall take elevations on the top of the pipe barrel at 100-foot
intervals along the pipe line and at any change in grade. These elevations shall be submitted to
the Engineer.
(K) Plastic pipe shall be installed in strict accordance with the provisions of ASTM D2321-74,
including those provisions in respect to compaction of bedding and haunching material. Class IV
or Class V materials as defined in ASTM D2321 shall not be used for bedding, haunching or initial
backfill.
1 .04 CONNECTIONS TO EXISTING MAINS
(A) Where connections are required between new work and existing utility mains, the connection
shall be made in a thorough and first class manner, using proper specials and fittings to suit the
actual conditions. Use ductile iron mechanical joint sleeve for connection to existing utility
mains. In case a connection is made to an existing fitting in the line, the Contractor shall
schedule his work so that digging and locating the existing fittings can be completed prior to
starting trench work on the line. Cut-ins into lines shall be done at a time approved by the
Utilities Engineer. The Contractor shall not make any connections or service taps into existing
utility mains until their work has been tested and accepted by the Utilities Engineer.
1 .05 TESTING PIPING SYSTEM
(A) FLUSHING
(i) After the mains have been laid and pressure tested, each run of pipe shall be thoroughly
flushed so as to remove all debris and foreign matter from the lines. Flushing will ordinarily be
done by opening fire hydrants or blowoffs along the pipe line. Where fire hydrants or blowoffs
are not available or are of insufficient capacity to permit adequate flushing, the pipe line shall
be opened and flumes or piping shall be provided by the Contractor to waste the water to the
nearest approved disposal point. Sufficient flushing water shall be introduced into the mains
to produce a velocity of note less than 2-1/2-feet per second, and this rate of flow shall be
continued until the discharge is clear and no evidence of silt or foreign matter is visible.
END OF SECTION
02610-1
SECTION 02610
FITTINGS
PART 1 - GENERAL
1.1 DESCRIPTION
The Contractor shall furnish and install fittings as shown on the Drawings or as directed by the
Engineer.
1.2 QUALITY ASSURANCE
A. The Contractor shall install fittings to meet the latest revision of the AWWA specification
for the pipe material specified.
1.3 SUBMITTALS
A. Submit manufacturer's certificate of conformance.
B. Shop Drawings: Submit manufacturer's drawings and data sheets for material to be
supplied under this Section. Indicate sizes and types to be installed.
1.4 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Upon delivery and before unloading, the Contractor must inspect the fittings for any
damage occurred in transit and note such damage on the delivery ticket.
B. The means by which the fittings are unloaded is the decision and responsibility of the
Contractor. The Contractor shall follow recommendations of the manufacturer.
C. The Contractor shall follow manufacturer's recommendations for storage of fittings in
order to minimize damage prior to installation.
D. The Contractor shall adhere to the standard procedures given by the manufacturer for
handling the fittings.
PART 2 - PRODUCTS
2.1 BENDS, REDUCERS AND TEES
A. Non-Pressure Pipe: All bends, reducers and tees required shall conform to the same
standards as the pipe.
B. Pressure Pipe: All bends, reducers and tees required shall conform to the following
requirement:
1. Ductile Iron Fittings: Shall be used for all pressure pipe. They shall conform
02610-2
with the latest revision of AWWA C110 "Gray-Iron and Ductile-Iron Fittings,
Three Inches Through Forty Eight Inches for Water and Other Liquids". They
shall be mechanical joint ends with a pressure rating of 350 psi. Compact
fittings, three inches through sixteen inches (3"-16") will be acceptable. The
compact fitting shall conform to the latest revision of AWWA C153 "Ductile Iron
Compact Fitting, Three Inches Through Sixteen Inches for Water and Other
Liquids". All joints materials, including rubber gaskets, glands, tee-head bolts,
and hex-head nuts, shall conform to the latest revisions of AWWA C111,
"Rubber-Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and Fittings".
2.2 JOINT RESTRAINT SYSTEM
All yard piping shall be restrained. Restraint system for fittings shall be "MEGA LUG 1100 Series"
Joint Restraint System as manufactured by EBAA Iron, Inc. or approved equal. Length and
location of restraining shall be determined by the Engineer. All fittings four inches (4") in
diameter and larger shall be restrained as shown on the plans. The Contractor shall submit a
pipe laying schedule.
2.3 Connection of existing pressure mains to the new mains will be accomplished with solid repair
sleeve, as approved by the Engineer. Repair clamps will not be allowed.
PART 3 - EXECUTION
A. Installation of ductile iron (DIP) fittings shall be in accordance with the latest revision of
AWWA C600, "Installation of Gray and Ductile Cast Iron Water Mains and
Appurtenances" for ductile iron. For PVC fittings, installations shall be in accordance
with manufacturer's recommendations.
B. Concrete thrust blocks or "kickers" shall be installed at all fittings (fourteen-inch (14")
and smaller as shown on the detail or unless otherwise directed by the Engineer. The
Contractor shall install a poly barrier between all concrete thrust blocks and fittings.
Where in the opinion of the Engineer, conditions prevent installing a concrete thrust
block behind a fitting, a joint restraint system shall be used in lieu of the concrete thrust
block. Joint restraint system shall be installed in accordance with manufacturer's
instructions so as to prevent joint separation under operating conditions on all fittings
sixteen inches (16") and larger. All concrete thrust block shall be inspected prior to
backfill by the Engineer. NOTE: Concrete thrust blocks shall not be installed in a "wet"
condition.
END OF SECTION
02616-1
SECTION 02616
POLYVINYL CHLORIDE (PVC) PIPE
Part I. GENERAL
1 .01 DESCRIPTION OF WORK
(A) The extent of PVC pipe is shown on the drawings.
(B) Reference to standard specifications herein shall be construed as to be in reference to the latest
revision or edition.
1 .02 SUBMITTALS
(A) One original certified test report and two copies of all required test reports shall be submitted
to the Engineer with each shipment of pipe. Certification shall include all test results required
by AWWA. Also the Contractor shall include the following data:
(i) Quick Burst Test, ASTM D1599.
(ii) Drop Impact Test, ASTM D2444.
1 .03 DELIVERY AND STORAGE
(A) In storing pipe, units shall be protected by dunnage in the same way they were protected while
loaded on the truck. Pipe shall be stored flat to protect against bending.
(B) In storing pipe, units shall be protected by dunnage in the same way they were protected while
loaded on the truck. If pipe is to be stored outside longer than 15-days the pipe shall be covered
with canvas or other opaque material to protect it from prolonged exposure to the sun.
Part II. PRODUCTS
1 .01 PVC PIPE (4-INCHES AND LARGER)
(A) SEWER:
(i) Force main pipe shall be SDR-26 and gravity pipe shall be SDR-26. Pipe shall be furnished in
standard 20' lengths. Gravity sewer pipe shall be furnished in 13' or 20’ lengths. Green pipe
for gravity and force main PVC pipe.
(ii) The joints for PVC pipe shall be rubber ring type consisting of integral, thickened, solid wall
bells which maintain the same standard dimension ration as the pipe barrel. Joint lubrication
shall be as furnished by the manufacturer of the pipe and joints made in accordance with the
manufacturer's instructions and recommendations.
(iii) Where necessary, solid repair sleeves or adaptor fittings shall be furnished and installed where
plastic pipe is connected to pipes or fittings of other materials. When pipe material changes
from one type to another, solid repair sleeves shall be used to transition.
1 .02 PVC PIPE (SMALLER THAN 4-INCHES)
(A) Unless otherwise specified, all PVC pipe smaller than four-inch (4") nominal diameter shall be
Schedule 80 PVC in accordance with ASTM D1785. Schedule 80 pipe shall have either solvent
welded or threaded joints. PVC pressure pipe shall bear the approved seal of the National
02616-2
Sanitary Foundation (NSF). PVC pipe that is exposed to sunlight shall be manufactured with
additives to provide resistance to ultraviolet deterioration.
(B) FITTINGS; Socket type, solvent welded fittings for schedule 80 PVC pipe shall be in
conformance with ASTM D2467. Threaded type fittings for Schedule 80 PVC pipe shall be in
conformance with ASTM D2464. All solvent welded or threaded joints shall be watertight.
(C) FLANGES; Flanges for Schedule 80 PVC pipe shall be rated for a 150 psi working pressure with
ANSI B16.1 dimensions and bolting pattern. Flanges shall be connected to PVC piping with
either solvent welded or threaded joints in accordance with ASTM D2467 or ASTM 2464,
respectively. Gasket shall be neoprene, full faced type with a minimum thickness of 1/8-inch.
Nuts and bolts shall be hexagonal with machine threads, manufactured of Type 316 stainless
steel in accordance with ASTM A320, Class 2. Type 316 stainless steel flat washer shall be
used against PVC flanges.
(D) SOLVENT CEMENT; PVC solvent cement shall be in compliance with ASTM D2564 and in
accordance with the pipe manufacturer's recommendations.
(E) THREAD LUBRICANT: Lubricant for Schedule 80 threaded joints shall be Teflon tape only.
1 .03 High Density Polyethylene (HDPE) Pipe
(A) Pipe shall be a PE3408 high density, extra high molecular weight polyethylene manufactured
from first-quality high density polyethylene resin containing no additives, fillers, or extenders.
The HDPE pipe shall have an ASTM D3350 cell classification of PE 345434C, and shall meet or
exceed the properties listed in the following table. The HDPE pipe shall be SDR-11 Phillips Drisco
pipe Series 1000, or approved equal, and shall bear the seal of approval of the National
Sanitation Foundation (NSF).
Property Specification Unit Nominal Value
Material
Designation PPI/ASTM PE 3408
Material
Classification ASTM D-1248 III C 5 P34
Cell
Classification ASTM D-3350 345434C
Density ASTM D-1505 gm/cm3 0.955
Melt Index ASTM D-1238 gm/10 min. 0.11
Flex Modulus ASTM D-790 psi 135,000
Tensile
Strength ASTM D-638 psi 3,200
HDB @ 730F ASTM D-2837 psi 1,600
U-V Stabilizer ASTM D-1603 % C ** 2.5
02616-3
Hardness ASTM D-2240 Shore "D" 65
Compressive
Strength
(yield) ASTM D-695 psi 1,600
Tensile Strength
@ Yield ASTM D-638
(Type VI Spec) (2"/min.) psi 3,200
Property Specification Unit Nominal Value
Elongation @
Yield ASTM D-638 % minimum 8
Tensile Strength
@ Break
(Type VI Spec) ASTM D-638 psi 5,000
Elongation @
Break ASTM D-638 % minimum 750
Modulus of
Elasticity ASTM D-638 psi 130,000
Linear Thermal
Expansion Coef. ASTM D-696 in./in./0F 1.2 x 10
-4
Brittleness
Temp. ASTM D-746 0F < -180
Vicat Softening
Temp. ASTM D-1525 0F 257
(B) Fittings shall be butt fusion type, meeting the requirements of ASTM D-3261, and shall be
pressure rated to match the system piping to which they are fused. At the point of fusion, the
outside diameter and minimum wall thickness shall meet the requirements of ASTM F-714 for
the same size pipe. Fitting shall be supplied by the pipe manufacturer. Connection to dissimilar
materials shall be joined by flanges, compression couplings, or other mechanical means as
approved by the Engineer.
END OF SECTION
02632- 1
SECTION 02632
INJECTION WELLS
PART I GENERAL
Section 1.0 Scope
1.01 The work consists of the construction of two Class V wastewater disposal injection wells for Key
Largo Waste Water Treatment Facility site, as shown on the Drawings and site plan; and
performance of all appurtenant work in accordance with the Contract Documents. The well shall
be constructed with an open hole configuration.
Section 1.1 General
1.1-1 The Contractor will take necessary measures to limit access to drilling sites to minimize public
hazards.
1.1-2 The contractor shall provide a qualification statement in order to demonstrate the experience with
installation of slotted casing wells. The statement at minimum shall demonstrate at least 3
successful projects with wells of similar depth and diameter. References shall be included in the
statement.
In addition to the statement the Contractor shall provide detailed well pre-drilling, assembly,
installation and grouting procedure for Engineer's and FDEP review and approval.
1.1-3 The Contractor shall furnish sound proofing barriers, provide mufflers on equipment, and take
other steps necessary during drilling, pumping, testing, and all other work to ensure that noise
levels conform to any applicable noise ordinances.
1.1-4 The Contractor shall furnish temporary pit casing at the well site to isolate surficial deposits from
the borehole and to prevent the collapse of the drilled hole from the elevation of the bottom of the
well control structure to the ground surface if necessary based on soil conditions. Costs for
furnishing and installation shall be included in the Contractor’s costs. The grout jacket shall
terminate within 1-foot below the bottom of the well control structure elevation. Installation shall
be in accordance with Contract Documents and Drawings.
1.1-5 The Contractor shall begin work within 14 calendar days of receiving the ‘Notice to Proceed’ from
the KLWTD. The work schedule shall continue without interruption until work is completed by the
Contractor, unless authorized by the owner. The sequence of work shall be as follows:
1. Site and access video
2. Clear site and establish vertical and horizontal control with reference to NAVD
1988
3. Mobilize drill rig and provide temporary piping for water supply, if necessary
4. Drill wells as designed by engineer and approved by FDEP.
5. Drill over-drill hole to a depth shown on the plans below the finished top of casing
elevation specified on the Project Plans. Over drill diameter shall be a minimum of
4 inches greater than the outer diameter of the well casing at the widest part.
6. Set cement basket in the borehole at the casing setting depth of at least sixty (60)
feet from the top of casing elevation to the cement basket, as approved by the
engineer.
7. Provide written notification to the DEP Fort Myers Office (David Rhodes, P.G.) and
to the DEP Marathon Office (Steve Johnson) at least 72 hours prior to grouting.
8. Set and cement final casing
02632- 2
1.2 Contractor Submittals
1.2-1 All Contractor submittals shall conform to the applicable requirements of Section 01300,
Administrative Requirements, and the supplementary requirements specified. Each item listed in
Section 01300, Administrative Requirements, shall be submitted to the Engineer with a clear
explanation or depiction of why or how the requirements, as listed, will be fulfilled by products or
services provided by the Contractor. This list shall not be considered all inclusive and maybe
extended by the Owner, Engineer, or Contractor.
1.2-2 The Contractor shall furnish capable personnel experienced in the type of work required by the
Contract Documents. In addition, the following shall apply:
a. Personnel shall be subject to Engineer’s approval. If required by the Engineer, a resume will be
submitted to the Engineer for review and approval prior to assignment of personnel to the
project.
b. The Contractor shall provide the services of drillers that are: experienced with the type of
formations expected, capable of making lithologic classifications of formations, and competent
regarding drilling fluids, additives and equipment maintenance.
c. The Contractor shall provide an adequate number of helpers.
d. The drillers shall maintain legible and clean well logs and drilling reports as instructed by the
Engineer. The Contractor is responsible for submitting the well logs to the Engineer within 2
weeks of completion of each well and to the FDEP within 30 days of completion of each well.
At a minimum, the following information shall be included in the well completion report:
1. Construction activity;
2. Information on bit assembly and drill string;
3. Drilling mud and additives;
4. Fluid losses and water and fluid level changes;
5. Footage drilled and lithological classification of formations encountered;
6. Quantity of material removed during drilling and location of disposal;
7. Length of pipe segments;
8. Cementing operations;
9. Maintenance and repair time along with details of repairs;
10. Presence and times of Contractor’s personnel and sub-contractor’s personnel;
11. Presence and times of City and Engineering personnel or others;
1.2-3 The Contractor shall submit a list of equipment proposed for use on the project. The list shall
include manufacturer’s load capabilities, horsepower, year of manufacture and year of purchase by
the present owner.
1.2-4 The Contractor shall submit a complete list of all subcontractors to be used. The Contractor may be
required to submit additional information or resumes for any of the Subcontractors proposed. As
specified in the FDEP Supplemental Conditions of the Contract Documents, the Contractor shall
provide 30.4% of the total contract value with Certified Minority Business Enterprise subcontractors
and suppliers.
1.2-5 The Contractor shall have experience cementing the type of formations encountered or provide the
services of a subcontractor with demonstrated experience in cementing.
1.2-6 The Contractor shall submit four (4) copies of a certified elevation survey to the Engineer in addition
to an electronic version. Horizontal control and vertical control (top of casing elevation) shall be
established by a State of Florida licensed land surveyor.
02632- 3
1.2-7 The Contractor shall collect samples of cement and grout during cementing of all casings. Mixed
samples shall be collected. Samples of the mixed product shall include at least three (3) two inch
cubes suitable for tests of compressive strength. Only 2-inch cubes will be acceptable as
representative cement samples for compressive strength tests. Samples shall be collected a
minimum of three (3) times during each cementing stage: Prior to pumping, at the middle, and the
end of the stage. If grout is mixed on site; mixing must be done in accordance with ASTM C 150. If
delivered by outside vendor, the vendor must demonstrate that the slurry density shall match the
specified slurry density indicated on the delivery certificate.
1.2-8 The Contractor shall ensure that the material used in sealing the casing shall consist of a neat
cement grout using Type II Portland cement conforming to ASTM C 150, and shall not contain more
than 5 gallons of water per ninety four (94) pound sack of cement. Additives may be used to speed
setting time or expand material, but shall not contain more than 2 percent by weight of calcium
chloride or 4 percent by weight of bentonite. All other additives require written FDEP approval
prior to use.
1.2-9 The Contractor shall submit to the Engineer, plans for casing installation and cementing at least 72
hours prior to commencing setting the casing and cementing the casing. The following information
shall be included:
a. tabulation of casing on site
b. length of each section of casing
c. cumulative string weight
d. locations of centralizers
e. method of emplacement of cement
f. calculation of expected mix temperature and maximum temperature well casing is
designed to withstand
g. any additives to be used
1.2-10 The Contractor shall submit to the Engineer written verification of the disposal site from the City of
Marathon prior to beginning drilling operations. The Contractor shall be responsible for providing
and maintaining all trucks, pipes, pumps, and other equipment needed to pump and haul excess
drilling fluids, drill cuttings, and produced water to authorized disposal sites in accordance with
Federal, State, and local regulations; or sub-contract with a firm capable of providing these services
when necessary.
1.2-11 The Contractor shall provide a final well description that conforms to the requirements of Section
01300, Administrative Requirements and shall show the diameter, wall thickness, depths and
lengths of casings installed; borehole diameters; depths and thickness of annular seals; quantity of
material removed during construction and any other pertinent details as required by the Engineer.
1.2-12 The Contractor shall provide one copy of any accident reports to the Engineer within 24 hours of
any accidents that occur in connection to the work.
