    Technical Site Survey ReportFor

    Site Sharing

    1. General Existing Site Sharing information

    PO Site ID/ Number:OP Site ID/ Number: 163357

    Principal Owner: PT. MitratelOther Party : PT. HCPT

    Site SharingUse:

    BTS UMTS HUB BSC others

    GPS Coordinates:

    Nominal: Latitude: 0.50587 Longitude: 117.5296

    Candidate: Latitude: 0.50594 Longitude: 117.52969

    Candidate Address:

    Contact person: Contact Number/s:

    Area/Location: SchoolcompoundHospital/Clinic

    MilitaryCompound

    Mountainarea

    Residential Road side Others:

    Existing Towertype:

    3 Legged towerHeight . m

    MD A/T HD A/T

    4 Legged towerHeight 44. m

    MD A/T HD A/T

    Monopoleheight . m

    Guyed poleHeight m

    Physicalappearance of thetower:

    GoodNot good

    Describe:

    Space availabilityon the tower

    Height available for Installation of antennas: 30 Brackets required : yes no

    EquipmentShelter:

    Collocate with CKD shelterpossible: Yes No

    If no, space for new outdoor unitAvailable: Yes No

    Distance from proposedequipment location to the tower

    m

    Cable tray available for usage:Yes No

    Other comments:

    ..

    Proposed equipment : Outdoor unit CKD Shelter Indoor room

    ExistingAccessroad:

    YesNo

    Describe the existing condition:

    Dimension:Length m Width .m

    Other important information / special requirement: (Re-Strengthening, Community, IMB, etc)

    Revision number: 02 23 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    2/15

    Technical Site Survey ReportFor

    Site Sharing

    2. Power Supply

    Connect to PLN:

    Installation of aerial cableallowed: Yes No Additional poles required to reach the 3 phase supply:Quantity pcs

    Power cable required to beinstalled underground:

    Yes No

    Length of required undergroundinstallation m

    Ground condition where cables willpass:

    Concrete mSoil mOthers:

    specify . length .. m

    Distance from thenearest transformer:.. m

    Capacity of the PLN Transformer: - KVA No. of poles required: - pcs.

    Any private property which will be affected by pole location and Right of way for the PLN connection:Yes No (Please show in the drawing.)

    Connect toBuilding:

    Type of supply available:single phasethree phase

    Spare breakers available for use:(capacity and qty)..

    Length of power cable from the sourceto our proposed sub-meter: ..m

    Length of cable from sub meter to ACPDB..m

    Demolition necessary: Yes NoSpecify type and length : ..

    Supply permanentGenerator:

    Explain the need for permanent generator:..

    Distance of the proposedlocation from site: .. m

    Soundproof required:Yes No

    Available spaceRooftopothers

    Other important information / special requirement:

    3. Grounding System

    Grounding System Available: Yes NoReading of available grounding (Existing): .ohms

    Possibility to connect with existing grounding (please discuss with owner): Yes No

    Estimated length of exposed (yellow green) grounding cable required: .m

    Demolition required for the installation of the copper rods:Yes (specify type and qty) . No

    Other important information / special requirement:

    Revision number: 02 24 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    3/15

    Technical Site Survey ReportFor

    Site Sharing

    4. Existing Antenna Information

    a. Radio Requirement

    Technology DCS GSM

    Antenna Type Number or Size*) see note 1

    Number of Antennas 3 3

    Antenna Pipe Mount(Diameter & Length)

    Antenna Orientation (deg.) & Tower LegMounting Position(Leg 1,2,3,4)

    30&1,90&2,210&3

    30&1,90&2,210&3

    Feeder Length (meters):

    Feeder size/type(i.e. 7/8; 1 ; etc):

    Antenna Height (meters)( Centre of ant. to ground level) 40 42

    Other information: Antenna Height is always taken from center of antenna

    b. Transmission Requirement

    Proposed Microwave Antenna Information

    No

    Tower LegMountingPosition

    (Leg 1,2,3,4)

    Diameter(m)

    Height(agl)

    Azimuthto F.E.(Deg)

    Typeof Antenna

    (HP, Std, Grid, etc)

    *) see note 2

    Antenna PipeMounting

    (Pipe Diameter & Length)

    Feeder Cable(Type & Diameter)

    1 Leg 1 0.6 31 7.81 HP - -

    2

    3

    4

    5

    6

    7

    8

    Other information : Antenna Height is always taken from center of antenna

    Note:There is not microwave, it is flexy1. If Radio antenna type not known then measure the size of the antenna (length, width, depth) and take photograph of front and rear of the antenna.2. HP = High Performance Microwave Antenna.