1.2-13 The Contractor shall submit a written well abandonment plan for review by the Engineer in the
event a well must be abandoned. The plan for well abandonment shall be in accordance with
applicable rules and regulations of governmental agencies having jurisdiction. The Engineer must
approve the abandonment plan in writing prior to Contractor abandoning the well. If Contractor
voluntarily stops work and/or fails to complete a hole in a satisfactory manner in accordance with
the Contract Documents or regulatory requirements, the well will be considered abandoned. The
Contractor will not be paid for all or part of a hole declared abandoned by the Owner. Costs of
properly plugging and sealing a well or hole in accordance with applicable regulations shall be paid
by the Contractor. If Owner, upon receipt of information that indicates well completion in a
02632- 4
satisfactory manner is not warranted, the Owner may terminate work at the site. If Owner
terminates work, Contractor will be paid the value of the work completed to that time based on
unit prices in the Bid Schedule. All salvageable material furnished by the Contractor may be
removed and remain his property. Owner may direct Contractor to relocate to another site to drill
another well. Plans to abandon or relocate wells must be submitted in writing to the DEP and may
not begin until written approval from the DEP is obtained.
1.2-14 The Contractor shall submit a schedule at the Pre-Construction meeting. The schedule shall be
updated and submitted to the Engineer monthly until completion of the project. If requested by
the Engineer, the Contractor shall revise, or update the schedule, or submit a new schedule.
1.2-15 The Contractor shall maintain all records required by agencies having jurisdiction and shall submit
such records to them as required. Two copies of submitted records shall be provided to the
Engineer.
1.2-16 The Contractor shall submit applications for all necessary drilling permits from applicable State and
local regulatory agencies. The Contractor shall apply for and obtain any and all other permits that
may be required to complete the drilling of the wells.
1.2-17 The Contractor shall submit a Water Well Completion Report {South Florida Water Management
District Form LEG-R.005.00 (10/05)} to the permit issuing agency within 30 days of completion of
construction. Contractor shall submit all required DEP forms in compliance with applicable
construction permit conditions.
Section 1.3 Quality Assurance
1.3-1 At all times, all work on the well shall be in accordance with all applicable Federal, State and local
regulations.
1.3-2 If it becomes necessary to perform remedial work prior to final acceptance in order for Work to
meet regulatory requirements and/or technical specifications and contract documents due to
defective materials, accident, loss of equipment or equipment malfunction, or from any other
cause directly attributable to actions or inactions of Contractor, the Contractor shall bear the entire
cost of remediation, including any engineering costs that will be
required to meet all requirements. If problems arise, Contractor shall notify Engineer immediately.
Any work performed after well completion reports have been submitted to the DEP will require
written DEP approval.
1.3-3 The Contractor shall submit a written plan of corrective action for review to the Engineer. If
approved by the Engineer, Contractor may implement the plan of corrective action.
1.3-4 The Contractor shall properly abandon any well that is deemed unacceptable by the Engineer, and
no remuneration will be made to the Contractor for work deemed unacceptable or incomplete.
1.3-5 If Contractor must repeat work as a result of performance, all additional materials, labor, and
equipment costs shall be at Contractors expense. No claims for additional compensation shall be
allowed, except as specifically provided.
1.3-6 Contractor shall perform all work in conformance with the applicable codes and standards relating
to the referenced portions of the following documents only to the extent that the requirements are
not in conflict with the provisions of this section:
Chapter 62-528 UIC Well Regulations, Florida Administrative Code
02632- 5
Chapter 62-531 Water Well Contractor Licensing Requirements
Chapter 62-532 Water Well Permitting and Construction Requirements
ASTM C150 Specification for Portland Cement
ASTM D1784 Specification for Rigid PVC Compounds and Chlorinated PVC Compounds
ASTM D2837 Standard Test Method for Obtaining Hydrostatic Design Basis for
Thermoplastic Pipe
Materials
ASTM F480 Specification for Thermoplastic Well Casing Pipe and Couplings made in
Standard
Dimension Rations (SDR) SCH40 and SCH80.
ASTM D-2564 Standard Specification for Solvent Cements for Poly Vinyl Chloride (PVC)
Plastic Piping Systems
AWWA A100 Standard for Water Wells
Section 3.3-7 Specification for Casing Centralizers
1.3-7 Contractor guarantees that Work performed pursuant to this section and that the workmanship,
materials, and equipment supplied or used in the execution of Work are free from defects or flaws
and are furnished in strict accordance with the Contract Documents.
1.3-8 Contractor guarantees that the performance test requirements of Contract Documents shall be
met. Contractor shall repair, correct, or replace all damage to work covered by failures under this
guarantee, at his own expense. The guarantee shall remain in effect for a period of 2 years from
the date of final acceptance by the Owner.
1.3-9 Contractor shall obtain a regulated materials list from the appropriate source and shall provide
Engineer with an inventory of all regulated materials to be used on the job site. All regulated
materials, liquids, and/or substances shall be stored in secondary containment in compliance with
applicable regulations of the State. The integrity of the secondary containment shall by
demonstrated by the Contractor upon request by the Engineer.
1.3-10 Contractor shall provide safe access to the site and will assist the Engineer in the collection of
information and samples during drilling operations.
1.3-11 Contractor shall cease operations if directed by Engineer so any extra work not included in the
specifications may be performed. The Engineer will advise Contractor of the request and will work
with Contractor to schedule request so as to cause minimal delay. All standby time and extra work
is required to be approved in writing by the Engineer.
1.3-12 Contractor shall provide notice of at least 72 hours (exclusive of weekends and holidays) to
Engineer and DEP prior to any grouting or testing activities.
1.3-13 Contractor shall comply with OSHA regulations contained in 29 CFR Section 1910 (General Industry
Regulations) and Section 1926 (Construction Regulations).
Section 1.4 Storage and Protection of Materials
1.4-1 Contractor shall ensure that all materials delivered are in an undamaged condition and are stored
to provide protection against damage. Damaged materials shall be rejected. Any materials that are
damaged as a result of storage shall be replaced with new materials at the Contractors expense.
Contractor shall provide a materials storage area and shall protect both the work site and storage
area from theft, vandalism, and unauthorized entry.
02632- 6
1.4-2 Contractor shall notify Engineer immediately upon discovery of any existing structures that may
prevent construction as shown. Any field relocations 10 feet or less that do not involve locating
across a street shall be made at the discretion of the Engineer. Relocations greater than 10 feet will
be made at the direction of the Engineer, after communication with DEP has been established and
written approval to relocate the facility obtained from the DEP.
Section 1.5 Contractors Equipment
1.5-1 Contractor shall maintain all equipment so that it is clean and in good operating condition when
delivered to the job site and throughout the entire operation. All equipment shall be of adequate
size, horsepower and capacity for the project and shall be of the type successfully utilized for the
construction of similar or larger wells within the last two years. All equipment shall have required
safety devices.
1.5-2 Contractor shall be responsible for equipment maintenance, and any damage of any nature due to
the Contractors operation to the well or surrounding property and/or facilities shall be repaired or
replaced.
1.5-3 Contractor shall provide and use safety equipment at all times as required by applicable
regulations.
Section 1.6 Mobilization, Preservation, Final Cleanup and Restoration
1.6-1 Contractor shall mobilize equipment and personnel to commence drilling operations within time
limit specified.
1.6-2 Contractor shall regularly remove accumulated debris and surplus materials from work site and
store in designated yard or dispose of properly.
1.6-3 Contractor shall perform clean up work regularly and with the frequency specified by Engineer.
1.6-4 Contractor shall perform basic site restoration immediately following installation or substantial
completion of facility. Sites should be restored if partially completed facilities must remain
incomplete pending resolution of unforeseen issues. Failure to perform restoration or clean up
work may result in Engineer providing a written request to the Contractor. If, within five days of
written notification to Contractor, the requested restoration or clean up work has not been done,
Engineer may employ such labor and equipment deemed necessary to provide clean up or
restoration at Contractors expense.
1.6-5 Contractor and all subcontractors shall take all necessary precautions to prevent contaminated
water, gasoline, or other hazardous substances from entering the ground either through the well or
seepage from ground surfaces. Contractor shall maintain precautions during and after construction
of the well and until acceptance of the well by Owner. If Contractor fails to prevent contaminants
from entering the groundwater, remedial action as required by the governing regulatory agencies
shall be performed by the Contractor at the sole expense of the Contractor.
1.6-6 Contractor shall remove all equipment and unused materials upon completion of work at a site.
Any temporary structures erected for use during drilling shall be dismantled. Any minor repairs
required shall be immediately affected. All excess drilling fluids, debris and other materials used
during construction shall be removed and disposed of by the Contractor. Mud sumps and other
work excavations shall be filled, compacted and graded to return the site to a condition equal to or
02632- 7
better than the condition at the start of the work. Completion of these activities shall be within one
month of drilling.
PART II PRODUCTS
Products are listed and described throughout Part 3, Execution, and shall conform to all requirements of
Part 1.
PART III EXECUTION
Section 3.1 General
3.1-1 Contractor shall provide competent personnel and adequate equipment to complete all phases of
injection well construction.
3.1-2 Contractor shall ensure that the depth of the borehole and the length of the casings are as shown in
the drawings unless otherwise determined by the Engineer. Payment will be based on actual
quantities furnished, installed or constructed in accordance with the schedule of values.
3.1-3 Contractor shall furnish all repeat work, additional materials, labor and equipment that are a result
of performance or lack of acceptable performance. No claim for additional compensation shall be
made or be allowed except as specifically provided.
Section 3.2 Drilling Operation
3.2-1 Contractor shall evaluate the selected locations for the injection wells prior to mobilizing
equipment to determine, based on the site limitations, the appropriate method of drilling.
3.2-2 Contractor shall utilize high-grade approved clays as the drilling fluid when using the rotary method
of well construction. The drilling fluid shall possess those characteristics which will condition the
walls of the hole to prevent caving.
3.2-3 Contractor will use only fresh water in drilling fluids whether alone or in combination with drilling
additives. The only acceptable additives are calcium chloride or bentonite. The use of any other
additive must be approved in writing by the Engineer and the FDEP prior to use.
3.2-4 Contractor shall monitor drilling fluids to ensure the proper fluid is in use throughout the drilling
process. If proper control of the fluid cannot be maintained, Contractor may be required, at his
own expense, to retain or employ a qualified mud engineer during all operations in order to
supervise and maintain correct drilling fluids characteristics.
3.2-5 Contractor shall properly handle all drilling fluids during the entire drilling process. Adequate
control may include, but not be limited to, providing holding tanks for the drilling fluid, construction
of barriers to retain fluids and prevent run off to surrounding areas, erosion control, and provide
protection to the public at all times. Upon completion of drilling, all mud and cuttings resulting
from well construction shall be removed from the site and disposed of properly by the Contractor.
The ground surface shall be restored to the original, or better, condition.
3.2-6 Contractor shall not allow the use of salt or brine as a method of increasing the mud weight during
drilling. Any materials proposed for controlling the flow must be reviewed and approved by the
Engineer prior to use.
02632- 8
3.2-7 Contractor will use water as the drilling fluid for well construction when using the reverse
circulation method of construction.
3.2-8 Contractor shall maintain control over the reverse air discharge at all times and shall ensure that no
flooding or the discharge of turbid water occurs. Contractor shall submit to the Engineer a flooding
control and material disposal site for approval if the reverse air discharge method is used.
3.2-9 If auger drilling is used, the Contractor shall clear bore hole and dispose of material properly
throughout drilling process to eliminate the collection of loose material at the base of the hole.
3.2-10 Contractor shall take all measures necessary to protect the top portions of the hole from caving or
raveling.
Section 3.3 Casing
3.3-1 Contractor shall determine the depth and diameter of any surface casing required during well
construction. The casing shall be factory assembled in not less than 20 foot lengths. 20 foot
segments shall be used for the casing except shorter pieces are allowed in the final part of the well.
The ends of each joint shall be machine beveled perpendicular to the casing axis to ensure that
each section is straight. No used casing will be accepted.
3.3-2 Contractor shall not use steel casing unless approval from Engineer and FDEP is obtained prior to
use.
3.3-3 Contractor shall use casing made of un-plasticized PVC compounds having a minimum cell
classification of 12454-B as defined in ASTM D1784. Pipe shall be SDR17, SCH 40 or SCH 80 PVC
that meets the requirements of ASTM D1748 and shall be factory assembled in 20 foot lengths and
may be cut for the final part of the well. All PVC casing shall be new.
3.3-3a Slotted section of the casing shall be factory supplied with precision-machined slots. Field or
contractor shop slots cutting will not be accepted. Slot sizes and spacing shall be as shown on the
plans and details.
3.3-3b Joints shall be of mechanical kind "Certa-Lock" or Engineer approved equal.
3.3-4 Contractor shall ensure that the casing is suspended in tension from the surface. The bottom of the
casing shall be at the elevation shown on the plans. Contractor shall ensure that the hook load of
the drill rig exceeds the maximum casing weight to be encountered during the construction of the
well to prevent collapse of the casing under vertical load.
3.3-5 Contractor shall ensure that the casing is correctly positioned and at a depth acceptable to the
Engineer. If unable to correctly position casing, Contractor shall obtain prior written DEP approval
to properly abandon the hole and construct another well immediately adjacent to the original
location. This well shall be completed in accordance with Contract Documents at no additional cost
to the Owner.
3.3-6 Contractor shall withdraw and replace any collapsed casing at his expense prior to well completion.
3.3-7 Contractor shall install two casing centralizers on all casings at 0/90/180/270 degrees at twenty feet
and at forty feet. Centralizers shall be attached to PVC casing with stainless steel straps or other
02632- 9
engineer approved method. All centralizer groups shall be vertically aligned one above the other in
order to permit the passage of tremie pipes alongside the casing to the bottom of the borehole.
3.3-8 Contractor shall be responsible for ensuring the suitability of all connections along the well casing
string. Casing joints shall be standard bell joints. Casing joints shall be attached using plastic pipe
cement meeting the requirements of ASTM D-2564. No external pipe-to-pipe restraining devices
that clamp onto the pipe surface shall be allowed.
Section 3.4 Grouting
3.4-1 Contractor shall grout the annular space between borehole wall and casing by pumping cement
grout from the bottom of the casing to ground surfaces. The first stage of cement pumped into the
annulus at the base of the well casing shall be neat cement slurry. The well shall remain
undisturbed for at least 24 hours after cementing is complete.
3.4-2 Contractor shall pump cement as a slurry of thoroughly mixed components in stages that fill the
annular space without exceeding the collapse pressure of the casing pipe. Minimum setting time
between stages is 8 hours if more than one stage is required.
3.4-3 Contractor shall take whatever steps are necessary to re-open any hole that has collapsed prior to
placement of the grout seal so that the seal may be installed as required.
3.4-4 Contractor shall ensure that the casing does not move in a vertical direction during grouting.
3.4-5 Contractor shall ensure that required pressure is maintained within the casing during pressure
cementing.
END OF SECTION
02800-1
SECTION 02800
VALVES
PART I - GENERAL
1.0 Scope
1.01 This section shall cover all drain, water main, force main, air, surge, and miscellaneous valves as
shown
on the drawings and as specified.
1.1 Basis of Measurement and Payment
1.11 See Section 01270, "Measurement and Payment".
1.2 Related Technical Specifications
1.21 See Sections 02732, "force main" and 02730, “underground vacuum sewer piping”
1.3 Submittals
1.31 The CONTRACTOR shall submit complete sets of shop drawings to the ENGINEER for approval,
prior to ordering any equipment.
1.32 The CONTRACTOR shall also provide parts lists for all valves, special fittings, hangars, etc., to the
ENGINEER prior to final payment.
PART II - PRODUCTS
2.0 Gate Valves (unless specified in the plans as HDPE fusible vales)
2.01 Gate valves 3-inch diameter and smaller shall be all bronze meeting Federal Specification WW-V-
54, rated at 200 psi/WOG unless shown otherwise. Valves shall open counterclockwise with non-rising
stem and hand wheel operator unless indicated otherwise on the drawings. End connections shall be
threaded unless shown otherwise.
2.02 Gate valves 4 to 12-inch diameter shall be cast iron body solid wedge resilient seat valves meeting
AWWA C-509 requirements. All gate valves shall open counterclockwise and have non-rising stems with
2" square operating nuts unless indicated otherwise on the drawings. End connections shall be
mechanical joint unless shown otherwise. Valves shall receive a minimum 8 mil protective interior
coating in accordance with AWWA C550.
2.03 Resilient seat gate valves shall be as manufactured by Mueller, Waterious or approved equal.
Bronze gate valves shall be as manufactured by ITT Grinell or approved equal.
2.1 Mud Valves (unless specified in the plans as HDPE fusible vales)
2.11 Mud valves shall have cast iron bodies with bronze stems, stem nuts, disc rings and seat rings. All
mounting hardware and assembly bolts and nuts are to be of stainless steel. All mud valves are to have
flanged ends and be equipped with rising stems unless shown otherwise. Each mud valve is to be
equipped with a corrosion resistant extension stem, extension support bracket and handwheel. Position
the handwheels approximately 1 foot above the top of the walkway.
2.2 Butterfly Valves (unless specified in the plans as HDPE fusible vales)
2.21 Butterfly valves 12-inch and smaller shall have cast or ductile iron bodies with resilient seats and
shall meet AWWA, C- 504 requirements. Valves for above ground service shall be flanged (unless shown
02800-2
otherwise), suitable for operation at temperatures of 200 degrees F. and equipped with 10 position
locking levers for variable flow control. Valve for buried service shall have mechanical joint ends and
actuators suitable for underground use. Valves shall have a minimum 8 mil thick protective interior
coating in accordance with AWWA C550.
2.22 Butterfly valves 14 to 48-inch diameter for potable water shall be ductile iron body meeting AWWA
C504. End connections shall be flanged unless shown otherwise and shall conform to "Short Body" laying
length requirements. Valves shall be class 150B. Shaft seals shall be Rubber O-ring type. Sprayed valve
seat mating surfaces shall not be used. Valve shafts shall be stainless steel. Valves shall be furnished
with manual actuators turning counterclockwise to open, 2-inch square operating nut, valve box,
extension stem and ground level disc position indicator unless indicated otherwise on the drawings.
Valves shall be suitable for buried service unless shown otherwise. All exterior bolts, nuts, studs,
washers, etc. shall be 304 stainless steel. Valves shall receive protective interior coating in accordance
with AWWA C550, minimum 8 mils thick. Flange gaskets for butterfly valves shall be full face, employing
one or more annular rings molded into the gasket.
2.23 Butterfly valves shall be as manufactured by Mueller, American Darling or approved equal. Flange
gaskets for butterfly valves shall be "TORUSEAL" as manufactured by American Cast Iron Pipe or
approved equal. Ground level disc position indicators shall be furnished by the valve manufacturer, or
approved equal.
2.3 Check Valves (unless specified in the plans as HDPE fusible vales)
2.31 Check valves shall be bronze fitted iron body and shall meet AWWA, C-508 requirements. Valves
shall be of the clear waterway type and shall have composition to metal seat construction. All check
valves shall be flanged with outside levers and weights unless shown otherwise. Check valves shall be
installed in a horizontal position. Valves shall have a minimum 8 mil thick protective interior coating in
accordance with AWWA C550.
2.32 Check valves shall be as manufactured by Mueller, American Darling or approved equal.
2.4 Plug Valves (unless specified in the plans as HDPE fusible vales)
2.41 Plug valves shall be eccentric resilient plug design with bodies of stainless steel or bronze in sizes to
3" unless used for chlorine solution where PVC is required. Valves larger than 3" shall have bodies of
epoxy coated cast iron, and be bi- directionally sealing.
2.42 Three inch and smaller valves shall have Victaulic end connections, or true union ends on PVC
valves. Metal body valves for above ground service shall be flanged and have adjustable memory stops
and valve position indicators. Valves for buried service shall have mechanical joint ends and actuators
suitable for underground use. Valves larger than 3 inches shall have 2 inch square actuating nuts and
valves 3 inches and smaller shall be furnished with non-removable levers.
2.43 Plug valves shall be a M & H Style 820, or approved equal.
02800-3
2.5 Shear Gates
2.51 Shear gates shall be iron body valves with replaceable wedges. All valves shall have flanged ends,
unless shown otherwise on the drawings, and lifting handles of proper length to allow operation from
the walkways. All mounting hardware and handle brackets shall be provided as required. Bolts and
hardware shall be of corrosion resistant material.
2.6 Ball Valves (unless specified in the plans as HDPE fusible vales)
2.61 Ball valves 3" and smaller, utilized for air control, shall be screwed end stainless steel lever
operated valves suitable for operation at temperatures of 200 degrees F. Ball valves 3" and smaller
utilized on sewage or water lines shall be true union PVC valves with permanently lubricated Teflon
seats and Viton "O" ring seal. End connections shall be threaded or flanged and valves shall be rated for
operation at 150 psi.
2.7 Solenoid Valves
2.71 All solenoid valves shall be threaded quick acting PVC or bronze body valves with 120 volt coils and
replaceable seats and diaphragms.
2.8 Air and Vacuum Relief (unless specified in the plans as HDPE fusible vales)
2.81 Air and vacuum relief valves for sewage shall be constructed of cast iron body and cover, stainless
steel trim and float, with an adjustable Buna-N seal to insure positive seating. Valve shall be of the type
that automatically releases air, gas or vapor under pressure during system operation. The valve shall
have working pressure of 150 psi. Valves shall be equipped with flushing attachments including an inlet
shut off valve, clear water inlet valve, rubber supply hose and quick connect coupling.
2.82 Air and vacuum relief valves for sewage shall be APCO Model 400, Golden-Anderson (GA), or
approved equal.
2.83 Air release valve for potable water shall be constructed of cast iron body and cover, stainless steel
float, leverage mechanism and internal trim, with adjustable Buna-N or Viton seals to insure positive
seating. Valve shall be of the type that automatically releases air, gas or vapor under pressure during
system operation. The valve shall have working pressure of 150 psi. Valve shall have 2-inch N.P.T. inlet
and 3/16- inch discharge orifice.
2.84 Air release valve for potable water shall be as manufactured by VAL-MATIC model no. 38 or
approved equal.
2.9 Valve Box
2.91 Valve boxes for underground valves shall be three piece screw type cast iron valve box and cover.
Cover shall be marked "water" or "sewer" as required. Valve stem extension, if required shall be steel
with centering device, 2-inch operating nut and socket for valve nut.
2.92 Valve box shall be as manufactured by Tyler Pipe, U.S. Foundry or approved equal. Valve stem
extension shall be as manufactured by the General Engineering Company or approved equal.
02800-4
PART III - EXECUTION
3.0 Installation
3.01 All valves shall be located as shown on the Plans. Any underground valves shall be furnished with
an adjustable cast iron valve box and cover marked "sewer" or "water" as required. Covers on valve
boxes shall be set to finished grade and a concrete box formed around the cover as detailed on the
Plans. All valves and valve boxes shall be set plumb.
3.02 Buried valves with operating nuts greater than 3 feet below finished grade shall be provided with a
valve stem extension. Where stem extensions are used, they shall extend to within 2 feet of the finish
grade, except where ground level disc position indicators are required, and the stem extensions shall be
pinned to the valve operating nut.
END OF SECTION
03300-1
SECTION 03300
CONCRETE
PART 1 GENERAL
1.01 Section Includes
General requirements for formwork, reinforcement, accessories and cast-in-place concrete.
1.02 References
A. American Concrete Institute (ACI) latest edition:
1. ACI 301 - Structural Concrete for Buildings
2. ACI 305 - Hot Weather Concreting
3. ACI 306 - Cold Weather Concreting
4. ACI 315 - Detailing Manual
5. ACI 318 - Building Code Requirements for Structural Concrete
6. ACI 347 - Formwork for Concrete
B. American Association of State Highway and Transportation Officials (AASHTO) latest
edition:
1. AASHTO T152 - Air Content of Freshly Mixed Concrete by the Pressure Method
C. American Society for Testing and Materials (ASTM) latest edition:
1. ASTM A185 - Steel Welded Wire Reinforcement, Plain, for Concrete
2. ASTM A615 - Deformed and Plain Billet-Steel Bars for Concrete Reinforcement
3. ASTM C31 - Making and Curing Concrete Test Specimens in the Field
4. ASTM C33 - Concrete Aggregates
5. ASTM C39 - Test Method for Compressive Strength of Cylindrical Concrete
Specimens
6. ASTM C94 - Ready-Mixed Concrete
7. ASTM C138 - Test Method for Density (Unit Weight), Yield, and Air Content
(Gravimetric) of Concrete
8. ASTM C143 - Test Method for Slump of Hydraulic Cement Concrete
9. ASTM C150 - Portland Cement
10. ASTM C173 - Test Method for Air Content of Freshly Mixed Concrete by the
Volumetric Method
11. ASTM C231 - Test Method for Air Content of Freshly Mixed Concrete by the
Pressure Method
12. ASTM C260 - Air-Entraining Admixtures for Concrete
13. ASTM C309 - Liquid Membrane-Forming Compounds for Curing Concrete
14. ASTM D1751 - Preformed Expansion Joint Filler for Concrete Paving and
Structural Construction (Nonextruding and Bituminous Types)
03300-2
1.03 Submittals
A. Submit reinforcement steel shop drawings in accordance with Section 01000 and
prepared in accordance with ACI 315, Manual of Standard Practice for Detailing
Reinforced Concrete Structures. Drawings shall indicate bending diagrams, shapes,
dimensions, clearances, splicing and laps, accessories, and installation notes.
B. Submit manufacturer's literature for all admixtures proposed for the work.
C. Submit delivery tickets in accordance with ASTM C94 for each batch of ready-mixed
concrete. Information on the ticket shall include class of concrete, water content, time
of loading, truck number, admixtures, and quantity.
D. At least 35 days prior to placing of concrete, the Contractor shall submit proposed mix
proportions and samples of proposed materials.
1.04 Quality Control
A. Materials and methods of mixing and placing concrete shall conform to ACI 318,
Building Code Requirements for Reinforced Concrete.
B. Tests for slump shall be made when directed by the Engineer in accordance with ASTM
C143.
C. Air content tests shall be made, when directed by the Engineer, in accordance with
ASTM C138, C173, C231, or AASHTO T-152.
PART 2 PRODUCTS
2.01 Formwork
Formwork lumber shall be straight and clean. All nails shall be withdrawn and surfaces in
contact with concrete shall be thoroughly cleaned before reuse.
2.02 Reinforcement
A. Reinforcement bars shall be ASTM A615, Grade 60 deformed bars, except as otherwise
indicated.
B. Welded wire fabric shall conform to ASTM A185. Where welded wire fabric is shown
but not sized on Drawings, use 6" x 6" x W2.9 x W2.9 WWF.
C. Accessories for proper installation of reinforcement shall conform to CRSI "Manual of
Standard Practice for Reinforced Concrete Construction". Bar supports at exposed
surfaces shall be Class C-Plastic Protected.
03300-3
D. Reinforcement fabrication shall conform to ACI 315 and ACI 318, and approved shop
drawings.
2.03 Joint Fillers
A. Joint fillers shall be products of the following manufacturers, or equal:
1. W. R. Meadows, Inc., Elgin, Illinois
2. W. R. Grace and Co., Cambridge, Massachusetts.
B. Preformed bituminous fiber joint filler shall be non-extruding type conforming to ASTM
D1751.
C. Control joint strips shall have a minimum depth of 25 percent of slab thickness and a
minimum thickness of 1/8 inch.
2.04 Concrete Materials
A. Water shall be clean and potable
B. Portland cement shall be ASTM C150 Type I, II or III.
C. Fine and coarse aggregate shall be clean, hard, natural, or manufactured material
conforming to ASTM C33.
D. The nominal maximum size of the aggregate shall not be larger than three-fourths of the
minimum clear spacing between individual reinforcing bars. Coordinate with maximum
aggregate sizes specified hereafter for classes of concrete.
E. Admixtures shall conform to ASTM C260 (air entrainment) or C494 (water reduction)
and shall be products of one of the following manufacturers, or equal.
1. Dewey and Almy Chemical Div., W. R. Grace and Co.
2. Euclid Chemical Co.
3. Master Builders Co.
4. Sika Chemical Corp.
2.05 Miscellaneous Materials
A. Vapor barrier shall be polyethylene film 0.006 inches thick and shall conform to Product
Standard PS-17.
B. Liquid membrane curing compound shall conform to ASTM C309, Type 1 or Type 2.
Type 2 compound shall be used for P.C.C. pavement only. All permanently exposed
exterior slabs shall receive clear acrylic curing and sealing compound. Moisture loss
shall not be more than 0.055 gr./sq. cm when applied to 200 sq. ft./gal.
03300-4
C. Liquid membrane curing compound shall be products of one of the following
manufacturers, or equal:
1. W.R. Meadows "Curettard"
2. Sonneborn_Contech "Sonsil"
3. Burke Co. "Res-Xnu"
4. Lambert Corp. "Gardseal"
D. Chemical hardener shall be colorless aqueous solution containing a blend of magnesium
fluosilicate and zinc fluosilicate combined with a wetting agent, conforming to Federal
Specifications TT-C-800A and Corps of Engineers Specification CE 204.
E. Chemical hardener shall be products of one of the following manufacturers, or equal:
1. Euclid Chemical Co. "Surfhard"
2. Sonneborn-Contech "Lapidolith"
3. Master Builders "Saniseal"
4. Lambert Corp. "Solidus"
2.06 Concrete Mixtures
A. Concrete not indicated otherwise shall be Class A concrete.
B. The proportions of cement, aggregate, and water shall be selected by the Contractor in
accordance with ACI 318 to provide a plastic and workable mix. Coarse aggregate shall
be limited to prevent harshness and honeycombing. Coarse aggregate size shall not be
greater than the maximum listed for the various classes of concrete and as previously
specified under aggregate.
C. Class A structural concrete shall have a 28-day strength of 4000 psi, shall contain not
less than 540 pounds (5-3/4 bags) of cement per cubic yard of concrete, shall have a
water-cement ratio of not more than 0.47 (5-1/4 gallons per bag of cement), and shall
contain 4 percent to 6 percent entrained air, by volume, except interior slabs subject to
abrasion shall not contain more than 3 percent entrained air. In addition, Class A
concrete shall contain a water-reducing, densifying admixture and have a maximum
slump of 4 inches. The maximum aggregate size for slabs shall be 1 inch.
D. Class B lean concrete shall have a 28-day strength of 2500 psi, it shall contain not less
than 420 pounds (4-1/2 bags) of cement per cubic yard of concrete, shall have a water-
cement ratio of not more than 0.71 (8 gallons per bag of cement), and shall have a 5
inch maximum slump. The maximum aggregate size shall be 2 inches.
E. Water-reducing densifying admixture added to Class A concrete shall reduce the water-
cement ratio while maintaining slump and compressive strength. Use as manufacturer
recommends.
03300-5
F. Other admixtures may be proposed by the Contractor or requested by the Engineer and
shall be provided at no additional cost to the Owner. Subject to approval, admixtures
may be used for the following:
1. To increase slump up to 50 percent while maintaining compressive strength and
water-cement ratio.
2. To retard set during hot weather
G. Calcium chloride, admixtures containing calcium chloride, or admixtures not approved,
in writing by the Engineer, are prohibited.
2.06 Flowable Fill
Flowable fill shall meet the requirements of Sections 121-1 through 121-6, “Flowable Fill” of
FDOT Standard Specifications for Road and Bridge Construction, 2004.
PART 3 EXECUTION
3.01 General
A. Comply with ACI 305 or 306 for hot or cold weather concreting.
B. Do not mix salt, chemicals, or other foreign materials with the concrete to prevent
freezing without approval of the Engineer. Maintain the temperature of concrete above
50 degrees F for 5 days after placement. When high early strength Portland cement
concrete is used, the temperature shall not be less than 70 degrees F for 2 days or 50
degrees F for 3 days.
C. In no case shall the temperature of concrete exceed 90 degrees F at the time of
placement.
3.02 Preparation
A. Remove existing concrete and provide openings for installation of new work as indicated
on Drawings. Repair all damage to existing work caused by concrete removal.
B. Coordinate with other trades and properly place and locate in position all necessary
dowels, bolts, anchors, anchor slots, inserts, sleeves, openings, hangers, metal ties and
other fastening devices required for attachment and support of adjacent work. Securely
anchor all embedded items.
C. The subgrade and/or bedding shall be compacted and free of frost. If placement is
allowed at temperatures below freezing, provide temporary heat and protection as
required to remove all frost. Saturate the subgrade approximately 8 hours before
placement and sprinkle ahead of the placement of concrete in areas where vapor
barrier is not used. Remove all standing water, ice, mud, and foreign matter before
concrete is deposited.
03300-6
D. On porous subgrade or beddings, or where indicated on the Drawings, provide vapor
barrier. Lay vapor barrier sheets with 6 inch edge laps and tape or seal with mastic.
Stretch and weight edges and laps to maintain their positions until concrete is placed.
Coordinate with placement of reinforcement.
3.03 Formwork Requirements
A. Formwork shall comply with ACI 347 and to shape, lines and dimensions as indicated on
the Drawings. Forms shall be properly braced or tied to maintain position and shape
under all dead and live loads and to prevent leakage. Forms shall be assembled so their
removal will not damage the concrete. Tolerances for formed surfaces shall be in
compliance with ACI 301.
B. Lumber formwork may be used for surfaces which will not be exposed to view. Use
plywood or metal forms for exposed surfaces.
C. The inside surface of lumber forms shall be soaked with clean water prior to placing
concrete. All other forms shall be treated with an approved form oil or lacquer. If oil is
used, all excess oil shall be wiped off.
3.04 Reinforcement
A. The placement of reinforcing steel shall conform to "Placing Reinforcing Bars", as
published by the Concrete Reinforcing Steel Institute except as noted.
B. Provide continuous reinforcement or dowels through construction joints. One half of
reinforcement shall be discontinued across control joints unless otherwise indicated. All
reinforcement shall be discontinued across expansion joints.
C. Splice laps shall be as indicated on the Drawings.
D. Fabric reinforcement for slabs shall be overlapped at splices not less than the spacing of
the cross wires plus 2 inches. Fabric shall extend to within 4 inches of concrete edges.
E. Unless otherwise shown, place reinforcement 2 to 3 inches below the top of the finished
slab. Mesh shall either be sandwiched between two layers of fresh concrete or
supported on mesh supports. Supports that may puncture the vapor barrier, if any,
shall not be used.
3.05 Joints
A. Provide construction joints with shear transfer keyways as indicated.
B. Tops of edge forms and screeds shall be set to the finished elevations and to provide
uniform pitch to drains as indicated on Drawings.
C. For drives, pavements, parking areas, walks and slabs on grade, provide preformed non-
extruding asphalt strip or bituminous fiber joint filler set 1/8 inch below finished surface
03300-7
unless otherwise indicated. Tool concrete edges on each side of joint. No sealant is
required.
3.06 Batching
A. Materials for concrete shall be proportioned and batched according to the approved
design mix.
B. Water shall be measured to within 1 pint of the total amount required per batch.
Admixtures shall be measured by weight or volume to an accuracy of 3 percent.
3.07 Mixing and Transporting Concrete
A. Concrete shall be ready-mixed or job-mixed at the Contractor's option. Ready-mixed
concrete shall be mixed and delivered to the project in accordance with ASTM C94. Job-
mixed concrete shall be in accordance with the requirements of ACI 318.
B. Concrete shall be in its final position within one hour after the water and aggregate have
been added to the cement, except in cool weather (50 degrees F or less).
C. Concrete shall be transported from the mixer to place of final deposit in such manner to
prevent separation or loss of ingredients.
3.08 General Concrete Placement Schedule
A. All structural concrete shall be Class A Concrete.
B. Sidewalks shall be Class B Concrete.
3.09 Depositing Concrete
A. Concrete shall be placed in accordance with the requirements of ACI 318 and within 10
feet of its final position. Place concrete only during normal working hours unless the
Engineer is notified at least 24 hours in advance. Concrete shall not be placed until the
Engineer has approved the formwork, reinforcement, and embedded items and debris
has been removed.
B. Whenever new concrete is to be placed against existing surfaces, roughen and clean the
surface to improve bond.
C. Provide runways and chutes to discharge concrete close to final position to minimize
spreading and segregation.
D. Place slabs-on-grade using formed construction joints. Maximum size of pour shall be
40 feet each way for slabs with wire mesh reinforcement and 75 feet each way for slabs
with bar reinforcement. Allow 24 hours between pours of adjacent slabs. Provide joints
as specified or shown. Set continuous joint strips between slabs and abutting vertical
surfaces as indicated on the Drawings.
03300-8
3.10 Finishing Slabs and Flatwork
A. Unless otherwise indicated, provide the following slab finishes:
Description Concrete Finish
Class B concrete surfaces Float
Submerged slabs 1 Troweling
Exposed slabs 3 Trowelings
Ramps and walks Float and broom finish
B. Concrete shall be within ¼ inch of a 10 foot straightedge in all directions except where
slabs are dished for drains. Deviations from the elevation indicated shall not exceed ¼
inch.