    STD = Standard Parabolic Antenna without Radome.STD+R = Standard Parabolic Antenna with Radome.Grid = Grid Antenna.

    Revision number: 02 25 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

    Existing 4 Leg

    Hight 44 mAGL

    Leg 1 Leg 2

    Leg 3Leg 4

  • 7/28/2019 Technical Site Survey Report 163357,,,

    4/15

    Technical Site Survey ReportFor

    Site Sharing

    ATTENDANCE:

    TeamPO

    (PrincipleOwner)

    OP

    (Other Party)Date Signature

    Construction Supervisor

    Acquisition Supervisor

    TR/MW Planner

    Radio Planner

    Implementation Supervisor

    Others attending

    Survey result: Accepted Rejected

    Comments (if rejected):

    Construction Plan : .

    Installation Plan : .

    Position of Site sharing : 1st 2nd 3rd Others .

    Revision number: 02 26 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    5/15

    Technical Site Survey ReportFor

    Site Sharing

    5. Drawings and sketches

    a. Access to site including the dimensions and distance of the road which is not accessible by car:b. Complete proposed layout (tower/pole position/equipment/ACPDB/cable route,etc. with all dimensions

    including set back from property line on all sides)c. Reflect any overhead/underground utilities crossing the site (powerline, telephone line, pipesetc.)d. Reflect existing facilities/obstructions/trees.etc.e. Reflect any high tension Cables running outside the building which can affect delivery (approx. height)f. Sketch the proposed route for power connection; specify the distances as stated in above datag. SITE CONTOUR / ELEVATION (reflect approximate contour of site/elevation view; provide the elevation

    reading per 3m)

    Site Layout

    Revision number: 02 27 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

    SST

    44M Propose

    Hcpt

    GensetBts Bts

    Kwh

    Kwh

    Pintu 0 30

  • 7/28/2019 Technical Site Survey Report 163357,,,

    6/15

    Technical Site Survey ReportFor

    Site Sharing

    Antenna Placement

    Revision number: 02 28 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

    DA

    CB

    EXISTINGANT

    RF

    SECTOR 1 30

    EXISTINGANT

    RF

    SECTOR 2 90

    EXISTINGANT

    RF

    SECTOR 3 210

    A

    CB

    D

    EXISTINGANT

    RF

    SECTOR 1 30

    EXISTINGANT

    RF

    SECTOR 3 90

    EXISTINGANT

    RF

    SECTOR 4 210

    42M.A.G.L

    40 M.A.G.L

    EXISTING

    MWANTENNA

    0.6 90

    DA

    CB

    EXISTINGANT

    RF

    SECTOR 2 180

    EXISTINGANT

    RFSECTOR 1 60

    EXISTINGANT

    RF

    SECTOR 3 300

    40M.A.G.L

    DA

    CB

    EXISTING

    MWANTENNA

    0.6 78

  • 7/28/2019 Technical Site Survey Report 163357,,,

    7/15

    Technical Site Survey ReportFor

    Site Sharing

    Note: Photo documentation should include but not limited to the following:a. Actual proposed site statusb. Panoramic Photos.c. Access information from the nearest road going to the actual site. Include information on the narrowest accessd. Power source. Including photo of the 3 Phase power source (i.e. 3 phase PLN pole) and nearest Transformere. Cable tray route and grounding route; including power route going to sourcef. Incase there is need to demolish existing structure, photo of which should also be presented

    g. Other necessary information should have photo attachment.

    Panoramic Photo

    0 30

    60 90

    120 150

    Revision number: 02 29 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    8/15

    Technical Site Survey ReportFor

    Site Sharing

    180 210

    240 270

    Revision number: 02 30 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    9/15

    Technical Site Survey ReportFor

    Site Sharing

    300 330

    Existing Main Access Road Proposed EquipmentRevision number: 02 31 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    10/15

    Technical Site Survey ReportFor

    Site Sharing

    Proposed Pole PLN/ KWH Meter Existing Access Road to Site

    Existing Access Road to Site Existing Access Road to Site

    Revision number: 02 32 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    11/15

    Technical Site Survey ReportFor

    Site Sharing

    VERTICAL TRAY HORIZONTAL TRAY

    TOP DOWN PICTURE TOWERRevision number: 02 33 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    12/15