C. Slabs sloped for drainage shall not have depressions that retain water.
D. Immediately after placement, screed concrete with straightedges or power strikeoffs.
Do not use roller screeds or vibrating screeds.
E. Stakes for wet screeds shall be driven down flush with subgrade or pulled out as work
progresses to avoid disturbing screeded concrete.
F. For drains in level slabs, form a 5 foot diameter depression approximately ½ inch below
the adjacent slab surface.
G. Unless otherwise indicated on the Drawings, slabs sloped for drainage shall be uniformly
pitched toward the drains at 1/8 inch per foot. Form a dished depression at drains
unless otherwise indicated.
H. Immediately after screeding, darby surface with wood or magnesium darby to eliminate
ridges and to fill in voids left by screeding.
3.11 Float Finish
A. Float concrete using magnesium or aluminum hand floats or power floats after the
concrete has stiffened to a point where only a ¼ inch indentation can be imparted by
normal foot pressure.
B. Float finish shall result in a uniform, smooth, granular texture. After floating, check slab
tolerances with 10-foot straightedge. Fill low spots with fresh concrete; do not sprinkle
with dry cement.
3.12 Trowel Finish
A. Where scheduled, or indicated, trowel with steel trowels after floating.
03300-9
B. Initial troweling shall be done either by power or by hand with the trowel blade kept as
flat as possible against concrete surface to prevent washboard or chatter effect.
C. Second troweling may be done by power if three trowelings are scheduled. If two
trowelings are specified, second troweling shall be done by hand.
D. Third troweling shall be done by hand and shall continue until the concrete is
consolidated to a uniform, smooth, dense surface free of trowel marks and
irregularities.
E. Allow sufficient time between successive trowelings to allow the concrete to become
harder. Each successive troweling shall be done with trowels that are progressively
smaller and are tipped more to increase compaction of the concrete surface.
3.13 Brooming
Broom at right angles to direction of traffic to give a non-skid finish. Use a fine, soft-bristled
broom for pedestrian ramps and walks, and a coarse, hard-bristled broom for vehicular
pavement.
3.14 Control Joints
A. Control joints for non-structural slabs shall consist of partial depth plastic strips set flush
with finished surface or 1/8 inch wide joints cut with a diamond saw. Control joints shall
be one- quarter to one-third the depth of the slab unless otherwise indicated.
B. Saw joints as soon as concrete has hardened sufficiently so aggregate will not be
dislodged but before shrinkage stresses develop cracks. Sawn joints shall be filled with
approved joint sealant.
C. Unless otherwise indicated on the Drawings, spacing of control joints shall not exceed
25 feet in each direction.
3.15 Protection and Curing
A. Comply with ACI 305 and 306 for protecting and curing concrete in hot and cold
weather. Fresh concrete shall be protected from rain, premature drying and excessively
hot or cold temperatures, and shall be maintained with minimal moisture loss for the
period of time necessary for the hydration of the cement and proper hardening of the
concrete. Cure all concrete for a minimum period of 7 days (3 days for high early
strength concrete) after placing.
B. Immediately after finishing, begin curing by covering with constantly saturated moisture
retaining fabrics, impervious sheeting, or membrane curing compounds. Surfaces shall
be thoroughly wetted with a fine spray before they are covered with sheeting.
03300-10
C. Sheeting shall provide complete surface coverage with all joints lapped at least 4 inches
and shall be placed and secured in a manner that will not mar or damage the concrete
surface.
D. Apply membrane-curing compound in accordance with manufacturer's
recommendations. Apply by spraying in a two coat continuous operation. Apply the
coats at right angles to each other with a coverage of 200 square feet per gallon per
coat. Begin application not later than 4 hours after finishing of the surface. The
application shall result in an uninterrupted adherent film free of defects.
E. On surfaces scheduled to receive sealants, paint, seamless flooring, or other adhesive
bonded finishes, either the membrane curing compound shall be compatible with the
bonding agent or the curing compound shall be removed with sandblasting, acid etching
or grinding, to the satisfaction of the installer of the finish surfacing. Bonded surfaces
that fail to adhere to the concrete shall be removed and replaced at no additional cost
to the Owner.
F. Apply hardener to floors of mechanical and electrical rooms and in other areas as
required. Application shall be in strict accordance with the manufacturer's
recommendations and as follows:
1. Hardener shall be applied at original container consistency without dilution to
dry, clean surfaces no sooner than 30 days following completion of curing.
NOTE: Hardener shall not be applied over surfaces covered with membrane
curing agent.
2. Application shall generally be a three-coat process adjusted to accommodate
extreme concrete densities only if prior review has been obtained from the
Engineer. Application coverage shall be made at the approximate rate of one
gallon to 100 square feet.
3. Apply first and second coats generously to surface, mop or squeegee standing
water to leave a uniformly wet surface, allow to dry. Apply third coat in a
manner similar to first two, except that surplus must be scrubbed with stiff
bristled broom and flushed from floor surface with clear water. Scrubbing and
flushing shall remove all traces of effervescence. Remove excess water and
allow to dry.
3.16 Defective Concrete
A. All concrete not formed as indicated on the Drawings within tolerances specified in ACI
347 shall be removed and replaced.
B. Temperature and shrinkage cracks which develop prior to final acceptance of the work
shall be repaired.
3.17 Miscellaneous Concrete Work
03300-11
Provide concrete equipment pads and supports as indicated and conforming to approved shop
drawings. Fastening devices and accessories shall be located by templates or setting diagrams
furnished by the manufacturer.
3.18 Clean-Up
A. All concrete floor construction shall have the surfaces thoroughly scrubbed and cleaned
with clear water. After cleaning, the floors shall be protected until they are accepted.
B. Clean all surfaces affected by the Concrete Work. No extraneous concrete or
discoloration shall be left on any construction.
3.19 Concrete Testing
A. Compressive Strength Tests: Conform to ASTM C31 and ASTM C39. One set of four
cylinders for each 50 cubic yards or fraction thereof, of each strength concrete placed in
any one day. Test one specimens at seven days; test two specimens at 28 days. One
specimen shall be retained for 56 days and tested only at the direction of the Engineer.
B. Slump Tests: Conform to ASTM C143. Perform one test for each load point of discharge
and one for each set of compressive strength test specimens.
END OF SECTION
09900
SECTION 09900
PROTECTIVE COATINGS
Part I. GENERAL
1 .01 WORK INCLUDED
A This Section covers the work required to provide all labor, materials, equipment and
incidentals to perform all of the necessary surface preparation and painting required to
complete this contract in its entirety.
B It is the intent of this specification to paint all concrete exposed miscellaneous ferrous
metals, pipes, fittings, valves, equipment and all other work obviously required to be
painted unless otherwise specified. Minor items omitted in the schedule of Work shall
be included in the Work of this Section where they come within the general intent of
the Specifications as stated herein.
C The following surfaces or items are not required to be painted:
(i) Aluminum: gratings, checkered plates, hatches, handrails, toeboards, stairways and
walkways (except as required for electrolytic protection).
(ii) Stainless Steel, brass and bronze.
(iii) Piping buried in the ground or embedded in concrete.
(iv) Ducts, pipes and other miscellaneous items covered with insulation or plastic coated.
(v) Concealed surfaces of pipe and crawl spaces.
(vi) Finish hardware.
(vii) Nonferrous architectural metals, unless specifically noted otherwise.
(viii) Packing glands and other adjustable parts and nameplates of mechanical equipment.
(ix) Concrete slabs and equipment pads.
(x) All manufactured painted electrical equipment (switchgear, transformers, motor
control centers, control panels, etc.).
1 .02 ABBREVIATIONS
A The abbreviations and definitions listed below, when used in this Section shall have the
following meanings:
(i) ANSI American National Standards Institute
(ii) ASTM American Society of Testing Materials
(iii) AWWA American Water Works Association
(iv) DFT Dry Film Thickness
(v) FRP Fiberglass Reinforced Plastic
(vi) HCL Hydrochloric Acid
(vii) MDFT Minimum Dry Film Thickness
(viii) MDFTPC Minimum Dry Film Thickness Per Coat
(ix) mil Thousandths of an Inch
(x) MIL-P Military Specification – Paint
(xi) NACE National Association of Corrosion Engineers
09900
(xii) NSF National Sanitary Foundation
(xiii) OSHA Occupational Safety and Health Act
(xiv) SFPG Square Feet Per Gallon
(xv) SFPGPC Square Feet Per Gallon Per Coat
(xvi) SP Surface PreparationSSPC Steel Structures Painting Council
1 .03 SUBMITTALS
A Submittals shall be made in accordance with the requirements specified in Section
01300 -Submittals.
B The following shall be submitted for each proposed coating system: manufacturer’s
specifications, surface preparation details, application procedures, technical data sheets
and dry film thickness or coverage.
C Schedule of Painting Operations: The CONTRACTOR shall include a complete Schedule of
Painting Operations with the overall project schedule.
1 .04 QUALITY ASSURANCE
A The paint manufacturer shall provide a representative to visit the jobsite at intervals
during surface preparation and painting as may be required for product application
quality assurance and to determine compliance with Manufacturers instructions and
these Specifications, and as may be necessary to resolve field problems attributable to,
or associated with, the manufacturer’s products furnished under this Contract.
1 .05 INSPECTION
A The CONTRACTOR shall give the ENGINEER a minimum of three (3) days advance notice
of the completion of any surface preparation work or start of coating application work.
B Before application of the base (prime) coat and each succeeding coat, all surfaces to be
painted shall be inspected by ENGINEER. Any and all defects or deficiencies shall be
corrected by the CONTRACTOR before application of any subsequent coating.
C Coating applications shall be checked for required MDFT as per these specifications. All
coated surfaces failing to meet the MDFT requirements shall be rejected.
D For all coatings subject to immersion, consult the coatings manufacturer’s written
instructions for time required after system application before immersion.
E Inspection by the ENGINEER or the waiver of inspection of any particular portion of the
Work shall not be construed to relieve the CONTRACTOR of his responsibility to perform
the Work in accordance with these Specifications.
F All equipment required for discontinuity (Holiday) testing of steel substrates and
continuity verification of concrete substrates shall be furnished and operated by the
painting contractor.
1 .06 PAINT DELIVERY AND STORAGE
A All materials shall be new and shall be delivered to the project site in unopened
containers that plainly show, at the time of use, the designated name, date of
manufacture, color, and name of manufacturer. Paints shall be stored in a suitable
protected area that is heated or cooled as required to maintain temperatures within the
range recommended by the paint manufacturer.
1 .07 PROJECT SITE CONDITIONS
A The location of this project requires observance and conformance with EPA Volatile
Organic Compound (VOC) restrictions. EPA limits the content of VOC’s in painting
09900
materials to 3.5 lbs./gallon. Information regarding the VOC content of proposed paints
will be required during submittals.
1 .08 WARRANTY
A CONTRACTOR shall warrant to the OWNER and guarantee the work under this Section
against defective workmanship and materials for a period of two (2) years commencing
on the final contract date of Final Completion of the Work.
B Warranties shall be submitted in accordance with Section 01740-Warranties and Bonds.
Part I. PRODUCTS
1 .09 GENERAL
A All products used in immersion service or in contact with potable water shall be certified
by NSF for use in contact with potable water.
B Products containing lead will not be allowed. Oil shall be pure boiled linseed oil.
1 .10 PAINT MATERIALS
A Products shall be manufactured by Tnemec Company, Inc., Xypex Chemical Corporation,
or equal.
B The following paint products are by Tnemec Company, Inc. or Xypex Chemical
Corporation, and are used for the basis of establishing the desired quality expected for
the project.
1 .11 PRODUCT TYPE
A Alkyd Primer
B Polyamine Epoxy (Primer)
C Polyamide Epoxy (Non-Potable)
D Aliphatic Acrylic Polyurethane
E Acrylic Emulsion (Flat)
F Acrylic Emulsion (Semi-Gloss)
G Polyamide Epoxy Coal Tar
H Polyamine Novolac Epoxy
I Waterborne Cementitious Acrylic
J Water Base Acrylic Epoxy
1 .12 TNEMEC COMPANY. INC. PRODUCT NAME
A Series 36 Undercoater
B Series 201 Epoxoprime
C Series 66 Hi-Build Epoxoline
D Series 73 Endura-Shield
E Series 6 Tneme-Cryl
F Series 7 Tneme-Cryl
G 46-413 Tneme-Tar
H Series 282 Tneme-Glaze
I Series 130-6602 Envirofill
J Series 113 Tneme-Tufcoat
1 .13 PRODUCT TYPE XYPEX CHEMICAL CORP. PRODUCT NAME
A Crystalline Waterproofing Concentrate
B Crystalline Waterproofing Modified
C Curing Agent Gammacure
09900
1 .14 EXTRA PAINT
A Furnish one (1) unopened container of each type and each color of paint used, properly
marked for future use by OWNER. Minimum size of one (1) gallon.
Part II. PART 3 – EXECUTION
1 .06 PROTECTION OF SURFACES NOT TO BE PAINTED
A Mask or otherwise protect hardware, lighting fixtures, switch plates, aluminum surfaces,
machined surfaces, couplings, shafts, bearings, nameplates and all other surfaces not
intended to be painted which cannot be removed.
B Provide drop cloths to prevent paint materials from falling on or marring adjacent
surfaces.
C Protect working parts of mechanical and electrical equipment from damage during
surface preparation and painting processes. Openings in motors shall be masked to
prevent paint and other materials from entering motors.
1 .07 ENVIRONMENTAL CONDITIONS
A Paint shall not be applied in temperatures exceeding the manufacturer’s recommended
maximum and minimum allowable, nor under adverse conditions such as dust, smoke-
laden atmosphere, damp or humid weather.
1 .08 SAFETY
A Painting shall be performed in strict accordance with the safety recommendations of the
paint manufacturer; with the safety recommendations of the National Association of
Corrosion Engineers contained in the publication, Manual for Painter Safety; Federal,
State, and local agencies having jurisdiction.
B Ultimate responsibility for safety is the CONTRACTOR’s.
1 .09 PREPARATION OF FERROUS METAL SURFACES
A All surfaces to be coated shall be prepared as specified herein and shall be dry and clean
before coating. Specific surface preparation shall be specified for the individual coating
systems.
B Standards for Ferrous Metal Surfaces Preparation
(i) SSPC-SP- 1 Chemical and/or Solvent Cleaning
1) Remove all grease, oil, salt, acid, alkali, dirt, dust, wax, fat, foreign matter and
contaminates, etc. by one of the following methods: steam cleaning, alkaline cleaning,
or volatile solvent cleaning.
(ii) SSPC-SP-2 Hand Tool Cleaning
1) Removal of loose rust, loose mill scale and loose paint to a clean sound substrate by hand
chipping, scraping, sanding and wire brushing.
(iii) SSPC-SP-3 Power Tool Cleaning
1) Removal of loose rust, loose mill scale and loose paint to a clean sound substrate by power
tool chipping, descaling, sanding, wire brushing and grinding.
(iv) SSPC-SP-4 Flame Cleaning
1) Dehydrating and removal of rust, loose mill scale and some light mill scale by use of flame,
followed by wire brushing.
(v) SSPC-SP-5 (NACE-1) White Metal Blast Cleaning
09900
1) Complete removal of all mill scale, rust scale, previous coating, etc., leaving the surface a
uniform gray-white color.
(vi) SSPC-SP-6 (NACE-3) Commercial Grade Blast Cleaning
1) Complete removal of all dirt, rust scale, mill scale, foreign matter and previous coating,
etc., leaving only shadows and/or streaks caused by rust stain and mill scale oxides. At
least 66% of each square inch of surface area is to be free of all visible residues, except
slight discoloration.
(vii) SSPC-SP-7 (NACE-4) Brush-Off Blast Cleaning
1) Removal of rust scale, loose mill scale, loose rust and loose coatings, leaving tightly-
bonded mill scale, rust and previous coatings. On concrete surfaces, brush-off blast
cleaning shall remove all laitance, form oils and solid contaminates. Blasting should be
performed sufficiently close to the surface so as to open up surface voids, bugholes, air
pockets and other subsurface irregularities, but so as not to expose underlying
aggregate.
(viii) SSPC-SP-8 Pickling
1) Complete removal of rust and mill scale by acid pickling, duplex pickling or electrolytic
pickling (may reduce the resistance of the surface to corrosion, if not to be primed
immediately).
(ix) SSPC-SP-10 (NACE-2) Near-White Metal Blast Cleaning
1) Removal of all rust scale, mill scale, previous coating, etc., leaving only light stains from
rust, mill scale and small specks of previous coating. At least 95% of each square inch of
surface area is to be free of all visible residues, and the remainder shall be limited to
slight discoloration.
(x) SSPC-SP-1 1-87 Power Tool Cleaning to Bare Metal
1) Complete removal of rust, rust scale, mill scale, foreign matter and previous coatings, etc.
to a standard as specified on a Commercial Grade Blast Cleaning (SSPC-SP-6, NACE-3) by
means of power tools that will provide the proper degree of cleaning and surface
profile.
C Ferrous metal shall be blasted unless otherwise specified. Blasting shall be done with a
centrifugal wheel or compressed air blasting equipment, using proper abrasives to attain
an average profile depth of 1.5 mils. Do not reuse sand or flint abrasives. Shot abrasives
must be thoroughly clean of contamination before reuse. Blow dust and grit from surface
with clean, dry air. Coat within 8 hours or before rust contamination occurs.
D Shop-Finished Surfaces: All shop-coated surfaces shall be protected from damage and
corrosion before and after installation by treating damaged areas immediately upon
detection. Abraded or corroded spots on shop-coated surfaces shall be prepared in
accordance with SSPC-SP2 (Hand Tool Cleaning) and then touched up with the same
materials as the shop coat. All shop coated surfaces which are faded, discolored, or which
require more than minor touch-up in the opinion of the ENGINEER shall be repainted. Cut
edges of galvanized sheets and exposed threads and cut ends of galvanized piping,
electrical conduit, and metal pipe sleeves, not to be finished painted, shall be cleaned in
accordance with SSPC-SP1 (Solvent Cleaned) and primed with zinc dust-zinc oxide metal
primer.
E Pre-Blast Cleaning ReQuirements
09900
(i) All oil, grease, welding fluxes, and other surface contaminants shall be removed prior to
blast cleaning. Preblast cleaning methods shall use steam, open flame, hot water, or cold
water with appropriate detergent additives followed with clean water rinsing.
(ii) Small isolated areas shall be cleaned as above or solvent cleaned with suitable solvents
and clean cloths.
(iii) All sharp edges shall be rounded or chamfered and all burrs, jagged edges, and surface
defects shall be ground smooth.
(iv) Welds and adjacent areas shall be prepared such that there is: (1) no undercutting or
reverse ridges on the weld bead, (2) no weld spatter on or adjacent to the weld or any
other area to be painted and (3) no sharp peaks or ridges along the weld bead. All
embedded pieces of electrode or wire shall be ground flush with the adjacent surface of
the weld bead.
1 .10 PREPARATION OF CONCRETE AND MASONRY SURFACES
A All surfaces to be coated shall be prepared as specified herein and shall be dry and clean
before coating. Specific surface preparation shall be specified for the individual coating
systems.
B Standards for concrete/masonry surface preparation shall be as defined and specified by
guideline No. 03732 (latest revision) as published by the International Concrete Repair
Institute.
C Concrete and masonry surfaces shall be prepared in accordance with the International
Concrete Repair Institute Guideline No. 03732 to provide the specified Concrete Surface
Profile CSP 2 -CSP 9, and the recommendations of the repair, coating and lining
manufacturer. According to ICRI, surface preparation methods that may result in a CSP 1 -
CSP 9, include acid etching, detergent scrubbing, low-pressure water blasting, abrasive
(sand) blasting, and high and ultra high pressure water jetting.
D Concrete and masonry surface preparation method shall be as selected by CONTRACTOR
to meet the specified concrete surface profile requirement and the other specified surface
preparation requirements.
E The Concrete Surface Profile (CSP) requirements shall be as follows:
(i) ICRI CSP 1 - Acid Etched.review.
F Shop finish coats may be the standard finish as ordinarily applied by the manufacturer if it
can be demonstrated to the ENGINEER that the paint system is equal to and compatible
with the paint system specified. However, all pumps, motors, valves, pipe and other
equipment shall receive at least one field applied finish coat after installation.
1 .11 COATING SYSTEM INDEX
A The following is a general index to the Coating System descriptions contained herein:
SYSTEM NUMBER TITLE
2E Below Grade Waterproofing 4 Exposed Metal - Highly Corrosive 7 Interior Metal - Highly Corrosive 23 Chemical Resistant Wall (Concrete masonry) 24 Exposed FRP, PVC 25 Interior FRP, PVC 27 Aluminum and Dissimilar Metal Insulation 100 Exterior Wood Trim ill Stucco-Cementitious Coating (Flat)
09900
I5ONS Concrete Floor - Chemical Resistant Non-Skid
1 .12 COATING SYSTEMS
A System No. 2E - Below Grade Waterproofing
(i) Surface Preparation: All curing oils, form oils, Iaitence, soluble salts and loose
concrete must be removed. Concrete must be dry and thoroughly clean before
coating.
First Coat: Crystalline Waterproofing (Concentrate) at 1.5 lbs/sy.
Second Coat: Crystalline Waterproofing (modified) at 1.5 lbs/sy.
Curing Agent: Curing agent at 800 SFPGPC.
Color: Gray.
B System No. 4 - Exposed Metal - Highly Corrosive.
Surface Preparation: Abrasive blast clean metal to an SSPC-SP1O (near-white metal
blast).
Prime Coat: Polyamide Epoxy (Non-Potable) 7.0 Mils DFT.
Sealant: Apply sealant as specified in Section 07900 - Sealants, at location where two
pieces of steel overlap, between flanges, etc.
Top Coat: Polyurethane 3.0 Mils DFT.
MDFT: 10.0 Mils for the two (2) coat system.
Color: Color as scheduled on Drawings.
C System No. 7 - Interior Metal - Highly Corrosive.
Surface Preparation: Abrasive blast clean metal to an SSPC-SP1O (near-white metal blast).
Prime Coat: Polyamide Epoxy (Non-Potable) 7.0 Mils DFT.
Top Coat: Polyamide Epoxy (Non-Potable) 3.0 Mils DFT.
MDFT: 10.0 Mils for the two (2) coat system.
Color: Color as scheduled on Drawings.
09900
D System No. 23 - Chemical Resistant Wall (Concrete Masonry)
Surface Preparation: Surface shall be clean, dry, free of dust, oil, curing compounds and
other foreign materials. Other requirements for existing surfaces as specified herein.
Prime Coat One (1) coat Epoxy waterborne cementitious acrylic at 80
SFPGPC.
Top Coat Two (2) coats Water Base Acrylic Epoxy (Semi-Gloss) at 4.0 - 6.0 rnils DFT
per coat.
Color: As scheduled on Drawings.
E System No. 24 - Exposed FRP, PVC.
Surface Preparation: Solvent cleaning, SSPC-SP1, to remove soluble contaminants.
Remove all insuluble contaminants or foreign materials by hand, SSPC-SP2, or Power Tool
Cleaning, SSPC-5P3.
Prime Coat: Polyamine Epoxy (non-potable) at 6.0 - 8.0 Mils DFT.
Top Coat: High Build Acrylic Polyurethane at 2.0 - 4.0 Mils DFT.
MDFT: 9.0 Mils for two (2) coat system.
Color: As scheduled on Drawings.
F System No. 25 - Interior FRP, PVC.
Surface Preparation: As specified herein and/or manufacturer’s recommendations.
Prime Coat: Polyamide Epoxy (Non-Potable) 3.0 Mils DFT.
Top Coat: Polyamide Epoxy (Non-Potable) 3.0 Mils DFT.
MDFT: 6.0 Mils for the two (2) coat system.
Color: As scheduled on Drawings.
G System No. 27 - Aluminum and Dissimilar Metal Insulation
Surface Preparation: Roughened surface.
Top Coat: Polyamide Epoxy Coal Tar at 10.0 mils DFT.
09900
MDFT: 10.0 mils for one (1) coat system.
Color: Black.
H System No. 100 - Exterior Wood Trim
Surface Preparation: Surface must be clean, dry and free of oil, grease and other
contaminants. Remove all loose existing coatings and sand rough areas. Seal all knots and
pitch pockets.
Prime Coat: One (1) coat alkyd primer 2.0 to 3.0 mils DFT.
Caulking: Prepare and fill all cracks, nail holes, seams and joints with sealants as
speciñed in Section 07900 - Sealants.
Top Coat: Two (2) coats acrylic emulsion (semi-gloss) at 3 mils DFT per coat.
MDFT: 8.0 mils DFT for three (3) coat system.
Color: As scheduled on Drawings.
I System No. 111 - Stucco - Cementitious Coating (Flat)
Surface Preparation: Allow cementitious finish a minimum of 28 days drying/curing time.
Surface shall be clean, dry, free of dust, oil, curing compounds and other foreign materials.
Prime Coat: Acrylic Emulsion (Flat) at 318 SFPGPC
Top Coat: Acrylic Emulsion (Flat) at 318 SFPGPC
Color: As scheduled on Drawings.
J System No. 15ONS - Concrete Floor (Chemical Resistant) Non-Skid
Surface Preparation: Allow new concrete to cure 28 days. Prepare concrete surface by
abrasive blast cleaning or acid etching to achieve a finish the roughness of 50 grit
sandpaper. Surface to be clean, dry and roughened prior to application of coating.
Prime Coat: Polyamine Epoxy (Primer) at 6.0-8.0 Mils DFT.
Intermediate Coat: Polyamine Novolac epoxy at 6.0-8.0 mils DFT. Broadcast 50 mesh
dry washed silica sand into the prime coat while still wet.
Top Coat: Polyamine Novolac epoxy at 6.0-8.0 mils DFT.
MDFT: 12.0 - 16.0 mils for two (2) coat system.
Color: Color as scheduled on Drawings.
1 .13 UNIDENTIFIED SURFACES
A Any surfaces not specifically named in the Schedule and not specifically excluded or
exempted shall be prepared, primed and painted in the manner and with materials
consistent with these Specifications. The ENGINEER shall select which of the
09900
manufacturer’s products, whether the type is indicated herein or not, shall be used for
such unidentified surfaces. This painting shall be done within the Scope of the Contract.
1 .14 WORKMANSHIP
A On metal surfaces apply each coat of paint at the rate specified by the manufacturer to
achieve the minimum dry mil thickness required. If material has thickened or must be
diluted for application by spray gun, the coating shall be built up to the same film thickness
achieved with undiluted material. One gallon of paint as originally furnished by the
manufacturer shall not cover a greater area when applied by spray gun than when applied
unthinned by the application of an additional coat(s). On masonry, application rates will
vary according to surface texture, however, in no case shall the manufacturer’s stated
coverage rate be exceeded. On porous surfaces, it shall be the painter’s responsibility to
achieve a protective and decorative finish either by decreasing the coverage rate or by
applying additional coats of paint.
B All safety equipment shall be painted in accordance with OSHA Standards as approved.
C Materials shall be mixed in proper containers of adequate capacity. All materials shall be
thoroughly stirred before use and shall be kept stirred while using. No unauthorized
thinners or other materials shall be added to any paint.
D Only skilled painters shall be used on the Work and specialists shall be employed where
required.
E Steel members, metal castings, mechanical and electrical equipment and other metals
which are shop primed before delivery at the site will not require a prime coat on the job.
All piping and other bare metals to be painted shall receive one coat of primer before
exposure to the weather, and this prime coat shall be the first coat as specified in the
painting schedule.
F Finish surfaces shall not show brush marks or other irregularities. Undercoats shall be
thoroughly and uniformly sanded with No. 00 sandpaper or equal to remove defects and
provide a smooth even surface. Top and bottom edges of doors shall be painted and all
exterior trim shall be back-primed before installation.
G Painting shall be continuous and shall be accomplished in an orderly manner so as to
facilitate inspection. All exterior concrete and masonry painting shall be performed in one
continuous manner structure by structure. Materials subject t’o weathering shall be prime
coated as quickly as possible. Surfaces of exposed members that will by inaccessible after
erection shall be cleaned and painted before erection.
H Before final acceptance of the Work, all damaged surfaces of paint shall be cleaned and
repainted as directed by the ENGINEER.
1 .15 APPLICATION SCHEDULE
A System No. 2E - Below Grade Waterproofing. This system shall be used on the exterior of
all below grade concrete walls.
B System No. 4 - Exposed Metal - Highly Corrosive. This system shall be used on all metal
surfaces exposed to weather including equipment, equipment frames, metal conduits,
pipe, valves and piping supports.
C System No. 7 - Interior Metal - Highly Corrosive. This system shall be used on the interior
metal surfaces including pumps, piping, valves, equipment, and other miscellaneous metal
surfaces.
09900
D System No. 23 - Chemical Resistant Wall (Concrete Masonry). This system shall be used on
interior walls as scheduled on the drawings.
E System No. 24 - Exposed FRP, PVC. This system shall be used for all PVC exposed to the
elements. DO NOT PAINT FLEXIBLE CONDUITS.
F System No. 25 - Interior FRP, PVC. This system shall be used on interior FRP, PVC piping for
color coding.
G System No. 27 - Aluminum and dissimilar metal insulation. This system shall be used on all
aluminum in contact with concrete. Insulate all contacting dissimilar metals with this
system. Neoprene pads may be substituted to insulate aluminum from concrete or
aluminum from steel.
H System No. 100 - Exterior Wood Trim. This system shall be used for the exterior wood trim
of the repump station building.
I System No. 111 - Stucco - Cementitious Coating (Flat). This system shall be used on
exterior concrete and concrete masonry walls as scheduled on the Drawings.
J System No. 15ONS - Concrete Floor (Chemical Resistant) Non-Skid. This system shall be
used for coating the interior concrete floor and equipment pad of the vacuum pump
station.
1 .16 COLOR CODING FOR PIPES AND EQUIPMENT
A All proposed piping, valves and equipment shall be color coded. When color coding is
specified, it shall consist of color code painting and lettering identification of all exposed
conduits, trough items and pipelines for the transport of gases, air, liquid and semi-liquids
including all accessories such as valves, insulated pipe coverings, fittings, junction boxes,
bus bars, connectors and all operating accessories which are integral to be whole function
mechanical pipe and electrical conduit system.
B All hangers and pipe support floor stands shall be painted. The system shall be painted up
to but not including the flanges attached to the mechanical equipment nor the flexible
conduit connected to electrical equipment. Colors shall be as noted in the Paint Color
Schedule.
C All systems which are an integral part of the equipment that is originating from the
equipment and returning to the same piece of equipment, shall be painted between and
up to but not including the fixed flanges or connections on the equipment.
D Color coding requirements are as indicated in the Ten State Standards
E CONTRACTOR shall submit proposed schedule for color coding pipes and equipment for
approval by ENGINEER/OWNER.
1 .17 CLEANUP
A It shall be the responsibility of the Contractor to collect and dispose of properly, all waste
materials from the site in accordance with all requirements of the Federal, State and local
Environment Protection Agencies.
B At completion of the Work, remove all paint where spilled, splashed, splattered, sprayed or
smeared on all surfaces, including glass, light fixtures, hardware, equipment, painted and
unpainted surfaces.
C After completion of all painting, the Contractor shall remove from the job site all painting
equipment, surplus materials and debris resulting from this Work.
END OF SECTION 09900
FDEP-1
Revision 4
September 1999
SUPPLEMENTARY CONDITIONS (CONSTRUCTION) EXHIBIT WWFS-04Li
Florida Department of Environmental Protection
Bureau of Water Facilities Funding
Supplementary Conditions
for
Formally Advertised
Construction Procurement
FDEP-2
Revision 4
September 1999
TABLE OF CONTENTS FOR THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
Article
Number Article Title Page
1 DEFINITIONS FDEP-4
2 PRIVITY OF AGREEMENT/CONTRACT FDEP-6
3 PROCUREMENT REQUIREMENTS FDEP-6
4 RESOLUTION OF PROTESTS AND CLAIMS/DISPUTES FDEP-7
5 CHANGES TO THE BIDDING AND CONTRACT DOCUMENTS FDEP-7
6 ADVERTISEMENT FOR BIDS; SUBMISSION OF BIDS;
OPENING OF BIDS FDEP-7
7 BONDS AND INSURANCE FDEP-8
8 AWARD OF AGREEMENT/CONTRACT FDEP-9
9 CONTRACT TIME AND NOTICE TO PROCEED FDEP-9
10 ITEMIZED CONSTRUCTION COST BREAKDOWN;
CONSTRUCTION AND PAYMENT SCHEDULES FDEP-9
11 AVAILABILITY OF LANDS FDEP-10
12 FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
CONSTRUCTION PERMIT(S) FDEP-10
13 ENGINEER FDEP-10
14 APPLICATIONS FOR PAYMENT FDEP-10
15 ACCESS TO RECORDS FDEP-10
16 ACCESS TO WORK SITE(S) FDEP-10
*17 MINORITY AND WOMEN'S BUSINESS ENTERPRISES FDEP-11
*18 VIOLATING FACILITIES (SECTION 306 OF THE CLEAN AIR
ACT, SECTION 508 OF THE CLEAN WATER ACT, AND
EXECUTIVE ORDER 11738) FDEP-11
*19 DEBARMENT AND SUSPENSION (EXECUTIVE ORDER 12549) FDEP-13
FDEP-3
Revision 4
September 1999
20 EQUAL EMPLOYMENT OPPORTUNITY (EXECUTIVE
ORDER 11246) FDEP-13
Appendix Appendix Title Page
Letter
*A CERTIFICATION REGARDING DEBARMENT, SUSPENSION,
INELIGIBILITY AND VOLUNTARY EXCLUSION - LOWER
TIER COVERED TRANSACTIONS FDEP-16
B NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION
TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY
(EXECUTIVE ORDER 11246) FDEP-18
C GOALS AND TIMETABLES FOR MINORITIES AND FEMALES FDEP-20
D EQUAL OPPORTUNITY CLAUSE FDEP-23
E NOTICE TO BE POSTED FDEP-25
F STANDARD FEDERAL EQUAL EMPLOYMENT
OPPORTUNITY CONSTRUCTION CONTRACT
SPECIFICATIONS (EXECUTIVE ORDER 11246) FDEP-26
G CERTIFICATION OF COMPLIANCE WITH 41 CFR 60-1.7:
REPORTS AND OTHER REQUIRED INFORMATION FDEP-31
H CERTIFICATION OF NONSEGGREGATED FACILITIES FDEP-33
*NOTE: Articles 17, 18, 19 and Appendix A apply only to projects of $10,000,000 or greater.
FDEP-4
Revision 4
September 1999
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
The intent of the Florida Department of Environmental Protection (FDEP) Supplementary Conditions is
to complement and supplement other provisions of the Bidding Documents. However, if there is any
conflict between the FDEP Supplementary Conditions and other provisions of the Bidding Documents,
the FDEP Supplementary Conditions shall take precedence over the other provisions except when the
other provisions are similar to, but more stringent than, the FDEP Supplementary Conditions. When
other provisions of the Bidding Documents are similar to, but more stringent than, the FDEP
Supplementary Conditions, the more stringent provisions shall apply.
ARTICLE 1 - DEFINITIONS
1.1. Wherever used in these Supplementary Conditions (except in the appendices to these
Supplementary Conditions), the following terms have the meanings indicated, which are applicable to
both the singular and plural thereof.
1.1.1. Addendum - A written or graphic instrument that is issued prior to the opening of bids and
that clarifies, corrects, or changes the Bidding Documents.
1.1.2. Agreement or Contract - The written agreement between the Owner and the Contractor
covering the Work to be performed and furnished; these Supplementary Conditions and other
Contract Documents are attached to the Agreement/Contract and made a part thereof as provided
therein.
1.1.3. Application for Payment - The form that is accepted by the Engineer and used by the
Contractor in requesting progress and/or final payments and that is to include such supporting
documentation as is required by the Contract Documents.
1.1.4. Bid - The offer or proposal of a bidder submitted on the prescribed form and setting forth the
price(s) for the Work to be performed and furnished.
1.1.5. Bidder - Any person, firm, or corporation that submits a bid directly to the Owner.
1.1.6. Bidding Documents - The Advertisement for Bids or the Invitation to Bid, the Instructions to
Bidders or the Information for Bidders, the Bid Form, the proposed Contract Documents, and all
addenda.
1.1.7. Bond - An instrument of security.
1.1.8. Change Order - A document that is recommended by the Engineer and signed by the
Contractor and the Owner; that authorizes an addition, deletion, or revision in the Work or an
adjustment in the Contract Price or the Contract Time; and that is issued on or after the Effective Date
of the Agreement/Contract.
FDEP-5
Revision 4
September 1999
1.1.9. Contract Documents - The Agreement/Contract; the Contractor's Bid when attached as an
exhibit to the Agreement/Contract; the Performance and Payment Bond(s); the General Conditions;
the Supplementary Conditions (including these Supplementary Conditions); the Specifications
(written technical descriptions of material, equipment, construction systems, standards, and
workmanship as applied to the Work and certain administrative details applicable thereto); the
Drawings (drawings that show the character and scope of the Work to be performed and furnished);
all addenda that pertain to the Contract Documents; and all change orders.