    Technical Site Survey ReportFor

    Site Sharing

    TOWER PICTURE 1 TOWER PICTURE 2

    TOP DOWN 1 TOP DOWN 2

    TOP DOWN 3 TOP DOWN 4

    Revision number: 02 34 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

    Propose antRF 30m

    Propose antMW 30m

  • 7/28/2019 Technical Site Survey Report 163357,,,

    13/15

    Technical Site Survey ReportFor

    Site Sharing

    5.A. Detailed Sketch of Transmission Cables and Transmission Cable Ladder System

    a. Provide details of the type, size and number of existing transmission cables including relative positions andarrangement on the cable ladder system.

    b. A new sketch for (a) above is required whenever there is a change in the number of cables and the sketchshould indicate the top and bottom tower elevations where the cable arrangement is applicable.

    c. Provide details of the cable ladder system including width, type and size of ladder rails, type size and spacingof cable support brackets.

    d. If the transmission cable ladder system is integral with the climbing ladder system then this sketch must

    include details of the climbing ladder system including the following :- Width, type and size of climbing ladder rails.- Diameter, type and spacing of ladder rungs.- Safety cage vertical flat bar size and arrangement.- Safety cage horizontal flat bar size and spacing.

    e. Provide measurement of vacant space available on the cable ladder system.f. If the transmission cable ladder system is isolated from the climbing ladder system then show the position on

    the tower.

    Revision number: 02 35 Document title: Site Sharing TSSR

    Date of issue: December 06, 2012 of Document number:163357/Mega/Batch 3G/

    References: M4. TSS Approved 38 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    14/15

    Technical Site Survey ReportFor

    Site Sharing

    Proposed Antenna Sector 1 Proposed Antenna Sector 2

    Proposed Antenna Sector 3 GPS Coordinate View

    Revision number: 00 36 Document title: Site Sharing TSSR

    Date of issue: November 03, 2008 of Document number: 2056

    References: M4. TSS Approved 37 Release status: Released

  • 7/28/2019 Technical Site Survey Report 163357,,,

    15/15

    Technical Site Survey ReportFor

    Site Sharing

    4.A. HCPT Propose Antenna Information

    a. Radio RequirementTechnology 2G 3G

    Sector 1 2 3 1 2 3

    Antenna Type NumberDX-1710-

    2170-65-

    19.5i-M

    DX-1710-2170-

    65-19.5i-M

    DX-1710-2170-

    65-19.5i-M

    DX-1710-2170-

    65-19.5i-M

    DX-1710-

    2170-65-

    19.5i-M

    DX-1710-

    2170-65-

    19.5i-M

    Number of Antennas 1 1 1 1 1 1

    Antenna Orientation (deg.) &Tower Leg Mounting Position(Leg 1,2,3,4)

    60/Leg 1 180/Leg 2 240/Leg 3 60/Leg 1 180/Leg 2 240/Leg 3

    Feeder Length (meters): 30 x 2 30 x 2 30 x 2 30 x 2 30 x 2 30 x 2

    Feeder size/type

    (i.e. 7/8; 1 ; etc):

    7/8" 7/8" 7/8" 7/8" 7/8" 7/8"

    Antenna Height (meters)( Center of ant. to ground level)

    30 m 30 m 30 m 30 m 30 m 30 m

    Other information: Antenna Height is always taken from center of antenna

    b. Transmission Requirement

    Proposed Microwave Antenna Information

    NoNearEndSite

    TowerLeg

    MountingPosition

    (Leg1,2,3,4)

    Diameter(m)

    Height

    (M.Agl)

    Azimuth

    to F.E.(Deg)

    Type ofAntenna(HP, Std,Grid, etc)

    FeederCable(Type &

    Diameter)

    Far EndSite

    Diameter(m)

    Height

    (M.Agl)

    Azimuthto N.E.(Deg)

    1 163357 1 0.6 31 7.81 HP 1/4 161059 0.6 30 187.81

    2

    3

    4

    5

    6

    Other information : Antenna Height is always taken from center of antenna

    Note:HP = High Performance Microwave Antenna.STD = Standard Parabolic Antenna without Radome.

    STD+R = Standard Parabolic Antenna with Radome.Grid = Grid Antenna.

    Revision number: 00 37 Document title: Site Sharing TSSR

    Date of issue: November 03, 2008 of Document number: 2056

    References: M4. TSS Approved 37 Release status: Released

    Existing 4 Leg

    Hight 44 mAGL

    Leg 1 Leg 2

    Leg 3Leg 4