1.1.10. Contract Price - The moneys payable by the Owner to the Contractor under the Contract
Documents as stated in the Agreement/Contract.
1.1.11. Contract Time - The number of days or the date stated in the Contract Documents for
completion of the Work.
1.1.12. Contractor - The person, firm, or corporation with whom or which the Owner enters into the
Agreement/Contract.
1.1.13. Effective Date of the Agreement/Contract - The date indicated in the Agreement/Contract on
which the Agreement/Contract becomes effective, or if no such date is indicated in the
Agreement/Contract, the date on which the Agreement/Contract is signed and delivered by the last of
the two parties to sign and deliver the Agreement/Contract.
1.1.14. Engineer - The person, firm, or corporation named as such in the Contract Documents.
1.1.15. Minority Business Enterprise (MBE) - A historically Black college or university or a
business that is (a) certified as socially and economically disadvantaged by the Small Business
Administration, (b) certified as an MBE by a state or Federal agency, or (c) an independent business
concern which is at least 51-percent owned and controlled by minority group members. (A minority
group member is an individual who is a citizen of the United States and one of the following: [i]
Black American; [ii] Hispanic American [with origins from Puerto Rico, Mexico, Cuba, or South or
Central America]; [iii] Native American [American Indian, Eskimo, Aleut, or native Hawaiian]; or
[iv] Asian-Pacific American [with origins from Japan, China, the Philippines, Vietnam, Korea,
Samoa, Guam, the U.S. Trust Territories of the Pacific, Northern Marianas, Laos, Cambodia, Taiwan,
or the Indian Subcontinent].)
1.1.16. Notice to Proceed - The written notice given by the Owner to the Contractor fixing the date
on which the Contract Time will commence to run and on which the Contractor shall start to perform
its obligations under the Contract Documents.
1.1.17. Owner - The local government (municipality, county, district, or authority; or any agency
thereof; or a combination of two or more of the foregoing acting jointly) with which the Florida
Department of Environmental Protection may execute, or has executed, a State revolving fund loan
agreement and for which the Work is to be provided.
FDEP-6
Revision 4
September 1999
1.1.18. Project - The total construction or facilities described in a State revolving fund loan
agreement between the Florida Department of Environmental Protection and the Owner, of which the
Work to be provided under the Contract Documents may be the whole or a part.
1.1.19. Subcontract - A direct contract between a subcontractor and the Contractor, or any other
subcontractor at any tier, for the furnishing of goods (material and equipment) or the performance of
services (including construction) necessary to complete the Work.
1.1.20. Subcontractor - A person, firm, or corporation having a direct contract with the Contractor,
or any other subcontractor at any tier, for the furnishing of goods (material and equipment) or the
performance of services (including construction) necessary to complete the Work.
1.1.21. Successful Bidder - The lowest responsive, responsible bidder to whom or which the Owner
intends to award the Agreement/Contract.
1.1.22. Women's Business Enterprise (WBE) - A business that is (a) certified as a WBE by a state or
Federal agency or (b) an independent business concern which is at least 51-percent owned and
controlled/operated by women. (Determination of whether a business is at least 51-percent owned by
women shall be made without regard to community property laws [e.g., an otherwise qualified WBE
that is 51-percent owned by a married woman in a community property state will not be disqualified
because the married woman's husband has a 50-percent interest in the married woman's share of the
business; similarly, a business that is 51-percent owned by a married man and 49-percent owned by
women will not become a qualified WBE by virtue of the married man's wife having a 50-percent
interest in the married man's share of the business].)
1.1.23. Work - The entire completed construction or the various separately identifiable parts thereof
required to be performed and furnished under the Contract Documents; Work is the result of
performing services, furnishing labor, furnishing material and equipment, and incorporating material
and equipment into the construction as required by the Contract Documents.
ARTICLE 2 - PRIVITY OF AGREEMENT/CONTRACT
2.1. The Owner expects to finance this Agreement/Contract with assistance from the Florida
Department of Environmental Protection, which administers a State revolving fund loan program
supported in part with funds directly made available by grants from the United States Environmental
Protection Agency. Neither the State of Florida nor the United States (nor any of their departments,
agencies, or employees) will be a party to this Agreement/Contract or any lower-tier subcontract.
ARTICLE 3 - PROCUREMENT REQUIREMENTS
3.1. This Agreement/Contract and the Owner's solicitation and award of this Agreement/Contract are
subject to requirements contained in Chapter 62-503 (Revolving Loan Program), Florida Administrative
Code.
FDEP-7
Revision 4
September 1999
ARTICLE 4 - RESOLUTION OF PROTESTS AND CLAIMS/DISPUTES
Resolution of Protests Concerning the Owner's Solicitation and/or Award of this
Agreement/Contract:
4.1. Protests concerning the Owner's solicitation and/or award of this Agreement/Contract must be filed
in writing with the Owner to be considered.
4.2. All timely written protests concerning the Owner's solicitation and/or award of this
Agreement/Contract are to be resolved in accordance with the Owner's dispute resolution process. A
copy of the ordinance(s), resolution(s), or written policy(policies) that set forth the Owner's dispute
resolution process is included elsewhere in the Bidding Documents or is to be made available by the
Owner upon request.
4.3. Neither the Florida Department of Environmental Protection (FDEP) nor the United States
Environmental Protection Agency (USEPA) will become a party to, or have any role in resolving,
protests concerning the Owner's solicitation and/or award of this Agreement/Contract. Protest decisions
made by the Owner can not be appealed to the FDEP or the USEPA.
Resolution of Claims and Disputes Between the Owner and the Contractor:
4.4. Unless otherwise provided in the Contract Documents, all claims and disputes between the Owner
and the Contractor arising out of, or relating to, the Contract Documents or the breach thereof are to be
decided by arbitration (if the Owner and the Contractor mutually agree) or in a court of competent
jurisdiction within the State of Florida.
4.5. Neither the Florida Department of Environmental Protection nor the United States Environmental
Protection Agency will become a party to, or have any role in resolving, claims and disputes between the
Owner and the Contractor.
ARTICLE 5 - CHANGES TO THE BIDDING AND CONTRACT DOCUMENTS
5.1. All changes to the Bidding Documents made subsequent to the Florida Department of
Environmental Protection's (FDEP's) acceptance of the Bidding Documents and prior to the opening of
bids are to be documented via addendum(addenda) to the Bidding Documents; all changes to the Contract
Documents made after the opening of bids are to be documented by change order(s) to the Contract
Documents. The Owner shall submit all addenda and change orders to the FDEP.
ARTICLE 6 - ADVERTISEMENT FOR BIDS; SUBMISSION OF BIDS; OPENING OF BIDS
Advertisement for Bids:
6.1. At a minimum, this Agreement/Contract is to be advertised for bids in local and statewide
newspapers.
FDEP-8
Revision 4
September 1999
Submission of Bids:
6.2. Bidders shall submit their bids at the place and by the deadline indicated elsewhere in the Bidding
Documents.
Opening of Bids:
6.3. Bids are to be opened and read aloud publicly at the time and place indicated elsewhere in the
Bidding Documents.
ARTICLE 7 - BONDS AND INSURANCE
Bid Guarantees:
7.1. Each bidder's bid is to be accompanied by a bid guarantee made payable to the Owner in an amount
at least equal to five percent of the bidder's maximum bid price and in the form of a certified check or bid
bond.
Performance and Payment Bond(s):
7.2. The Contractor shall furnish a combined performance and payment bond in an amount at least
equal to 100 percent of the Contract Price (or, if required elsewhere in the Contract Documents, the
Contractor shall furnish separate performance and payment bonds, each in an amount at least equal to
100 percent of the Contract Price) as security for the faithful performance and payment of all the
Contractor's obligations under the Contract Documents. This(these) bond(s) are to be delivered to the
Owner by the Contractor along with the executed Agreement/Contract. The Owner shall forward a copy
of this(these) bond(s) to the Florida Department of Environmental Protection.
Insurance:
7.3. The Owner and/or the Contractor (as required elsewhere in the Contract Documents) shall purchase
and maintain, during the period of construction, such liability insurance as is appropriate for the Work
being performed and furnished and as will provide protection from claims that may arise out of, or result
from, the Contractor's performance and furnishing of the Work (whether the Work is to be performed or
furnished by the Contractor or any subcontractor at the Work site) and the Contractor's other obligations
under the Contract Documents. This insurance is to include workers' compensation insurance,
comprehensive general liability insurance, comprehensive automobile liability insurance, and contractual
liability insurance applicable to the Contractor's indemnification obligations and is to be written for not
less than the limits of liability and coverages determined by the Owner or required by law, whichever is
greater.
7.4. The Owner and/or the Contractor (as required elsewhere in the Contract Documents) shall purchase
and maintain, during the period of construction, property insurance upon the Work at the Work site in an
amount equal to the full replacement cost of the Work or the full insurable value of the Work. This
insurance is to include the interests of the Owner, the Contractor, and all subcontractors at the Work site
(all of whom are to be listed as insureds or additional insured parties); is to insure against the perils of fire
and extended coverage; and is to include "all-risk" insurance for physical loss or damage due to
FDEP-9
Revision 4
September 1999
theft,vandalism and malicious mischief, collapse, water damage, and/or all other risks against which
coverage is obtainable.
7.5. Before any Work at the Work site is started, the Contractor shall deliver to the Owner certificates
of insurance that the Contractor is required to purchase and maintain in accordance with Paragraphs 7.3
and 7.4 of this Article and other provisions of the Contract Documents, and the Owner shall deliver to the
Contractor certificates of insurance that the Owner is required to purchase and maintain in accordance
with Paragraphs 7.3 and 7.4 of this Article and other provisions of the Contract Documents.
ARTICLE 8 - AWARD OF AGREEMENT/CONTRACT
8.1. If this Agreement/Contract is awarded, it is to be awarded to the lowest responsive, responsible
bidder. A fixed-price (lump-sum or unit-price or both) agreement/contract is to be used. A clear
explanation of the method of evaluating bids and the basis for awarding this Agreement/Contract are
included elsewhere in the Bidding Documents. All bids may be rejected when in the best interest of the
Owner.
ARTICLE 9 - CONTRACT TIME AND NOTICE TO PROCEED
Contract Time:
9.1. The number of days within which, or the date by which, the Work is to be completed and ready for
final payment (the Contract Time) is set forth elsewhere in the Contract Documents.
Notice to Proceed:
9.2. The Owner shall give the Contractor a notice to proceed fixing the date on which the Contract
Time will commence to run. The Owner shall forward a copy of this notice to proceed to the Florida
Department of Environmental Protection.
ARTICLE 10 - ITEMIZED CONSTRUCTION COST BREAKDOWN; CONSTRUCTION AND
PAYMENT SCHEDULES
10.1. The Contractor shall submit to the Owner, within ten calendar days after the Effective Date of this
Agreement/Contract, an itemized construction cost breakdown and construction and payment schedules.
10.1.1. The itemized construction cost breakdown, or schedule of values, is to include quantities and
prices of items aggregating the Contract Price and is to subdivide the Work into component parts in
sufficient detail to serve as the basis for progress payments during construction. Such prices are to
include an appropriate amount of overhead and profit applicable to each item of Work.
10.1.2. The construction, or progress, schedule is to indicate the Contractor's estimated starting and
completion dates for the various stages of the Work and is to show both the projected cost of Work
completed and the projected percentage of Work completed versus Contract Time.
FDEP-10
Revision 4
September 1999
10.1.3. The payment schedule is to show the Contractor's projected progress and final payments
cumulatively by month.
ARTICLE 11 - AVAILABILITY OF LANDS
11.1. The Owner shall furnish all lands and shall obtain all rights-of-ways and easements upon which
the Work is to be performed and furnished.
ARTICLE 12 - FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
CONSTRUCTION PERMIT(S)
12.1. The Owner shall obtain the appropriate Florida Department of Environmental Protection
construction permit(s) required for the Work.
ARTICLE 13 - ENGINEER
13.1. The Owner shall employ a professional engineer registered in the State of Florida to oversee
the Work.
ARTICLE 14 - APPLICATIONS FOR PAYMENT
14.1. The Contractor's applications for payment are to be accompanied by such certificates or
documents as may be reasonably required. The Owner shall forward a copy of such certificates or
documents as may be reasonably required to the Florida Department of Environmental Protection.
ARTICLE 15 - ACCESS TO RECORDS
15.1. Authorized representatives of the Owner, the Florida Department of Environmental Protection,
and the United States Environmental Protection Agency shall have access to, for the purpose of
inspection, any books, documents, papers, and records of the Contractor that are pertinent to this
Agreement/Contract. The Contractor shall retain all books, documents, papers, and records pertinent
to this Agreement/Contract for a period of three years after receiving and accepting final payment
under this Agreement/Contract.
ARTICLE 16 - ACCESS TO WORK SITE(S)
16.1. Authorized representatives of the Owner, the Florida Department of Environmental Protection
(FDEP), and the United States Environmental Protection Agency (USEPA) shall have access to the
Work site(s) at any reasonable time. The Contractor shall cooperate (including making available
working copies of documents and supplementary materials) during Work site inspections conducted by
the Owner, the FDEP, or the USEPA.
FDEP-11
Revision 4
September 1999
NOTE: Articles 17, 18 and 19 apply only to projects of $10,000,000 or greater.
ARTICLE 17 - MINORITY AND WOMEN'S BUSINESS ENTERPRISES
17.1. A goal of NINE* percent of the Contract Price is established for Minority Business Enterprise
(MBE) participation in the Work, and a goal of THREE* percent of the Contract Price is established
for Women's Business Enterprise (WBE) participation in the Work. If bidders or prospective
contrators (including the Contractor) intend to let any lower-tier goods or services (including
construction) subcontracts for any portion of the Work, they shall physically include these percentage
goals for MBE and WBE participation in all solicitations for subcontracts and shall take affirmative
steps to assure that MBEs and WBEs are utilized, when possible, as sources of goods and services.
Affirmative steps are to include the following: (a) including small, minority, and women's businesses
on solicitation lists; (b) assuring that small, minority, and women's businesses are solicited whenever
they are potential sources; (c) dividing total requirements, when economically feasible, into small tasks
or quantities to permit maximum participation by small, minority, and women's businesses; (d)
establishing delivery schedules, when requirements permit, that will encourage participation by small,
minority, and women's businesses; and (e) using the services of the Small Business Administrative and
the Office of Minority Business Enterprise of the United States Department of Commerce as
appropriate.
*The percentage goals for MBE and WBE participation are to be inserted by the Owner and are
to be based upon the percentage goals that have been, or will be, stipulated in the State
revolving fund loan agreement for the Owner's FDEP-assisted Project.
17.2. Within ten calendar days after being notified of being the apparent Successful Bidder, the
apparent Successful Bidder shall submit to the Owner documentation of the affirmative steps it has
taken to utilize Minority and Women's Business Enterprises (MBEs and WBEs) in the Work and
documentation of its intended use of MBEs and WBEs in the Work. The Owner shall keep this
documentation on file and shall forward to the Florida Department of Environmental Protection a copy
of the apparent Successful Bidder's documentation concerning its intended use of MBEs and WBEs in
the Work.
17.3. Minority and Women's Business Enterprise (MBE and WBE) participation in the Work is to be
considered in the award of this Agreement/Contract. The Owner shall not execute this
Agreement/Contract until the Florida Department of Environmental Protection has approved the extent
of MBE and WBE participation in the Work.
ARTICLE 18 - VIOLATING FACILITIES (SECTION 306 OF THE CLEAN AIR ACT, SECTION
508 OF THE CLEAN WATER ACT, AND EXECUTIVE ORDER 11738)
18.1. The Contractor, and all subcontractors at any tier, shall comply with all applicable standards,
orders, or requirements issued under Section 306 of the Clean Air Act (42 U.S.C. 1857[h]), Section
508 of the Clean Water Act (33 U.S.C. 1368), Executive Order 11738 (Administration of the Clean Air
Act and the Federal Water Pollution Control Act with Respect to Federal Contracts, Grants, or Loans),
and 40 CFR Part 15, which prohibit the use, under nonexempt Federal contracts, grants, or loans, of
facilities included on the United States Environmental Protection Agency's List of Violating Facilities.
FDEP-12
Revision 4
September 1999
18.2. In accordance with 40 CFR Part 15, if the price of this Agreement/Contract exceeds $100,000
and/or if this Agreement/Contract is otherwise nonexempt from 40 CFR Part 15, the Contractor agrees
to the following:
18.2.1. the Contractor will not use any facility on the United States Environmental Protection
Agency's List of Violating Facilities in the performance of this Agreement/Contract for the duration of
time that the facility remains on the List;
18.2.2. the Contractor will notify the Florida Department of Environmental Protection/United
States Environmental Protection Agency (USEPA) if a facility it intends to use in the performance of
this Agreement/Contract is on the USEPA's List of Violating Facilities or if it knows that a facility it
intends to use in the performance of this Agreement/Contract has been recommended to be placed on
the USEPA's List of Violating Facilities; and
18.2.3. in the performance of this Agreement/Contract, the Contractor will comply with all
requirements of the Clean Air Act and the Clean Water Act, including the requirements of Section 114
of the Clean Air Act and Section 308 of the Clean Water Act, and all applicable clean air standards and
clean water standards.
18.3. If the Contractor, or any subcontractor at any tier, awards any lower-tier goods or services
(including construction) subcontracts for any portion of the Work, it shall physically include in all such
subcontracts the following provision:
18.3.1. The Subcontractor shall comply with all applicable standards, orders, or requirements
issued under Section 306 of the Clean Air Act (42 U.S.C. 1857[h]), Section 508 of the Clean
Water Act (33 U.S.C. 1368), Executive Order 11738 (Administration of the Clean Air Act and
the Federal Water Pollution Control Act with Respect to Federal Contracts, Grants, or Loans),
and 40 CFR Part 15, which prohibit the use, under nonexempt Federal contracts, grants, or
loans, of facilities included on the United States Environmental Protection Agency's (USEPA's)
List of Violating Facilities. In accordance with 40 CFR Part 15, if the price of this Subcontract
exceeds $100,000 and/or if this Subcontract is otherwise nonexempt from 40 CFR Part 15, the
Subcontractor agrees to the following: (a) the Subcontractor will not use any facility on the
USEPA's List of Violating Facilities in the performance of this Subcontract for the duration of
time that the facility remains on the List; (b) the Subcontractor will notify the Florida
Department of Environmental Protection/USEPA if a facility it intends to use in the
performance of this Subcontract is on the USEPA's List of Violating Facilities or if it knows
that a facility it intends to use in the performance of this Subcontract has been recommended to
be placed on the USEPA's List of Violating Facilities; and (c) in the performance of this
Subcontract, the Subcontractor will comply with all requirements of the Clean Air Act and the
Clean Water Act, including the requirements of Section 114 of the Clean Air Act and Section
308 of the Clean Water Act, and all applicable clean air standards and clean water standards.
In addition, if the Subcontractor awards any lower-tier goods or services (including
construction) subcontracts under this Subcontract, the Subcontractor shall physically include
this provision in all such subcontracts.
FDEP-13
Revision 4
September 1999
ARTICLE 19 - DEBARMENT AND SUSPENSION (EXECUTIVE ORDER 12549)
19.1. If the price of this Agreement/Contract equals or exceeds $25,000, the Owner shall not award
this Agreement/Contract, nor permit any lower-tier goods or services (including construction)
subcontract with a price equaling or exceeding $25,000 to be awarded, to any party that is debarred or
suspended or is otherwise excluded from, or ineligible for participation in, Federal assistance programs
under Executive Order 12549 (Debarment and Suspension).
19.2. The attention of all bidders or prospective contractors (including the Contractor) is directed to
the certification/clause entitled "Certification Regarding Debarment, Suspension, Ineligibility and
Voluntary Exclusion - Lower Tier Covered Transactions", which has been extracted from Appendix B
to 40 CFR Part 32 and included as Appendix A to these Supplementary Conditions. The
certification/clause entitled "Certification Regarding Debarment, Suspension, Ineligibility and
Voluntary Exclusion - Lower Tier Covered Transactions" is applicable to this Agreement/Contract if
the price of this Agreement/Contract equals or exceeds $25,000.
19.3. If bidders or prospective contractors (including the Contractor), or any prospective
subcontractors at any tier, intend to let any lower-tier goods or services (including construction)
subcontracts for any portion of the Work, they shall physically include the certification/clause entitled
"Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion - Lower Tier
Covered Transactions", which is included as Appendix A to these Supplementary Conditions, in all
lower-tier goods and services (including construction) subcontracts with a price equaling or exceeding
$25,000 and in all solicitations for such subcontracts.
ARTICLE 20 - EQUAL EMPLOYMENT OPPORTUNITY (EXECUTIVE ORDER 11246)
20.1. If the price of this Agreement/Contract exceeds $10,000, the Contractor, and each construction
subcontractor awarded a lower-tier construction subcontract with a price exceeding $10,000, shall
comply with Executive Order 11246 of September 24, 1965 (Equal Employment Opportunity), as
amended by Executive Order 11375 of October 13, 1967, and as supplemented in United States
Department of Labor regulations (41 CFR Part 60).
20.2. The attention of all bidders or prospective contractors (including the Contractor) is directed to
the following, all of which are applicable to this Agreement/Contract if the price of this
Agreement/Contract exceeds $10,000:
20.2.1. the "Notice of Requirement for Affirmative Action to Ensure Equal Employment
Opportunity (Executive Order 11246)", which has been extracted from 41 CFR 60-4.2(d) and
included as Appendix B to these Supplementary Conditions;
20.2.2. the "Goals and Timetables for Minorities and Females", which are included as
Appendix C to these Supplementary Conditions;
20.2.3. the "Equal Opportunity Clause", which has been extracted from 41 CFR 60-1.4(b) and
included as Appendix D to these Supplementary Conditions;
FDEP-14
Revision 4
September 1999
20.2.4. the "Notice to Be Posted", which has been extracted from 41 CFR 60-1.42(a) and
included as Appendix E to these Supplementary Conditions;
20.2.5. the "Standard Federal Equal Employment Opportunity Construction Contract
Specifications (Executive Order 11246)", which have been extracted from 41 CFR 60-4.3(a)
and included as Appendix F to these Supplementary Conditions;
20.2.6. the "Certification of Compliance with 41 CFR 60-1.7: Reports and Other Required
Information", which is required by 41 CFR 60-1.7(b) and is included as Appendix G to these
Supplementary Conditions; and
20.2.7. the "Certification of Nonsegregated Facilities", which is required by 41 CFR 60-1.8(b)
and is included as Appendix H to these Supplementary Conditions.
20.3. If bidders or prospective contractors (including the Contractor), or any prospective construction
subcontractors at any tier, intend to let any lower-tier construction subcontracts for any portion of the
Work, they shall physically include in all lower-tier construction subcontracts with a price exceeding
$10,000 and in all solicitations for such subcontracts the "Notice of Requirement for Affirmative
Action to Ensure Equal Employment Opportunity (Executive Order 11246)", the "Goals and
Timetables for Minorities and Females", the "Equal Opportunity Clause", the "Notice to Be Posted",
the "Standard Federal Equal Employment Opportunity Construction Contract Specifications
(Executive Order 11246)", the "Certification of Compliance with 41 CFR 60-1.7: Reports and Other
Required Information", and the Certification of Nonsegregated Facilities", which are included as
Appendices B through H to these Supplementary Conditions.
20.4. If the price of this Agreement/Contract exceeds $10,000, all bidders shall complete and submit
to the Owner, with their bids, the "Certification of Compliance with 41 CFR 60-1.7: Reports and Other
Required Information", which is included as Appendix G to these Supplementary Conditions. In
addition, if bidders (including the Contractor), or any prospective construction subcontractors at any
tier, intend to let any lower-tier construction subcontracts for any portion of the Work, they shall obtain
the "Certification of Compliance with 41 CFR 60-1.7: Reports and Other Required Information" from
each prospective construction subcontractor that may be awarded a lower-tier construction subcontract
with a price exceeding $10,000 and shall do so at the time bids or offers for each such subcontract are
received or at the outset of negotiations for each such subcontract.
20.5. If the price of this Agreement/Contract exceeds $10,000, the apparent Successful Bidder shall
complete and submit to the Owner, within ten calendar days after being notified of being the apparent
Successful Bidder, the "Certification of Nonsegregated Facilities", which is included as Appendix H to
these Supplementary Conditions. In addition, if the Contractor, or any construction subcontractor at
any tier, intends to let any lower-tier construction subcontracts for any portion of the Work, it shall
obtain the "Certification of Nonsegregated Facilities" from each prospective construction subcontractor
that will be awarded a lower-tier construction subcontract with a price exceeding $10,000 and shall do
so before awarding each such subcontract.
20.6. If the price of this Agreement/Contract exceeds $10,000, the Owner shall give written notice to
the Director of the Office of Federal Contract Compliance Programs within ten working days of award
of this Agreement/Contract. The notice is to include the name, address, and telephone number of the
FDEP-15
Revision 4
September 1999
Contractor; the employer identification number of the Contractor; the dollar amount of this
Agreement/Contract; the estimated starting and completion dates of this Agreement/Contract; the
number of this Agreement/Contract; and the geographical area in which the Work is to be performed.
If the price of this Agreement/Contract equals or exceeds $50,000 and if the Contractor has 50 or more
employees, the Contractor shall file with the Florida Department of Environmental Protection
(FDEP)/United States Environmental Protection Agency (USEPA), within 30 calendar days after the
award of this Agreement/Contract, a report on Standard Form 100 (EEO-1), which has been
promulgated jointly by the Office of Federal Contract Compliance Programs, the Equal Employment
Opportunity Commission, and Plans for Progress, unless the Contractor has submitted such a report
within 12 months preceeding the date of award of this Agreement/Contract. In addition, the Contractor
shall ensure that each construction subcontractor having 50 or more employees and a lower-tier
construction subcontract with a price equaling or exceeding $50,000 also files with the FDEP/USEPA,
within 30 calendar days after the award to it of the lower-tier construction subcontract, a report on
Standard Form 100 (EEO-1) unless the construction subcontractor has submitted such a report within
12 months preceding the date of award of the lower-tier construction subcontract. (Subsequent reports
are to be submitted annually in accordance with 41 CFR 60-1.7(a) or at such other intervals as the
Director of the Office of Federal Contract Compliance Programs may require.)
FDEP-16
Revision 4
September 1999
NOTE: THIS APPENDIX APPLIES ONLY TO PROJECTS OF $10,000,000 OR GREATER
APPENDIX A TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY AND
VOLUNTARY EXCLUSION - LOWER TIER COVERED TRANSACTIONS
[Note: This certification/clause has been extracted from Appendix B to
40 CFR Part 32 and is applicable to all FDEP-assisted goods and services (including construction)
contracts and subcontracts with a price equaling or exceeding $25,000; this certification/clause is to be
included in all FDEP-assisted goods and services (including construction) contracts and subcontracts with
a price equaling or exceeding $25,000 and in all solicitations for such contracts and subcontracts.]
Instructions for Certification
1. By signing and submitting this proposal, the prospective lower tier participant is providing the
certification set out below.
2. The certification in this clause is a material representation of fact upon which reliance was placed
when this transaction was entered into. If it is later determined that the prospective lower tier participant
knowingly rendered an erroneous certification, in addition to other remedies available to the Federal
Government, the department or agency with which this transaction originated may pursue available
remedies, including suspension and/or debarment.
3. The prospective lower tier participant shall provide immediate written notice to the person to which
this proposal is submitted if at any time the prospective lower tier participant learns that its certification
was erroneous when submitted or has become erroneous by reason of changed circumstances.
4. The terms "covered transaction", "debarred", "suspended", "ineligible", "lower tier covered
transaction", "participant", "person", "primary covered transaction", "principal", "proposal", and
"voluntarily excluded", as used in this clause, have the meanings set out in the Definitions and Coverage
sections of rules implementing Executive Order 12549. You may contact the person to which this
proposal is submitted for assistance in obtaining a copy of those regulations.
5. The prospective lower tier participant agrees by submitting this proposal that, should the proposed
covered transaction be entered into, it shall not knowingly enter into any lower tier covered transaction
with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation
in this covered transaction, unless authorized by the department or agency with which this transaction
originated.
6. The prospective lower tier participant further agrees by submitting this proposal that it will include
this clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion
- Lower Tier Covered Transactions", without modification, in all lower tier covered transactions and in
all solicitations for lower tier covered transactions.
FDEP-17
Revision 4
September 1999
7. A participant in a covered transaction may rely upon a certification of a prospective participant in a
lower tier covered transaction that it is not debarred, suspended, ineligible, or voluntarily excluded from
the covered transaction, unless it knows that the certification is erroneous. A participant may decide the
method and frequency by which it determines the eligibility of its principals. Each participant may, but is
not required to, check the Nonprocurement List.
8. Nothing contained in the foregoing shall be construed to require establishment of a system of records
in order to render in good faith the certification required by this clause. The knowledge and information
of a participant is not required to exceed that which is normally possessed by a prudent person in the
ordinary course of business dealings.
9. Except for transactions authorized under paragraph 5 of these instructions, if a participant in a
covered transaction knowingly enters into a lower tier covered transaction with a person who is
suspended, debarred, ineligible, or voluntarily excluded from participation in this transaction, in addition
to other remedies available to the Federal Government, the department or agency with which this
transaction originated may pursue available remedies, including suspension and/or debarment.
Certification Regarding Debarment, Suspension, Ineligibility and Voluntary
Exclusion - Lower Tier Covered Transactions
(1) The prospective lower tier participant certifies, by submission of this proposal, that neither it nor its
principals is presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily
excluded from participation in this transaction by any Federal department or agency.
(2) Where the prospective lower tier participant is unable to certify to any of the statements in this
certification, such prospective participant shall attach an explanation to this proposal.
(3) The prospective lower-tier participant also certifies that it and its principals:
(a) Have not within a three-year period preceding this proposal been convicted of or had a civil
judgment rendered against them for commission of fraud or a criminal offense in connection with
obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract
under a public transaction; violation of Federal or State anti-trust statutes or commission of
embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements,
or receiving stolen property;
(b) Are not presently indicted for or otherwise criminally or civilly charged by a governmental
entity (Federal, State or local) with commission of any of the offenses enumerated in paragraph (3)(a)
of this certification; and
(c) Have not within a three-year period preceding this proposal had one or more public transactions
(Federal, State or local) terminated for cause or default. Where the prospective lower-tier participant
is unable to certify to any of the above, such prospective participant shall attach an explanation to this
proposal.
FDEP-18
Revision 4
September 1999
APPENDIX B TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY (EXECUTIVE ORDER 11246)
[Note: This notice has been extracted from 41 CFR 60-4.2(d) and is applicable to all FDEP-assisted
construction contracts and subcontracts with a price exceeding $10,000; this notice is to be included in all
FDEP-assisted construction contracts and subcontracts with a price exceeding $10,000 and in all
solicitations for such contracts and subcontracts.]
1. The Offeror's or Bidder's attention is called to the "Equal Opportunity Clause" and the "Standard
Federal Equal Employment Specifications" set forth herein.
2. The goals and timetables for minority and female participation, expressed in percentage terms for the
Contractor's aggregate workforce in each trade on on all construction work in the covered area, are as
follows: __________________________________________________________________________________
Timetables Goals for minority Goals for female
participation for each participation in each
trade trade
__________________________________________________________________________________
NINE PERCENT THREE PERCENT
__________________________________________________________________________________
These goals are applicable to all the Contractor's construction work (whether or not it is Federal or
federally assisted) performed in the covered area. If the contractor performs construction work in a
geographical area located outside of the covered area, it shall apply the goals established for such
geographical area where the work is actually performed. With regard to this second area, the contractor
also is subject to the goals for both its federally involved and nonfederally involved construction.
The Contractor's compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be
based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations
required by the specifications set forth in 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours
of minority and female employment and training must be substantially uniform throughout the length of
the contract, and in each trade, and the contractor shall make a good faith effort to employ minorities
and women evenly on each of its projects. The transfer of minority or female employees or trainees
from Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor's
goals shall be a violation of the contract, the Executive Order and the regulations in 41 CFR Part 60-4.
Compliance with the goals will be measured against the total work hours performed.
FDEP-19
Revision 4
September 1999
3. The Contractor shall provide written notification to the Director of the Office of Federal Contract
Compliance Programs within 10 working days of award of any construction subcontract in excess of
$10,000 at any tier for construction work under the contract resulting from this solicitation. The
notification shall list the name, address and telephone number of the subcontractor; employer
identification number of the subcontractor; estimated dollar amount of the subcontract; estimated
starting and completion dates of the subcontract; and the geographical area in which the subcontract is
to be performed.
4. As used in this Notice, and in the contract resulting from this solicitation, the "covered area" is
_______________________________________________________________________________
(insert description of the geographical areas where the contract is to be performed giving the state,
_______________________________________________________________________________
county and city, if any)
FDEP-20
Revision 4
September 1999
APPENDIX C TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
GOALS AND TIMETABLES FOR MINORITIES AND FEMALES
[Note: These goals and timetables are the goals and timetables referred to in Paragraph 2 of the "Notice
of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order
11246)"; these goals and timetables are to be included in all FDEP-assisted construction contracts and
subcontracts with a price exceeding $10,000 and in all solicitations for such contracts and subcontracts.]
Appendix A
The following goals and timetables for female utilization shall be included in all Federal and federally
assisted construction contracts and subcontracts in excess of $10,000. The goals are applicable to the
contractor's aggregate on-site construction workforce whether or not part of that workforce is
performing work on a Federal or federally-assisted construction contract or subcontract.
Area covered: Goals for Women apply nationwide.
Goals and Timetables __________________________________________________________________________________
Timetable Goals (percent)
Indefinite 6.9
___________________________________________________________________________________
Appendix B-80
Until further notice, the following goals for minority utilization in each construction craft and trade shall
be included in all Federal or federally assisted construction contracts and subcontracts in excess of
$10,000 to be performed in the respective geographical areas. The goals are applicable to each
nonexempt contractor's total onsite construction workforce, regardless of whether or not part of that
workforce is performing work on a Federal, federally assisted or nonfederally related project, contract or
subcontract.
Construction contractors which are participating in an approved Hometown Plan (see 41 CFR 60-4.5)
are required to comply with the goals of the Hometown Plan with regard to construction work they
perform in the area covered by the Hometown Plan. With regard to all their other covered construction
work, such contractors are required to comply with the applicable SMSA or EA goal contained in this
Appendix B-80.
FDEP-21
Revision 4
September 1999
Economic Areas
________________________________________________________________________________
State Goal (percent)
________________________________________________________________________________
Florida 30.4
043 Miami - Fort Lauderdale, FL:
SMSA Counties:
2680 Fort Lauderdale - Hollywood, FL--------------------------------------------15.5
FL - Broward
5000 Miami, FL------------------------------------------------------------------------39.5
FL - Dade
8960 West Palm Beach - Boca Raton, FL-----------------------------------------22.4
FL - Palm Beach
Non-SMSA Counties---------------------------------------------------------------------30.4
FL - Glades, Hendry, Indian River, Martin,
Monroe, Okeechobee, St. Lucie
FDEP-22
Revision 4
September 1999
APPENDIX D TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
EQUAL OPPORTUNITY CLAUSE
[Note: This clause has been extracted from 41 CFR 60-1.4(b) and is applicable to all FDEP-assisted
construction contracts and subcontracts with a price exceeding $10,000; this clause is to be included in
all FDEP-assisted construction contracts and subcontracts with a price exceeding $10,000 and in all
solicitations for such contracts and subcontracts.]
During the performance of this contract, the contractor agrees as follows:
(1) The contractor will not discriminate against any employee or applicant for employment because of
race, color, religion, sex, or national origin. The contractor will take affirmative action to ensure that
applicants are employed, and that employees are treated during employment without regard to their race,
color, religion, sex, or national origin. Such action shall include, but not be limited to the following:
Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or
termination; rates of pay or other forms of compensation; and selection for training, including
apprenticeship. The contractor agrees to post in conspicuous places, available to employees and
applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination
clause.
(2) The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the
contractor, state that all qualified applicants will receive considerations for employment without regard
to race, color, religion, sex, or national origin.
(3) The contractor will send to each labor union or representative of workers with which he has a
collective bargaining agreement or other contract or understanding, a notice to be provided advising the
said labor union or workers' representatives of the contractor's commitments under this section, and
shall post copies of the notice in conspicuous places available to employees and applicants for
employment.
(4) The contractor will comply with all provisions of Executive Order 11246 of September 24, 1965,
and of the rules, regulations, and relevant orders of the Secretary of Labor.
(5) The contractor will furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto,
and will permit access to his books, records, and accounts by the administering agency and the Secretary
of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
(6) In the event of the contractor's noncompliance with the nondiscrimination clauses of this contract or
with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or
suspended in whole or in part and the contractor may be declared ineligible for further Government
contracts or federally assisted construction contracts in accordance with procedures authorized in
Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies
invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of
the Secretary of Labor, or as otherwise provided by law.
FDEP-23
Revision 4
September 1999
(7) The contractor will include the portion of the sentence immediately preceding paragraph (1) and the
provisions of paragraphs (1) through (7) in every subcontract or purchase order unless exempted by
rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order
11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or
vendor. The contractor will take such action with respect to any subcontract or purchase order as the
administering agency may direct as a means of enforcing such provisions, including sanctions for
noncompliance: Provided, however, That in the event a contractor becomes involved in, or is threatened
with, litigation with a subcontractor or vendor as a result of such direction by the administering agency
the contractor may request the United States to enter into such litigation to protect the interests of the
United States.
FDEP-24
Revision 4
September 1999
APPENDIX E TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
NOTICE TO BE POSTED
[Note: This notice has been extracted from 41 CFR 60-1.42(a) and is the notice referred to in Paragraphs (1) and
(3) of the "Equal Opportunity Clause"; this notice is to be included in all FDEP-assisted construction contracts
and subcontracts with a price exceeding $10,000 and in all solicitations for such contracts and subcontracts.]
EQUAL EMPLOYMENT OPPORTUNITY IS THE LAW - DISCRIMINATION IS PROHIBITED
BY THE CIVIL RIGHTS ACT OF 1964 AND BY EXECUTIVE ORDER NO. 11246
Title VI of the Civil Rights Act of 1964 - Administered by:
THE EQUAL EMPLOYMENT OPPORTUNITY COMMISSION
Prohibits discrimination because of Race, Color, Religion, Sex, or National Origin by Employers with 75 or more
employees, by Labor Organizations with a hiring hall of 75 or more members, by Employment Agencies, and by
Joint Labor-Management Committees for Apprenticeship or Training. After July 1, 1967, employers and labor
organizations with 50 or more employees or members will be covered; after July 1, 1968, those with 25 or more
will be covered.
ANY PERSON
Who believes he or she has been discriminated against
SHOULD CONTACT
THE EQUAL EMPLOYMENT OPPORTUNITY COMMISSION
2401 E Street NW, Washington, D.C. 20506
Executive Order No. 11246 - Administered by:
THE OFFICE OF FEDERAL CONTRACT COMPLIANCE PROGRAMS
Prohibits discrimination because of Race, Color, Religion, Sex, or National Origin, and requires affirmative
action to ensure equality of opportunity in all aspects of employment.
By all Federal Government Contractors and Subcontractors, and by Contractors Performing Work Under a
Federally Assisted Construction Contract, regardless of the number of employees in either case.
ANY PERSON
Who believes he or she has been discriminated against
SHOULD CONTACT
THE OFFICE OF FEDERAL CONTRACT COMPLIANCE PROGRAMS
U.S. Department of Labor, Washington, D.C. 20210
FDEP-25
Revision 4
September 1999
APPENDIX F TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
STANDARD FEDERAL EQUAL EMPLOYMENT OPPORTUNITY CONSTRUCTION
CONTRACT SPECIFICATIONS (EXECUTIVE ORDER 11246)
[Note: These specifications have been extracted from 41 CFR 60-4.3(a) and are applicable to all
FDEP-assisted construction contracts and subcontracts
with a price exceeding $10,000; these specifications are to be included in all FDEP-assisted
construction contracts and subcontracts with a price exceeding $10,000 and in all solicitations for such
contracts and subcontracts.]
1. As used in these specifications:
a. "Covered area" means the geographical area described in the solicitation from which this
contract resulted;
b. "Director" means Director, Office of Federal Contract Compliance Programs, United States
Department of Labor, or any person to whom the Director delegates authority;
c. "Employer identification number" means the Federal Social Security number used on the
Employer's Quarterly Federal Tax Return, U.S. Treasury Department Form 941.
d. "Minority" includes:
(i) Black (all persons having origins in any of the Black African racial groups not of
Hispanic origin);
(ii) Hispanic (all persons of Mexican, Puerto Rican, Cuban, Central or South American or
other Spanish Culture or origin, regardless of race);
(iii) Asian and Pacific Islander (all persons having origins in any of the original peoples of
the Far East, Southeast Asia, the Indian Subcontinent, or the Pacific Islands); and
(iv) American Indian or Alaskan Native (all persons having origins in any of the original
peoples of North America and maintaining identifiable tribal affiliations through
membership and participation or community identification).
2. Whenever the Contractor, or any Subcontractor at any tier, subcontracts a portion of the work
involving any construction trade, it shall physically include in each subcontract in excess of $10,000
the provisions of these specifications and the Notice which contains the applicable goals for minority
and female participation and which is set forth in the solicitations from which this contract resulted.
3. If the Contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by
the U.S. Department of Labor in the covered area either individually or through an association, its
affirmative action obligations on all work in the Plan area (including goals and timetables) shall be in
accordance with that Plan for those trades which have unions participating in the Plan. Contractors
FDEP-26
Revision 4
September 1999
must be able to demonstrate their participation in and compliance with the provisions of any such
Hometown Plan. Each Contractor or Subcontractor participating in an approved Plan is individually
required to comply with its obligations under the EEO clause, and to make a good faith effort to
achieve each goal under the Plan in each trade in which it has employees. The overall good faith
performance by other Contractors or Subcontractors toward a goal in an approved Plan does not excuse
any covered Contractor's or Subcontractor's failure to take good faith efforts to achieve the Plan goals
and timetables.
4. The Contractor shall implement the specific affirmative action standards provided in paragraphs
7a through p of these specifications. The goals set forth in the solicitation from which this contract
resulted are expressed as percentages of the total hours of employment and training of minority and
female utilization the Contractor should reasonably be able to achieve in each construction trade in
which it has employees in the covered area. Covered construction Contractors performing construction
work in geographical areas where they do not have a Federal or federally assisted construction contract
shall apply the minority and female goals established for the geographical area where the work is being
performed. Goals are published periodically in the FEDERAL REGISTER in notice form, and such
notices may be obtained from any Office of Federal Contract Compliance Programs office or from
Federal procurement contracting officers. The Contractor is expected to make substantially uniform
progress in meeting its goals in each craft during the period specified.
5. Neither the provisions of any collective bargaining agreement, nor the failure by a union with
whom the Contractor has a collective bargaining agreement, to refer either minorities or women shall
excuse the Contractor's obligations under these specifications, Executive Order 11246, or the
regulations promulgated pursuant thereto.
6. In order for the nonworking training hours of apprentices and trainees to be counted in meeting
the goals, such apprentices and trainees must be employed by the Contractor during the training period,
and the Contractor must have made a commitment to employ the apprentices and trainees at the
completion of their training, subject to the availability of employment opportunities. Trainees must be
trained pursuant to training programs approved by the U.S. Department of Labor.
7. The Contractor shall take specific affirmative actions to ensure equal employment opportunity.
The evaluation of the Contractor's compliance with these specifications shall be based upon its effort to
achieve maximum results from its actions. The Contractor shall document these efforts fully, and shall
implement affirmative action steps at least as extensive as the following:
a. Ensure and maintain a working environment free of harassment, intimidation, and coercion
at all sites, and in all facilities at which the Contractor's employees are assigned to work. The
Contractor, where possible, will assign two or more women to each construction project. The
Contractor shall specifically ensure that all foremen, superintendents, and other on-site
supervisory personnel are aware of and carry out the Contractor's obligation to maintain such
a working environment, with specific attention to minority or female individuals working at such
sites or in such facilities.
FDEP-27
Revision 4
September 1999
b. Establish and maintain a current list of minority and female recruitment sources, provide
written notification to minority and female recruitment sources and to community organizations
when the Contractor or its unions have employment opportunities available, and maintain a
record of the organizations' responses.
c. Maintain a current file of the names, addresses and telephone numbers of each minority
and female off-the-street applicant and minority or female referral from a union, a recruitment
source or community organization and of what action was taken with respect to each such
individual. If such individual was sent to the union hiring hall for referral and was not referred
back to the Contractor by the union or, if referred, not employed by the Contractor, this shall be
documented in the file with the reason therefor, along with whatever additional actions the
Contractor may have taken.
d. Provide immediate written notification to the Director when the union or unions with which
the Contractor has a collective bargaining agreement has not referred to the Contractor a minority
person or woman sent by the Contractor, or when the Contractor has other information that the
union referral process has impeded the Contractor's efforts to meet its obligations.
e. Develop on-the-job training opportunities and/or participate in training programs for the
area which expressly include minorities and women, including upgrading programs and
apprenticeship and trainee programs relevant to the Contractor's employment needs, especially
those programs funded or approved by the Department of Labor. The Contractor shall
provide notice of these programs to the sources compiled under 7b above.
f. Disseminate the Contractor's EEO policy by providing notice of the policy to unions and
training programs and requesting their cooperation in assisting the Contractor in meeting its EEO
obligations; by including it in any policy manual and collective bargaining agreement; by
publicizing it in the company newspaper, annual report, etc.; by specific review of the policy with
all management personnel and with all minority and female employees at least once a year; and by
posting the company EEO policy on bulletin boards accessible to all employees at each location
where construction work is performed.
g. Review, at least annually, the company's EEO policy and affirmative action obligations under
these specifications with all employees having any responsibility for hiring, assignment, layoff,
termination or other employment decisions including specific review of these items with onsite
supervisory personnel such as Superintendents, General Foremen, etc., prior to the initiation of
construction work at any job site. A written record shall be made and maintained identifying the
time and place of these meetings, persons attending, subject matter discussed, and disposition of
the subject matter.
h. Disseminate the Contractor's EEO policy externally by including it in any advertising in the
news media, specifically including minority and female news media, and providing written
notification to and discussing the Contractor's EEO policy with other Contractors and
Subcontractors with whom the Contractor does or anticipates doing business.
FDEP-28
Revision 4
September 1999
i. Direct its recruitment efforts, both oral and written, to minority, female and community
organizations, to schools with minority and female students and to minority and female
recruitment and training organizations serving the Contractor's recruitment area and employment
needs. Not later than one month prior to the date for the acceptance of applications for
apprenticeship or other training by any recruitment source, the Contractor shall send written
notification to organizations such as the above, describing the openings, screening procedures, and
tests to be used in the selection process.
j. Encourage present minority and female employees to recruit other minority persons and
women and, where reasonable, provide after school, summer and vacation employment to
minority and female youth both on the site and in other areas of a Contractor's work force.
k. Validate all tests and other selection requirements where there is an obligation to do so under
41 CFR Part 60-3.
l. Conduct, at least annually, an inventory and evaluation at least of all minority and female
personnel for promotional opportunities and encourage these employees to seek or to prepare
for, through appropriate training, etc., such opportunities.
m. Ensure that seniority practices, job classifications, work assignments and other personnel
practices, do not have a discriminatory effect by continually monitoring all personnel and
employment related activities to ensure that the EEO policy and the Contractor's obligations under
these specifications are being carried out.
n. Ensure that all facilities and company activities are nonsegregated except that separate or
single-user toilet and necessary changing facilities shall be provided to assure privacy between
the sexes.
o. Document and maintain a record of all solicitations of offers for subcontracts from
minority and female construction contractors and suppliers, including circulation of solicitations
to minority and female contractor associations and other business associations.
p. Conduct a review, at least annually, of all supervisors' adherence to and performance under
the Contractor's EEO policies and affirmative action obligations.
8. Contractors are encouraged to participate in voluntary associations which assist in fulfilling one or
more of their affirmative action obligations (7a through p). The efforts of a contractor association,
joint contractor-union, contractor-community, or other similar group of which the contractor is a
member and participant, may be asserted as fulfilling any one or more of its obligations under 7a
through p of these Specifications provided that the contractor actively participates in the group, makes
every effort to assure that the group has a positive impact on the employment of minorities and women
in the industry, ensures that the concrete benefits of the program are reflected in the Contractor's
minority and female workforce participation, makes a good faith effort to meet its individual goals and
timetables, and can provide access to documentation which demonstrates the effectiveness of actions
taken on behalf of the Contractor. The obligation to comply, however, is the Contractor's and failure
of such a group to fulfill an obligation shall not be a defense for the Contractor's noncompliance.
FDEP-29
Revision 4
September 1999
9. A single goal for minorities and a separate single goal for women have been established. The
Contractor, however, is required to provide equal employment opportunity and to take affirmative
action for all minority groups, both male and female, and all women, both minority and non-minority.
Consequently, the Contractor may be in violation of the Executive Order if a particular group is
employed in a substantially disparate manner (for example, even though the Contractor has achieved
its goals for women generally, the Contractor may be in violation of the Executive Order if a specific
minority group of women is underutilized).
10. The Contractor shall not use the goals and timetables or affirmative action standards to
discriminate against any person because of race, color, religion, sex, or national origin.
11. The Contractor shall not enter into any Subcontract with any person or firm debarred from
Government contracts pursuant to Executive Order 11246.
12. The Contractor shall carry out such sanctions and penalties for violation of these specifications
and of the Equal Opportunity Clause, including suspension, termination and cancellation of existing
subcontracts as may be imposed or ordered pursuant to Executive Order 11246, as amended, and its
implementing regulations, by the Office of Federal Contract Compliance Programs. Any Contractor
who fails to carry out such sanctions and penalties shall be in violation of these specifications and
Executive Order 11246, as amended.
13. The Contractor, in fulfilling its obligation under these specifications, shall implement specific
affirmative action steps, at least as extensive as those standards prescribed in paragraph 7 of these
specifications, so as to achieve maximum results from its efforts to ensure equal employment
opportunity. If the Contractor fails to comply with the requirements of the Executive Order, the
implementing regulations, or these specifications, the Director shall proceed in accordance with 41
CFR 60-4.8.
14. The Contractor shall designate a responsible official to monitor all employment related activity to
ensure that the company EEO policy is being carried out, to submit reports relating to the provisions
hereof as may be required by the Government and to keep records. Records shall at least include for
each employee the name, address, telephone numbers, construction trade, union affiliation if any,
employee identification number when assigned, social security number, race, sex, status (e.g.,
mechanic, apprentice trainee, helper, or laborer), dates of changes in status, hours worked per week in
the indicated trade, rate of pay, and locations at which the work was performed. Records shall be
maintained in an easily understandable and retrievable form; however, to the degree that existing
records satisfy this requirement, contractors shall not be required to maintain separate records.
15. Nothing herein provided shall be construed as a limitation upon the application of other laws which
establish different standards of compliance or upon the application of requirements for the hiring of local
or other area residents (e.g., those under the Public Works Employment Act of 1977 and the Community
Development Block Grant Program).
FDEP-30
Revision 4
September 1999
APPENDIX G TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
CERTIFICATION OF COMPLIANCE WITH 41 CFR 60-1.7: REPORTS AND OTHER REQUIRED
INFORMATION
[Note: This certification is required by 41 CFR 60-1.7(b) and is applicable to all FDEP-assisted
construction contracts and subcontracts with a price exceeding $10,000; this certification is to be
included in all FDEP-assisted construction contracts and subcontracts with a price exceeding $10,000 and
in all solicitations for such contracts and subcontracts.]
This certification relates to a construction contract proposed by _________________________, which
(insert the name of the Owner)
expects to finance the proposed construction contract with assistance from the Florida Department of
Environmental Protection (which administers a State revolving fund loan program supported in part with
funds directly made available by grants from the United States Environmental Protection Agency). I am
the undersigned prospective construction contractor or subcontractor. I certify that:
(1) I _____ have / _____ have not participated in a previous contract or subcontract subject to the
Equal Opportunity Clause and
(2) if I have participated in a previous contract or subcontract subject to the Equal Opportunity
Clause, I ____ have / _____ have not filed with the Joint Reporting Committee, the Director of
the Office of Federal Contract Compliance Programs, or the Equal Employment Opportunity
Commission all reports due under the applicable filing requirements.
I understand that, if I have participated in a previous contract or subcontract subject to the Equal
Opportunity Clause and have failed to file all reports due under the applicable filing requirements, I am
not eligible, and will not be eligible, to have my bid or offer considered, or to enter into the proposed
contract or subcontract, unless and until I make an arrangement regarding such reports that is satisfactory
to the office where the reports are required to be filed.
I agree that I will obtain identical certifications from prospective lower-tier construction subcontractors
when I receive bids or offers or initiate negotiations for any lower-tier construction subcontracts with a
price exceeding $10,000. I also agree that I will retain such certifications in my files.
______________________________________________________ ______________
(Signature of Authorized Official) (Date)
__________________________________________________________________________
(Name and Title of Authorized Official [Print or Type])
___________________________________________________________________________
(Name of Prospective Construction Contractor or Subcontractor [Print or Type])
FDEP-31
Revision 4
September 1999
__________________________________________________________________________________
(Address and Telephone Number of Prospective Construction Contractor or
Subcontractor [Print or Type])
__________________________________________________________________________________
(Employer Identification Number of Prospective Construction Contractor or
Subcontractor)
FDEP-32
Revision 4
September 1999
APPENDIX H TO THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
SUPPLEMENTARY CONDITIONS
CERTIFICATION OF NONSEGREGATED FACILITIES
[Note: This certification is required by 41 CFR 60-1.8(b) and is applicable to all FDEP-assisted
construction contracts and subcontracts with a price exceeding $10,000; this certification is to be
included in all FDEP-assisted construction contracts and subcontracts with a price exceeding $10,000
and in all solicitations for such contracts and subcontracts.]
This certification relates to a construction contract proposed by _______________________________,
(insert the name of the Owner)
which expects to finance the proposed construction contract with assistance from the Florida
Department of Environmental Protection (which administers a State revolving fund loan program
supported in part with funds directly made available by grants from the United States Environmental
Protection Agency). I am the undersigned prospective construction contractor or subcontractor. I
certify that I do not and will not maintain any facilities I provide for my employees in a segregated
manner and that I do not and will not permit my employees to perform their services at any locations
under my control where segregated facilities are maintained.
I agree that I will obtain identical certifications from prospective lower-tier construction subcontractors
prior to the award of any lower-tier construction subcontracts with a price exceeding $10,000. I also
agree that I will retain such certifications in my files.
____________________________________________________ _______________
(Signature of Authorized Official) (Date)
___________________________________________________________________________________
(Name and Title of Authorized Official [Print or Type])
___________________________________________________________________________________
(Name of Prospective Construction Contractor or Subcontractor [Print or Type])
___________________________________________________________________________________
(Address and Telephone Number of Prospective Construction Contractor or Subcontractor [Print or
Type])
___________________________________________________________________________________
(Employer Identification Number of Prospective Construction Contractor or Subcontractor)